![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 10 September 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2014-404-000337 [2014] NZHC 1783
BETWEEN
|
PEDESTAL LIMITED
Plaintiff
|
AND
|
CITY BUILD CONSTRUCTION LIMITED
Defendant
|
Hearing:
|
15 April 2014
|
Appearances:
|
J D Turner for the Applicant
D M Hughes and A Stuart for the Respondent
|
Judgment:
|
5 August 2014
|
JUDGMENT OF ASSOCIATE JUDGE
SARGISSON
This judgment was delivered by me on 5 August 2014 at 4.30 p.m. pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date.......................................
Solicitors:
McVeagh Fleming, Auckland
Kensington Swan, Auckland
Case officer: Lena Wong
PEDESTAL LIMITED v CITY BUILD CONSTRUCTION LIMITED [2014] NZHC 1783 [5 August 2014]
Introduction
[1] Pedestal Ltd applies for an order under s 290 of the Companies Act 1993 setting aside a statutory demand. City Build Ltd served the demand on Pedestal on
5 February 2014, claiming Pedestal owes it $244,477.12 on a payment claim by
virtue of ss 22 and 23 of the Construction Contracts
Act 2002 for work
undertaken on a building in Takapuna. City Build delivered the payment claim
for that amount (Payment Claim 11)
on 16 December 2013 as its final
claim.
[2] Under the Construction Contracts Act 2002 (the Act), if a payment
claim is served on a party to a construction contract
and payment of the lesser
of the claimed amount or the amount scheduled in a payment schedule is not made
within the time allowed
in the contract or otherwise within 20 working days, the
claimant is entitled to recover the amount of the claim as a debt
due.1
[3] Pedestal has not paid any part of the claimed amount. It asserts it
is entitled to an order setting aside the demand under
s 290 of the Companies
Act 1993 on the basis that it has responded to City Build’s payment claim
by providing a valid payment
schedule in response that was within the
“indeterminate” time the contract allowed, or on the alternative
basis that
the payment claim is invalid. Additionally, it claims that it has an
available set-off for liquidated damages which should be applied
in reduction of
the amount due should the Court find that the payment claim is valid and that it
did not provide a valid payment
schedule.
[4] City Build opposes the application.
[5] The time for compliance with the statutory demand has been extended
by interim order pending determination of the application.
Background
[6] Consideration of the issues that arise for determination
necessitates that I
refer in some detail to the factual background. I begin with the
construction contract.
1 Construction Contracts Act 2002, s 23.
The contract
[7] Pedestal engaged City Build to undertake the refurbishment of a
commercial building in Hurstmere Road, Takapuna, for $1,064,000
excluding GST.
The parties’ contract, entered into on 24 October 2012, is a construction
contract within the meaning of the
Act. The contract provides for a
practical completion date of March 2013 and allows Pedestal to call on City
Build to pay liquidated
damages for late completion of $1,100 per day subject to
any agreed extension of the completion date.
[8] The general conditions of the contract are the New Zealand
Institute of Architects Standard Conditions Contract
(SCC: 2011). These
conditions relevantly provide for:
(a) A complex progress payment regime. This is based on
monthly payment claims and a final payment claim, pursuant
to authority given
under the Act to parties to a construction contract.
(b) The due dates for payment of monthly payment claims. In the case
of the final payment claim, the due date is calculated
from the date of the
final payment schedule that the architect is required to deliver in
response to the claim. This contrasts
with prior monthly schedules, the due
date for which is 17 working days after the date of the delivery of
the relevant
payment claim.
(c) The provision of payment schedules. In the first instance these are provided by the architect in provisional form as the mechanism for giving notice to the contractor and the principal of the amounts the architect has certified for payment (the scheduled amount). They are also the mechanism for giving the principal the opportunity to require amendments and deductions to the certified amounts. In such a case, the architect is required to provide the contractor with a further payment schedule, and the reduced amount becomes the new scheduled amount for payment, leaving any remaining amounts to be
determined by adjudication, court action or other means of dispute
resolution.
[9] The general conditions also require the principal to ensure that an
architect is appointed throughout the contract to represent
the principal and to
impartially administer the contract. It is the architect’s
responsibility to issue the payment
schedules and to certify the scheduled
amounts in provisional payment schedules, and to consult with the principal
about any challenges
and changes to the payment claims.
Extension to May 2013
[10] City Build did not complete the refurbishment work within the time allowed in the contract, and the architect Pedestal had appointed, Mr Greg O’Connell, allowed an extension of the date for practical completion to
16 May 2013. Practical completion was not achieved until 30 September
2013.
Payment Claim 10 and payment schedule in response
[11] Throughout the period that the contract works were
undertaken
City Build sent monthly payment claims to Pedestal. On 27 September
2013
City Build served Payment Claim 10. The claim was for $83,928.66 for
“work to
31 August 2013”. Though a requirement under the contract, the claim omitted any statement that it was “made under the Construction Contracts Act 2002”. The omission was of no moment. The architect and Pedestal treated it as a claim made under the Act. On 1 October 2013 the architect responded to it in accordance with the procedure set out in r 14 of the contract, by sending a provisional payment schedule to Pedestal and City Build. In the schedule he certified most but not all of the components of the claim as, he says, there were still outstanding works and remedial works to be completed. On 2 October Pedestal’s lawyers requested amendments, including a deduction to the amount of the claim to provide for liquidated damages for late completion. After considering the request, on 3 October the architect issued an amended payment schedule which asserted that City Build was indebted to Pedestal for $67,871.34 and effectively reversed the claims the
provisional payment schedule allowed. This was principally because he allowed
the claimed deduction for liquidated damages of $151,800.
These were calculated
at the rate of $1,100 per day for 138 days, from 16 May to 30 September 2013
– the time from the final
date of the granted extension to the date of
actual completion. The architect also took into account the release of 40% of
the retentions,
the costs of rectifying certain defective work, and several
disputed variations.
Payment Claim 11 and request for extension of time
[12] On 16 December 2013 City Build served its Payment Claim 11
plus a covering letter, having raised no dispute
about the amended
payment schedule for Payment Claim 10.
[13] The new claim, made under the final claim provisions in r 15 of the contract, indicates that it is a “final account” and a payment claim under the Act. It is for
$244,477.12 for “work to 30 November 2013”, which includes $74,689 for variations (as opposed to $33,960 claimed for variations in Payment Claim 10) plus
$61,452 for costs relating to the extension of time claim, but it is otherwise for substantially the same amounts as claimed in Payment Claim 10, and excludes the liquidated damages that the architect imposed in the payment schedule for Payment Claim 10. The claim states that the due date for payment as 14 January 2014, while the covering letter states the due date for payment as 17 working days from
16 December 2013.2 However, as will be further discussed below,
neither of these
dates is the correct due date for payment. The claim does not mention the
due date for payment as it is specified in the contract;
if that were the case
it would have said “10 Working Days after the issuance of a final Payment
Schedule”. It does
not mention the time limit for delivery of the
provisional payment schedules, and is not required to under the Act or the
contract.
[14] At the same time as City Build delivered Payment Claim 11, it made a written request for the extension of time to cover the period between 16 May and
30 September 2013.
2 The definition of working day in the contract excludes weekends, public holidays and
24 December to 5 January. The date that is 17 working days from 16 December 2013 by my calculation is 21 January 2014.
Response to final payment claim / request for extension
[15] The architect’s response to the final payment claim and the
extension request
took several forms:
(a) On 23 December he sent an email to City Build indicating aspects of
the claim that without further information from City
Build he could not fully
assess or certify. These included the release of 100% of retentions, and claims
for several variations.
He also pointed out items requiring attention or
remediation at City Build’s expense. He invited City Build to
“adjust
[its] claim accordingly”.
(b) On 10 January 2013 he wrote declining the claim for an extension of
time on the basis that no written request had been made
within the time allowed
for such requests under the contract.
(c) On 12 February 2014 he provided City Build with a document he
called “Provisional Payment Schedule 11” which
he believed to be in
time under the contract. The schedule contains his assertion first made on 3
October 2013 that City Build
owes Pedestal $67,871.34.
(d) On 19 February he provided a document he termed the
“finalised provisional payment schedule”, having consulted
with
Pedestal which did not seek any changes to the scheduled amount in the
provisional schedule of 12 February. It repeats his
assertion of 3 October
2013 that City Build owes Pedestal $67,871.34.
(e) He followed up the payment schedule of 19 February by subsequently issuing monthly provisional payment schedules, the first being on
19 March. This was in purported compliance with the requirement in r 15.2.5 of the contract to provide monthly schedules when a provisional payment schedule is issued under r 15.2.4 in response to the final payment claim, “pending the time when the final payment schedule can be issued”.
[16] Pedestal’s lawyers also responded to the
payment claim on
23 December 2013 by writing to City Build’s lawyers. Their essential
message was that Pedestal owed City Build nothing as it
was City Build that was
liable to Pedestal for some thousands of dollars, and that City Build should
anticipate that it would receive
a payment schedule to that effect. They
referred first to settlement discussions the parties were apparently engaged
in.
They then discussed the final payment claim and the request for an
extension. In essence they relayed Pedestal’s unwillingness
to
immediately agree to an extension for practical completion. They further noted
that the final payment claim and the claim for
the extension “must now be
considered” by the architect and “prior to the issuance of a
provisional final payment
schedule”. This was an obvious reference to the
provisions of r 15.2.4 of the contract. Additionally they pointed out (as
r
15.1.3 of the contract provides) that the time for payment of a final
payment claim is “10 Working Days after
the issuance of a final
Payment Schedule” and “not 17 working days from 16 December as set
out in the final Payment
Claim”. They also touched upon outstanding
aspects of defective work.
The statutory demand
[17] There was no immediate response from City Build or its
lawyers until
5 February 2014 when City Build’s lawyers arranged service of its
statutory demand on Pedestal. On 19 February City Build filed
and served its
application to set aside the demand.
[18] On 7 and 10 February Pedestal, through its lawyers, repeated its
message that it was the party that was owed money. They
wrote to City
Build’s lawyers about the final payment claim, raising again various
challenges to the claim. Additionally:
(a) On 14 February it invoked the disputes procedure under r 17 of the contract. It also gave notice of the dispute to City Build and to the architect, whose task it was to identify the areas in dispute and to issue a direction as to the process to resolve them.
(b) On 19 February it filed its application for an order to set aside
the demand.
[19] The parties have agreed to submit their dispute to adjudication
under the Act. In the meantime Pedestal wants the statutory
demand set aside.
City Build opposes this course as it wishes to be paid on its final claim,
pending the outcome of adjudication.
Its position, counsel submits, is that it
firmly believes a payment schedule has not been provided within the time
allowed, but
it also fully accepts that if it is wrong about that, it would have
to concede there is a dispute as contemplated by the s 290(4)(a)
of the
Companies Act that should properly be determined in all its facets by an
adjudication under the Act or the Court in the ordinary
way.
Issues
[20] In determining whether to set aside the statutory demand, there
are two overarching issues that have been raised for
determination. The first
issue is whether or not there is a substantial dispute that the payment of City
Build’s final payment
claim is owing or due. For the purpose of
determining this issue, the following questions arise:
(a) As Payment Claim 11 omits to state the relevant period to which the
amount claimed relates and does not correctly state
the due date for payment,
does that mean it is an invalid claim?
(b) Does the contract provide the time for providing a
provisional payment schedule in response to a final payment
claim, or does the
default time limit in s 22 of the Act apply – whichever is the case, was
the architect’s provisional
payment schedule of 12 February in time or too
late?
(c) If too late, is it open to Pedestal to assert that other documents constitute a provisional payment schedule and were in time – such documents being the payment schedule for Payment Claim 10, and the communications of 23 December and 10 January?
[21] Question (a) is subject to an objection which I disallow for reasons
I come to presently.
[22] The second issue is does Pedestal have a set-off of $151,800 that
it is entitled to rely upon for the purpose of setting
aside the demand, or is
such reliance barred by s 79 of the Act?
[23] For the purpose analysing these issues, I begin with the relevant
provisions of the Companies Act, the Construction Contracts
Act and related
legal principles.
Relevant statutory and legal principles
Companies Act 1993
[24] Pedestal relies on the grounds set out in 290(4) of the Companies
Act in support of its application under. Section 290(4)
states:
(4) The Court may grant an application to set aside a statutory demand if it
is satisfied that—
(a) There is a substantial dispute whether or not the debt is owing or
is due; or
(b) The company appears to have a counterclaim, set-off, or
cross-demand and the amount specified in the demand less the amount
of the
counterclaim, set-off, or cross-demand is less than the prescribed amount;
or
(c) The demand ought to be set aside on other grounds.
[25] The Court’s approach to an application for an order to set
aside a statutory demand based on s 290(4) is well understood.
The onus is on
the applicant to demonstrate grounds for a dispute. The applicant must show a
fairly arguable basis on which it
is not liable for the amount claimed. Once
that position is demonstrated, the statutory demand should be set aside and the
dispute
resolved, if necessary, by other proceedings in the normal
way.
[26] Where a dispute is relied upon, the Court of Appeal has noted that the assessment to be made by the Court is whether there is a genuine and substantial
dispute and that it is not the task of the Court to resolve the
dispute.3 If the applicant can show that there is such a dispute, the
dispute should be resolved in the usual way and not by the Companies Court
or by
liquidation.
[27] When a matter is to be determined pursuant to s 290(4)(b),
the Court’s approach is as set out in Covington Railways Ltd v
Uni-Accommodation Ltd where the Court said:4
Where a company which is the subject of a liquidation application is
indisputably in debt to the applicant creditor, it may nonetheless
be able to
show that it has a claim against the applicant which reduces the net balance
owing to the creditor or even off-sets it
altogether. Where there are liquidated
sums due each way, that is simply an arithmetical exercise. It is more difficult
if, on the
applicant’s side, there is an indisputable liquidated sum, but
the other party’s claim is for an unliquidated sum with
liability and/or
quantum in dispute. Then, in order to impeach the statutory demand and overcome
the presumption in s287(a) that
the company is unable to pay its debts when it
has failed to comply with the demand, it must be able to do more than merely
assert
that there is an available set-off. It must be able to point to evidence
before the Court showing that it has a real basis for the
claimed set-off and
that accordingly, the applicant’s claim to be a creditor is, to the extent
of the set-off, seriously in
doubt. In the words of Buckley LJ in Bryanston
Finance Ltd v De Vries (No.2) [1976] Ch 63, 78, it must show that there are
“clear and persuasive grounds” for the set-off claim. Where this can
be
done, the party who has issued the statutory demand against the company will
be shown to be using the statutory demand and liquidation
procedures improperly
because there is a “genuine and substantial dispute” about the net
amount of the company’s
indebtedness (Taxi Trucks Ltd v Nicholson
[1989] 2 NZLR 297, 299). The dispute should then be resolved in the ordinary
way – except as to any undisputed balance –
rather than upon the
hearing of a liquidation application.
[28] Where, as here, the application to set aside the demand gives rise
to an argument about a set-off under a construction contract,
s 290(4)(b) may be
trumped by the operation of s 79 of the Construction Contracts Act to which I
turn presently.
Construction Contracts Act
[29] The present dispute, as with other disputes between parties to a construction contract, must be approached with the purpose of the Act in mind.5 The purpose of
the Act is set out in s 3. The Act reforms the law relating to
construction contracts for
3 Industrial Group Ltd v Bakker [2011] NZCA 142; (2011) 20 PRNZ 413 at [24].
4 Covington Railways Ltd v Uni-Accommodation Ltd [2011] 1 NZLR 272 (CA) at [11].
5 Subsequent references to “the Act” in this judgment are references to the Construction Contracts Act 2002. When reference is made to the Companies Act 1993, the name of that Act is stated in full.
the purpose of facilitating regular and timely payments between parties to a
construction contract, and provides remedies for the
recovery of payments that
are due.
[30] Justice Asher in Marsden Villas Ltd v Wooding Construction Ltd
pertinently stated:6
The Act therefore has a focus on a payment procedure, the results that arise
from the observance or non-observance of those procedures,
and the quick
resolution of disputes. The processes that it sets up are designed to side-step
immediate engagement on the substantive
issues such as set-off for poor
workmanship which were in the past so often used as tools for unscrupulous
principals and head contractors
to delay payments. As far as the principal is
concerned, the regime set up is “sudden death”. Should the principal
not
follow the correct procedure, it can be obliged to pay in the interim what
is claimed, whatever the merits. In that way if a principal
does not act in
accordance with the quick procedures of the Act, that principal, rather
than the contractor and sub-contractors,
will have to bear the consequences of
delay in terms of cashflow.
[31] The Court of Appeal in George Developments Ltd v Canam
Construction Ltd
similarly stated:7
Cash flow was intended to be protected by the Act and it is to be interpreted
so as to achieve its object of speeding up payments.
[32] Relevantly, s 14 gives contracting parties the freedom to
agree on a contractual mechanism for the contractor
(the payee) to
make regular payment claims for progress payments which may also include due
dates for payment under the contract,8 and the times for the
principal to respond with payment schedules. Such schedules are the statutory
and contractual mechanism that
the principal (the payer) must use should it wish
to halt the imposition of “deemed” liability under the Act and the
contract for immediate payment of disputed payment claims despite the existence
of disputes.
[33] Section 20 deals with payment claims. Materially, subss (1) and (2)
provide:
20 Payment claims
6 Marsden Villas Ltd v Wooding Construction Ltd [2006] NZHC 569; [2007] 1 NZLR 807 (HC) at [17].
7 George Developments Ltd v Canam Construction Ltd [2005] NZCA 84; [2006] 1 NZLR 177 (CA) at [55].
8 If the parties do not specify a due date for payment, the default position in s 18 of the Act applies and provides that a progress payment is due 20 working days after the payment claim is served under s 20.
(1) A payee may serve a payment claim on the payer for each progress
payment,—
(a) if the contract provides for the matter, at the end of the relevant
period that is specified in, or is determined in accordance
with the terms of,
the contract; or
(b) if the contract does not provide for the matter, at the end of the relevant period referred to in section 17(2).
(2) A payment claim must—
(a) be in writing; and
(b) contain sufficient details to identify the construction contract to which
the progress payment relates; and
(c) identify the construction work and the relevant period to which the progress payment relates; and
(d) indicate a claimed amount and the due date for payment; and
(e) indicate the manner in which the payee calculated the claimed amount;
and
(f) state that it is made under this Act.
[34] Section 21 sets out the requirements for payment schedules. It
provides:
21 Payment Schedules
(1) A payer may respond to a payment claim by providing a payment schedule
to the payee.
(2) A payment schedule must—
(a) be in writing; and
(b) identify the payment claim to which it relates; and
(c) indicate a scheduled amount.
(3) If the scheduled amount is less than the claimed amount, the payment schedule must indicate —
(a) the manner in which the payer calculated the scheduled amount;
and
(b) the payer's reason or reasons for the difference between the scheduled
amount and the claimed amount; and
(c) in a case where the difference is because the payer is withholding
payment on any basis, the payer's reason or reasons for
withholding
payment.
[35] Section 22 deals with the consequences of failing to provide a
payment
schedule within the time limit prescribed by the parties’ construction contract or, if
the contract fails to prescribe a time, within the default
time limit of
20 working days after the payment claim is served:
22 Liability for paying claimed amount
A payer becomes liable to pay the claimed amount on the due date for the
progress payment to which the payment claim relates if—
(a) a payee serves a payment claim on a payer; and
(b) the payer does not provide a payment schedule to the payee
within—
(i) the time required by the relevant construction contract; or
(ii) if the contract does not provide for the matter,
20 working days after the payment claim is served.
[36] Section 23 allows recovery of an amount that becomes payable under s
22 as a debt in any court together with the “actual
and reasonable costs
of recovery” awarded against the payer by the court. Service of a
statutory demand has been held to be
a proceeding for recovery of a debt under s
23.9 The same consequences apply under s 24, though s 24 only
concerns cases where a payment schedule has been provided.
[37] Section 79 of the Act restricts the parties’ ability to raise
a counterclaim or
set-off in opposition to a payment claim under s 23. It states:
79 Proceedings for recovery of debt not affected by
counter-claim, set-off, or cross-demand
In any proceedings for the recovery of a debt under section 23 or section 24
or section 59, the court must not give effect to any
counterclaim, set-off, or
cross-demand raised by any party to those proceedings other than a set-off of a
liquidated amount if—
(a) judgment has been entered for that amount; or
(b) there is not in fact any dispute between the parties in relation to the
claim for that amount.
[38] Of particular importance is the authoritative ruling of the Court of Appeal in Laywood v Holmes Construction Wellington Ltd10 which holds that s 79 prevails over s 290(4)(b) of the Companies Act and prohibits the court from giving effect to any counterclaim, set-off or cross demand. The Court recognised the tension between the
two provisions. Under the latter, the Court may set aside a statutory
demand if
9 Volcanic Investments Ltd v Dempsey & Wood Civil Contractors Ltd (2005) 18 PRNZ 97 (HC).
10 Laywood v Holmes Construction Wellington Ltd [2009] NZCA 35; [2009] 2 NZLR 243.
satisfied that the amount claimed in the set-off is less than the
amount in the statutory demand. Following Volcanic Investments Ltd v
Dempsey & Wood Civil Contractors Ltd the Court of Appeal accepted that s
79 prevails due to the fact that s 79 concerns recovery of specific types of
debt under a specific
type of contract, whereas s 290 relates to the recovery of
debts generally. As Randerson J notes, s 79 simply requires that the
set-off
may not be given effect in the contractor’s recovery proceeding, but the
set-off may still be pursued in a separate
proceeding.
[39] Subsections (1) and (2) of s 25 make clear that the parties to a
construction contract retain the right to pursue disputed
amounts under the
regime through adjudication, even though the dispute is the subject of
proceedings between the same parties in
a court or tribunal:
25 Right to refer disputes to adjudication
(1) Any party to a construction contract—
(a) has the right to refer a dispute to adjudication; and
(b) may exercise that right even though the dispute is the subject of
proceedings between the same parties in a court or tribunal.
(2) An example of a dispute is a disagreement between the parties to
a construction contract about whether or not an amount
is payable under the
contract (for example, a progress payment) or the reasons given for non-payment
of that amount.
[40] I turn them to consider the issues for determination with these
provisions and principles in mind.
Discussion
Given that Payment Claim 11 omits to state the relevant period to which
amount claimed relates and does not correctly state the date
for payment, is it
is an invalid claim?
[41] I am satisfied that the claim is not invalid by reason of the omission and the error Pedestal has raised. My reasons may be stated briefly, but I pause momentarily to mention an objection counsel for City Build made to this submission. Counsel for City Build is quite right that there is no apparent basis in Pedestal’s application for challenging the validity of the payment claim. The application relies on grounds that lack particulars and essentially do no more than reproduce the provisions of s 290(4).
[42] However, the validity of the payment claim was a matter that City
Build itself recognised the need to address, as its own
grounds of opposition
demonstrate, and it makes no claim. The obligation to include or indicate
certain matters in payment claims
(including the omitted matters) is both
a statutory requirement under s 20(2)(d) and a contractual requirement under
r
15.1.3. City Build makes no claim to be prejudiced by the belated reference
to invalidity, and nor could it reasonably do so. In
these circumstances I
prefer to deal with Pedestal’s submission on its merits.
[43] Counsel for Pedestal submits that the final payment claim is invalid
as it breaches two requirements of r 15.1.3 of the contract
(and essentially the
same requirements in s 20(2)). The first breach is that the claim does not
identify “the relevant period”
in which the construction work
claimed for was undertaken as it identifies the completion date but not the
commencement date for
the various works it lists and claims for. Additionally,
the covering letter simply says it is for “work completed ... to 30th
November 2013”, by way of repeating the completion date indicated in the
claim. The second breach is that the claim
does not indicate
correctly that the due date for payment is “10 Working Days after the date
of the Final Payment Schedule”
as set out in r 15.1.3(d). It states
incorrectly that the total amount is due on 14 January 2014 and the covering
letter states
that the “due date for payment of this claim is 17 working
days from the 16th December 2013”.
[44] Pedestal has the onus however of showing that the omissions are not
simply technical omissions that have caused City Build
no prejudice. In respect
to the due date, counsel for City Build points to decisions of the Court that
are apposite and are to the
effect that minor errors in a payment claim, such as
an error in the due date, should not be allowed to frustrate a
subcontractor’s
entitlement to payment under the Act.
[45] I accept the approach of Associate Judge Faire in CMP
Construction Ltd v
Aluminium Technology Ltd where he states:11
[27] Although s 20(2)(d) of the Construction Contracts Act 2002 requires that
a payment claim indicates the due date for payment,
[counsel] drew attention to
decisions of the court that have held that minor errors in a payment claim, such
as an error in the due
date, should
11 CMP Construction Ltd v Aluminium Technology Ltd [2013] NZHC 2481.
not be allowed to frustrate a subcontractor’s entitlement to payment under the Construction
Contracts Act 2002. Such errors are regarded as mere technical
quibbles.
[28] [Counsel] drew attention to the fact that there is no evidence that the applicant has been misled by the error. He referred me to the two decisions where the courts have disregarded
an error in the due date for payment as being a ground for holding that the
payment claim was invalid.11
[29] I conclude that there is nothing in this case that would justify my
concluding that an error in the payment date should invalidate
the payment
claim.
[46] There is nothing in the evidence that seriously suggests that prejudice of any kind is a real possibility because Payment Claim 11 did not reproduce the provisions of the contract that state the due date for payment. Pedestal’s proposition that the omission to include in the payment claim the words that “the due date for payment is
10 Working Days after the date of the Final Payment Schedule” is fatal
may be superficially attractive because timing is
crucial in certain
respects under the statutory payment regime (whether or not modified by
contract). However the argument
does not bear scrutiny, as:
(a) It is established authority that quibbles about technical
deficiencies are not enough to invalidate payment claims.12 The
deficiencies that Pedestal relies on are just that – and the complaint a
technical quibble.
(b) Even if the payment claim intended the omitted words, they would
not have alerted Pedestal to the need to take steps to
avoid the consequences of
a failure of not providing a payment schedule on time. Those consequences are
prescribed by the Act. Pedestal
would still be confronted with the need to
acquaint itself with the agreed provisions of contract that govern the
requirements
for timely payment schedules (which are after all agreed
provisions), and with the related default provisions of the Act.
(c) Had Pedestal been concerned about the omission that it now seeks to
rely on, it would no doubt have said so in
the grounds of
its
12 George Developments Ltd v Canam Construction Ltd, above n 7.
application, as would the architect in the provisional payment
schedule that he issued on 12 February.
(d) It is clear that Pedestal’s real concern is not about the omitted
words.
Rather, it is about the possibility that it has been caught out by its own
failure to meet the relevant time limit for issuing the
provisional payment
schedule that is required under r 15.2.4 of the contract. That is where the
real argument lies.
[47] I am also satisfied that there is no evidence of prejudice of
disadvantage emanating from the omission to identify the beginning
as well as
the end of the period covering the work claimed for. The claim identifies each
category of the work allegedly completed
by 30 November 2011. Pedestal does
not claim it was taken by surprise by these categories, or that it could not
tell what work
has been done under each category over the period of the
contract, or what part of that work it had already paid for.
[48] I do not accept Pedestal’s argument. I am satisfied
that City Build’s omissions to include correct
advice in the final
payment claim as to when payment was due in compliance with r 15.1.3, and to
state the commencement of the period
the claim covers do not invalidate the
payment claim.
[49] I turn next to Pedestal’s alternative arguments. I proceed
on the basis that
Payment Claim 11 is a valid claim.
Does the contract provide the time for providing a provisional payment schedule in response to a final payment claim, or does the default time limit in s 22 of the Act apply – whichever is the case, was the architect’s provisional payment schedule of
12 February in time or too late?
[50] The central point at issue is whether for the purpose of s 22(b)(i), r 15.2.4 of the contract makes provision for “the time required” within which a provisional payment schedule must be delivered in response to the final payment claim.
[51] Counsel for City Build submits that there are two possibilities.
The first is that r 15.2.4 provides that the provisional
payment schedule is to
be delivered one month after delivery of the final payment claim if the
architect is unable to issue the provisional
final payment schedule within that
time. The second is that the rule omits any such provision, with the result
that the time allowed
for providing the provisional payment schedule is
determined by the default provision in s 22(b)(ii), and is 20 working days after
delivery of the final payment claim.
[52] Counsel submits in either case the provisional payment
schedule on
12 February was delivered too late, and therefore that payment of the entire claimed amount became due on 16 January (a month after the claim was served), or
23 January 2014 at the latest.13 As payment was not made, the
consequences in s 23
follow. Counsel also relies on Ainsworth v Collinson, where
Associate Judge Gendall, as he then was, found in dealing with
identical provisions that “on a generous
view” the payer must
provide a provisional final payment schedule within one month from the receipt
of the final payment claim,
or instead, a provisional payment schedule within 20
working days of such receipt.14
[53] Counsel for Pedestal argues that r 15.2.4 does not provide a finite allowable time within which a provisional payment schedule may be delivered in response to a final payment claim, but rather prescribes a process that is intended to give the architect however long it takes to assess all amounts claimed. He submits that this is the reason why the contract stipulates payment is due within 10 working days after the issue of the final payment schedule, and why r 15.2.4 does not fix a time for delivery of the provisional payment schedule. The process, he submits, is subject to built-in safeguards by allowing the parties to resort to the contract’s disputes procedure under r 17 in the event of undue delay. In this sense, he submits, “the time required” for delivery of the provisional payment schedule might be described as “indeterminate” but the time is nevertheless provided for. Counsel submits
additionally that the decision in Ainsworth v Collinson is
wrong.
14 Ainsworth & Collinson Ltd v Edmunds HC Napier CIV-2009-441-348, 7 October 2009 at [43].
[54] Analysis of the contractual intention of r 15.2.4 is assisted by
reading the rule together with r 15.2.5:
15.2.4. Should the issue of the provisional Final Payment Schedule take
longer than 1 month, the Architect must issue a certificate in the form
of a provisional Payment Schedule for all amounts due under the Contract
which can be certified at that time and the process under Section
14 rules 14.3
to 14.7 will apply. The provisional Payment Schedule must be accompanied by
a statement setting out the reasons why the provisional final Payment Schedule
cannot be issued.
15.2.5 The Architect must continue to issue further provisional
Payment Schedules at monthly intervals until the provisional
Final Payment
Schedule is issued.
(Emphasis added).
[55] These rules provide alternative processes for the initial scheduled
response to the final payment claim, prior to delivery
of the final payment
schedule. Under r 15.2.4 the initial schedule is to be either a provisional
Final Payment Schedule or a provisional Payment Schedule, as a
pre-requisite to the issue of a provisional final payment schedule (dealt with
under r 15.2.4).
[56] If the first of the two processes is adopted:
(a) The architect is to complete an assessment (required by r 15.2.1)
of the amounts claimed in the final payment claim. The
architect must then
prepare the provisional final payment schedule to certify the amounts
claimed.
(b) Delivery of the provisional final payment schedule is required
within one month of receipt of the final payment claim.
[57] The second process however allows for the eventuality that the assessment cannot in fact be completed within the time required for the first process, by permitting the architect to issue a provisional payment schedule in place of the provisional final payment schedule. In such a case the architect is required by r 15.2.5 to issue further provisional payment schedules at monthly intervals until able to issue the provisional final payment schedule – in which case the process applicable to all prior payment claims prescribed by rr 14.3 to 14.7 applies.
[58] Counsel agree the intent of the two processes is generally
non-contentious. There is however a material point of difference
between
counsel: it is whether r 15.2.4 specifies by when, in the event
the architect is unable to issue a provisional final payment schedule within the
one month time limit, he or she must
issue the first provisional payment
schedule. Additionally, whether s 22 of the Act requires that the relevant rule
in the contract
must state when (in an definitive sense), or whether
compliance allows that “the time required” may be an indeterminate
time.
[59] As counsel both appeared to recognise at the hearing, the matter is
one of contractual interpretation and is not free of
difficulty. Realistically,
neither counsel suggests that the contractual intent of r 15.2.4 is that the
time limit of 5 working
days after receipt of a payment claim as set out in r
14.3 is applicable. If it was, it would mean in practice that the architect
would have to decide within 5 working days of receiving the payment claim
whether it was feasible to complete the task of assessment
within a month. That
would force on the architect the need to make an arbitrary decision on the
matter that may not reflect the reality
of the task involved. I do not think
that intention is to be readily inferred.
[60] I am satisfied that on an objective reading, the purport of r 15.2.4
is this:
(a) The architect has one month after receiving the final
payment claim to endeavour to complete the assessment required and issue the
provisional final payment schedule
(b) Failing this, he or she must issue a certificate in the
form of a provisional payment schedule, for all amounts
due under the contract
which can be certified at that time (being the one month
point).
[61] It would be pointless to require certification of all amounts due at the one month point, if the intention were that delivery of the certificate should be free of the same time constraint and withheld indefinitely. There would be no sense in requiring certification in the form of the provisional payment schedule at the one month point if only to allow the architect (as counsel for Pedestal submits) to withhold the schedule for an indeterminate time.
[62] Such an approach to the interpretation of r 15.2.4 would also run
counter to the obvious purpose of the r 15.2.5 (that the
architect is to conduct
an ongoing assessment of the components of the final payment claim, to enable
monthly certification of scheduled
amounts for payment). That would allow the
indefinite stalling of the start of the monthly provisional payment schedules as
contemplated
by r 15.2.5, and then defeat the intent that there be monthly
payments of assessed and certified amounts. I do not think that can
be the
contractual intent of these rules, or that it would be consistent with the
legislative intent which the parties must be taken
to have had in mind they
entered into the contract (in terms of protecting cash flow and maintaining
payments).
[63] I see no merit in counsel for Pedestal’s argument that the
obvious difficulties with the approach he espouses are
answered by the
availability of the disputes procedure under r 17 of the contract.
[64] For these reasons, I am satisfied that as a matter of contractual
interpretation that the time required within which the
initial provisional
payment schedule had to be issued in response to the final payment claim under r
15.2.4 was one month after receipt.
Additionally, I am satisfied that
there is no room to interpret s 22 as permitting a construction contract
to allow an
“indeterminate” time. To that extent I agree with
Ainsworth v Collinson. Parliament did not intend that the contract could
leave the time “indeterminate” by, for instance, allowing a
“reasonable
time”.
[65] I acknowledge that there remains however at least one unanswered
question, and it concerns the import of r 14.7.3, which
states:
14.7.2 In the event of an unreasonable delay in the issue of a Payment
Schedule for any claim which is later the subject of a Payment
Schedule, the
contractor will be entitled to interest on the amount owing as set out in rule
14.7.2, from the date on which it would
have been payable if the delay had not
occurred, to the date of payment.
[66] Materially, “Payment Schedule” is defined in the
contract as including any
such schedule, including a provisional payment schedule.
[67] If the contractual intention of this provision is to allow an extension of time or an “elastic” time for issuing a provisional payment schedule, then the provision would be contrary to and trumped by the Act – in which case the contract must be interpreted as if it is of no effect by virtue of s 12 of the Act15. Either the one month period in r 15.4.5 would stand (if my findings are correct) or the default period in s 23 (b)(ii) would apply. Either way, the provisional payment schedule of
12 February was too late.
[68] I am satisfied that such a schedule had to be issued (and not merely
prepared) one month from the receipt of the final payment
claim. Allowing for a
clear calendar month, the schedule had to be issued by 16 January
2014.
[69] I turn then to Pedestal’s alternate claim that other
documents issued to City Build before 16 January 2014
constituted a legitimate
payment schedule for the final payment claim.
Did Pedestal issue to City Build before 16 January 2014 documents
constituting a legitimate provisional payment schedule for the final
payment
claim?
[70] Counsel for Pedestal relies on certain correspondence as constituting a legitimate payment schedule for the final payment claim. These are the letter Pedestal’s lawyers sent to City Build’s lawyers on 23 December 2014, the email that the architect sent to City Build that same day, and the architect’s further letter of
10 January 2014.
[71] In essence Pedestal’s submission is twofold. First, the components of this correspondence, if individually not sufficient to constitute a payment schedule, collectively constitute a composite and legitimate payment schedule in response to the final payment claim. Any doubt about this, counsel says, fades when the correspondence is viewed collectively with the payment schedule for Payment Claim 10, as a major component of the final payment claim is merely a duplicate of
that claim, which has been countered substantially by the
payment schedule
delivered in response to
that claim; and because the other major component (the extension of time claim)
is clearly disputed.
[72] The second submission is that even though the correspondence does
not, at first glance, state the “scheduled amount”
(as required by s
21 of the Act and r 14.4 of the contract) it does contain the clear
message needed to comply with
the minimum requirements of the Act and r
14.4 of the contract. Pedestal did therefore issue a payment schedule in
response to the
final payment claim before the time limit of 16 January
2014.
[73] As counsel for Pedestal points out, there is no prescribed form for a payment schedule.16 And there is nothing in s 21 or r 14.1, as he also points out, that says a payment schedule must be comprised in one document. A payment schedule may take the form of a letter, even if the letter does not strictly adopt the terminology of the Act and does not specify that what the scheduled amount is, or that it is “nil”. It will be sufficient if the essential message is clear and unequivocally consistent with the requirements of s 21.17 An unduly technical approach to the fulfilment of the
requirements for payment schedules is not warranted.18
[74] Justice Hansen’s observation in Westnorth Labour Hire Ltd v S B Properties Ltd, that even where a document does not adopt the terminology of the Act it will be valid where the essential message is “clear and unequivocal”, is apposite.19 In that case, His Honour declined to treat a disputed payment schedule as invalid. Though the letter did not state it was a payment schedule or specify that the scheduled amount was nil, it conveyed the essential message that the amount the principal was willing to pay was nil and the reasons for that position. It identified changes for materials returned, instances of faulty workmanship and indicated there would be no
payment until the contractor provided full particulars of what work had been
done.
[75] The essential message of a payment schedule must be the precise
nature of the monetary dispute between the parties, which
is otherwise known as
the scheduled
16 NCB 2000 Ltd v Hurlstone Earthmoving Ltd CIV-2010-404-8096, 23 June 2011 at [41].
17 Westnorth Labour Hire Ltd v S B Properties Ltd HC Auckland CIV-2006-404-1858..
18 NCB 2000 Limited v Hurlstone Earthmoving Limited, above n 16, at [50].
19 Westnorth Labour Hire Ltd v S B Properties Ltd, above n 17, at [28].
amount. Justice Venning in West City Construction Ltd v Edney
described the purpose of a payment schedule in the following
way:20
[44] The purpose of the payment claim and payment schedule provisions of the
Act is to enable a contractor to make a claim for work
done in an identified sum
and, in the event the employer disputes the claim, the employer has the ability
to challenge the claim
by formally referring to it but importantly in doing so
is required to specify how much the payer says is actually payable. The
legislation
is designed to ensure the parties identify the difference between
them, and to identify what is in issue between the parties in
monetary terms
so that the parties are adequately advised as to the extent of the
difference.
[45] It is not sufficient to refer in some general way to a formula of the
nature referred to by the respondent in this case. That
is not the intent of the
legislation.
[76] Bearing these principles in mind, I accept, in general terms,
counsel for Pedestal’s submission that several documents
taken
individually or cumulatively may constitute a valid payment schedule. I do not
however accept his primary submission that
the particular correspondence relied
upon can be viewed as a legitimate payment schedule to the final payment claim.
My reasons
can be stated briefly.
[77] First, I begin with Payment Claim 10. The thrust of counsel’s argument is that as the final payment claim is just a re-issue of the prior payment claim albeit with some additions, it has been substantially dealt with by the payment schedule for Payment Claim 10. Rule 15.1.2 of the contract notably provides that no further payment claims may be issued after the service of the final payment claim, Payment Claim 11. There is nothing in the Act or the contract that prevents a contractor from effectively resubmitting prior progress payment claims by repeating them in
subsequent monthly claims,21 or that prevents the principal from
reiterating the same
response in the next payment schedule if it still holds its former concerns.
Because the effect of resubmission reactivates the claim,
the principal cannot
simply sit on its hands if it wishes to avoid the statutory consequences
of not responding to a
payment claim.
[78] The second reason relates to Pedestal’s lawyer’s letter
of 23 December 2013. Before turning to this reason, I
put to one side the
unanswered question whether
20 West City Construction Ltd v Edney HC Auckland CIV-2005-404-1066, 24 August 2005.
21 George Developments Ltd v Canam Construction Ltd, above n 7.
because of the particular contractual regime the parties have adopted, the
provisional payment schedule must be the certificate of
the architect.22
It is not necessary to answer this question because the letter cannot
properly be characterised as a payment schedule for another
reason. To
characterise the contents of the letter as such would be to ignore the fact that
it was written to provide clarification
of settlement terms, and not as a
purported payment schedule.
[79] In this last respect, the letter makes clear that Pedestal proceeded
on the basis that the architect’s response under
r 15.2.4 was to be its
payment schedule response. It advises that the final payment claim and the claim
for the extension of time
“must now be considered” by the
architect “and prior to the issuance of a provisional final payment
schedule”. Had the lawyers intended their letter to convey the
message that it was one or other of the two kinds of provisional payment
schedule permitted under r 15.2.4, or that it was somehow a separate response
under s 22, they could have said that in place of the
contrary message the
letter conveyed – and no doubt they would have. Instead, their message
was clear that the architect
had yet to do what was needed to complete a
provisional payment schedule.
[80] I therefore reject the submission that Pedestal’s
lawyer’s letter of
23 December is a payment schedule or a part of a composite
schedule.
[81] The third reason is the architect’s own communications of 23
December and
10 January cannot be construed as being the provisional payment schedule. Not only do they suffer from omissions (most notably, they omit to state a scheduled amount or convey the essential message of what was in issue in monetary terms), it is clear the architect did not intend them to be the payment schedule response. The
23 December email was essentially raising concerns about various aspects of the final claim and seeking information. The 10 January letter simply declines the claim for an extension of time only and deals with no other matters. Tellingly, the
architect’s own evidence makes no suggestion that he issued these
communications
22 This appears to be inferred by the approach that the Court adopted in Marsden Villas Ltd v Wooding Construction Ltd [200] 1NZLR 807, at [81]. The Court inferred that if the parties had intended that there could be two possible responses to each payment claim (one for the contract from the architect, and one for the Act from the principal), the contract would have provided for this.
intending them to be taken as the provisional payment schedule. Rather, in
his evidence he makes clear his understanding was that
the payment schedule
response was not subject to a strict time limit. Consistent with that
understanding, he states that it was
on 12 February 2014 that he issued the
payment schedule response. Materially, in his evidence he says:
There is no strict time frame on when the provisional payment schedule has to
be issued under the contract in response to a final
payment claim, but it is
clear that I have to assess it on the month after receipt, and I did so and
corresponded to City Build seeking
information.
I have not received any response to my email dated 23 December from City Build. No further response was received following my advice to City Build on 10 January
2014, that the claim for extension of time and alleged prolongation costs had
been declined.
On 12 February 2014 I issued a provisional payment schedule in respect of the final
payment claim to City Build and Pedestal...
On 17 February Pedestal advised me no amendments or deductions were required from the provisional payment schedule dated 12 February 2014, and so on 19
February 2014 I issued a “finalised provisional payment schedule” as required by
the contract to City Build...
[82] It would be stretching the reality of the situation to now attempt
to construe communications that the architect sent to
City Build prior to 12
February as something that he clearly intended the 12 February communication to
be.
[83] I accept the communications that Pedestal wishes to rely upon must
have left
City Build in no doubt that the claim for extension of time for the period 16
May to
30 September was disputed and that Pedestal indicated it considered it
retained the contractual right to liquidated damages for delay.
Similarly City
Build would have known that Pedestal disputed certain variations and claims for
defective works. In these circumstances,
when it received these communications,
City Build could not but have anticipated that if the overall dispute was not
settled it was
going to receive a provisional payment schedule. It appears
clear enough that it hoped it would not do so until after 16 or 23 January.
But
in my view that is where the matter was left by Pedestal until 12
February.
[84] I am therefore led to the only tenable conclusion – that there was no payment schedule, provisional or otherwise, issued before the 1 month time limit. Harsh as it may seem, particularly when City Build seemingly deliberately failed to respond to
the architect’s queries and Pedestal’s lawyer’s
letters, such is the effect of the statutory regime
and of the contractual
mechanism the regime authorises. Unless Pedestal can establish an entitlement to
rely on its claimed set off,
it is liable to pay the full amount claimed now
and must leave its argument until later (whether through the disputes
procedure that the parties are presently engaged in or such other avenues as may
be open to it to challenge the final payment claim).
[85] Given the findings I have reached to this point, I conclude that the
provisions in r 14.7, which deal with the time when
the principal must pay the
scheduled amount shown in the provisional payment schedule, apply. That time is
set out in r 14.7.1 as
follows:
...within 12 working days of the date of the provisional Payment Schedule, or
if one has been issued, within 7 working days of
the date of the Payment
Schedule, whichever is the earlier.
[86] The entire amount of Payment Claim 11 is therefore due, subject only
to any available set-off. I turn then to that question.
Does Pedestal have a set-off of $151,800 that it is able to rely on for
the purpose of its application to set aside the statutory
demand?
[87] Counsel for Pedestal submits that in the event I find that
a provisional payment schedule has not been issued
on time for the purpose of r
15.2.4 then I should find that Pedestal may rely on a set-off for liquidated
damages which, he submits,
it is unarguably entitled to. It follows, he
submits, that the amount of the liability that may be enforced by the statutory
demand
is extinguished by the amount of Pedestal’s contractual entitlement
to liquidated damages for delay.23
[88] A proceeding based on an application for an order to set aside a statutory demand is a proceeding for the recovery of a debt under s 23.24 The court may not therefore give effect to a counterclaim within the contemplation of s 290(4) of the
Companies Act unless it is a set-off that comes within the terms of s
79. To permit
23 In payment claim 10, City Build claimed $82,081.12. In payment schedule 10 Pedestal deducted
$151,800.00 and released only 40% of the retentions. Consequently, Pedestal claims that City
Build owes it $67,871.34. It is in respect of this amount that Pedestal claims it has a set-off.
24 Volcanic Investments Ltd v Dempsey & Wood Civil Contractors Ltd, above n 5, at [19] and [20].
an unproven set-off to be raised as a means of avoiding payment of an
established debt would be inconsistent with the purpose of the
Act, which
contemplates quick resolution of disputes and payment of due
debts.25
[89] A s 79 claim to a set-off against the amount of the statutory demand
can only be taken into account if:26
(a) The amount of the set-off is a liquidated amount; and
(b) Judgment has been entered for that amount or there is not in fact any
dispute in relation to the claim for that amount.
[90] There is no dispute that the amount Pedestal claims as a set-off
satisfies the first requirement. It is a liquidated
amount. As it
has no judgment for the set-off, the question remains whether or not the
parties are in genuine dispute over
its entitlement to the set-off.
[91] The issue of liquidated damages (for the daily penalties
allowed under
Specific Conditions of Contract for failing to achieve practical
completion on
16 May 2013 and not until 30 September 2013) first arose in Payment Schedule
10. At the time City Build raised no dispute about the
amended payment schedule.
Counsel for Pedestal submits the parties cannot be in dispute as to the quantum
of liquidated damages,
as the parties contractually agreed on the
amount of daily penalty fees for late completion, and because City Build took
no issue with the set- off at that time. The particular contract provision
states:
14.10.1 If the Contractor does not achieve Practical Completion of the
Contract Works ... within the time stated in the Specific
Conditions as adjusted
for extensions of time, the Principal is entitled to deduct liquidated damages
at the rate stated in the Specific
Conditions. The liquidated damages will run
from the due date for Practical Completion of the Contract Works ... to the
actual date
of Practical Completion of the Contract Works, or Separate
Section.
25 At [32].
26 At [22].
[92] Counsel for City Build submits to the contrary that the parties are in dispute for the purposes of s 79. He submits that the evidence is that in April 2013 the architect and City Build agreed there would be no liquidated damages and that accordingly, there is a dispute. Reference is necessary to the factual evidence before the Court. The minutes of the meeting held between the parties and the architect on
26 March record that after the first date for practical completion had passed, City Build issued a revised construction programme with a final completion date of
20 May. On 5 April the architect issued a certificate of extension of time
to 16 May. This was then confirmed in the minutes
of the meeting held on
11 April. The following day City Build and the architect exchanged emails, where
City Build asserted that
it never confirmed that it was on track to completion
by 16 May, and where the architect disputed this fact.
[93] On 13 April City Build sent the following email to the
architect:
Can you please confirm if you intend to pursue any penalties under the
contract or is it still your intention to work with us in good
faith to achieve
final completion.
[94] The architect responded as follows:
We have no intention to pursue penalties. The Extension of Time & revised
practical completion date is a necessary formality.
We are simply trying to facilitate completion in as timely a manner as
possible, and are under additional pressure to do so due to
the tenant
requirements.
[95] City Build argues that it understood this statement as Pedestal, via the architect, waiving its contractual right to pursue liquidated damages for late completion beyond 16 May, which is the reason City Build did not apply for further extensions of time. The architect, on the other hand, deposes that his understanding was that Pedestal were not going to pursue liquidated damages for the period
15 March to 16 May, namely the period between the two formal completion dates. The question is whether the architect’s email, on behalf of Pedestal, constituted a waiver of liquidated damages for late completion.
[96] The answer to that question turns on what each party understood the
other to mean in relation to the period for which
penalties would not
be pursued. It is arguable that in the context of disputing the extension to
16 May as being too short,
the architect’s assurance of Pedestal’s
intention to continue working in good faith and that the extension is a only
a
formality gave City Build the understanding that Pedestal waived its right to
pursue penalties for completion after 16 May. It
is also arguable that Pedestal
would not have intended to grant an open-ended extension.
[97] On the material before me, I cannot determine this issue. I am
therefore satisfied that there is a dispute in fact between
the parties in
relation to Pedestal’s claim for liquidated damages, and as such, I am
prevented from finding that Pedestal
has a set-off for the purpose of dealing
with its application to set aside City Build’s statutory
demand.
Result
[98] For the reasons I have discussed, I decline Pedestal’s application for an order to set aside City Build’s statutory demand. I consider however that Pedestal should have time to satisfy the demand, and I extend time for compliance to the expiry of
15 working days from the date of this judgment.
[99] Failing compliance, pursuant to s 290(3) of the Companies Act, City Build may proceed with an action for liquidation. In so ordering, I do not wish to be seen as expressing any view on the merits of such an application. I simply observe that the Court, in exercising discretion to set aside a statutory demand under s 290, decides whether it is just to allow the statutory demand to stand so that non-
compliance will give rise to a presumption of inability to pay debts.27
In that context,
the Court however does not exercise discretion whether a liquidation order should be made.28 As the Court of Appeal in Laywood v Holmes Construction observed obiter
different considerations arise in a proceeding for an
application to set aside a
27 Volcanic Investments Ltd v Dempsey & Wood Civil Contractors Ltd (2005) 18 PRNZ 97 (HC) at
[13], [19] and [20].
28 At [13].
statutory demand on the one hand and an adjudication of an order to wind up a
company on the other, but it expressed no opinion on
the
point.29
[100] Additionally, as noted in 239 Queen Street Developments Ltd v
Watts & Hughes Construction Ltd30 by Associate Judge Bell
in citing the observation in Laywood, claims of a set-off that could be
raised on liquidation should be heeded and not be brushed aside by an immediate
order for liquidation.31 Upon production of further evidence as to
its claims for damages for delay, it is conceivable that Pedestal may be able to
defend
itself in liquidation proceedings if they are filed. This judgment does
not purport to deal with that question.
Costs
[101] Costs are reserved. If the parties cannot agree on costs, any party seeking costs is to file and serve a memorandum within 8 working days of the date of this judgment. Any memorandum in opposition is to be filed and served within a further
8 working days.
Associate Judge
Sargisson
29 Laywood v Holmes Construction Wellington Ltd [2009] NZCA 35; [2009] 2 NZLR 243 (CA) at [61] and [65].
30 239 Queen Street Developments Ltd v Watts & Hughes Construction Ltd [2012] NZHC 1791.
31 At [24].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/1783.html