![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 16 July 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2014-404-1182 [2014] NZHC 1454
UNDER
|
THE UNIT TITLES ACT 2010
|
BETWEEN
|
BODY CORPORATE 341188
First Plaintiff
DARREN COTTINGHAM AND MICHAEL ELLIOTT as trustees of the LINCOLN
TRUST
Second Plaintiffs
|
AND
|
STEPHEN ROBERT KELLY AND THE FINAL HARGREAVES TRUST COMPANY LIMITED
First Defendant
ALLENBY GROUP NZ LTD Second Defendant
SOCIAL IMPACT STRATEGIES LIMITED
Third Defendant
|
Hearing:
|
17 June 2014
|
Appearances:
|
P K McGrath & T M Bates for plaintiff applicants
T Bowler for the first and third defendant repondents
|
Judgment:
|
26 June 2014
|
JUDGMENT OF WINKELMANN J
This judgment was delivered by me on 26 June 2014 at 3.00 pm pursuant to
Rule 11.5 of the High Court Rules.
Registrar/ Deputy Registrar
BODY CORPORATE 341188 v KELLY [2014] NZHC 1454 [26 June 2014]
[1] The respondents are building on the roof of an existing apartment building in Hargreaves Street, St Mary’s Bay, converting “future development units”1 they own into residential apartments. Beneath the development site are four floors of residential apartments. The first applicant is the body corporate for the apartment building, and the second applicants are the registered proprietors of one unit in the apartment building. The applicants say the respondents’ construction work has
caused damage to the building, allowing water to enter the structure of the building when it rains, and some of the apartments beneath the construction zone. The applicants allege that the respondents should have taken steps to ensure the building remained watertight before they began building, and that their failure to do so is negligent, a nuisance and a breach of their obligations under the Unit Titles Act
2010.
[2] As a result of the water ingress, the applicants say that the body
corporate’s insurer has now excluded all cover
for water damage claims,
and for any claims arising from the respondents’ construction work. It
has also signalled its intention
to withdraw all cover from 30 June 2014 if the
building is not watertight by then. The applicants also allege that the leaks
caused
by the respondents have caused physical damage to the building and to
some apartments.
[3] The applicants seek an injunction:
1. Restraining the respondents from carrying out any construction
work to any part of the apartment building until the trial
of this
action.
2. Restraining the respondents from transferring any interest in
future development units to any other party, as such a transfer
may defeat the
restraint of work.
3. Allowing the applicants or their agents to enter the respondents’
units
on level 5, between 9 am and 5 pm Monday to Saturday to make level
5 watertight.
1 In terms of the Unit Titles Act 2010, a future development unit is a unit proposed for development at a later stage of the development, that is shown on a stage unit plan as a future development unit.
[4] There is some procedural history that must be traversed to make
sense of the point now reached in this proceeding. The
application for
injunction was initially called before Andrews J on 22 May 2014. At that time
she made an order restraining any party
other than Supercity Interiors from
carrying out work on the buildings. Supercity Interiors was the
respondents’ builder on
site. The Judge was satisfied that the builder
had a public liability policy in place which would respond in the event of any
unforeseen
circumstance, so that it should be able to continue work. She also
restrained the respondents from transferring any interest in
the
respondents’ units.
[5] The application for interim injunction was listed for argument
before me on
28 May 2014. At that time the respondents’ position was that although
there had
been leaks in the past, these had been addressed with temporary
waterproofing.2
They argued they should be allowed to continue work on the roof because it
was in everybody’s interests that they close the
roof in to waterproof the
building. Once the roof was closed in, there was no need to construct a
waterproof membrane above the
construction site. The applicants responded
with evidence that the leaks were ongoing and that a roof on its own would
not waterproof the site. In submissions counsel for the applicants doubted the
respondents’ ability to complete the roof as
quickly as they estimated
— they said previous time indications given by the respondents had been
very inaccurate.
[6] After discussion with counsel it was agreed I would appoint an
expert to report to me on the following questions:
1. Does construction on level 5 allow water ingress into the
structure of the building, and/or the units below? It is common
ground that
water ingress has occurred in the past. The issue is whether there is ongoing
potential for water ingress.
2. Is there adequate waterproofing on the construction on level 5 to
prevent water ingress into the building at any level?
3. Does construction need to stop to enable –
(a) existing water ingress issues to be addressed, and
(b) to allow any existing damage caused by water ingress to be assessed and
addressed?
4. What is the best way to make the building weather
tight as soon as possible (noting that the applicants’ case is
that
construction of a waterproof membrane over the site is necessary, and it is the
respondents’ case that the roof needs
to proceed as quickly as
possible);
5. Is there any other step the expert recommends to protect the
building from water ingress during the course of construction?
[7] With the consent of the parties I appointed Mr Neil Alvey from
Kaizon Ltd and adjourned the proceeding to the next day 29
May 2014 to await his
report.
[8] In brief, Mr Alvey reported that the construction on level 5
continued to allow water in to the structure of the building
and had allowed
water into apartments. He identified the main areas of concern as
follows:
- removed or altered parapet cap flashings;
- areas of the roof membrane that had been penetrated in order to provide
fixings to secure temporary weather proofing;
- damage to seals and joints within parapet cap flashings which had been
altered to accommodate the new structure;
- exposed parapet upstands where cap flashings and membrane had been
removed;
- retained timbers following removal of previous construction being not fully
protected by shrinkwrap;
- new construction above retained construction where shrinkwrap is provided
between the two elements;
- exposed ply sections inadequately sealed where investigation of the
structure below has occurred;
- new timber frame construction fixed directly through existing membrane;
- abutment of new construction and retained internal linings where protected
by building wrap;
- abutment of new construction and retained construction where protected by a
tarpaulin and polythene with duct tape;
- where scaffolding penetrates the temporary weather proofing;
- where insufficient, damp proof material was provided beneath
new construction built directly off retained construction;
- to the location of new timber construction directly in front of the
retained parapet where previous handrails were cut off;
- voids within the new timber frames;
- voids within the shrinkwrap;
- exposed building wrap and voids between the external cladding to the outer
face of the previous parapet;
- the exposed void between the retained timber parapet and the
vertical cladding face following the removal of the cap flashings;
and
- retained timbers with void between left exposed and unprotected following
removal of previous construction.
He detected high non-invasive moisture readings from the external lounge wall
of one of the apartments, and elevated non-invasive
moisture readings obtained
from previously repaired ceilings.
[9] Mr Alvey concluded there was not adequate waterproofing on level 5 to prevent water entering into the building. He said construction needed to stop to enable inspection of existing water ingress issues to take place, and damage to be assessed and addressed. He said that the best solution for the issue was a shrinkwrap
membrane, placed around scaffolding, which would encapsulate the existing
construction area. He provided specifications for the necessary
shrinkwrap.
[10] Following receipt of Mr Alvey’s reports, the parties were able
to negotiate and agree the form of orders which should
be made. On that basis
I made the following consent orders on 30 May 2014:
1. That the first and third respondents will ensure that by 5 pm on
Tuesday 3 June temporary protection via tarpaulins is
provided to all areas
currently allowing water ingress including the deck areas where cut outs
and/or penetrations have been
made in the course of the respondents’ work
on Level 5 of the building at 21 Hargreaves Street, St Mary’s bay,
Auckland
(“the Building”) to the satisfaction of the Court appointed
expert, Mr Neil Alvey. On 4 June, Mr Alvey is to report
to the Court as to
whether or not he approves of the tarpaulin installation;
2. The first and third respondents will obtain quotes for a comprehensive shrinkwrapping and scaffolding contract based upon the plan at Appendix B to Mr Alvey’s evidential report of 29 May
2014 (“Shrinkwrap Plan”) by 5 pm on Friday 6 June 2014. The
Shrinkwrap Plan is to be provided to the quoting contractors. The quotes are
to include structural and engineering design for uplift,
and specify lead time
(to commencement of works), and contract duration to completion of works.
The quote should provide
aforementioned information for a particular scope of
works which requires shrinkwrap to be bought up to the (to be built) roofline
(“the Reduced Shrinkwrap Plan”). The first and third respondents
may continue with the install of the roof/s until
5 pm on 11 June 2014;
3. Pending further order of the Court, no work is to be carried out
to the external envelope on level 5 of the Building other
than installation of
the roof/s. The roofing work (if still incomplete) is to cease by 5pm on
Wednesday 11 June. Any roof that
is not complete is to be protected by
shrinkwrap in accordance with the Shrinkwrap Plan. The order made on 22 May 2014
by Justice
Andrews that only Super City Interiors Limited may carry out work on
the respondents’ units is rescinded;
4. By 5pm on Monday 9 June Mr Alvey will recommend at least two
shrink wrap quotes, one of which must be accepted by the first
respondents who
must engage a shrinkwrap contractor as per the relevant quote by 5pm Wednesday
11 June and provide a copy of the
contract/terms of engagement to the applicants
contemporaneously;
5. During the shrinkwrapping, Mr Alvey will visit the site and report to the Court at weekly intervals as to whether the weather protection is proceeding to his satisfaction/in accordance with the program, and will provide a further report at the end of the works as to whether it has been properly completed;
6. The first and third respondents must pay all contractors involved
in the completion of the Shrinkwrap Plan by the due date
in accordance with the
contractors’ terms and provide proof of payment to the applicants within
24 hours of the due date;
7. Before the works are completed, Mr Alvey will provide a report as to what (if any) water ingress issues and/or damage exist at levels 4 and
5 of the Building, their cause/s, and what is required to remedy any
damage;
8. Following receipt of Mr Alvey’s report, the proceeding
will be brought back for mention before Her Honour
to decide what further
orders may be necessary. Until then the proceeding is adjourned and the
respondents are not to carry
out any work on the external envelope
apart from the roofing and shrinkwrap work referred to in these orders;
9. Mr Alvey’s costs for investigating and reporting as to water
ingress and damage are to be paid 50/50 by the applicants
and the first/third
respondents severally in the first instance, and these costs will then become
costs in the proceeding;
10. The interim order made on 22 May 2014 restraining the respondents
from transferring any ownership interests in the respondents’
units
pending further order of the Court, remains in place, but it is noted that the
order does not restrict the respondents’
ability to refinance;
11. Leave is reserved to apply to the Court on 48 hours notice;
12. Costs reserved.
[11] Following the making of these orders, there have been significant developments that have caused the applicants to renew their original application for an interim injunction pursuant to the leave reserved to apply. They say that the respondents have breached the consent orders. Although the respondents undertook the initial temporary waterproofing, it is not disputed they failed to meet the timetable for the provision of quotes for shrinkwrapping for the building and that this has delayed the implementation of the shrinkwrap waterproofing solution. It is also not in dispute that there have been further leaks in the intervening period. Counsel for the respondents say that the respondents’ delay was due to confusion as to whose responsibility it was to obtain quotes. I do not accept this explanation. Mr Kelly, the first respondent, and a director of the second respondent was actively involved in negotiating the consent orders. It is clear to me he was aware of his obligations under them.
[12] The respondents also say that the leaks are not attributable to
anything they have done since the temporary waterproofing
was put in
place. They say that although they installed the temporary waterproofing
stipulated by Mr Alvey, it blew off in
the strong winds that hit Auckland during
an extreme weather event. They point to the deterioration of the roofing
membrane on the
roof of the apartment blocks, away from the construction
zone.
[13] The applicants say that the leaks are entirely due to the
fact of the construction work. They say that in the
course of the
respondents’ race to finish the roof, they removed the temporary
waterproofing. Although the applicants accept
there were leaks through the
existing roof membrane in an area outside the construction zone, they say that
the foot traffic caused
by the construction work, and other damage inflicted by
the workmen, caused the leaks.
[14] The respondents also sought to vary the consent orders to enable
them further time to complete the roof. The respondents
said in support of that
application that the extreme weather event had caused delay in the roofing
programme. Following a telephone
conference to discuss developments I
declined the respondents’ application for variation and directed that
the
applicants’ renewed application for injunction be listed before me on
17 June 2014. I asked Mr Alvey to attend at the hearing
to assist me with
issues that arose.
[15] During the course of the 17 June hearing the respondents offered to consent to orders that they stop work on the exterior of the building, and to shrinkwrap promptly the building in accordance with a detailed quote obtained. This quote accorded in nearly every respect with Mr Alvey’s specifications but allowed them to continue with the roof. They also offered to retain suitable project management skills on the site. The applicants were not content with the proposed consent orders. They maintained their application for an order restraining the respondents from undertaking any further work on the site pending the substantive hearing. They also maintained their application for an order that they be authorised to conduct the shrinkwrap work themselves.
[16] In support of this position Mr McGrath expressed the concern that
the work on site was not being conducted in an adequate
fashion, citing as
evidence of the lack of competence the evidence of ongoing leaks which suggested
that contractors were not adequately
mindful of the need to maintain water
tightness of the existing apartment buildings. He also pointed to what he said
was an example
of unsafe work practices. One of the apartment owners
filed an affidavit recounting an incident on 12 June 2014 when
a large piece
of 6 x 2 landed on his terrace. This was a serious incident. It could have
seriously injured, perhaps killed, someone
standing on the terrace. Fortunately
nobody was on the terrace when the piece of wood fell.
[17] Ultimately I was satisfied the consent orders offered by the
respondents were adequate to respond to the legitimate concerns
of the
applicants. Because the applicants were not prepared to agree to the
resolution offered by the respondents, I set out my
reasons for making the
orders I made on the day, and for not making the order sought by the applicants
restraining the respondents
from further work on-site until the substantive
hearing, and allowing the applicants to engage, pay for and supervise the
shrinkwrappers.
Principles applying where mandatory interim injunction
sought
[18] The framework for analysis of an application for interim injunction
is as follows:
(1) Is there a serious question to be tried?
(2) Where does the balance of convenience lie between the
parties?3
(3) Having regard to the earlier two factors, where does the
overall justice lie?
[19] In Roseneath Holdings Ltd v Grieve the Court of Appeal
discussed the object of an interim injunction as follows:4
The object of an interim injunction is to protect the plaintiff from harm
occasioned by any breach of rights, that is the subject
of current
litigation,
3 American Cyanamid Co v Ethicon Ltd [1975] UKHL 1; [1975] AC 396 (HL); and Klissers Farmhouse Bakeries
Ltd v Harvest Bakeries Ltd [1985] 2 NZLR 129 (CA).
4 Roseneath Holdings Ltd v Grieve [2004] 2 NZLR 173 (CA).
for which the plaintiff might not be adequately compensated by an award of
damages by the court, if successful at the trial. Against
that object it is
necessary to weigh the consequences to defendants of preventing them from acting
in ways which the trial may determine
are in accordance with their rights. The
well established two stage approach to addressing applications for interim
injunctions involves
first, ascertaining whether there is a serious question to
be tried and secondly, considering the balance of convenience if the relief
sought is granted.
Serious question to be tried
[20] The applicants have framed their case as follows.
Section 80 of the Unit Titles Act 2001
[21] The applicants say that the respondents have breached each of s 80(1)(g), (h) (i) and (j) of the Unit Titles Act 2010. Sections 80(1)(g)–(k) of the Unit Titles Act
2010 provides that principal unit owners:
(g) must repair and maintain the unit and keep it in good order to
ensure that no damage or harm, whether physical, economic,
or otherwise, is, or
has the potential to be, caused to the common property, any building element,
any infrastructure, or any
other unit in the building:
(h) must notify the body corporate of his or her intention to carry
out any additions or structural alterations before the
commencement of any
work:
(i) must not make any additions or structural alterations to the unit
that materially affect any other unit or the common
property without the written
consent of the body corporate:
(j) must comply with the body corporate operational rules:
(k) must not do anything that breaches or in any way undermines any
policy of insurance in the name of the body corporate.
[22] The applicants say s 80(2) extends the application of s
80(1) to the respondents because the future development
units on the 5th floor
are “in use as a place of residence or business or
otherwise”.
[23] The respondents say that s 80(1) does not apply because “otherwise” does not include occupation by builders, relying upon a determination in Mr Kelly’s favour in the Tenancy Tribunal that the word “otherwise” in s 121 of the Unit Titles Act did not encompass occupation for building purposes.
Negligence
[24] The applicants submit that this is a case where:
(a) it was reasonably foreseeable that the applicants and other owners would
suffer harm if the respondents were careless;
(b) the relationship between the applicants/other owners and
the respondents was sufficiently proximate to give rise
to a duty of
care;
(c) there are no relevant policy considerations that might militate against
the imposition of such a duty; and
(d) the duty of care has been breached as set out in affidavits supplied by
the expert retained by the applicants, Mr Wiemann.5
Nuisance
[25] The applicants submit that the respondents have carried out the
building work in a manner which has created an unreasonable
interference with
the applicants’ right to use or enjoy their interest in the property.
This is a case where physical damage
to property has been caused, as opposed to
mere discomfort or inconvenience. The applicants emphasise the strict
liability nature
of the tort of nuisance and in particular that it is no excuse
for the defendant to say that reasonable precautions were taken. They
also note
that an injunction is the usual remedy in a case of nuisance.
[26] The respondents reply to the nuisance and negligence causes of action that the onus is on the applicants to establish that they have a case in nuisance and/or negligence and that they cannot meet the test because the Council has inspected and signed off the works. They say that in a case where a mandatory injunction is sought, as here, the applicants must show a strong case.
Analysis
[27] As to whether or not there is a serious question to be tried, Fisher
J in Peters v Collinge stated: 6
The plaintiff need not finally prove his case today but his evidence must
take matters to the point that a seriously arguable case
has been demonstrated.
This requires a consideration of the affidavit evidence and then by
application of the law.
[28] In this case it is not seriously disputed by the
respondents that the respondents’ works have allowed water
to enter the
fabric of the building and some of the existing apartments in the apartment
block. On the evidence before me it is
not capable of credible dispute that
this is an ongoing problem. The respondents have attempted to argue that
these incidents
have been caused by two extreme weather events and that
temporary measures have met the concern. However the applicants’
evidence, not rebutted by the respondents, demonstrates ongoing leaks, occurring
outside the time frame of extreme weather events.
This is corroborated by Mr
Alvey’s investigations. It is true that the temporary weather protection
designed by the Court
appointed expert would likely have prevented leaks from
the construction area. However during the course of the hearing on 17 June,
Mr
Alvey was invited to give evidence (with the consent of both parties). He said
he had inspected the site following the last
extreme weather event, and his
assessment was that the respondents had removed some of that temporary weather
protection in their
rush to complete the roofing and that this had allowed
further leaks.
[29] As to the legal principles, I also have no difficulty in finding that there is a serious question to be tried in connection with the negligence and nuisance causes of action. The evidence establishes there is a seriously arguable case that work being undertaken by the respondents on the roof of the apartment building caused the leaks which in turn caused both physical damage. Although issues of foreseeability, duty and breach can only be determined at trial there seems to be a good argument that there is sufficient proximity for the purposes of a negligence cause of action, and no public policy reasons which would undermine the imposition of a duty. The case for
nuisance may be simpler to establish because of the strict liability aspects
of that cause of action.
[30] I also consider that there is a serious question to be tried that
the duties imposed by s 80(1) do apply to the respondents.
The interpretation
applied by the Tenancy Tribunal adjudication to the words “or
otherwise” may not be simply
transferable to s 80(2), as the
respondents would have it. These expressions sit in different parts of the Act,
within provisions
that have different purposes. There is at least a serious
question whether “otherwise” in s 80(2) encompasses use for
construction work. If it does then s 80(1) applies. For these reasons the
first question, of whether there is a serious question
to be tried, is answered
in the affirmative.
Balance of convenience
[31] As to what is meant by the balance of convenience, May LJ observed
in Cayne v Global Natural Resources pl7 that although the
phrase may well be substantially less elegant, a better description of the
process is a consideration of the “balance
of the risk of doing an
injustice”. Relevant considerations include the adequacy of damages for
the applicant or respondent,
consequences for third parties, a consideration of
the steps most likely to preserve the status quo, the conduct of the parties and
the relevant strength of each party’s case as revealed by the affidavit
evidence.
[32] Particular considerations come into play where, as here, a mandatory injunction is sought. A mandatory injunction is one that requires a person to do a particular act or thing. Special circumstances are usually required before a mandatory interim injunction will be granted. This is particularly so where the mandatory interim injunction will deprive the unsuccessful party of all the normal safeguards that will ensure a fair hearing. The Courts are reluctant to grant mandatory injunctions where the form of obligations imposed are imprecise, and
potentially require ongoing supervision by the
Courts.8
7 Cayne v Global Natural Resources plc [1984] 1 All ER 225 (CA) at 237.
8 Morton v Eltham Borough [1961] NZLR 1 (SC); and Co-op Insurance Society v Argyll Stores
(Holdings) [1997] UKHL 17; [1998] AC 1 (HL).
Adequacy of damages
[33] Damages are not an adequate remedy for the applicants in this case.
The apartment owners should be able to enjoy their residential
units free of
leaks and the ensuing damp environment. The applicants’ evidence also
establishes that the issue of watertightness
must be addressed to ensure that
the applicants’ insurance position is not detrimentally
affected.
[34] Conversely, if the respondents’ building works are delayed for
a month, they will incur financing costs, but these
can be met with an award of
damages.
Status quo
[35] The erection of a shrinkwrap waterproof membrane is clearly
consistent with the maintenance of the status quo. Allowing
ongoing leaks into
the building could cause further damage to the apartments, and damage to the
fabric of the building itself.
It is the opinion of Mr Alvey that the
best way to make the building weathertight as soon as possible is to erect
a
shrinkwrap cover.
[36] During the course of the hearing Mr Alvey agreed that the
construction needed to stop to allow further identification
of water ingress
issues and addressing of the causes and the damage. The evidence suggests that
a stop work for these purposes
is necessary to maintain the status
quo.
[37] The respondents have agreed that they should stop work while that shrinkwrap is being put in place, and also until Mr Alvey has had the opportunity to undertake a further inspection of the site to identify ongoing water ingress issues, and to identify damage that needs to be rectified. However the applicants are not content with this proposal, and persist in their application to have construction on the site stopped pending substantive hearing. I asked counsel for the applicants to articulate the basis on which the applicants can have a legitimate interest in a stop work until hearing if watertightness issues are addressed. He says it is on the basis that the work being done by the respondents is sub-standard, and that the applicants have health and safety concerns given the incident with the falling piece of wood.
[38] The evidence before me does not raise a serious issue that the
buildings themselves will be leaky once work has finished.
The evidence is not
directed to that. I note the evidence that the Auckland City Council has been
involved in signing off work
along the course of the construction. The
respondents have agreed to retain a project manager with suitable construction
experience.
[39] I also take into account, as I must, that a long term stop work is a
substantial interference with the respondents’
rights. The
respondents’ evidence is that it will cause them substantial loss, and
imperil the finance for the project.
[40] The applicants wish to undertake the shrinkwrapping themselves.
However the orders I made contain sufficient safeguards
to ensure the
respondents move quickly to get the work needed underway. Should there be
further delay the applicants will have
a strong argument for this further
incursion into the respondents’ rights, but I am satisfied at this point
the orders I made
strike an appropriate balance.
[41] There was also a suggestion during the hearing that the respondents
should be required to cover the roof membrane outside
the construction zone with
shrinkwrap, because their actions had caused the membrane to deteriorate. I
have considered the evidence
of Mr Wiemann the applicants’ expert, and the
views expressed by Mr Alvey. Although some deterioration is no doubt the
respondents’
responsibility, it is clear on the evidence available at this
point that the membrane is past its useful life. The applicants would
need to
address this whether or not the respondents were doing the work. I do not
consider the obligation to shrinkwrap this area
should be imposed on the
respondents. The applicants do not need the Court’s permission to
waterproof the zone. They are
free to do so, and who should bear the cost can
be determined at the substantive hearing.
Conduct of parties
[42] The respondents raise delay on the part of the applicants as a factor weighing against the grant of injunctive relief. From the narrative emerging from the affidavits, I am not satisfied there has been any unjustified delay on the part of the applicant. Any delay in their bringing this issue to court has been caused by their attempts to resolve reasonably issues with the respondents. It is to their credit that
they took such steps before bringing the matter before the Court. In any
case, there is no evidence that delay has in any way prejudiced
the
respondents.
Overall justice
[43] Taking a step back and looking at the overall justice of
the situation, I consider the overall justice favours
the grant of the orders
as made, and not the more extensive orders the applicants seek. On the evidence
before me the applicants
have strongly arguable causes of action against the
respondents — the respondents should have taken steps to waterproof the
building site before commencing construction, and their failure to do so has
caused harm to the applicants. I have no hesitation
in concluding that
injunctive relief should be granted to require the respondents to create a
shrinkwrap solution for the building.
[44] Result
[45] Having heard argument therefore I granted orders in the following
terms:
1. The respondents are to undertake urgently (no later than 5.00 pm,
18
June 2014) remedial work to the temporary waterproofing to reinstate the
waterproofing which Mr Alvey previously directed.
2. (a) The respondents are to engage Scaf-Wrap to undertake the
programme of works to create shrinkwrapping of
the property in
Hargreaves Street. That engagement is to be on the basis that the programme is
to be in accordance with the Scaf-Wrap
quotation (noting it will not commence
until toward the end of the week commencing 16 June, and to be completed by 27
July 2014 –
weather permitting) and in accordance with the Millic Auckland
Ltd detail 1 and 2 provided in support of that quotation.
(b) The respondents are to pay the shrinkwrap contractors by the due date and provide proof of payment to the applicants within 24 hours of the due date.
3. The stop work on all work on the site is to continue in force,
with the exception of the remedial work to temporary
waterproofing, until
further order of the Court.
4. Following completion of the shrinkwrapping the respondent
is to engage the shrinkwrapping company Scaf-Wrap to
attend at site twice
weekly, Tuesdays and Fridays, to ensure that the shrinkwrapping protection
remains adequately in place.
5. Once the respondents advise that the shrinkwrap is
complete, Mr Alvey is to return to the site to check
completion of
the shrinkwrapping and investigate the new water ingress issues that have
occurred since his last report. He is
to report as to:
(a) Whether he is satisfied that the shrinkwrapping has been completed in
accordance with specifications.
(b) The cause of that water ingress and identify any remedial work
necessary.
6. The respondents are to engage a project manager with
suitable building qualifications in time to take charge of
any resumed work by
the respondents on the site.
7. The interim order restraining the respondents from transferring
any ownership interests pending further order of the Court
remains in place,
with the proviso that the respondents may grant security interests in
their ownership interests for the
purpose of refinancing.
8. The parties have leave to apply on 48 hours’ notice.
9. The costs of this application are reserved.
[46] On receipt of confirmation of the appointment of a project manager,
and receipt of Mr Alvey’s report, I will release
the respondents to
continue the construction work if satisfied at that point as to weathertightness
issues.
[47] I record that if Mr Alvey is not available to undertake the
investigations and prepare the report mentioned in these orders,
his assistant
Mr Brooks may undertake that inspection work on his behalf. He will do that in
accordance with Mr Alvey’s directions.
This is necessary as Mr Alvey has
signalled that he will be absent from New Zealand for a period of time in the
near future.
[48] The costs of the shrinkwrapping are to be costs of the respondents
initially. Which party should ultimately bear those costs
will be determined in
the proceeding.
[49] The ongoing costs of Mr Alvey’s and his assistant attending on site to check that the shrinkwrapping is completed appropriately and to check for any water ingress cause and identify remedial steps, are initially to be borne 50/50 between the applicants and respondents but ultimately to be costs in the proceeding. Each of the applicants and respondents are to pay by 5.00 pm 2 July $9,000 security for those costs, and also as security for the costs of Mr Alvey’s earlier work in relation to identifying causes of water ingress and the necessary remedial steps.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/1454.html