Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 16 October 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2012-404-6491 [2014] NZHC 2156
BETWEEN
|
SHAOHE ZHANG
Plaintiff
|
AND
|
XIAOJUN ZHAI and AIDONG ZHANG Defendants
|
Hearing:
|
8 August 2014
|
Appearances:
|
E St John and D Liu for Plaintiff
C Henry for Defendants
|
Judgment:
|
8 September 2014
|
JUDGMENT OF TOOGOOD
J
This judgment was delivered by me on 8 September 2014 at 3:0 pm
Pursuant to Rule 11.5 High Court Rules
Registrar/Deputy Registrar
ZHANG v ZHAI & ANOR [2014] NZHC 2156 [8 September 2014]
Introduction
[1] In 2003, the plaintiff, Mr Shaohe Zhang, and the defendants, Mr Xiaojun Zhai and his wife Ms Aidong Zhang, entered into a sale and purchase agreement (“the agreement”) for a property in Auckland. Although the plaintiff paid a deposit, the transaction was never completed. In 2012, the plaintiff served a settlement notice on the defendants. When they refused to settle, the plaintiff filed an application for specific performance. I granted that application in a judgment delivered on 16 May
2014 (“the principal judgment”).1 The defendants have
since appealed that decision.
[2] In the principal judgment, I reserved leave to the parties to apply
for any further orders that were necessary or desirable
to give effect to the
order for specific performance.2 The parties have been unable to
agree on precisely what the order requires. That is the subject of this
decision.
Facts
[3] The facts are described fully in the principal judgment at
[6]-[18]. They may be briefly restated. On 3 August 2003, the
plaintiff agreed
to buy the defendants’ property in New Lynn, Auckland (“the
property”) for a price of $348,000.
The agreement was unconditional
except for the issuing of a new title. The agreed possession date was
the later of 3 November
2003 or five days after the issue of the title. Title
was issued on or about 22 June 2004. The defendants did not notify the plaintiff
that the title had been issued but the plaintiff and his solicitor soon became
aware that this was the case.
[4] Construction of the house on the property was completed in December 2003. Under the agreement, the defendants warranted that at the date of possession the property would comply with the requirements set out in the Building Act 1991 and would have a code compliance certificate (“CCC”). However, the property failed final code compliance inspections and the Council declined to issue a certificate. A
notice to rectify was issued by the Council.
1 Zhang v Zhai [2014] NZHC 1026, [2014] 3 NZLR 69.
2 At [71].
[5] On 27 January 2004, the defendants claimed through their solicitors
that the agreement was frustrated and sought confirmation
that the plaintiff
would “withdraw from the alleged agreement”. The plaintiff
declined to regard the agreement
as frustrated. A determination on behalf
of the Chief Executive of the Department of Building and Housing, released on 28
October
2005, held that the refusal to grant the CCC was justified because of
identified defects attributable to poor workmanship. The determination
held that
rectification of the defects to the Council’s approval would likely result
in compliance with the Building Code but
the remedial work was not undertaken
and no CCC has ever been issued for the property.
[6] It appears the defendants moved into the property when construction of the dwelling was complete and that they lived there until sometime in 2008. In about March 2008, the defendants listed the property for sale on the open market but withdrew the listing in May 2008. The property was rented out by the defendants from 2008 and at the date of hearing they were receiving rent from the property of
$700 per week.
[7] Not long after becoming aware that the defendants had misgivings about the transaction in November/December 2003, the plaintiff lodged a caveat against dealing which lapsed in mid-2004. The plaintiff lodged a second caveat on 4 March
2008 but he never tendered the amount to settle required by the agreement and
did not demand performance by the defendants at that
stage. There was a further
long period of inactivity and it was not until 11 May 2012 that the plaintiff
arranged for service of
a settlement notice on the defendants. The defendants
refused to settle the transaction and on 1 November 2012 the plaintiff filed
the
present proceeding.
The principal judgment
[8] The plaintiff sought specific performance of the agreement. I said
in the principal judgment that:
[19] ... It is common ground that equitable title to the property has already passed. The plaintiff seeks an order compelling the defendants to transfer legal title to the property to him on the basis of the purchase price that was agreed in 2003, namely $348,000. He also says, however, that interest payable by the defendants for late settlement has accrued at the default rate
set out in the agreement and that at the date of hearing it amounted to not
less than $283,000. In effect, therefore, the plaintiff
seeks an order
compelling the defendants to transfer legal title to him for net consideration
of around $65,000 for the property,
calculated as at the date of
hearing.
[20] In July 2011 the property was assessed as having a current capital value
for rating purposes of $540,000.
[9] According to the latest documents presented by the plaintiff, as at
23 May
2014 the default interest owed by the defendants had increased to
$331,221.64.3
[10] The defendants argued various affirmative defences to the plaintiff’s claim – that it was barred by analogy under s 4 of the Limitation Act 1950; that it was barred by laches; and that performance of the agreement was frustrated. They also argued that the plaintiff had failed to comply with his own contractual obligations. None of these defences succeeded. In respect of the Limitation Act argument, I held that claims for specific performance are not barred by limitation by analogy.4 In dismissing the laches argument, I relied on Supreme Court authority that equity has been most reluctant to accept that an equitable interest in land can be “lost or
destroyed by mere inaction” and that this defence requires not just
delay but also prejudice;5 financial hardship suffered by the
defendants was not sufficient. I held that the defendants must have been aware
that under the agreement
they were liable to pay default interest but they chose
to ignore that risk. I also found that the delay was not attributable to
the
plaintiff alone and in any event he had taken steps to demonstrate his interest
in settling the transaction by lodging two caveats
against dealings.6
I found that frustration was not made out either, as the authorities are
clear that “it is not sufficient that the contract
has become
more burdensome or performance more expensive”.7 Specific
performance was ordered in the following terms:8
I direct that the defendants shall settle the agreement with the plaintiff
for the sale and purchase of the property at 23A Margan
Avenue, New Lynn (CT
NA854/224) forthwith...
3 Letter from the plaintiff ’s solicitor, dated 19 May 2014.
4 P & O Nedlloyd BV v Arab Metals Co (No 2) [2006] EWCA Civ 1717, [2007] 1 WLR 2288.
5 Eastern Services Ltd v No 68 Ltd [2006] NZSC 42, [2006] 3 NZLR 335.
6 Zhang v Zhai, above n 1, at [52].
7 The Power Co Ltd v Gore District Council [1997] 1 NZLR 537 (CA) at 553.
8 Zhang v Zhai, above n 1, at [71].
Defendants’ submissions
[11] Claiming to be entitled to further consideration of the remedy
granted under the leave reserved, the defendants submit that
substantial
amendments should now be made to the terms of the agreement which they have been
directed to perform. They ask that:
(a) the agreed purchase price for the property be revised to reflect
today’s
market value;
(b) they be relieved of their contractual obligation to pay default
interest to the plaintiffs, or that both parties are ordered
to pay default
interest to each other; and
(c) they be relieved of their contractual obligation to secure a CCC
for the property.
[12] While Mr Henry acknowledges that he is asking the Court to rewrite key terms of the agreement in its order for specific performance, he submits this is possible because the underlying agreement is unenforceable at law due to the operation of the Limitation Act 1950. He argues that the order for specific performance meant no more than that the defendants must transfer legal title to the plaintiff. It follows, in counsel’s submission, that the terms of the transfer can be determined by the Court on the basis of what is equitable between the parties, with reference to the principle that specific performance is intended to put both parties in the same position as if their respective contractual obligations had been timeously
performed by both of them. The defendants cite Singh v Nazeer9
for the proposition
that the original agreement must yield to whatever conditions are set by the Court in the order for specific performance, and point to other authority stating that specific
performance “may be granted subject to
conditions”.10
9 Singh v Nazeer [1979] Ch 474.
10 R Meagher, D Heydon and M Leeming Meagher, Gummow & Lehane’s Equity: Doctrines and
Remedies (4th ed, Butterworths LexisNexis, Chatswood (NSW), 2002) at [20-275].
[13] On that basis, it is submitted that it is inequitable to allow the
plaintiff to have the property according to the agreement’s
original terms
because of the substantial increase in property values that has occurred since
the agreement was signed. To do so
would allow the plaintiff to have the benefit
of both the capital gain and the property’s purchase price (less the
deposit),
which he never paid over to the defendants. The defendants also
submit that, had the plaintiff transferred the purchase
price to them in
2004, they would have used it to purchase another property which would have
enjoyed a similar increase in value.
As things stand they have missed this
opportunity. Relevant also to the consideration of the respective equities, they
submit, is
the fact that the plaintiff did not seek to “mitigate his
loss” after signing the agreement.
Plaintiff ’s submissions
[14] The plaintiff submits that the order for specific performance
requires the contract to be performed according to its terms
so far as that is
possible and he resists any amendments being made to the agreement. He submits
that even if the Court had the power
to rewrite the agreement, equity would not
support the conditions contended for by the defendants, because:
(a) Had the agreement been settled in a timely manner, the plaintiff
would have had the benefit of being able to either live
at the property or
receive rental income for the past 10 years.
(b) The authorities confirm the principle that the fruit of the
property, including any capital gain, belong to the purchaser
from the agreed
date of settlement.
(c) There is no support for the defendants’ argument that the plaintiff
ought to have mitigated his loss by purchasing another house.
(d) There is no reason why the defendants should be relieved of their
obligation under the agreement to provide a CCC.
Amending the terms of the agreement
[15] Specific performance is a discretionary remedy that is awarded
according to equitable principles.11 However, there is no basis for
the defendants’ submission that when ordering specific performance the
Court can embark on a
wholesale rewrite of the contract. Specific performance is
a means by which parties are held to the bargain they entered into.
It is a
remedy which requires a party “to act consistently with the contract of
sale”.12 In the words of Miller J, “It is not for the
Court to modify the agreement before ordering that it be
performed.”13 If the court were to do so, it would risk holding
the parties to an agreement they never intended to make.
[16] But in some instances it is necessary for the Court to amend the
terms of the agreement in order that it can be performed. Singh v
Nazeer14 is authority for this limited proposition – not
for the wider interpretation favoured by the defendants. The relevant passage
by
Megarry J is worth quoting at length:15
First, it seems clear that when an order for the specific performance of a
contract for the sale of land is made, the contract continues
to exist and is
not merged in the order... That, however, does not conclude the point before
me. To say that a contract still exists does not necessarily mean that the
exercise
of the rights that it confers remains unaffected by an order for
specific performance of that contract.
Second... By applying to the court for an order of specific performance,
and obtaining it, I think that the applicant has put it into the hands
of the
court how the contract is to be carried out. As the court has become seized
of the matter, and has made an order, it seems to me that subject to anything
that the parties may
then agree, the working out, variation or cancellation of
that order is essentially a matter for the court. The continued existence of
the contract is one thing, its working out is another.
Third, it seems plain that in ordinary circumstances the machinery provisions
of a contract for the sale of land are intended to govern
the carrying out of
the contract between the parties out of court, and are not directed to carrying
it out when an order for specific
performance has been made. That order is
made, of course, by reference to the rights of the parties under the
contract;
11 Laws of New Zealand Specific Performance (online ed) at [5].
12 Tom Bennion and others New Zealand Land Law (2nd ed, Thomson Reuters, Wellington, 2009) at
[1.5.06].
13 Serepisos v Steele (No 1) HC Wellington CIV-2003-485-1335, 13 August 2004 at [75].
14 Singh v Nazeer, above n 9.
15 At 480-1.
but, when made, it is the provisions of the order and not of the contract
which regulate how the contract is to be carried out. Provisions
in the contract
as to the deduction of title, the preparation and delivery of the conveyance,
the mode and date of completion and
many other matters must all, it seems to me,
yield to any directions on these matters which are given in or under the order
for specific
performance. Mr. Ritchie attempted to drive a wedge between
compliance with contractual obligations and compliance with the order for
specific
performance, emphasising that a failure to comply with the order
was not a breach of contract but was a contempt of court, and
so on. I think
that this approach is ill-founded. It gives little or no weight to the
consideration that the order of the court is
not independent of the contract,
but is the court's order as to how that contract is to be carried out, replacing
the mode in which
it should have been carried out had no order been
made.
[Emphasis added.]
[17] Two points are evident. First, when an order for specific performance is made, the underlying contract continues to exist and is not merged in the order.16
This indicates that, generally speaking, the relationship between the parties
continues to be governed by the terms of the contract.
Second, the contractual
terms the court may rewrite in order to give it effect are what might be called
the “machinery provisions”
of the contract, such as “deduction
of title, the preparation and delivery of the conveyance, the mode and date of
completion
and many other matters”. Amending these terms will often be a
matter of practical necessity because disputes have meant that
the contract can
no longer be carried out according to the timetable and in the way initially
envisaged by the parties. As Megarry
J said, “The continued existence of
the contract is one thing, its working out is another.” Rewriting the
essential terms
of the contract, such as the purchase price and the obligation
to provide a CCC, would be to substitute the original contract with
another.
[18] Specific performance may be ordered on conditions.
Spry’s Equitable
Remedies says:17
... in many cases specific performance may be ordered in a conditional or
limited form. [Citing Hutchinson v Payne [1975] VicRp 17; [1975] VR 175 (SC).]
For example, a condition may be appropriate that the plaintiff should pay
interest in order not to obtain
an unjust benefit. [Citing Harvela
Investments Ltd v Royal Trust Company of Canada (CI) Ltd [1986] 1 AC 207
(HL).] Further,
16 This was followed in Jansen v Whangamata Homes Ltd HC Hamilton CIV-2003-419-1511, 22 May
2006 at [39]: “A decree of specific performance does not cause the contract to merge with the order. The contract remains operative and enforceable unless varied by the Court...”
17 ICF Spry The Principles of Equitable Remedies (9th ed, Lawbook Co, Pyrmont (NSW), 2014) at
207.
specific performance may properly be ordered of agreements for the sale of
land, although there has been a misdescription of quantity
or title, where
justice can be sufficiently done through the payment of compensation or through
an abatement of the purchase price.
[19] Issuing an order for specific performance is an exercise of judicial discretion and must be carried out in a principled way.18 The cases cited in the passage by Spry provide some concrete examples. Conditions concerning compensation or abatement of the purchase price may be justified on the basis that there is a deficiency in what the vendor promised to convey.19 In other instances the adjustments are made on the basis of the equitable principle that, subject to any contractual provision to the contrary, from the date of settlement in a contract of sale the fruits of the property belong to the purchaser and the fruits of the purchase money belong to the vendor.20
Hutchinson v Payne,21 for example,
concerned a sale and purchase agreement for a
property. Delay in settlement was the fault of the defendant vendor, but the plaintiffs were ordered to pay interest on the purchase money for the period of the dispute because they had for that time lived in the property rent free. In Harvela Investments Ltd v Royal Trust Company of Canada (CI) Ltd,22 when the defendant vendor had caused delay in the transfer of a parcel of shares – although it had not acted unreasonably – and the value of those shares had risen substantially in the interim,
the plaintiff purchaser was ordered to pay interest on the purchase
price. Lord Templeman said: “Harvela are not
entitled to the benefit of
interest attributable to the purchase money as well as the profits attributable
to the contractual property.”23
[20] There is force in the defendants’ submission that the plaintiff should not have the benefit both of the property’s capital gain and the purchase money that it has retained all these years. However, the agreement addresses that issue at cl 3.10, which governs the payment of interest for late settlement when the vendor is in default. The clause states:
3.10 (1) For the purposes of this subclause 3.10: (a) the default period
means:
18 Attorney-General for England & Wales v R [2002] 2 NZLR 91 (CA) at [94] per Tipping J.
19 See for example Peacock v Penson [1848] EngR 859; (1848) 11 Beav 355, 50 ER 854 (Ch).
20 Harvela Investments Ltd v Royal Trust Company of Canada (CI) Ltd [1986] 1 AC 207 (HL) at 236.
21 Hutchinson v Payne [1975] VicRp 17; [1975] VR 175 (SC).
22 Harvela Investments, above n 20.
23 At 237.
(i) in subclause 3.10(2), the period from the possession date
until the date when the vendor is able and willing to provide
vacant possession
and the purchaser takes possession; and
...
(2) If this agreement provides for vacant possession but the
vendor is unable or unwilling to give vacant possession
on the possession date,
then, provided that the purchaser is not in default:
(a) the vendor shall pay the purchaser, at the purchaser’s
election, either:
(i) compensation for any reasonable costs incurred for
temporary accommodation for persons and storage of chattels
during the default
period; or
(ii) an amount equivalent to interest at the interest rate for
late settlement on the entire purchase price during the
default period;
and
(b) the purchaser shall pay the vendor an amount equivalent to
the interest earned or which would be earned on overnight
deposits lodged in the
purchaser’s solicitor’s trust bank account on such portion of
the purchase price (including
any deposit) as is payable under this agreement on
or by the possession date but remains unpaid during the default period
less:
(i) any withholding tax; and
(ii) any bank or legal administration fees and commission charges;
and
(iii) any interest payable by the purchaser to the purchaser’s
lender during the default period in respect of any mortgage
or loan taken out by
the purchaser in relation to the purchase of the property.
[21] By the terms of the agreement, the defendants’ liability to
pay interest for late settlement is offset against the
plaintiff’s
liability to pay interest on the purchase money for the period in which he has
had the benefit of it.
[22] As to the Court’s power to revise the default interest clauses
to avoid inequity
in ordering specific performance, authorities support the plaintiff’s contention that
the terms of the underlying contract should apply. Varney v Anderson24 and Jansen v Whangamata Homes Ltd25 are cases in which the parties had returned to court for further directions following orders for specific performance of property agreements. In each case, the purchasers had been successful against the vendors in default. The
issue was how much the purchasers were required to pay: the purchase price as
stated in the agreement, or that sum offset by the vendors’
contractual
liability for default interest. In both cases, the purchasers were held to be
entitled to rely on their strict contractual
rights and tender the reduced
purchase price.
[23] In Varney, it was held that the order for specific performance of a sale and purchase agreement expressed “in terms of the agreement” was just what it seemed – the contract was to be performed on its terms as stated, including provisions as to liquidated damages. In Jansen, the Court similarly held that the purchasers were entitled to pay the purchase price less the penalty interest that had accrued under the
contract. It was said of the Jansens’ right to
interest:26
A decree of specific performance does not cause the contract to merge with
the order. The contract remains operative and enforceable
unless varied by the
Court and the Jansens retained their accrued benefit... at the date of the
decree Whangamata had been in default
since March 2004, even since October 2003,
and was vulnerable to the present claim for liquidated damages. If Whangamata
had wished
to be excused that liability it ought to have raised that with the
Court and it did not... The price was not just the nominal sum
owing. It was the
price properly payable under the agreement. That price was open to be offset by
a proper claim for interest for
late settlement.
[24] The cases do not state that there is no jurisdiction for a court to
vary the contractual provisions governing default interest
in ordering specific
performance. However, they do demonstrate that, generally:27
Where there has been a dispute leading to litigation, resulting in a finding
that the vendor is in default and ordering specific performance,
the amount
payable on settlement is to be determined in accordance with [the contractual
clause concerning default interest] without
any express order to that effect by
the Court. The clause is a part of the contract and an order for performance in
terms of the
contract includes the clause; the onus is rather on the vendor at
the hearing to seek relief from the consequences of the clause.
24 Varney v Anderson (1992) 2 NZ ConvC 191,347 (CA).
25 Jansen v Whangamata Homes Ltd, above n 16.
26 At [39], [46] and [47].
27 DW McMorland Sale of Land (3rd ed, Cathcart Trust, Auckland, 2011) at 510.
[25] I am not persuaded to think there is any principled basis on which to amend the order for specific performance so as to relieve the defendants of their obligation to pay default interest. The effect of the clause was taken into account when specific performance of the agreement was ordered, in the finding that the defendants must have been aware that they were liable to pay default interest but that they chose to
ignore that risk.28 An assertion of financial hardship was held to
be of no particular
significance to the defendants’ claim as the default interest provision
was part of the bargain made between the parties. It
is relevant that the
defendants have had the benefit of the property’s rental income for the
period of default. They say that
the property is tenanted, so this benefit is
ongoing.
[26] I comment briefly on the defendants’ other points of argument.
Mr Henry contends that the relief sought by the plaintiff
was merely the
transfer of legal title, and that the enforcement of the terms of the contract
remain barred by express provisions
of the Limitation Act 1950. He argues that
although specific performance of an obligation to transfer legal title cannot be
barred
by analogy, the terms of the contract are nevertheless unenforceable at
law. There is no merit in the point. The order for specific
performance directs
the defaulting vendors to perform the entire contract, not just part of it.
Taken to its logical conclusion,
Mr Henry’s contention would result in the
vendors not being entitled to receive consideration for the performance of their
obligation to transfer title.
[27] Second, there is no support for the defendants’ submission that the plaintiff was required to mitigate his losses. This principle is relevant to assessing the level of damages, not in the context of an order for specific performance, in which case the claim is not for any “loss”. Reference to the Canadian decisions is misguided as that jurisdiction has taken a different approach in terms of the presumption of specific performance as the appropriate remedy in sale of land cases. In New Zealand law, specific performance is still the primary remedy for breaches of contracts for the sale
of land, and issues of mitigating loss do not come in to the
equation.29
28 Zhang v Zhai, above n 1, at [52].
29 See the discussion in John Burrows, Jeremy Finn and Stephen Todd Law of Contract in New
Zealand (4th ed, LexisNexis NZ Ltd, Wellington, 2012) at [21.4.2].
Result
Terms of settlement
[28] It follows that I accept the plaintiff’s submissions. The
property is to be transferred according to the terms of the
agreement, including
the parties’ respective liabilities for interest under cl
3.10.
[29] Modifying the agreement to accommodate a settlement many years after
the date originally contemplated, I adopt the terms
set out in the
plaintiff’s amended notice of opposition dated 28 July 2014, which refers
to a letter sent by the plaintiff’s
solicitors dated 19 May 2014 and which
has not been disputed by the defendants.
Order
[30] On that basis, within seven days the defendants shall:
(a) Tender a settlement statement calculated in accordance with the agreement’s provisions as to interest under cl 3.10, with the default interest period running from 29 June 2004 until the date of settlement. The amount owing is to be offset by the amount already paid by the defendants when, on 13 August 2013, their solicitor transferred
$22,161.46 to the bank account of the plaintiff’s solicitors (a sum
said to represent the deposit of $20,000 paid by the plaintiff
plus interest,
payment of which had not been requested by the plaintiff).
(b) Provide undertakings that they have certified, signed and
pre- validated:
(i) a discharge of mortgage 5265546.4; and
(ii) a transfer instrument conveying title to the property at 23A Margan Avenue (identifier 78277) from their names into the plaintiff’s name; and
(iii) immediately following receipt of confirmation of the deposit of
settlement funds to their trust account, they will:
1. release the discharge of mortgage and transfer instrument from the
LandOnline workspace to the plaintiff’s control; and
2. not attempt to withdraw such release or attempt any alteration of those
instruments following settlement or release.
Stay of judgment
[31] The defendants seek a stay of execution of the principal judgment
and any orders made in this judgment pending the final
disposition of their
appeal. The plaintiff resists, saying that the property should be transferred to
him straight away. He points
to an undertaking signed by him on 25 July 2014
that he will not “sell, convey, transfer, mortgage, pledge, exchange or
otherwise
dispose of the property” until the appeal is determined.
He undertakes further that he will transfer the property
back to the
defendants immediately should their appeal succeed.
[32] It is convenient to adopt the principles applicable to granting a
stay set out by Hammond J in Dymocks Franchise Systems (NSW) Pty Ltd v
Bilgola Enterprises Ltd30 as follows:
[9] The factors to which Courts conventionally address themselves to find
this balance include the following:
(1) If no stay is granted will the applicants’ right of appeal be
rendered nugatory?
(2) The bona fides of the applicants as to the prosecution of the appeal.
(3) Will the successful party be injuriously affected by the stay? (4) The
effect on third parties.
30 Dymocks Franchise Systems (NSW) Pty Ltd v Bilgola Enterprises Ltd (1999) 13 PRNZ 48 (HC). The summary was approved by the Court of Appeal in New Zealand Insulators Ltd v ABB Ltd (2006)
[2006] NZCA 330; 18 PRNZ 459 (CA).
(5) The novelty and importance of the question involved. (6) The public interest in the proceedings.
(7) The overall balance of convenience.
[10] I add, that these factors are not comprehensive. A review of them
serves merely to show the breadth of the matters which,
in any given case, may
have to be addressed by a Court to balance the overall interests of
justice.
[33] On weighing the factors in this case, I find that it is appropriate to grant a stay, on the condition that the defendants keep up the current momentum in prosecution of their appeal.31 The effect on third parties is relevant, as the property is currently tenanted but the terms of the agreement require it to be transferred with vacant possession. The balance of convenience also weighs in favour of granting a stay, given the efforts and costs that will be required to transfer the property – for example, the defendants must defray the cost of the mortgage over the property to discharge it. In the event the defendants are successful on appeal, all that will have
been for nothing. Moreover, the plaintiff’s interest in the property
is in the meantime
protected as he has lodged a caveat over it.
[34] Execution of the order for specific performance in the principal
judgment and the terms of this judgment shall be stayed
subject to the
condition, proposed by the defendants, that the case on appeal shall be filed
within one month of the date of this
judgment (subject to any delays not
occasioned by the defendants) and the defendants shall seek a hearing of
the appeal
at the earliest date available.
Costs
[35] The plaintiff seeks indemnity costs on this application, which he contends was an unwarranted revisiting of matters already decided in the specific performance judgment. However, indemnity costs are exceptional and would require the defendants to have acted “vexatiously, frivolously, improperly, or unnecessarily”.32 I
do not think this can be said of their actions in this
case.
31 The defendants filed their notice of appeal in June and security for costs in July 2014.
32 See r 14.6(4) of the High Court Rules.
[36] The plaintiff is entitled to costs on a 2B scale basis, with
disbursements to be fixed by the
Registrar.
..........................................
Toogood J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/2156.html