Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 1 July 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2012-404-1857 [2014] NZHC 1269
BETWEEN
|
MARLEY NEW ZEALAND LIMITED
Plaintiff
|
AND
|
SKELLERUP RUBBER SERVICES LIMITED
Defendant
PRECISE IRRIGATION LIMITED Former First Third Party
|
Hearing:
|
On the papers
|
Counsel:
|
R M Gapes for the Plaintiff
M C Sumpter and JWJ Graham for the Defendant
C A McVeigh QC and H R Catherwood for the Former First
Third Party
|
Judgment:
|
6 June 2014
|
COSTS JUDGMENT OF ELLIS J
This judgment was delivered by me on Friday 6 June 2014 at 4.30 pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date:...............................
Counsel/Solicitors:
R Gapes, Simpson Grierson, Auckland
M C Sumpter, Chapman Tripp, Auckland JWJ Graham, Chapman Tripp, Auckland C A
McVeigh QC, Barrister, Christchurch H R Catherwood, Solicitor,
Christchurch
MARLEY NEW ZEALAND LTD v SKELLERUP RUBBER SERVICES LTD [2014] NZHC 1269 [6 June 2014]
[1] In my judgment dated 12 August 2013 I declined Skellerup’s
application for review of a decision of Associate Judge
Sargisson, in which she
had set aside third party notices issued by Skellerup to Precise Irrigation Ltd
(Precise) and PGG Wrightson
Ltd and dismissed Skellerup's claims against
them.1
[2] At [34] of my judgment I said:
I trust that the issue of costs (which are payable by Skellerup on a 2B
basis) will be resolved between counsel without the need for
the assistance of
the Court. But if agreement cannot be reached, memoranda may be
filed.
[3] Associate Judge Sargisson also awarded costs to Precise on a 2B
basis.
[4] Costs have not, however, been resolved between counsel. That is
largely because, notwithstanding what I said in my judgment,
Precise now seeks
costs from Skellerup on an indemnity or (in the alternative) an increased basis.
There is a subsidiary argument
about how any 2B payment should be
quantified.
Background
[5] The substantive proceedings involved a claim by Marley against
Skellerup for breach of contract and in negligence relating
to defective
irrigation systems supplied by Skellerup to Marley. The damages for which
Marley sued comprised monies paid by Marley
to settle potential claims made
against it by landowners on whose properties the systems had been
installed.
[6] Skellerup issued third party notices to various installers of the irrigation systems, including Precise. Skellerup said that negligent installation had contributed to the failures and claimed contribution from the third parties as joint tortfeasors, pursuant to s 17(1) of the Law Reform Act 1936 (the LRA). Precise applied to have the third party notice set aside and was successful before Associate Judge Sargisson
and on review.
1 Marley New Zealand Ltd v Skellerup Rubber Services Ltd [2013] NZHC 1443 and Marley New
Zealand Ltd v Skellerup Rubber Services Ltd [2013] NZHC 2035.
[7] The heart of the reasoning underlying my decision to uphold the
Associate
Judge can be found at [25] – [30] where I said:
In terms of s 17(1) of the LRA, the relevant requirement is that the
“damage” caused by the tortfeasor from whom a contribution
is sought
(here, the third parties) must be the “same” as that caused by the
original tortfeasor (here, Skellerup). There
is no magic in those words; they
mean what they say.
I acknowledge that Skellerup’s pleading effectively is that any
loss and damage suffered by Marley as a result of Skellerup’s
negligence
was also caused or contributed to by the third parties, i.e. that the loss and
damage from Skellerup’s and the third
parties’ negligence is the
“same”. Ordinarily the Court determining an application to strike
out/set aside would
proceed on the basis that that allegation is true. But it is
not required to do so when the relevant pleaded fact is demonstrably
without
foundation or incorrect. For the reasons I have already given, I consider that
to be the case here.
Rather, and as I have said, the relevant “damage” that must be
assumed to have been caused by Skellerup is Marley’s
liability as seller
of the pipes/irrigation system to the purchasers of the pipes/system. Although
negligent installation by the
third parties might well have caused or
contributed to damage suffered by landowners, it simply could not cause
the damage to Marley upon which its claim against Skellerup is based, for the
reasons I have already given.
That leads on to one final point which, in my view, further supports the
conclusions I have reached. That is that the unusual features
and conceptual
difficulties of this case arise because of certain choices that have been made
by Marley. Those features are that:
(a) Marley has paid out $7 million to “settle” claims which had
not in fact been brought against it; and
(b) Marley has chosen to sue Skellerup in tort as well as
contract.
It seems to me that in the absence of the first feature, the claim would no
doubt have taken a more orthodox shape, namely:
(a) A claim in contract against Marley and (possibly) the installers
by the landowners for the defective irrigation systems;
and
(b) Subsequent joinder by Marley of:
(i) Skellerup, if there was an indemnity clause in the contract between them;
and/or
(ii) (if necessary) the installers, on the basis of their common
(contractual) liability to the plaintiff landowners.
In the absence of the second feature noted at [29(b)] above, there would, of course, be no possibility of a contribution claim by Skellerup against the installers as joint tortfeasors under s 17(1)(a).
[8] As these paragraphs of my judgment make clear, it proceeded on the
entirely orthodox basis that it was the legal, rather
than the factual,
tenability of the third party claims that was to be scrutinised.
[9] It is against that background that I turn to consider the costs
issues raised by
Precise.
Indemnity costs
[10] In seeking costs on an indemnity basis Precise relies on r
14.6(4)(a) and alleges that Skellerup “acted vexatiously,
frivolously,
improperly, or unnecessarily in commencing [and] continuing” the
proceeding. The basis for this allegation
is Precise’s contention
that Skellerup knew or should have known that there was no evidentiary basis for
proceeding against
it. That contention is based on 2011 correspondence between
Skellerup and a Vietnamese rubber company in the course of which Skellerup
appears to accept that the cause of the defects was faulty Z rings that had been
supplied to it by that company. Precise says that
this correspondence means
that Skellerup knew that there was, as a matter of fact, no fault on the part of
the installers.
[11] Precise also alleges that Skellerup joined Precise (and other third
parties) for an improper purpose, namely an attempt
to force those third parties
to contribute to a settlement.
[12] I have to say that I am at a loss as to how Precise considers that I
am able to deal with these issues. The evidence upon
which it relies has not
been tested and played no part in my judgment. Indeed, my judgment proceeded on
the opposite but orthodox
assumption (in a strike out context) that the
installers were at fault. Moreover, acceptance by Skellerup that there was a
problem
with the Vietnamese Z rings does not, in my view, lead inexorably to the
conclusion that that problem was the (sole) cause of the
defects in the
irrigation systems.
[13] In addition, Skellerup’s response to the application for indemnity costs refers in some detail to briefs of expert evidence it has obtained which, on their face, support its contention that problems with installation did contribute to the failure of
the systems. Necessarily, that evidence has also not been sworn and has not
been tested.
[14] Irrespective of whether these briefs refer specifically to Precise
(as opposed to other installers) and irrespective of when
those briefs were
prepared, I am both unwilling and unable to make findings about their
evidentiary scope or sufficiency in the context
of a costs argument. Nor am I
prepared to draw from the “evidence” an adverse inference about
Skellerup’s motives
in issuing the third party notices. In my view there
is no proper basis for the contention that r 14.6(4)(a) applies.
Increased costs
[15] It is accepted by Precise and by Skellerup that the approach to
determining whether an award of increased costs should be
made is as set out in
Holdfast NZ Ltd v Selley’s Pty Ltd.2
[16] The first step is to assign to the proceedings the appropriate costs category, which, here, is agreed to be category 2. Next, it is necessary to work out a reasonable time for preparation in relation to each step in the proceeding. Precise’s only submission in that respect is that the nature of the present proceeding was such that the time required to complete the preparation of submissions for the setting aside hearing and on the application for review substantially exceeds the time allocated under band C (r 14.6(3)(a)). The time allocated under band C for the preparation of submissions on an interlocutory application is three days. Precise says an award of five days (setting aside) and four days (review) is warranted. The Court of Appeal in Holdfast said that where it is shown that substantially more time for a particular step
has been required:3
...the appropriate judicial response is to increase the amount of
time allocated for the particular step, and then to apply
the appropriate daily
recovery rate to the time so fixed.
[17] Then, as the Court in Holdfast
noted:4
2 Holdfast NZ Ltd v Selley’s Pty Ltd [2005] NZCA 302; (2005) 17 PRNZ 897 (CA).
3 At [44].
4 At [45].
Additional grounds for awarding increased costs are given in r [14.6(3)3(b)].
All these grounds depend on a finding that “the
party opposing costs has
contributed unreasonably to the time or expense of the proceeding or step in the
proceeding”. The
conduct justifying increased costs under subcl (3)(b) is
to be contrasted with conduct that warrants indemnity costs, as set out
in subcl
(4)(a) and (b).
[18] But none of the subcl (3)(b) grounds are relied on by Precise.
Rather, it relies on r 14.6(3)(c) (the predecessor of which
was not discussed in
Holdfast) which permits an increase if:
...the proceeding is of general importance to persons other than just the
parties and it was reasonably necessary for the party claiming
costs to bring it
or to participate in it in the interests of those affected...
[19] Precise says that an uplift of 50 per cent is warranted on the basis
of this provision.
Discussion
[20] As far as r 14.6(3)(c) is concerned, I am prepared to accept that
Precise took something of a leadership role amongst the
third parties in seeking
to have the notices set aside. I say that because Precise was the first third
party to be joined and also
because although the third and fourth third parties
had filed applications to set aside they did not participate in the hearings
before me and Associate Judge Sargisson. The arguments marshalled and
presented by counsel for Precise and counsel for the second
third party were
therefore effectively made on behalf of the other third parties. I also
acknowledge that Precise instructed senior
counsel for the purposes of arguing
the applications and that Mr McVeigh QC did, in the hearing before me, lead the
charge for the
third parties. And I accept that the applications to set aside
were of considerable moment to the third parties themselves.
[21] Notwithstanding all these matters, however, it does not appear to me that the terms of the relevant rule are engaged here. In particular, the applications were not of general importance to anyone other than the (third) parties concerned. The present is very different from those cases in which an increase under r 14.6(3)(c) has been granted. I decline to order an increase on that basis.
[22] In terms of r 14.6(3)(a), the band C allowance for submissions in
relation to both the application to set aside and the application
for review is,
as I have noted, three days. Taking into account what I have said above about
the role played by Precise in the
proceedings and the fact that (in my view) the
matters at issue were analytically rather subtle and the circumstances were, in
some
senses, novel, I am prepared to accept that (substantially) more than three
days was required to prepare submissions for the initial
setting aside hearing.
I consider that an increase that is equivalent to two days is warranted, which I
will round up (by $20) to
$4,000. I do not, however, accept that the same
considerations are at play in the review hearing which largely involved a rerun
of the earlier arguments. The standard 1.5 days remains, in my view,
appropriate.
[23] The upshot is, therefore, that Precise are entitled to 2B costs, but
with an increase of $4,000. It is accordingly to that
calculation which I now
turn.
2B scale costs
[24] Very regrettably the parties have not even been able to agree on a 2B scale calculation. Indeed there is a difference of almost 100 per cent between them. Precise’s calculation of 2B costs gives a total of $45,173. Skellerup’s calculation of
2B costs amounts merely to $24,775.50. Skellerup also says that the $1,990
incurred by Skellerup in preparing its costs’ memorandum
in response to
Precise’s claim should be deducted from that amount because Precise
rejected an offer by Skellerup to pay $40,000
to settle the costs’ issues
between them.
[25] The specific 2B matters with which Skellerup takes issue are
Precise’s claims
for:
(a) full costs in relation to five out of six joint memoranda filed
between
February and July 2013 (0.4 days x 5, totalling $3,980);5
5 Issue appears not to be taken for the full costs claimed in relation to a joint memorandum dated
29 April 2013
(b) full costs for five further memoranda filed but which did not
relate to specific case management conferences or mentions
hearings (0.4 days x
5, totalling $3,980);
(c) costs on the affidavit filed in support of the application to set
aside the third party notices, for which Precise accepts
no provision is made in
Schedule 3 (1.4 days, totalling $2,786);
(d) two claims for inspection of documents when inspection was
not required because (Skellerup says) Precise’s
application to be removed
from the proceedings was well advanced by the time it received documents for
inspection (1.5 days x 2,
totalling $5,970);
(e) the full costs for discovery (2.5 days, totalling
$4,975), in circumstances where (Skellerup says) Precise
provided
discovery:
(i) after the resolution of Marley’s application for non-party
discovery (on a basis said not to have been fully not disclosed
to Skellerup);
and
(ii) at a time when Precise was no longer a party to the
proceeding;
(f) the costs of preparing a notice of opposition to Marley’s
application
for non-party discovery (0.6 days totalling $1,194).
[26] Of the disputed items, the last (discovery) requires further
explanation. The relevant chronology (which was not set out
in either
party’s submissions, so has been pieced together from the extensive Court
file) appears to be as follows:
(a) On 21 December 2012 Precise was served with a third party notice;6
(b) On 20 March 2013 Associate Judge Abbott ordered that Precise provide standard discovery by 3 June 2013. The Judge’s minute notes that the scope of the discovery required was nonetheless quite limited. It also makes it clear that a date after the hearing of Precise’s proposed application to set aside the third party notices was deliberately chosen. The Judge reserved leave to Precise to apply for a variation “should
circumstances change”;7
(c) On 15 April 2013 Precise formally applied to have the third party
notice set aside;
(d) The application was heard before Associate Judge Sargisson on 22
May 2013;
(e) Associate Judge Sargisson’s judgment setting aside the third
party
notices was issued on 17 June 2013;
(f) On 18 June 2013 Skellerup applied for review of that
decision;
(g) On 9 July 2013 July Marley applied for non-party discovery against
the former third parties, including Precise. The application
noted that, as a
result of the discovery orders made whilst Precise remained a third party,
Precise had “already undertaken
some but not all of the work to provide
discovery”. The scope of the application was comprehensive, and required
disclosure
of documents falling within six broad categories relating to
purchases and installation of Z rings between 2006 and 2009.
Marley
undertook to pay Precise’s reasonable costs of complying with the
non-party discovery order, from the date of the
application;
(h) Precise filed a notice of opposition to the application on the grounds that the discovery sought was wider than the discovery it had been required to give whilst it remained a third party;
(i) The order requiring Precise to give non-party discovery to Marley
by
14 August 2013 was made by consent on 24 July 2013;8
(j) Skellerup’s application for review was heard on 31 July
and my
judgment declining the application was issued on 12 August 2013;
(k) Precise’s affidavit of documents (comprising approximately 800 documents) was sworn on 22 August 2013 and filed on 27 August
2013.
[27] Precise’s counsel has subsequently confirmed that Precise
received an agreed figure from Marley for costs of conducting
that non-party
discovery. Skellerup says that although its lawyers have asked Precise to
confirm how much it received for that,
Precise has declined to do so. Skellerup
therefore alleges that Precise is seeking to “double-dip” on costs
for undertaking
the non-party discovery. Skellerup submits that it should only
be required to pay Precise half of the standard allocation for preparation
of
the affidavit of documents (1.25 days, totalling $2,487.50).
[28] My determination of the disputed costs items is as follows: (a) no costs for joint memoranda;
(b) full costs for four of the six further memoranda (0.4 days x 4,
totalling
$3,184);
(c) no costs on the affidavit filed in support of the application to set
aside, which was made (and granted) on legal rather than
factual
grounds;
(d) half the costs claimed for inspection (1.5 days, totalling
$2,985);9
(e) half the costs claimed for discovery, for the reasons advanced
by
Skellerup (1.25 days, totalling $2,487.50);
8 It is not clear to me whether the categories of documents required to be discovered by this order
are the same as the categories sought in Marley’s application.
9 I am unclear as to why Precise claimed for twice this amount.
(f) no costs on the notice of opposition to Marley’s application
for non- party discovery, which seems to me to have nothing
to do with Skellerup
or the third party issue.
[29] When these amounts are added to the 2B costs accepted by Skellerup
of
$24,775.50, the total claimable 2B costs amount to $33,432. To that must be added the $4,000 increase for the preparation of submissions in relation to the setting aside. Given the conclusions I have reached, however, I also agree with Skellerup that
$1,990 should be deducted for the preparation of its costs memorandum. The
total
payable by Skellerup to Precise is therefore
$35,442.
Rebecca Ellis J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/1269.html