Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 9 September 2014
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV 2008-409-002301 [2014] NZHC 2118
BETWEEN
|
CONCRETE STRUCTURES (NZ)
LIMITED Plaintiff
|
AND
|
NZ WINDFARMS LIMITED Defendant
|
Hearing:
|
21-24 July 2014
|
Counsel:
|
G P Blanchard for Plaintiff
J Smith QC and R G Smedley for Defendant
|
Judgment:
|
3 September 2014
|
JUDGMENT OF WHATA J
Introduction
[1] Concrete Structures (NZ) Limited (CSL) and NZ Windfarms
Limited (NZ Windfarms) entered into a construction contract
under which CSL was
engaged to assist in the construction of a wind farm. The wind farm was duly
constructed, but there were several
problems along the way. CSL seeks to
recover about $250,000 plus interest for variations that were not approved by NZ
Windfarms’
engineer. The critical issue before me therefore is whether or
not the sought after variations should have been approved.
Background facts
[2] In March 2006 CSL entered into a contract with NZ Windfarms to carry out civil engineering and construction work at NZ Windfarms’ Te Rere Hau Windfarm Development, Palmerston North. There were two key aspects of the contract namely to upgrade and maintain roads to enable access to the various tower locations and to construct
the bases for the towers.
CONCRETE STRUCTURES (NZ) LIMITED v NZ WINDFARMS LIMITED [2014] NZHC 2118 [3 September
2014]
The contract
[3] The contract included the following particulars:
(a) The contract was a measure and value contract that included a schedule of
quantities and prices;
(b) The contract price was $832,218.30 including GST or such other or lesser
sum shall become payable under the contract;
(c) NZS 3910:2003 (“3910”) was incorporated into the contract as
the general
conditions of contract except as where modified by the special
conditions;
(d) Murray Fletcher was appointed by the defendant as the engineer to the
contract;
(e) Clause 5.11.3 of the contract contained provisions concerning the
obtaining of licences and consents under the contract:
5.11.3 The Principal shall at the Principal’s expense obtain all
licences, which may be required for the construction
of the Contract
Works and for the use of the Contract Works when constructed except as otherwise
provided for in 5.11.4.
(f) Clause 5.11.6 of the contract provided that:
5.11.6 If licences, obtained by the Principal or by the Contractor are
subject to conditions affecting the carrying out of the Contract
Works, those
conditions shall be notified to the other party and to the Engineer. If the
compliance with these conditions causes
delay in the completion of the Contract
Works or additional Cost to the Contractor which in either case the Contractor
could not
reasonably have foreseen when tendering the compliance will be treated
as if it was a Variation.
(g) Clause 6.2.1 of the contract provided that the dual role of the engineer
in the administration of the contract was:
i. As an expert adviser to and representative of the defendant; and
ii. To independently of the contracting parties, fairly and
impartially make decisions entrusted to him under the contract,
to the value of
the work and to issue certificates.
(h) Clause 6.7.1 of the contract provided that if the suspension of the
whole or part of the works became necessary the engineer
was required to
instruct the contractor in writing to suspend the progress of the whole or any
part of the works for such time as
the engineer may think fit, and the
contractor was required to comply with the instructions.
(i) Clause 6.7.3 of the contract provided that unless a suspension was
due to default on the part of the contractor, the suspension
was to be treated
as if it was a variation.
(j) There are detailed provisions dealing with variations.
Given their significance to the case I deal with them
separately below at
[45].
(k) Clauses 12.7.3 and 12.7.4 of the contract provided that in the
event of unreasonable deduction of any amount from
any contractor’s
payment claim, or final payment claim required the principal was to
pay the contractor interest
compounding monthly at a rate of interest equal to
1¼ times the average monthly interest rate payable by the contractor for
overdraft facilities.
The claims
[4] CSL makes five different claims for variations to the construction contract. The first three relate to delays. The fourth and primary claim relates to works through inclement weather in winter.1 There is also a claim for miscellaneous matters. This is
addressed at [50].
1 As I will explain below, CSL pleaded that the Engineer
should have suspended the works through winter. This was abandoned at the
hearing
in favour of an amended claim for variation. Refer to [14]
below.
[5] The first of the delays involved the suspension of the tower
foundation work in the period 21 March to 24 March 2006. CSL
complains that it
was required to demobilise its work force from the tower foundation sites
pending the obtaining of the land use
consents. CSL says that as a result of
this suspension it was delayed in carrying out the tower foundation work for
four working
days. The defendant does not accept that the delay in obtaining
the land use consent was the problem; rather CSL was at
fault because
it unilaterally decided to commence the Tower works ahead of
schedule.
Road works suspension
[6] Road works had to be suspended on 30 March 2006 to resolve issues
identified by the Palmerston North City Council (Council).
CSL claims that the
Council advised it that NZ Windfarms had not completed the necessary resource
consent requirements to be able
to carry out the roading work and that the work
should not continue. CSL says it was forced again to demobilise and that it
was
delayed in carrying out the roading work for approximately two days. It
says that the engineer has failed to issue a variation
to take account of this
delay. NZ Windfarms says that the issue arose because of non-compliance by
CSL.
Further tower work delay
[7] There was then a further delay relating to the tower foundation
work on or about
24 April 2006. A building consent had not been obtained for the necessary
works but NZ Windfarms says that the plaintiff knew consent
had not been granted
and agreed to find alternative work. Nevertheless the plaintiff claims that it
was forced to demobilise its
work force away from the tower foundation sites and
that the suspension was in no part due to CSL’s work and that as a
result of the suspension CSL incurred additional costs to demobilise and
remobilise its work force and that the suspension
spanned nine working
days.
[8] The main claim relates to winter work. CSL contends that there
was unusually inclement weather in the period April 2006
to July 2006 affecting
the way that CSL could carry out its contractual obligations. CSL says that it
advised the engineer that
it was impossible to perform the work due to the
extraordinary inclement weather conditions and sought a suspension of the works.
It claims that the engineer failed or refused to suspend the works, and instead
issued variations to enable work to continue. The
primary variation is said to
be the relaxation of the compaction standard which then enabled CSL to work
through winter instead of
seeking an extension of time. Overall CSL submits
that the duration of the earthworks was significantly extended
and
the earthworks were significantly disrupted due to NZ Windfarms’
requirement for CSL to work through winter.
[9] NZ Windfarms accepts that the engineer subsequently issued a
variation to place
200 mm layer of river run metal on the road to the workface to
facilitate working continuing through winter and relaxed
requirements for
compaction. But NZ Windfarms says that the problem was that CSL under resourced
the works in winter, and that the
variations simply assisted CSL complete the
works as it had already promised to do.
Progress payment claims
[10] CSL claims it made various progress payment claims concerning the
above matters in the period March 2006 to February 2007
including as
follows:
(a) A variation claim as a result of the first and second suspension of
work at the tower foundations when the defendant did
not have the necessary land
use and building consents;
(b) A variation claim as a result of roading work being suspended when the defendant had not satisfied the necessary PNCC resource consent conditions;
(c) A variation claim as a result of additional P & G costs and
inefficiency costs as a result of having to carry out roading
and earthworks
during winter that otherwise would have been carried out in summer;
(d) A claim for additional road earthworks in excess of the tender quantities; (e) A variation claim in respect of two other minor items.
[11] NZ Windfarms denies that any variation claims were made in the
proper form. In any event, the engineer rejected the claims
as having no valid
basis.
Dispute resolution
[12] Attempts at dispute resolution and adjudication were fraught. Some
matters were resolved by the adjudication. Other matters
stalled while a debate
about proper notice was resolved. The Court of Appeal ultimately found that
appropriate notice was given,
with the result that the substantive matters are
now before me by agreement.2
Evidence
[13] The plaintiff produced evidence by Messrs Pohlen and Romanes of CSL, Mr Gair of Gair Contracting Ltd (GCL) and Mr Draper, an independent expert engineer. A single brief was produced on behalf of NZ Windfarms by Mr Murray David Fletcher. Mr Fletcher was the engineer to the contract. Messrs Pohlen, Romanes, Gair and Fletcher were primary actors in the narrative of events. Their evidence essentially chronicles their perspective of what occurred and why. I do not propose to restate their evidence as I address the primary facts in my assessment below. Mr Draper provides expert evidence on CSL’s approach to calculating the P and G and loss of productivity claims and the rates and factors used by CSL in its calculations. For reasons that will become clear, the significance
of this evidence is diminished given my findings on the winter work
claim.
2 Concrete Structures (NZ) Ltd v NZ Windfarms Ltd [2010] NZCA 450.
Preliminary issue - pleadings
[14] CSL’s second cause of action was based on an allegation that
the engineer was required to suspend works for the winter.
That claim was
abandoned at the hearing. Mr Blanchard sought instead to raise a fresh cause of
action, namely that the engineer
wrongly failed to approve a variation for works
associated with the relaxation of the loading specification. Initially Mr
Blanchard
sought to persuade me that he could run this claim without
amendment, presumably to avoid any limitation issue. But I
accept Mr
Smith QC’s submission that a revision of this nature needed to be properly
pleaded. Indeed it was not until I had
heard full argument on the issue that the
specific nature of the claim became clear.
[15] Against this, paragraph 55 of the latest amended statement of claim
expressly refers to CSL’s claims for variation
for works through the
winter period and that those claims were evidenced by the progress payment
schedules provided to the defendant.
Putting aside for one moment the issue of
limitation, it seems to me that the factual basis for variation of a claim is
foreshadowed
at paragraph 55 if not ventilated in the form of a cause of action
by failure to approve a variation to the works. The current pleadings
also
refer to the relaxation of the compaction specification and the work through
winter. Accordingly I do not consider that the
defendant is prejudiced by the
amendment to the pleadings in the manner sought, given that the facts underlying
the claim must have
been known to the defendant for some time.
[16] I deal with the issue of limitation below.
Issues
[17] I consider that the following issues require resolution
(following the late amendment to the
pleadings):3
3 This is largely drawn from the agreed statement of issues.
Delays
1. Who should bear the cost (if any) of the alleged four day
suspension of tower foundation work between 21 and
24 March
2006? (“Tower foundation suspension”);
2. Who should bear the cost (if any) of the alleged two day suspension of
work
between 30 and 31 March 2006? (“Road works
suspension”);
3. Who should bear the cost (if any) of the alleged suspension of
work
between 24 April and 4 May 2006? (“Further tower work
delay”).
Inclement weather
4. Should the engineer have approved a variation claim for the winter
works?
And
5. Who bears the risk of inclement weather?
(“Winter works”)
Miscellaneous
6. Who pays for the miscellaneous items?
Limitation defence
7. Is the [second] cause of action time barred? Contractual interest
8. Is contractual interest payable on any proven default? [18] I propose to
deal with each of the issues in turn.
[19] The central factual issue is whether NZ Windfarms agreed to modify the works programme so that CSL could undertake the construction of the tower bases in March
2006. Mr Pohlen was adamant that Mr Fletcher approved an amendment to the tender construction programme to allow the works to occur in March instead of April. He emphasised that the tender contract methodology expressly contemplated that the tower works and road works may, where possible, be undertaken at the same time. Mr Fletcher says that he made it clear that the resource consent required the completion of the road works first and that he was surprised that the towers works had already commenced on
20 March. He says that had the tower works commenced when scheduled there
would have been no need for any suspension.
[20] I think there is room for a difference of recollection on this issue. But I do not think that Mr Fletcher would have agreed to an amendment to the construction programme that would inevitably involve a clear breach of the resource consent conditions. Condition
9 states:
9. The Consent Holder shall compete (sic) the roading works required
and specified in the approved engineering plans (condition
8) prior to the
commencement of the construction works on the wind farm.
[21] The road works had not been completed by 20 March 2006. Works on
the tower bases should not have commenced before or on
that date.
[22] Subsequent actions taken by Mr Fletcher to regularise the position
by obtaining approval to weatherproof the tower works
is consistent with him
taking a prudent and compliant approach to the consent requirements.
Conversely it does not support
the inference that he was prepared to push on
with non-compliant works.
[23] In these circumstances, I find that CSL did not have the requisite
permission to commence the tower works and must
bear the cost of the
delay caused by the first suspension.
[24] CSL was ordered to suspend road works in the period 30 March 2006
and 31 March
2006. CSL contends that the Council stopped the works because NZ Windfarms
had not responded to a Council letter seeking confirmation
of certain items. NZ
Windfarms says the works were stopped because of poor traffic management by CSL
and its subcontractor on the
road works, GCL.
[25] A careful review of the contemporaneous record makes it tolerably
clear that the reason for the stoppage arose from NZ Windfarms’
failure to
respond to the Council’s letter. This is largely confirmed in a file
note dated 30 March 2006 of a conversation
between Messrs Fletcher, Pohlen and
Freear (of NZ Windfarms) which records:
Subject: PNCC letter of 9 March 2006
John/Chris
Attached is the mistery (sic) letter from PNDC (sic) of 7 March 2006. Our
reading of the letter is that we have approval to proceed
subject to meeting the
various conditions. These include supplying road opening notice and traffic
management plan. Both were
supplied early last week. The four
items, Land, Pavement Material, As Builts & Cut Batters, are all being
dealt with
as we proceed.
There is obviously confusion between Council Officers and ourselves which we
will get sorted out today and tomorrow. Mike Romanes
is still meeting with
Martin Skinner of PNCC today, I have asked both to ensure that minutes are
taken.
Regards
Murray
[26] I have also considered the concerns raised in an email from the Council on traffic management matters. Commonsense suggests that the majority of these matters could
have been dealt with without lengthy suspension.4
Further, the same email records:
4 The listed concerns were:
No correct Hi Viz vests worn onsite – Must be orange reflective vests
No STMS onsite – Needs correct yellow reflective vest
No Construction Zone approved. All unregisted [sic] vehicles must be noted and recorded for council & Land Transport records
Information sign at start of site is too small & has no contact phone number
Under the TW1 sign is an illegal company sign saying “NO ENTRY” on a public
road
TW1 Road work sign must be on each side with “NEXT 5km” supplementary
underneath
Meet Steve Galbraith, Gair Contracting Foreman, onsite (0920hrs). Concerns: With plans that the Council have – Tender Documents only.
That a letter sent to Jim Dale, Connell Mott MacDonald, had not been responded too – therefore work should not be progressing.
About site issues above
Steve holds a “Temporary Controllers Certificate” for Working on the Roads.
Level should be Site Traffic Management Supervisor (STMS). (Emphasis
Added)
[27] In these circumstances, NZ Windfarms must pay CSL for the costs of
the suspended works on 30 and 31 March 2006.
Further towers works suspension
[28] The tender construction programme envisaged works on the towers
commencing in April. By 10 April building consent still
had not been obtained
to allow the pouring of the concrete for the tower foundations. An email from
Mr Fletcher to Mr Pohlen on
this date records:
2 Building Consent. Spoke to head building inspector on last
Friday. He is aware of work on the site as he knows the guys
tying the steel.
He said that the consent should be ready by the end of this week, until then you
can complete the site concrete
and place and tie the steel, shutter up etc. You
are not to pour the main concrete until we receive the building
consent.
[29] On 24 April Mr Pohlen wrote to Mr Fletcher (cc Mr Freear),
noting:
We record that Tower Base 15 is completed ready for concreting, and that this
was booked for Wednesday 26th April.
30/100k signs must be on both sides. The 30 sign must have the word
“TEMPORARY” underneath it
Every 400m there should be a double side 30k sign with the word TEMPORARY
underneath them.
First site excavator clearing out drain channel – spoil on road surface that would belly out a car.
2nd Excavator – corner widening – held up for 5minutes – had to reverse 300m to let loaded work truck pass.
3rd Excavator – corner widening – road completely closed – no truck to load to. No way through –reversed 400m to turn around and go back.
Initial Establishment Site – Shipping container in the Road Reserve – no approval.
No toilet facilities noticed.
Blocked road culvert near first site with swale water flowing cross road width – limited traction here.
Further to your advice that the issue of the Building Permit is still
outstanding, we have cancelled this pour.
Due to the delays to date we have stood our crew down and will endeavour to
find alternative work to mitigate any further costs/losses.
In the event that
you wish us to remain on site and are happy to pay further standing charges
please advise immediately.
[30] This is then followed by a letter dated 26 April stating that Mr
Freear had contacted him and advised that the “crew
should remain away
from the site, pending the issue of a Building Permit”. He also
states:
I trust that Chris has since spoken to you, and request that in accordance
with Section 6.7 of the General Conditions of Contract,
you issue a Contract
Instruction suspending the Tower Foundations portion of the works.
[31] There is no response to this letter until about 3 May, in the form
of a letter from Mr Fletcher enclosing a copy of the building
consent. There
is however another letter dated 5 May detailing at length criticisms of
CSL’s project management, including
references to unsafe practices. More
specifically it records the following:
In regard to your facsimile dated 26 April 2006 regarding Mr Chris Freear’s
instruction to remain away from the site pending the issue of a Building
Consent.
1 The main concrete work cannot be carried out with[out] a Building
Consent. While the Consent has now been issued, this was
not the only reason
why the work could not proceed.
2 No concrete work can proceed until you have provided us with the tower
co-ordinates as set out.
3 The road must be made safe prior to concrete trucks using the road.
There has been debate over this, however, with the Department of
Labour letter, there is clearly work to be done prior to concrete trucks
using the road. It is the Contractor’s responsibility
to organise and co-
ordinate work in such a way to ensure that work dependent on other work is
carried out first and that safety
is maintained.
4 While you are instructed to suspend work on the supply and placing of
concrete for the five tower concrete bases, this does
not constitute a variation
to the contract.
[32] I do not consider that this response satisfactorily deals with the failure by NZ Windfarms to obtain building consent within the timeframe contemplated by the tender construction programme. In reality, whatever the work practices employed by CSL, it could not commence the tower pours until building consent was obtained. It was in fact and law, a condition precedent to commencement of any such work. In addition, had the
work practices of CSL been a major concern, I would have expected that the
detailed catalogue of criticisms would have been given
to CSL well before 24
April and certainly in immediate response to the letter from Mr Pohlen of that
date, especially if they were
going to relied upon for refusing to approve a
variation in accordance with cl 6.7.1.
[33] In the result, I am satisfied on the balance of probabilities that
the primary and major reason for the stoppage was the
failure to obtain building
consent. Conversely I am not persuaded that CSL’s allegedly poor
construction standards materially
contributed to this stoppage. I reject also
any suggestion that NZ Windfarms was not properly on notice of this claim. The
abovementioned
correspondence clearly placed the engineer on notice whatever the
precise requirements of the construction contract.
The winter works
[34] The road works were affected by inclement weather, including heavy rain and on occasion snow. Mr Gair was responsible for the road works. He attests to the fact that the conditions were very trying. Various extensions were sought and obtained for the works.5
As Mr Blanchard put it, by 24 May 2006 the contract had reached a cross
roads. CSL and GCL claimed that the works had become impossible
and something
needed to be done. Mr Pohlen suggested three alternatives with indicative costs,
namely:
(a) Continuing work through winter until completion at an estimated cost
of
$150,000;
(b) Continuing work through winter with relaxed compaction standard
and using borrowed fill ex windfarm site at an estimated
cost of
$120,000;
(c) Winter close down and remobilise next spring at an estimated
cost of
$80,000.
[35] The second option specifically noted that the specified compaction standard has not been achieved and that the cut materials that they are using are variable and moisture
sensitive and is currently wet of optimum.
[36] A response was received
from Dr Jan Kupec of Connell Wagner on the same day stating:
We are willing to reduce our acceptance criteria to Maximum Dry Density in
order to progress the job. The required densities are
only few per cent of the
optimum moisture content and we infer that the material:
a) is highly variable, being cut waste from roading;
b) is slightly off optimum moisture content; and
c) Can be selected from suitable sources, i.e. rotten rock outcrops.
We are willing to accept average densities of 95% of MDD for all fill
operations. This should allow for soil variation, slightly too
wet or too dry
in-situ material and rapid construction progress. We also note that due to
highly variable fill the occasional
test may indicate slightly lower bound
results. Which we ask you to forward to us for discussion.
I would appreciate if you would be able to confirm the above with Murray
Fletcher or myself in order to clarify the timing and inform
our
client.
[37] Mr Fletcher also endorsed the use of additional gravel fill for the
length of the roads to assist progress. The cost of
this was subsequently
approved by way of formal variation. But additional costs of the winter works
said to be enabled by the
relaxation of the compaction standard were never
approved.
[38] Mr Blanchard submits that CSL must be entitled to the costs of the
winter works enabled by the variation to the compaction
standard, as without
that variation CSL would have been able to obtain an extension of time and
avoided those costs. He submits
that NZ Windfarms approved the variation so
that it could meet its own contractual obligations to third parties.
[39] I am unable to accept this argument. My reasons follow.
[40] First, as Mr Smith submitted the contract apportioned the risk of
inclement weather to CSL for the purpose of time
extensions and claims
based on unforeseen weather conditions. More specifically, special cl
10.3.1 allows ten days for inclement
weather. Further extensions are permitted
for inclement weather, but cl 10.3.7 of the special conditions states:
Approval of an extension of time by the Engineer shall not be grounds for payment of Time Related Expenses. Any costs associated with an extended contract period shall be borne by the Contractor.
[41] Under cl 9.5 a contractor can claim increased costs for
unforeseen physical conditions as a variation. But cl
9.5.1 specifically
excludes weather conditions from the definition of unforeseen physical
conditions, unless those conditions occur
as a result of weather away from the
site.
[42] A corollary of these combined provisions is that CSL must have
appreciated that weather related losses per se were not recoverable.
It would
be remarkable then that CSL could claim essentially time based weather related
costs under the auspices of a variation
relaxing the specification
requirements.
[43] Second, the relaxation variation reduced the standards for
compliance, but did not by itself increase the scope of works.
This has two
related consequences. CSL was not “required” to do any works that
it was not already contracted to provide
and therefore was not
“required” by the variation to extend the period of works. Quite
the opposite, the variation
was beneficial to CSL because it shortened the
period of required works.
[44] Third, I do not think that NZ Windfarms could have reasonably
expected that relaxing the compaction standard would expose
them to the full
additional costs of the weather related costs. Notably provision was made and
agreed for the additional gravel.
But nothing was agreed for the relaxation or
the additional time specifically involved with the ongoing road works enabled by
this
relaxation. Mr Pohlen’s letter of 24 May refers to “additional
downtime due to work out of season” in relation
to his options. But there
is no clear explanation that this in fact means all additional work over the
winter period. On its face
it simply refers to “downtime” not
additional works.
[45] Fourth, I think that given the care taken with variations in the contract, NZ Windfarms could have expected a detailed breakdown of the additional costs attributable to the relaxation prior to the works continuing. Yet there is nothing even approximating to the procedures envisaged by the contract for the valuation of variations. It is worth noting in this regard the specific requirements of s 9 of the contract dealing with variations and valuation of variations.6 Clause 9.1.1(c) contemplates variation for changes in character or quality of work. The relaxation of the compaction standard qualifies under
this heading. Clause 9.3 then provides a detailed methodology for
valuation of changes by
6 Refer s 9 NZS 3910:2003.
agreement (9.3.1), before the work is done (9.3.2) and where the change in
work needs to be measured, there shall be an exchange of
evidence supporting
calculations of those measurements (9.3.3). If there is an applicable schedule
of prices, it should be applied
to derive the Base Value7 of the
additional works (9.3.4) and where there is no such schedule, and it would not
be reasonable to derive new prices under the
schedule, then the Base Value
should be determined on the basis of Net Cost.8 Allowances are then
to be provided for such things as on site overheads (9.3.8) and where the
contractor is entitled to an extension
of time, for related costs together with
an allowance for profit (9.3.10). It appears that none of these clauses were
considered,
let alone complied with, at the time of the variation or
subsequently.
[46] Fifth, the value of the claimed additional works was not quantified
until well after they had been completed. Not only is
this contrary to the
process envisaged at cl 9, but an essential term, that is the price of the
additional works, was uncertain
throughout. Indeed, CSL left open the value of
the works and simply submitted process payments claims for “Additional P
&
G costs associated with increased scope of work, inefficiencies due to
working in winter period” with the relevant sums described
as
“TBA”. I accept that Mr Fletcher did not immediately reject the
claims. But that would have been hard to do given
that they were not quantified
at all. An outright rejection could have been perceived to be arbitrary,
invoking dispute resolution
procedures and adding still further cost and delay
to the project. In any event, the lack of certainty on a key term, ie price
until
well after the works were completed strongly militates against the
inference that NZ Windfarms agreed to it when it relaxed the compaction
standard.
[47] Sixth, I accept that cl 9 contemplates some latitude on the timing of valuation of works that is when practicable. But I do not consider that it was impracticable for CSL to submit evidence as to the value of the works contemporaneously with the progress claims or indeed before the works were undertaken. GCL kept a record of its road work
attendances. It would have been a simple enough matter to collate from
those records a
7 BASE VALUE refers to the prices or rates applicable to the circumstances and nature of the work or part of the work.
8 NET COST means the actual or assessed expense or direct cost to the Contractor of the Variation, plus return on investment in Plant, after deduction of trade discounts and exclusive of the Contractor’s On - Site Overheads, Off-Site Overheads and Profit.
suitable rate for the additional works and submit the rate to NZ Windfarms
for approval. Ultimately that is what CSL in fact did when
it finally quantified
its claim.
[48] Seventh, I do not accept that CSL could simply have sought a time
extension to avoid all work during the winter and thus
avoided the additional
cost while leaving the risk of delay with NZ Windfarms. Any extension would
have to be assessed on a case
by case basis so as to determine whether an
extension was reasonably necessary. I am highly doubtful that Mr Fletcher
would have
simply approved an unqualified cessation. Furthermore, the entire
risk of delay did not sit solely with NZ Windfarms. CSL had managed
to exclude
liquidated damages for delay. But CSL remained liable for unliquidated damages
for non-compliance with time for completion.
The counterfactual was therefore
implausible and does not lend weight to CSL’s case.
[49] Accordingly for reasons of process and substance, I do not
consider that the relaxation of the compaction standard
provided a proper
basis for a variation for winter works.
Miscellaneous items
[50] CSL makes claims for three miscellaneous items: (a) Geotextile valued at $3,830.40
(b) Filter cloth valued at $2,240 (c) Fencing valued at $3,870.
[51] Mr Pohlen says he called Mr Fletcher to get approval for the geotextile and filter cloth rather than make additional undercuts to the subgrade. This was not provided for in the contract. Apparently there was no objection to this registered by Mr Fletcher. Evidence given by Mr Gair however suggests that when Mr Pohlen tried to but did not reach Mr Fletcher about these items and simply instructed Mr Gair to purchase them. This brings into focus the need to comply with the processes laid out in the contract. Regrettably, whatever the underlying merits of Mr Pohlen’s claim, he did not follow those procedures, so that there is no record of the variation having been formally sought let alone
approved. In the absence of this record, and in circumstances where the
evidence is equivocal, the plaintiff cannot succeed in this
claim.
[52] The fencing is in a different category. While the documentary
record is also sparse on this issue, I am satisfied that Mr
Fletcher requested
that CSL to undertake, among other things, fencing to block walls works on a
neighbour’s property given
a communication from Mr Pohlen dated 10 August
2006 seeking fencing details. There is also an email dated 26 August from Mr
Fletcher
that Mr Arnold Chamove, the neighbour, was not happy with the works
carried out on his land, and that “NZ Windfarms are prepared
to pay for
any reasonable extra work required by Arnold”. Mr Pohlen later responds
on 4 September that Mr Chamove “would
be satisfied if he received a new
fence”. Mr Fletcher then says there remain issues with Mr Chamove in a
letter dated 19 January
2007. Mr Pohlen replies in a fax to Mr Fletcher dated 2
February 2007 that he has spoken to Mr Chamove who had “no outstanding
issues”. Against this background, it was and is for Mr Fletcher to
justify why he should not pay for the fencing works. He
was equivocal at best
about this under cross- examination. The most persuasive evidence therefore is
that the neighbour is now
not unhappy, so the reason for not paying has gone
away.
[53] Accordingly, NZ Windfarms must pay for the fencing
works.
Limitation
[54] In light of my findings on the winter works claim I apprehend that the limitation issue is now moot. It was originally pleaded by way of affirmative defence to the “second cause” of action. At the time of this pleading it was addressing a claim based on the Contractual Remedies Act 1979 and misrepresentation, but that claim did not resurface in subsequent pleadings. The current version of the second cause of action relates to the winter works and the failure to approve a variation. As noted above, Mr Smith objected to this late amendment and also submitted it was now time barred. I do not agree. The essential claim was filed in time (September 2008). The key facts upon which the claim is based have been pleaded throughout. The action is not therefore time barred.
Contractual interest
[55] CSL claims that contractual interest is payable on the unpaid suspension or variation claims, because they were “unreasonable deductions” for the purpose of cl 12.7.3. NZ Windfarms contends that cl 12.7.3 is a punitive clause deliberately designed to discourage not simply non or late payment of amounts due and owing and/or late certification, but an “unreasonable” deduction. In this context it is said that “unreasonable” means serious default, including irrational, perverse, or bias behaviour.9
There is also the suggestion that the test is essentially subjective,
namely that if the
engineer honestly considered that the deduction was reasonable, then absent
irrationality10
or impropriety, the decision should be deemed to be
reasonable.11
[56] Given the central importance of cl 12.7.3 I repeat it in full
here:
12.7.3 In the event of unreasonable deduction of any amount
from any Contractor’s payment claim or final payment claim being
made in
any Payment Schedule, and where such amount is later paid by the Principal or
found by an adjudicator to be payable by
the Principal, the Contractor
shall be entitled to interest compounding Monthly on that amount from the
date on which it
would have been payable if the unreasonable deduction had not
occurred down to the date of payment.
[57] The plain meaning of “unreasonable” in context12 connotes something more than simple default, but does not require proof of bias or impropriety as suggested by NZ Windfarms. The Oxford dictionary helpfully refers to “going beyond what is reasonable or equitable, excessive”.13 Therefore the litmus test is simply whether the decision of the engineer to decline to make payment was reasonable or fair in the particular circumstances, acknowledging that the construction process relies heavily on timely payment for costs
incurred.
9 Citing authority that emphasises the importance of impartiality: Canterbury Pipelines Ltd v
Christchurch Drainage Board [1979] 2 NZLR 347 (CA).
10 In the sense of a deduction that “no reasonable engineer, properly directing himself or herself to the
facts, could possibly take on the information available”.
11 Citing Secretary of State for Transport v Birse-Farr Joint Venture (1993) 35 ConLR 8 and Royal
Borough of Kingston-Upon-Thames v AMEC Civil Engineering Ltd (1993) 35 ConLR 39.
12 As to the relevance of context, refer Vector Gas Ltd v Bay of Plenty Energy Ltd [2010] NZSC 5, [2010]
2 NZLR 44 at [119].
13 Lesley Brown (ed) The New Shorter Oxford English Dictionary (Clarendon Press, Oxford 1993) – see
definition of “unreasonable”.
[58] I reject an essentially subjective test of reasonableness. The engineer when deciding to certify payment was performing a contractual duty, not exercising an unfettered discretion of an administrative law kind.14 In the absence of clear words,15 I am not prepared to assume that commercially minded contracting parties engaged on the basis that their entitlements are dependent on whether the engineer was acting irrationally in the sense that no reasonable engineer would act in that way. In the context of deductions, such a threshold test could perversely favour the Principal because the ability to seek contractual interest would be very difficult, even though the clear object of the condition is to
encourage timeous payment.
[59] Plainly an adjudicator or Court must bring some commercial
commonsense to the assessment, and acknowledge the difficult circumstances
under
which an engineer must operate. Where appropriate, deference must be given to
the engineer’s on the ground assessment
of the facts. But ultimately the
test of reasonableness must be an objective assessment and requires a
careful examination
of whether the reasons given for non payment were
justified.
[60] I now turn to examine each of the defaults. I preface my comments
with the observation that none of the defaults involved
particularly complex
facts, so there is no need for undue deference to the engineer’s
assessment.
[61] The road suspension was due to the failure by NZ Windfarms to reply to a letter from the Council. The issue of poor road management raised by Mr Fletcher may have aggravated the Council’s discontent, but it was not the major reason for the suspension. An engineer, acting reasonably, would have acknowledged this and agreed to account to CSL
for associated costs.
14 Even administrative law struggles with the application of this concept – R v Secretary of State for the
Home Department ex parte Daly [2001] UKHL 26, [2001] 2 AC 532 at 548 per Lord Cooke.
cases the engineer was required to certify “the amount which in the opinion of the Engineer...is due”.
As Hobhouse J observed in the first case: “Therefore the obligation of the engineer is in each case expressed to be to form an opinion or to decide what he considers is proper” (at 25). By contrast, Section 12 in the present case dealing with payments does not make certification conditional on the “opinion” of the engineer. Rather the engineer must state his reasons, which is a clear pointer to the substantive reviewability of his decision.
[62] The further tower works delay was due to the failure by NZ Windfarms
to obtain a building consent. Ample warning was given
to the engineer of the
problem presented to CSL if pouring of the concrete could not proceed on
time.16 Conversely the problems with CSL work management practices
were not outlined in detail until after the period of the delay. As with
the
previous default, an engineer acting reasonably, would have acknowledged the
major reason for the delay, and agreed to account
for CSL’s associated
costs.
[63] Similarly, the costs associated with the fencing should have been
approved from 2
February 2007 when there was no objective reason to decline payment for them. [64] Accordingly contractual interest is payable on all proven claims.
Result
[65] Given my above findings I resolve the key issues as
follows:
(a) CSL must bear the cost of the tower foundation suspension between 21
and
24 March 2006;
(b) New Zealand Windfarms must pay CSL for the costs of the roadworks
suspension on 30 and 31 March 2006;
(c) New Zealand Windfarms must pay CSL the costs of the further tower work
delay between 24 April and 4 May 2006;
(d) The engineer was not required to approve the variation claim for the
winter works;
(e) CSL bore the risk of inclement weather;
(f) New Zealand Windfarms must pay CSL the costs of the
fencing;
16 There was some suggestion in the evidence that CSL indicated that it would seek alternative work. But that could not be a reason to refuse payment for delay if no alternative work was found. At most, had alternative work been found, this may have reduced the quantum of the loss payable by the engineer.
(g) The second cause of action (the winter works claim) is not time barred;
and
(h) Contractual interest is payable on the sums owed for the road
works suspension, the further tower delay and the fencing.
[66] I will leave it to the parties to resolve quantum and revert to the
Court if necessary within 15 working days.
[67] The parties have 15 working days to seek costs if they cannot
be agreed. Submissions on costs must not be greater
than five pages in
length.
Solicitors:
Kevin A Badcock, Rotorua
Anthony Harper, Christchurch
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/2118.html