![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 5 August 2014
IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY
CIV-2013-442-000174 [2014] NZHC 1574
BETWEEN
|
IAN WALTON DAVEY, NOVA
ELIZABETH DAVEY and CARL JORGENSEN
First Plaintiffs
|
AND
|
IAN WALTON DAVEY and NOVA ELIZABETH DAVEY
Second Plaintiffs
|
AND
|
NICHOLAS DE CHAIR BAKER Defendant
|
AND
|
NORMAN MICHAEL PAVELKA First Third Party
|
AND
|
SELWYN RAYMOND COLWELL LIGHT
Second Third Party
|
Hearing:
|
23 June 2014
|
Appearances:
|
G W Allan for Plaintiffs
G M Downing for Defendant
G J Praat for Second Third Party
No appearance for First Third Party
|
Judgment:
|
7 July 2014
|
JUDGMENT OF ASSOCIATE JUDGE MATTHEWS
[1] This case concerns a right of way easement over the defendant’s
land, in
favour of land owned by the plaintiffs.
[2] On 17 February 2014 the Court granted leave to the plaintiffs to file a second amended statement of claim, to include a cause of action based on rectification of the
easement. A second amended statement of claim was then filed, and a
statement of
DAVEY v BAKER [2014] NZHC 1574 [7 July 2014]
defence followed. Shortly after that, within a period of 10 working days,
the defendant filed and served third party notices against
Mr N M Pavelka, the
first third party, who owned the property now owned by the defendant at the time
the easement was created, and
against Mr S R C Light, the surveyor who acted in
relation to creation of the easement.
[3] The plaintiffs apply to set aside the third party notices, under r
4.16(2). The relevant parts of r 4.16 are these:
4.16 Setting aside third party notice
(1) ...
(2) A party to a proceeding served with a third party notice issued and
served without leave of the court may apply to the court
to have the notice set
aside.
(3) In either case, the court may –
(a) set the third party notice aside and dismiss the defendant’s
statement of claim against the third party –
(i) on the merits; or
(ii) without prejudice to the right of the defendant to pursue that
claim against the third party in an independent proceeding;
or
(b) give other directions.
[4] The defendant opposes the application. Neither third party has
taken any steps on this application, but each has filed
a statement of defence,
in which each pleads as a positive defence that each claim now brought by the
defendant is statute- barred.
[5] When considering an application under r 4.16 the Court is to have regard to r 4.4(1) which sets out four circumstances in which a third party notice may be issued.1 Rule 4.16 does not require the Court to be confined to the circumstances set out in r 4.4.2 Even if a third party notice is properly issued under one of the sub- paragraphs in r 4.4(1), it may still be set aside under r 4.16. A defendant cannot
insist that a third party be joined to a proceeding as of
right.3 Broader considerations, such as convenience and
overall justice, may separately justify an order setting aside a third party
notice.4 Factors for consideration when assessing the overall
justice of a case may include the strength of the claim against a third party,
delay to the plaintiff ’s proceeding, and whether the lengthening of the
trial brought about by additional parties being involved
is outweighed by such
positive aspects as allowing all issues arising from a certain fact situation to
be determined at the same
time.
[6] Mr Downing says that the defendant has brought each third party
proceeding on the basis that each fits within sub-paragraphs
(c) and (d) of r
4.4(1). These provide:
(c) that a question or issue in the proceeding ought to be determined not
only between the plaintiff and the defendant but also
between –
(i) the plaintiff, the defendant, and the third party; or
(ii) the defendant and the third party; or
(iii) the plaintiff and the third party:
(d) that there is a question or an issue between the defendant and the
third party relating to, or connected with, the subject
matter of the proceeding
that is substantially the same as a question or an issue arising between the
plaintiff and the defendant.
[7] Mr Allan says that neither of the claims against the third parties
is within either of these paragraphs, that in any event
each claim is
statute-barred, and that the claims should not be allowed to lengthen and
increase the cost of the plaintiffs’
proceeding. Mr Downing says that
neither claim is statute-barred, each of the third parties would be a
witness at the trial
in any event, and that the trial of the
proceeding would not be delayed or lengthened.
[8] The issue in this case is whether, in relation to each of the third party claims, it is within the ambit of paragraphs (c) and (d) and whether, if it is, it should nonetheless be set aside in the circumstances of this case.
[9] For completeness, Mr Allan says that each third party notice should
be set aside without prejudice to the right of the defendant
to pursue his claim
against that party in an independent proceeding.
The causes of action in the second amended statement of
claim
[10] In the second amended statement of claim the plaintiffs plead an
agreement between the first-named plaintiff, Mr I W Davey,
and the first third
party, Mr N M Pavelka, on the line that the agreed right of way was to follow.
In their first cause of action
the plaintiffs seek rectification of the easement
which was subsequently created, to reflect the agreed line the easement should
follow. Mr Allan says that the plaintiffs will bear all costs associated with
this exercise.
[11] In their second, and alternative, cause of action the plaintiffs
plead that the easement is a restrictive covenant, the burden
of which for both
the plaintiffs and the defendant is, or is likely to be, increased as a result
of the position of the easement
because the cost of maintaining it is likely to
be higher, given the instability of the land over which it has been created. It
is said that the easement should be modified, and the proposed modification
would reduce those burdens. It is said that the modification
is necessary,
for stated reasons. The plaintiffs claim an order that the easement be modified
by relocating it to a different area
on the defendant’s land. Again, Mr
Allan says that the plaintiffs will bear the cost.
[12] In their third, and alternative, cause of action the plaintiffs
plead that the defendant has allowed trees to obstruct the
plaintiffs’
ability to use the existing easement, and that the defendant is obliged to
remove the trees and to take certain
other steps so the easement can be used.
They seek orders to that effect.
[13] In their fourth cause of action the plaintiffs plead numerous breaches by the defendant of the implied term in Schedule 4 cl 14(b) of the Land Transfer Regulations 2002 to meet and in good faith try to resolve the dispute between the plaintiffs and the defendant. They seek $75,000 by way of damages for breach of this obligation.
[14] In their fifth statement of claim the plaintiffs seek aggravated
damages as a result of the conduct relied on in the fourth
cause of action. In
my view the fifth cause of action is not a separate cause of action. It is a
further claim for relief on the
fourth cause of action, and I treat the two
causes of action as one for present purposes.
The claim against the first third party
[15] The defendant says the first third party owed a duty of care (of
unspecified ambit) to subsequent purchasers of the servient
land (which include
the defendant). He says that the first third party failed to ensure that the
right of way easement followed the
line of the existing track on the property
and/or the most practicable and obvious route over the property (where the track
was indefinite),
that he failed to properly instruct the surveyor and/or failed
to ensure that the surveyor’s plans achieved what he had agreed
with the
plaintiffs, and that he failed to ensure that the subdivision application which
created the right of way achieved what he
had agreed with the plaintiffs. He
says that these failures constituted a breach of the duty of care. He says he
only became
aware of the first third party’s negligence, as he describes
it, when the plaintiffs filed this proceeding.
[16] The defendant then says that if the Court makes any order
against the defendant in favour of the plaintiffs there
should be an order that
the first third party pay to the defendant all damages, losses and costs
suffered by the defendant resulting
from such order.
The claim against the second third party
[17] The defendant says the second third party owed a duty of care to subsequent purchasers of the servient land, though, again, he does not specify the ambit of that duty. He says that the second third party failed to follow the instructions of the plaintiffs and the first third party in carrying out the survey of the easement, that he failed to ensure that the easement which was created followed the line of the existing track and/or the most practicable and obvious route (where the track was indefinite), and that he failed to ensure that the subdivision application which created the
easement achieved what he had been instructed to do by the plaintiffs and the
first third party. He says that the duty of care was
owed to him as a
subsequent purchaser of the servient land and that he only became aware of the
second third party’s negligence,
as he describes it, when the plaintiffs
filed this proceeding.
[18] As a result the defendant seeks an order that the second third party
pays to the defendant all damages, losses and costs
suffered by the defendant
resulting from any order made in favour of the plaintiffs.
Discussion
[19] Looked at broadly the first two causes of action raise the question
of whether the right of way is in the location that it
was intended to be at the
time that it was created. This is certainly squarely raised in the first cause
of action; the second
cause of action raises the same point, albeit more
obliquely, on the basis that a negative covenant has been created that is more
burdensome to both parties than it should have been.
[20] In his claims against the first and second third parties the
defendant says that if this is so, it is the fault of one or
other or both of
them.
[21] Viewed narrowly, this is a different issue from the issue between
the plaintiffs and the defendant. Viewed more broadly,
however, both issues
raise the fundamental question of what was agreed at the time, not only by the
original parties to the easement
(the plaintiffs and the first third party), but
also between the first third party and the second third party. Viewed this way,
the ground for the issue of a third party notice under r 4.4(1)(d) might be seen
to be made out. However, that is not, in my view,
sufficient to determine this
application in favour of the defendant, in relation to the first and second
causes of action. There
are further issues to be considered.
[22] First, as noted earlier, the plaintiffs do not seek from the defendant any part of the cost of carrying out the rectification or modification which they seek. They simply seek an order that one or other of these actions occur. There is not, therefore, any cost to the defendant which can be the basis of a claim against either the first or
the second third party, under either of the first or second causes of action,
leaving aside questions of litigation costs.
[23] The defendant also claims any “losses” or
“damages” he might suffer as a result, but none is
pleaded even
in general terms, let alone with sufficient particularity for the Court to
understand how there might be any
sum for the defendant to recover.
[24] Secondly, as I have noted, the duties of care alleged on the part of
each of the third parties are not specified. There
can be little doubt that
each of the third parties will require particulars, and given the tenuous
relationship between the defendant
and each of the third parties, there is a
real prospect that the existence of any duty of care, however it may be
particularised,
will be firmly called into question, whether by way of an
interlocutory application for strike out or summary judgment, or by way
of
defence at trial. This issue alone has the potential to embroil the plaintiffs
in a prolonged proceeding, either before or at
trial. Even though the
plaintiffs would not be involved in the provision of further particulars of the
alleged causes of action,
nor necessarily in any applications that might be made
for strike out or summary judgment by the third parties, this proceeding
would be delayed while these processes took place.
[25] Thirdly, both third parties have pleaded limitation as a separate
defence. This, too, is an issue which may give rise to
an application to strike
out or for summary judgment, but if not will occupy time at trial. Again, the
plaintiffs would be delayed
by an application for strike out or summary
judgment, and the trial would be prolonged if the point were left to argument at
that
stage.
[26] All these points weigh in favour of the third party notices being set aside, in relation to the first and second causes of action. A further point in favour of this outcome is that no limitation issue has been identified which might exist now, but which did not exist when the third party proceedings were issued. Therefore it appears the defendant can now sue the third parties in separate proceedings without any additional barrier by way of limitation standing in his way.
[27] The third cause of action relates to the trees which were planted on
parts of the existing right of way, in around 1992.
The defendant bought the
properties with the trees on it, in 2002. If the plaintiffs succeed on this
cause of action, the cost
of removal of some of the trees, and other works as
may be required, would fall on the defendant. On this cause of action,
therefore,
if the defendant were found liable to the plaintiffs he would incur
costs which he would then seek to recover from the third parties.
In this way,
this cause of action differs from the first and second causes of action.
However, the defendant’s claims face
much the same hurdles as are faced on
the first and second causes of action: the second and third factors
I have identified
above again weigh in favour of the third party notices being
set aside, on this cause of action.
[28] The fourth and fifth causes of action do not fall within either (c)
or (d) of r 4.4(1). They rely entirely on the conduct
of the defendant some 20
years after either the first or second third party was last involved in this
case. I cannot see any basis
upon which the defendant might recover from the
first or the second third party any damages that may be awarded against him
under
either of these causes of action.
[29] Mr Downing notes that the defendant appears under objection
to the jurisdiction of this Court to hear and determine
parts of this claim, as
the easement registered on the titles of the plaintiffs and the defendant
provides for any dispute or difference
arising between them, relating to the
easement or its meaning or interpretation, to be referred to arbitration. The
objection refers
to the amended statement of claim filed in April 2013, not the
current pleading, but relates to the causes of action which are now
the third,
fourth and fifth causes of action in the second amended statement of
claim.
[30] So far as the present third cause of action is concerned, Mr Downing says that this is already the subject of a proceeding in the District Court for the removal of the trees, and that Court has decided that this issue is subject to arbitration and has ordered a stay. Therefore issue estoppel prevents the question of whether this part of the claim can be considered by the Court being revisited.
[31] It is unclear how a claim that this cause of action is issue-estopped, and that in any event it is subject to an objection to jurisdiction, assists with the proposition that a third party claim in respect of it should remain on foot. It also seems arguable that the defendant has submitted to the jurisdiction of this Court, in any event, given the filing of two statements of defence, which challenge the merits of the proceeding, as well as the filing of third party proceedings. These might form the basis of a submission that the defendant has submitted to the jurisdiction of this Court
notwithstanding the notice.5 I refrain from making
any finding or further
observation beyond noting that I do not find the protest to
jurisdiction of any assistance either way in reaching my conclusion
on this
application.
[32] Mr Downing notes that at an earlier point the Court allowed the
filing of a second amended statement of claim, after a stipulated
close of
pleadings date, noting that the alternative for the plaintiffs was to file a new
proceeding (which would not have been time-barred)
and then to apply for
consolidation. Mr Downing says that it would be fair to treat the defendant in
a similar way. Accurately,
he notes that when dealing with that issue, I said
that it was in the interests of justice that all causes of action were heard at
the same time. Analysis, however, shows that there is little similarity
between the two situations. Although the leave granted
to the plaintiffs had
the effect of allowing all the plaintiffs’ causes of action against the
defendant to be heard in one
single proceeding, that would almost inevitably
have occurred in any event, had the plaintiff taken the alternative option of a
separate
proceeding and consolidation. The position here differs. Although the
defendant seeks, also, to have all his issues relating to
this right of way
decided in the same proceeding, on this application there is potential for real
prejudice to the plaintiffs, for
the reasons I have set out. Two additional
parties would be involved, and the causes of action against them face
self-evident head
winds. It is by no means a foregone conclusion that any
separate proceeding the defendant may bring against the first or second
third
party would be consolidated with this one.
[33] For these reasons I conclude that the third party notices
should be set aside.
5 See, generally, McGechan on Procedure HR5.49.10(2).
Outcome
[34] Each of the third party notices is set aside and the
defendant’s statements of claim against the first and second third
parties
are dismissed, without prejudice to the rights of the defendant to pursue each
claim against either or both of the third
parties in an independent
proceeding.
[35] The plaintiffs are entitled to costs on a 2B basis together with
disbursements to be fixed by the Registrar.
Procedural direction
[36] The case will be called at the Nelson List on 21 August 2014, for
review. In the meantime, any further interlocutory application will be
filed and served no later than 10 clear working days prior to the
next
call.
[37] Counsel are to consider the effect of the notice of objection and
the steps to be taken in relation to it.
[38] A close of pleadings date will be set very shortly after the next
call, and a timetable set for the exchange of briefs of
evidence.
J G Matthews
Associate Judge
Solicitors:
Pitt & Moore, Nelson.
McFadden McMeeken Phillips, Nelson. Knapps Lawyers, Nelson.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/1574.html