Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 13 June 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2012-404-001797 [2014] NZHC 1188
BETWEEN
|
CHRISTINE ANNE BETHELL
Plaintiff
|
AND
|
VICTORIA ELIZABETH BETHELL Defendant / First Counterclaim
Plaintiff
MARIA GAEL BETHELL Second Counterclaim Plaintiff
|
Judgment: 30 May 2014
JUDGMENT OF COURTNEY J
This judgment was delivered by Justice Courtney on 30 May 2014 at 1.00 pm
pursuant to R 11.5 of the High Court Rules
Registrar / Deputy Registrar
Date.............................
BETHELL v BETHELL [2014] NZHC 1188 [30 May 2014]
Introduction
[1] In my decision 20 December 2013 I found largely in the
plaintiff’s favour and made the order for specific performance
sought.
The plaintiff now seeks costs on a 2B basis.
[2] The defendant and counterclaim plaintiff accept that, in general,
the plaintiff is entitled to costs on a 2B basis. However,
they do not accept
that she is entitled to costs for steps relating to the claim for compensation
for income earned from the land
during the relevant period. There are also some
other minor aspects on which the parties do not agree.
Costs relating to the issue of income derived from the
land
[3] It was accepted at trial that the defendant had received income from the land in respect of which the plaintiff obtained an order for specific performance. In addition to the order for specific performance, the plaintiff sought compensation for the period over which she was entitled to the land. However, that cause of action failed. The defendant and counterclaim plaintiff resist costs for the plaintiff’s application for further and better discovery and interrogatories on the ground that
they relate to this issue.1
[4] The material relevant to the defendant’s income from the land
was relevant and liable to be discovered and was also
properly the subject of
interrogatories. However, it involved collating and analysing a very substantial
amount of material. It was
clear from Vicky Bethell’s evidence that the
exercise took up significant time.
[5] The fact that discovery and interrogatories on this aspect took up a great deal of time, and the fact that there was pressure of time does not necessarily detract from the plaintiff’s right to costs. However, this was an issue that, ultimately, was of peripheral significance to the resolution of the case. It took up a disproportionate
amount of trial time and the plaintiff failed on it. For those reasons
this aspect of the
1 Items J, K and V in the table to Mr Thompson’s memorandum 23 January 2014.
proceeding falls within r 14.7(d) of the High Court Rules as justifying
either a refusal to award costs or a reduction in costs.
[6] I consider it appropriate to decline the plaintiff’s costs in
relation to discovery and interrogatories. Further,
I consider that there
should be a reduction of 10 per cent in the overall costs awarded to reflect the
extent to which the trial
was devoted to this issue.
Other costs items in dispute
[7] The defendant and counterclaim plaintiff dispute items I and N in
the table contained in Mr Thompson’s memorandum
on the basis that they
relate to consent memoranda which were actually drafted by defence counsel. The
plaintiff says that there
was input into the memoranda by the plaintiff’s
counsel and she should therefore be entitled to costs. Whilst that might be
right, these items are specifically directed to the preparation of memoranda and
I therefore disallow them.
Disbursements
[8] Most of the disbursements claimed are not in dispute.
However, the defendant and counterclaim plaintiff dispute
items 10, 11 and 12
of Mr Thompson’s table. These are disbursements relating to the
plaintiff’s application for an extension
of the resource consent relating
to the use of the land in question. It is resisted on the basis that they are
not disbursements
reasonably necessary for the conduct of the proceedings as
required by r 14.12(2).
[9] Mr Thompson submits that they are reasonably connected to the litigation because, as I found, the obligation lay with Ross Bethell to implement the resource consent. It was his failure to do so that ultimately meant that the plaintiff had to incur the costs of obtaining an extension to the consent. I accept that this is the correct position and that the plaintiff is entitled to the disbursements as claimed.
Leave reserved
[10] The parties should be able to re-calculate the costs payable based on these orders. Leave is reserved to seek further directions if there are aspects of the
calculation upon which agreement cannot be
reached.
P Courtney J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/1188.html