High Court of New Zealand Decisions |
Last Updated: 26 June 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-4991 [2014] NZHC 1390
BETWEEN
|
ANITA MARIA FINNIGAN,
TINOS TRUSTEE LIMITED and CARYTIDS TRUSTEE LIMITED Plaintiffs
|
AND
|
AUCKLAND COUNCIL First Defendant
FEARON HAY ARCHITECTS LIMITED Second Defendant
|
Hearing:
|
18 June 2014
|
Appearances:
|
D K Wilson for Plaintiffs
No appearance for First Defendant
J M Keating for Second Defendant
|
Judgment:
|
18 June 2014
|
ORAL JUDGMENT OF ASSOCIATE JUDGE
BELL
Solicitors:
Ellis Gould, Auckland, for Plaintiffs
MinterEllisonRuddWatts, for First Defendant
Kennedys, Auckland, for Second Defendant
Copy for:
D K Wilson, Barrister, Auckland, for Plaintiffs
FINNIGAN, TINOS TRUSTEE LIMITED and CARYTIDS TRUSTEE LIMITED v AUCKLAND COUNCIL [2014] NZHC 1390 [18 June 2014]
[1] This leaky-building case concerns a house built at 38 View Road,
Waiheke Island. The plaintiffs, the trustees of the Irini
Trust, are the owners
of the property. The Irini Trust is a sub-trust of the Tinos Trust, which owned
the property at the time of
construction. Anita Finnigan is one of the
trustees of both trusts. She is the plaintiff who dealt with the second
defendant.
[2] The second defendant is the architect that designed the house. It
has applied to strike out and for summary judgment on
the grounds that it has
already entered into an agreement with the plaintiffs in full and final
settlement of their claim.
What the case is about
[3] The trustees of the Tinos Trust had the house built at View Road
between
2004 and 2006. Ms Finnigan engaged the architect to design the house, apparently in 2003. The architect carried out the design work and applied for a building consent in early 2004. It was a major job. Construction costs are said to have come to about
$1m. The architect’s fee was for approximately $100,000. When extras
were added on, it was ultimately paid about $115,000.
[4] In 2009 the owners found that the house had water-ingress problems.
They instructed a building consultant, Mr Medricky,
to inspect the building. He
reported that the defects required repair. That repair work has now been
carried out. The cost of
the repairs, including GST, is said to come to
$651,066. The plaintiffs have sued for the recovery of these repair costs plus
general
damages. The defendants are the Auckland Council and the
architect.
[5] The claim against the architect is for negligence in its design work. Specifically, it is alleged that there was inadequate detail. There was insufficient detail for the council to assess the application for building consent adequately and for the builder to put up a house that was free of defects, weathertight, and which met reasonable standards of construction. The details were so lacking that the building did not comply with the Building Code and was not weathertight and suitable for residential use.
[6] The statement of claim contains, as a first schedule, an extensive
pleading of defects in the house. A second schedule
sets out alleged
deficiencies in the design documentation and specifications of the architect.
That schedule reinforces the
primary pleading that the deficiencies in design
were a lack of sufficient information and detail.
The settlement agreement
[7] The settlement agreement the architect relies on arose out of an earlier proceeding. In 2005 the architect sued Ms Finnigan in the District Court at Auckland for outstanding fees. It appears that while Ms Finnigan had paid the initial agreed fee, the architect claimed for extras for additional work. It applied for summary judgment. This was before the changes to the District Courts Rules in
2009. It was the kind of summary judgment application that may be made under
the High Court Rules, although the amount was clearly
within the jurisdiction of
the District Court.
[8] Ms Finnigan opposed the summary judgment application. For this hearing the parties have not provided the pleadings in the District Court but they have put in evidence copies of affidavits by Ms Finnigan and her builder, Mr Campbell; Mr Fearon, director of the second defendant; and the project architect, Mr Atcheson. They have also put the settlement agreement in evidence. That was a letter dated
10 May 2006 signed by counsel on both sides that recorded the terms of
settlement. The relevant parts of the letter are:
Further to our various discussions, we confirm settlement of the proceedings
on the following basis:
1 In full and final settlement of all issues as between the
parties, howsoever arising including but not limited to
all allegations of
negligence and breach of contract, the defendant has made against the plaintiff
the defendant will pay to the
plaintiff by 1:00pm today the sum of $10,000 to
the trust account of John Ewart, Solicitor, and the defendant will pay
a
further sum of $4,000 upon delivery of certain drawings which are described in
more detail below.
[Paragraphs 2 and 3 of the letter deal with delivery of drawings and payment of the sum of $4,000.]
4 Upon payment above, the proceedings will be discontinued.
[9] The architect relies on that agreement to say that Ms
Finnigan and the trustees of the Irini Trust are barred
from suing it for the
alleged defects in design leading to the water-ingress problems which are the
subject of this proceeding.
[10] I record one matter which is not in dispute. In the District Court
the architect sued only Ms Finnigan. The architect
did not sue the other
trustees of the Tinos Trust or the Irini Trust. However, it seems to be common
ground that that agreement
binds not only Ms Finnigan personally but also the
trustees of the Tinos Trust, the owners of the property at View Road at that
time,
and the trustees of the Irini Trust (as sub-trustees and current owners of
the property). No point was taken as to Ms Finnigan’s
authority to bind
not only herself but also the other trustees.
[11] The plaintiffs say that the agreement of 10 May 2006 did not settle
the claims now made in this proceeding which, they say,
were not known at that
time. It is necessary therefore to consider these matters:
(a) What does the agreement of 10 May 2006 mean?
(b) On its true construction, does it apply to the claims made in this
proceeding?
Interpretation of the agreement
[12] The architect says that the agreement operates as a general release.
It says first, as a matter of the plain meaning of the
words, and second, when
the agreement is read in its context, it is released from all liability for the
plaintiffs’ claim.
[13] Counsel have referred to a number of authorities which deal with the interpretation of a settlement agreement containing a general release. The two more significant cases are the Court of Appeal’s decision in Tag Pacific Ltd v The Habitat
Group Ltd1 and the House of Lords’
decision in Bank of Credit and Commerce
1 Tag Pacific Ltd v The Habitat Group Ltd (1999) 19 NZTC 15,069 (CA).
International SA v Ali.2 Counsel agreed that there is not
any significant difference of approach between the Court of Appeal in Tag
Pacific and the majority in Bank of Credit and Commerce International SA
v Ali. I take the following extract from Tag Pacific as setting out
the applicable principles. Tipping J said:3
It is not always helpful to focus on so-called rules of construction.
Certainly they are not to be elevated into principles of law.
The ultimate
objective is always to ascertain the intention of the parties from the words
they have used, interpreted in the light
of the objective circumstances known to
them at the time. The general rule said to govern this case represents no more
than a reflection
of the inherent probabilities, ie that people are unlikely to
intend to release a claim of which they are unaware at the time.
But it is
always possible for parties to do so, and such an intention will be found if
clearly demonstrated by the words used. This
we consider to be the correct
modern approach to the construction of documents such as releases and, indeed,
all contractual documents.
It is not inconsistent with the various authorities
to which we were referred, which included London & South Western Railway
Co v Blackmore (1870) LR 4 HL 610 at 623 per Lord Westbury) and Grant v
John Grant & Sons Pty Ltd [1954] HCA 23; (1954) 91 CLR 112 at 129 per Dixon CJ,
Fullagar, Kitto and Taylor JJ. The summary to be found in Chitty
on Contracts (Vol 1, General Principles (27th ed, 1994) paras 22-003
to 22-005 is to the same effect...
Although each case will turn on the words used in their factual setting, the
actual decisions in Grant and in Blackmore show that an intention
to release an unknown claim is not lightly to be inferred, even when apparently
very general words have been
used. This accords with commercial common sense.
To that extent it may be helpful to speak of a rule of construction, provided
it
is remembered always that everything turns on the words used interpreted in
their factual setting.
[14] The speeches of the majority in Bank of Credit and Commerce
International SA v Ali are to similar effect, in particular the speeches of
Lord Bingham4 and Lord Nicholls5 emphasising the
importance of context.
[15] Other cases were also cited. I apply the principles above, while bearing in mind that the terms and circumstances of agreements were different in other cases. Therefore, while other cases are of assistance in seeing how the principles are applied, they are not directly applicable to the circumstances of this case. In
particular, Nixon v Richardson is about the dissolution of a
partnership.6 That is a
2 Bank of Credit and Commerce International SA v Ali [2001] UKHL 8, [2002] 1 AC 251.
3 At 15,074.
4 At [8]-[9].
5 At [23], [27]-[29].
6 Nixon v Richardson HC Auckland CIV-2010-404-1412, 1 September 2010.
different matter, both because the agreement used different words from the
present one (it referred to “all claims”) and
because the context
was different. Similarly, McGowan v Hamblett7 dealt
with settlement in a probate dispute where an agreement was made for the
distribution of an estate. It is important
to understand that in both those
cases, there was high value placed on finality in settling disputes.
[16] The architect’s first submission was that the wording of the
agreement was sufficient to conclude the matter in its
favour. The
architect’s argument focused on the words:
all issues between the parties, howsoever arising, including but not limited
to all allegations of negligence and breach of contract.
[17] The submission was that “all issues” can extend widely,
to encompass not just claims but matters going beyond
claims. The agreement
was not limited to allegations of negligence and breach of contract, but
extended more widely than that.
“Howsoever arising” had a temporal
aspect. It applied not only to “howsoever” a claim might arise
under
any head of law, but also to claims, unknown to the parties, that might
arise later.
[18] I do not accept that this agreement can be read out of context in
the way proposed by the architect. Since the decision
of the Supreme Court in
Vector Gas Ltd v Bay of Plenty Energy Ltd,8 it has become
clear that agreements must be construed within their context. It is therefore
inappropriate to try to interpret an
agreement purely on its text, without
regard to the surrounding circumstances.
[19] The submission of the architect can be tested by taking a counter-example. As an extreme example, if following this settlement agreement the architect published defamatory statements about the plaintiffs, that would be an issue between the parties, “howsoever arising”. The words “including but not limited to all allegations of negligence and breach of contract” allow claims outside allegations of negligence or breach of contract. Taken literally therefore, the architect could
defame Ms Finnigan with impunity. Clearly that is absurd.
This settlement
7 McGowan v Hamblett [2007] 1 NZLR 120 (HC).
8 Vector Gas Ltd v Bay of Plenty Energy Ltd [2010] NZSC 5, [2010] 2 NZLR 444.
agreement was not intended to deprive Ms Finnigan of the right to
sue for defamation but taking the words literally,
without regard to the
context, can lead to that absurd result. Obviously it is necessary to
read this agreement within
its context.
The context of the agreement
[20] I start generally, and then look at the matter more narrowly. The agreement had its origins in Ms Finnigan’s project to build the house at 38 View Road. It arose out of the provision of services by the architect, in particular the design and specifications.9 The problem that arose in 2005 and 2006 was that the architect had not been paid all that it claimed it was entitled to. That situation is not unusual. Towards the end of any building project, those who provided services may claim that more is due to them than what they have been paid to date. Often their claims arise out of variations and extras on the job. In response, employers want to lower their
liability as much as they can. They will try to contend that there have been
short supplies, defects, delays or overcharging by the
service provider. They
will raise these arguments to cut down what they have to pay.
[21] In this case the matters raised by both sides were exactly of that
sort. The architect was claiming more than the initial
fee it had negotiated
for on the basis of variations and extra work which it said it had had
to carry out arising out
of additional instructions given during
construction. In response, Ms Finnigan contended that some of that was
necessary re-design
work to repair deficiencies in the architect’s
original work.
[22] Ms Finnigan also raised complaints that she had not signed any agreement with the architect. She complained of lack of detail in the architect’s invoices. She went on to complain about double-charging. She contended that there were errors in the plans supplied by the architect. A builder on the job, Mr Campbell, who seems to
have acted as a project manager, also made complaints about the
architect’s designs:
9 The architect stresses that it was required to provide only design services and not supervision.
The plaintiffs note that the architect did come on site occasionally after
the issue of the building consent. I am not required to
resolve that, but the
allegations in the statement of claim focused on alleged deficiencies in the
architect’s design, not
on inadequate supervision or observation of the
building work.
(2) Dumb waiter – no detailed finish of space around the dumb
waiter.
(3) Waste water from roof – no provision made for waste water from the
concrete terrace roof.
(4) Bath mixer set out – not included in plans and
specifications.
(5) Master bedroom – headboard needed changing.
(6) Lounge fireplace – as designed the lifter did not work.
(7) Track design for cedar shutters – inadequate plans.
(8) Stainless steel terrace roof garden rail required redesigned.
(9) Front door pivot hinges – top of door hit block lintel above
it.
(10) Wall between bedrooms 3 and 4 – needed amending for doors to fit. (11) Garage door – replacement needed.
(12) Kitchen door detail – could not be built as designed.
The architect, in turn, replied with evidence countering the complaints made
by
Ms Finnigan and Mr Campbell.
[23] The evidence of Ms Finnigan and Mr Campbell was in opposition to an application for summary judgment. The complaints went not only to the quantum of the architect’s claim – such as double-charging and excessive charging – but also the quality of the work provided by the architect. That was to raise matters that went to
abatement under the rule in Mondel v Steel10
or could be raised by way of equitable
10 Mondel v Steel [1841] EngR 61; (1841) 8 M & W 858, 151 ER 1288 (Exch).
set-off. These are matters of defence which would go to extinguish or reduce
any liability on a summary judgment application.
[24] The outcome is unsurprising – in fact, fairly typical for such
a dispute. Both sides had legal advice and I have no
doubt that each received
advice recommending that the matter be settled rather than go to hearing. For
both sides there would be
efficiencies in obtaining a settlement rather than
having a protracted dispute. For the architect, there would be uncertainty
whether
it could obtain summary judgment, given the kinds of issues raised by Ms
Finnigan and Mr Campbell. They are matters that would
not lend themselves
to ready resolution on an opposed summary judgment application. But,
likewise on Ms Finnigan’s
side, a long-term view would indicate to her
that there would be increasing costs in defending a relatively small claim, and
there
would be advantages in trying to resolve matters.
[25] Seen in that way, this dispute is little different from others that
arise towards the end of a construction project where
contractors and other
service providers want to get paid and there are disputes as to what is owed,
with the employer trying to reduce
the amount claimed. That provides the context
for the agreement.
[26] The wording of the letter of 10 May 2006 can be seen as settlement
of issues required as part of the “wash-up”
of the construction
project and of the architect’s part in it. The amount for which they were
to be paid for the job was to
be finally settled. Complaints that Ms Finnigan
might want to raise to avoid payment were now to be written-off, so that she
could
not raise new matters to resist payment. A fixed sum was agreed for
payment. The terms of payment were fixed. That was the context.
[27] The terms of payment were drawn so as to prevent Ms Finnigan raising
new matters, between the time of the agreement and the
time for payment, to
again avoid payment.
[28] Now for the claim for design defects leading to water-ingress
problems. It is necessary to bear in mind that such problems
take time to show
up. It is not just a case of an occasional leak but the fact that rot can set
in over time, which can lead to
major problems. Experts are required to
identify problems arising out of water ingress, to establish the scope of any
defects and
resulting damage, and to assess whether there can be any liability
attaching to any of those associated with the construction and
design of the
building. Expertise is needed to know whether alleged defects can result
in breaches of the Building Code.
[29] It is not suggested that any of those matters could have been
appreciated by either side at the time of the agreement of
10 May 2006. The
architect did not suggest that this was a known problem at the time of the
agreement of 2006. Neither Ms Finnigan
nor Mr Campbell identified that as a
problem in May 2006.
[30] The architect says that in this agreement Ms Finnigan was not just
squaring up what she ought to pay to the architect for
outstanding work, but had
given away a claim for over half a million dollars. Both the Court of
Appeal’s decision in Tag Pacific Ltd v The Habitat Group Ltd and
the House of Lords’ decision in Bank of Credit and Commerce
International SA v Ali say that parties can competently contract to
give a release for claims of which they know nothing. Both the majority in the
House
of Lords and the Court of Appeal in Tag Pacific said that such an
intention would be found if clearly demonstrated by the words used. I do not
regard the words used as clearly demonstrating
an intention to oust an unknown
claim for a leaky building for which the cost of repairs has gone to
$650,000.
[31] Ms Keating sought to establish that there was a common thread between the complaints raised by Mr Campbell in 2006 and the complaints against the architect in this proceeding. She made the point that Mr Campbell complained about lack of detail in the plans. She noted that on his evidence Mr Campbell had undertaken work himself because he did not have sufficient detail or information to go from the plans provided by the architect. Ms Keating pointed to the pleadings against the architect and noted that complaints were of insufficient detail and insufficient
information, rather than incorrect design. She therefore said that
there was a common complaint underlying matters raised
by Mr Campbell and the
matters in the statement of claim.
[32] I prefer instead the evidence of Mr Medricky on that issue. Mr
Medricky, the building consultant, has given an affidavit
considering the
defects identified in 2006 and has compared them with his own inspection of the
premises in 2009 and with the pleadings.
He finds that the matters raised by Ms
Finnigan and Mr Campbell were by and large superficial. Two matters he dealt
with separately
were wastewater from the roof and a stainless steel terrace roof
garden rail. But he makes the point that those are not related
to
weathertightness issues. His evidence is that the plaintiffs’ proceeding
now is based on weathertightness issues, not
on the matters raised by Ms
Finnigan and Mr Campbell in their affidavits of 2006. It is arguable for the
plaintiffs that there is
not the common thread which Ms Keating tries to draw
between the defects raised in 2006 and the defects in the pleading.
[33] The architect has not adduced any evidence to refute Mr
Medricky’s evidence. It probably would not have
been useful to do so
because, in a summary judgment application, the court is unlikely to resolve
differences between expert witnesses.
Outcome
[34] On the interpretation I have given to this settlement agreement, I find that it is arguable for the plaintiffs that the matters raised in this proceeding are outside the matters settled in the agreement of May 2006. Accordingly, because the plaintiffs, in my view, have an arguable case against the second defendant, notwithstanding the agreement of May 2006, I cannot find that the architect has a watertight defence. I dismiss the application for summary judgment, and I dismiss the application to strike out the statement of claim against the second defendant.
[35] I make an order for costs in favour of the plaintiffs
against the second defendant on a 2B basis. I expect counsel
to be able to
agree costs but if they cannot memoranda may be filed. The party filing
submissions second should file them within
five working days of the first
party’s submissions.
...........................................
R M Bell
Associate Judge