Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 3 November 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2011-404-8000 [2014] NZHC 2306
IN THE MATTER
|
Known as “C-Vu Apartments”
|
BETWEEN
|
BODY CORPORATE 325261
First Plaintiff
RODNEY WILLIAM COOKE AND OTHERS
Second Plaintiffs
|
AND
|
JAMES McDONOUGH First Defendant
Continued...
|
Hearing:
|
25 and 26 August 2014
|
Counsel:
|
G J Kohler QC and C Baker for Plaintiffs
S Mills QC and B O’Callahan for Sixth and Seventh
Defendants
|
Judgment:
|
23 September 2014
|
JUDGMENT OF KATZ J
This judgment was delivered by me on 23 September 2014 at 11:00 am
Pursuant to Rule 11.5 High Court Rules
Registrar/Deputy Registrar
Solicitors: Price Baker Berridge, Auckland
Simpson Grierson, Auckland
Carter Kirkland Morrison, Auckland
Duncan Cotterill, Auckland
Counsel: G J Kohler QC, Shortland Chambers, Auckland
S Mills QC, Shortland Chambers, Auckland
BODY CORPORATE 325261 v COOKE AND McDONOUGH & ORS [2014] NZHC 2306 [23 September
2014]
MAUNGA MAUNGA REI NZ LIMITED
Second Defendant AUCKLAND COUNCIL Third Defendant
GARY BICKERTON Fourth Defendant RACHEL VENABLES Fifth Defendant
STEPHEN MITCHELL ENGINEERS LIMITED
Sixth Defendant
STEPHEN ROBERT MITCHELL
Seventh Defendant
MACDONALD BARNETT PARTNERS LIMITED, Eighth Defendant
MICHAEL SIMPSON
Ninth Defendant
FRAMERITE INSTALLATIONS LIMITED
Third Third Party
Introduction
[1] The first plaintiff is the body corporate of a unit title
development known as the C-Vu apartment building, which is on
the corner of
Hopetoun and Day Streets in Auckland. The second plaintiffs are the owners (or
former owners) of the 130 apartments
in the building.
[2] Due to a recent settlement between the plaintiffs and seven of the
nine defendants, the only remaining claims are against
the building’s
structural engineers, Stephen Mitchell Engineers Limited and Stephen Robert
Mitchell (together referred to as
“SML”). As a result of the
settlement, the original July 2014 trial date was adjourned. The hearing of the
plaintiffs’
claims against SML is now scheduled to proceed in July 2015
(although I note that the plaintiffs have raised some concerns regarding
that
date).
[3] Following the settlement, leave was granted to file a 10th amended
statement of claim (“10AMSOC”) focussing
solely on the claims
against SML. SML now seeks orders striking out parts of that document or,
alternatively, requiring SML to
provide further particulars and/or a more
explicit pleading (“pleadings application”). Further, SML seeks to
strike
out parts of the plaintiffs’ reply briefs (“evidence
application”) on the basis that some of that evidence
is not strictly in
reply or is irrelevant to the claims against SML.
[4] I will consider each application in turn. First, however, I will
consider what the general approach to interlocutory and
case management issues
should be, now that the claims against most of the defendants have settled and
the trial against SML is not
due to take place until July 2015.
The current status of the proceeding and the appropriate way
forward
[5] The proceeding was initially commenced as a leaky building claim. Claims relating to structural defects were subsequently added, and Stephen Mitchell Engineers Limited and Stephen Mitchell were joined as further defendants.
[6] The trial was originally scheduled to commence on 14 July 2014,
with an estimated hearing time of 10 weeks. As a result
of slippage in the
original timetable, the plaintiffs’ reply evidence on structural
engineering issues was not due to be served
until the end of the third week of
trial. The timetable then provided for an experts’ conference on
structural engineering
issues over the course of the following week, culminating
in a joint expert’s report. It was hoped that the joint expert’s
report would significantly narrow the scope of the structural engineering issues
for trial. Although challenging, this timetable
was potentially workable if the
first half of the trial had focused primarily on the weathertightness
issues against the
non-SML defendants, as was initially envisaged.
[7] As I have noted above, however, shortly before the trial
was due to commence, the plaintiffs settled with
all of the defendants
save for SML. This resolved most or all of the weathertightness issues. As a
result of the settlement,
the trial commencement date was adjourned for three
weeks. This was to enable the settlement agreements to be finalised, the
pleadings
to be appropriately amended, and the parties to review the
evidence and prepare for a much more narrowly focussed trial,
involving
the plaintiffs and SML only.
[8] An application for leave to amend the pleadings was required, given
that the pleadings had closed. Many of the proposed
amendments were
uncontroversial, as they were simply a consequence of the settlement that had
been reached. Other proposed amendments
were of an updating or corrective
nature. Indeed some of the changes resulted in a reduction of the claim against
SML. Several
changes were, however, objected to by SML on the basis that they
either introduced new causes of action or were otherwise unfairly
prejudicial to
SML, given the imminence of the trial date.
[9] The plaintiffs’ application for leave to file the 10AMSOC was heard on 28 and 29 July 2014. I rejected SML’s submission that the proposed 10AMSOC raised any new causes of action. Rather, I concluded that the core pleadings regarding the duties of care owed, the defects in the building, the alleged breaches by SML and the remedial works required, were the same in the proposed 10AMSOC as they had been in the ninth amended statement of claim (“9AMSOC”). I accordingly granted leave
to file the 10AMSOC, although I disallowed several, relatively minor,
proposed amendments.
[10] As a consequence of the three week adjournment to the trial start
date, the plaintiffs’ reply evidence on structural
engineering issues was
served on the Friday before the trial was due to start. SML’s expert
witnesses reviewed that evidence
over the weekend, ultimately concluding that it
would not be possible to adequately deal with all of the matters raised within
the
existing trial window. Nor was it seen as realistic for the experts to have
a conference and produce a joint report within the first
week of the trial
window. SML accordingly sought, and was granted, an adjournment of the
trial date. In my minute of 4
August 2014 I recorded the reasons for the
adjournment as follows:
[2] The structural engineering reply briefs were not due to be served until
last Friday, 1 August 2014. The timetable then provided
for an experts’
conference this week, culminating (hopefully) in a joint expert’s report.
It was anticipated that that
report would significantly narrow the issues for
trial.
[3] It is now apparent from the reply evidence that the structural
engineering issues in this case, which have always been recognised
as complex,
are perhaps even more complex than they initially appeared.
[4] There is some dispute as to whether the reply evidence that was served last Friday is strictly in reply or not. Obviously that may need to be resolved at some stage, given the potential costs implications. The key issue at present, however, is that SML’s experts are not going to be able to properly analyse the structural engineering reply evidence and respond to it within the trial window. Further, an experts’ conference within the next week, or so, culminating in a joint report, is simply unrealistic.
[5] Accordingly, in the interests of ensuring that the real issues are able
to be determined at trial, an adjournment is necessary.
[11] A new trial date has since been allocated, in July 2015.
SML’s view is that, notwithstanding the year long adjournment,
the
existing close of pleadings date should be retained. In its view the plaintiffs
should only be able to make any further amendments
to the pleadings if they
apply for, and are granted, leave of the Court.
[12] SML takes a similar position in relation to the evidence. It accepts that, given the lengthy adjournment, it would be appropriate for there to be some rationalisation of the existing briefs (for example merging multiple briefs from the same witness
together into one brief). It submits, however, that any procedural
“tidying up” of the evidence should not impact on
its underlying
content. Rather, the content of any revised briefs should be restricted solely
to evidence that has already been
served (albeit excluding any
“reply” evidence that is not strictly in reply).
[13] The guiding principle in civil litigation is that the parties should
have every opportunity to ensure that the real controversy
goes to trial so as
to secure the just determination of the proceedings. The High Court Rules
provide a framework that is intended
to achieve this outcome in a way that is as
just, economical and prompt as the circumstances allow.
[14] To maximise the prospects of the real controversy being determined,
parties are at liberty to amend their pleadings prior
to the close of pleadings
date. After that date, however, leave is required. This reflects that the
trial date is imminent and
allowing any late amendments to the pleadings at that
stage may cause injustice, as it could jeopardise the trial date or otherwise
prejudice an opposing party. Different considerations apply when a trial date is
not imminent.
[15] The practical reality in this case is that, shortly before trial,
most of the case settled. Of the original nine defendants,
only SML remains.
As a result of the settlement, the pleadings required fairly radical
revision. That revision was
undertaken under considerable time pressure,
given that (at the time) the trial had only been adjourned for three weeks. The
plaintiffs
therefore endeavoured to limit any amendments to the pleadings
as much as possible, to avoid any claim of prejudice
by SML. This has
resulted in a pleading which largely mirrors the structure and content of
the 9AMSOC, with most of the
paragraphs relating the defendants who have settled
simply being deleted. It is fair to say that, as a result of this approach,
the
10AMSOC is a somewhat cumbersome and inelegantly drafted document.
[16] Now that the proceedings have been adjourned until July 2015, there is ample opportunity for a more comprehensive redrafting of the pleading to take place, in order to ensure that the claims against SML are expressed with a greater degree of precision and clarity, rather than being cluttered by “orphan” paragraphs or sentences
from the 9AMSOC whose precise relevance to the claims against SML are not
clear. Further, the pleadings need to properly reflect the
settlement that has
occurred and the future implications of that settlement. By the time
of trial in July 2015 (or
possibly later) matters will have moved on
significantly. For example, the remedial works agreed as part of the
settlement
with the other defendants will have been progressed. The plaintiffs
will have to address the structural defects as part of the remedial
works that
are being undertaken. As a result, damages will be able to be approached on an
actual, rather than a hypothetical, basis.
[17] Obviously, the plaintiffs are not entitled to plead any new causes
of action that are time barred. However, there is considerable
scope for the
existing causes of action to be “tidied up”. The prospect of the
real controversy between the parties
being determined will be maximised if the
pleadings are put into the best shape possible prior to trial. SML’s
preferred course
of retaining the existing close of pleadings date would mean
that any further amendments to the pleading could only be made with
leave of the
Court. Based on the previous interlocutory history of these proceedings, any
such leave application may well be opposed,
save in relation to the most minor
or routine of amendments. As a result, if the pleadings remained closed, then
considerable
court resources may be required to micro-manage the
re-drafting process. This in itself could result in significant further
delays.
[18] Such a course would run contrary to the objectives of the
efficient, expeditious and economical management of
proceedings. The
proceedings cannot be simply frozen in time as at July or August 2014. Rather,
appropriate directions must be
made to enable the parties to get the proceedings
in the best possible shape for trial in July 2015, with (hopefully) a
minimum
of court intervention being required. This requires that a new
close of pleadings date be set and new timetable directions be
made.
[19] Against these background observations as to the appropriate approach to interlocutory and case management issues in all the circumstances of this case, I now turn to consider the two specific interlocutory applications that are before the Court.
The pleadings application
[20] SML seeks orders that certain parts of the 10AMSOC be struck out and
that further and better particulars or a more explicit
pleading be provided in
relation to other parts of the document. SML submitted that the 10AMSOC does
not comply with the requirements
of r 5.26, because it does not state the
plaintiffs’ claim in an accurate, clear and intelligible manner that
enables SML and
the Court to be fairly informed of the claims made. Further,
the challenged parts of the claim are said to be likely to cause prejudice
or
delay, or are otherwise an abuse of the process of the Court.
[21] I have already observed that the 10AMSOC is a cumbersome document.
While there was a clear rationale for trying to keep changes
to a minimum when
the trial date was imminent, that is no longer the case. The adjournment of the
trial date provides the opportunity
for a significant “tidy up” of
the pleadings. The plaintiffs should be given an opportunity to put the
pleadings in
the best shape possible prior to trial. If SML still has concerns
once the plaintiffs have done so (for example if it believes a
new cause of
action has been pleaded, that is statute barred) then it will be able to raise
such concerns by way of further application.
[22] SML’s pleadings application does, however, identify a
number of areas where the current pleading could be
significantly improved to
ensure that both SML and the Court are properly informed of the claims made. I
will summarise these below.
[23] The statement of claim originally pleaded 48 specific defects in respect of which one or more of the nine defendants was said to be liable. Only a subset of these was specifically pleaded against SML (“SML defects”). The remaining defects were pleaded against other defendants (“other defects”). Some of the other defects are, however, still referred to in the 10AMSOC. The reasons why the other defects are said to be relevant to the claims against SML is, for the most part, unclear. During the course of the hearing Mr Kohler QC explained that some of the other defects impact indirectly on the claim against SML, even though the relevant defect is not a result of any negligence on the part of SML. For example, the existence of
other defects could increase the costs that will be incurred when remediation
of the structural defects for which SML is responsible
is
undertaken.
[24] It is open to the plaintiffs to argue at trial that some of the
other defects are relevant to their claims against SML.
The pleading needs to
make clear how this arises. A clear distinction needs to be drawn, for liability
purposes, between the SML
defects and other defects. In relation to any other
defects that are said to be relevant to the claims against SML, any amended
pleading needs to clearly set out why and how they are so relevant. Any defined
terms need to avoid confusing the two different
categories of defects.
Clarifying these issues will hopefully also clarify the related Building Code
references, and their precise
relevance to SML, in paragraphs 27(c) – (f)
of the 10AMSOC. These are unclear in the current pleading.
[25] I also accept SML’s related submission that there is a lack of
clarity in the
10AMSOC between the SML defects and the damage that is said to arise from
those defects. This arises in part from definitions of
“Defects”
and “Damage” which are carried over from the 9AMSOC and are
therefore much more broadly focussed
than the current pleading requires. This
gives rise to a lack of conceptual clarity, now that the claim is focussed
solely on SML.
Similarly, the current definition of “Remedial
Works” is also somewhat confusing in the context of a claim where SML
is
the sole defendant. A clear distinction needs to be drawn between the entirety
of the remedial works being undertaken and that
portion of them that SML is said
to be liable for. Put simply, the pleading must make it clear exactly what
damages are sought against
SML and the causal nexus between those damages and
any wrongdoing on SML’s part.
[26] Further, to the extent that a claim is made against SML in relation
to any weathertightness issues (as opposed to structural
issues) the pleading
should make it clear which of the SML defects (if any) have given rise to
weathertightness issues and what the
causal nexus is.
[27] In relation to the claims for post-remediation stigma, I have not been persuaded that the current pleading is deficient, although it could certainly be drafted with a greater degree of precision.
[28] In terms of the capital losses claimed at paragraphs 47
and 55 of the
10AMSOC (as particularised in Schedule G), Mr Kohler acknowledged that the
figures are historic and will need to be updated to reflect
the settlement
reached with the other defendants. As a result of that settlement the focus of
the claim is now squarely on remedial
costs, although the plaintiffs are not
willing at this stage to abandon an alternative claim for capital
costs.
[29] These issues will need to be addressed in the further amended
pleading that Mr Kohler has foreshadowed, along with any updated
information on
remediation works and so on.
Evidence application
[30] SML seeks a number of orders in relation to the further evidence
that was served by the plaintiffs on 1 August 2014, purportedly
in reply. Four
expert briefs are involved. Three are from the plaintiffs’ structural
engineering experts, Mr Pont, Dr Brooke
and Mr Bradley. The fourth is from Mr
Ewen, a quantity surveyor who has given evidence about the cost of the remedial
work, based
on the evidence of Dr Brooke.
[31] SML’s position is that significant parts of these further expert briefs are not in reply. Other aspects of the evidence are said to be irrelevant, based on the
10AMSOC. Further, SML seeks leave to respond to the further evidence, even
if the Court accepts that it is properly in reply, on
the basis that, to a
significant extent, the plaintiffs’ real case is emerging for the
first time in their reply
evidence. In particular, SML says that the
plaintiffs’ initial evidence proceeded on an incorrect basis.
SML’s expert
witnesses drew attention to this in their own briefs, which
proceeded on the correct basis. As a result, SML says that those parts
of
SML’s further expert briefs which were in reply comprised evidence that
should have been put forward from the outset. The
interests of justice require
that SML should be able to respond to some of that evidence.
[32] The plaintiffs submitted, on the other hand, that the further expert evidence was properly in reply and relevant. If the Court concludes otherwise, the plaintiffs submitted that the further evidence should be admitted as supplementary evidence.
The plaintiffs further submitted that, having obtained an adjournment of the
trial to enable it to deal with the further evidence,
it was not appropriate for
SML to now object to the admission of that further evidence.
[33] The structural engineering evidence in this case is
extremely complex. Indeed, the evidence is of such complexity
that counsel has
previously suggested that the Court may need to consider the appointment of a
structural engineering expert to assist
the Court at trial. In such
circumstances it is extremely difficult for the Court to confidently determine,
at this preliminary
stage and without having actually heard from any of the
relevant experts, the extent to which certain highly technical aspects of
the
plaintiffs’ expert evidence are strictly in reply or not. Fortunately, in
light of the conclusions I have reached as
to the appropriate way forward
from a case management perspective, it is not necessary to do so.
[34] The practical reality is that SML sought an adjournment of the trial
as a result of the filing of the plaintiffs’
further evidence, on
the basis that it would be prejudiced if forced to continue to trial
without an adequate opportunity
to fully engage with that evidence. SML
accepts that an adjournment would have been necessary even if the further
evidence had
been limited to those portions of the further briefs that SML
accepts was genuinely in reply. It cannot therefore be said that the
adjournment was caused by the plaintiffs’ inclusion of non-reply evidence
in their further briefs (if that was indeed the case).
Even if the Court had
been able to identify and exclude that evidence, SML would not have been able to
proceed to trial on 4 August
2014.
[35] Unfortunately, the risk that an adjournment might prove necessary was always inherent in a timetable which (due to earlier slippage) provided for very complex structural engineering evidence to be served during the course of trial. This is particularly so given that it was envisaged that the experts would confer and prepare a joint report during the trial window. That was a fairly challenging scenario in any circumstances, even more so once the weathertightness claims were settled and the sole focus of the trial became the structural issues.
[36] The current situation is that the trial has been adjourned for a
year. There is now ample time for SML to properly analyse
and engage with the
further expert evidence, whether it is characterised as reply evidence or
supplementary evidence. As I have noted,
the guiding principle should be that
the parties have every opportunity to ensure that the necessary evidence is
before the Court
to enable it to determine the real controversy between the
parties and secure the just determination of the proceedings. Any attempt
by
the Court to “take a red pen” to the expert evidence at this
preliminary stage and exclude parts of it on the basis
that it may not have been
strictly in reply would run counter to the objective of facilitating the just
determination of the real
controversy between the parties.
[37] In addition, further supplementary evidence will now be necessary to
address the recent settlement and the remedial work
agreed to be undertaken as
part of that settlement, which is likely to be well underway prior to
trial.
[38] It is neither efficient nor cost effective for the Court to
micromanage the process of getting the evidence into proper
shape, this
far out from trial. Any potential prejudice to SML arising out of the
content of the reply briefs has largely
been addressed by the adjournment of the
trial date, which provides SML with ample time to analyse and respond to it.
Further,
if the plaintiffs’ evidence (initial and reply briefs) are now
amalgamated, to the extent that that is possible or appropriate,
this will
address SML’s concern that it has been prejudiced by the plaintiffs’
“real” case only emerging
in their reply briefs. Such a
rationalisation of the evidence will help ensure that the plaintiffs’
“real” case
is properly set out in its initial briefs, which SML
will then be able to respond to.
[39] As for issues of relevance, it is not appropriate at this preliminary stage to rule any of the plaintiffs’ evidence as inadmissible on grounds of lack of relevance. Issues of relevance cannot be determined until the final form of the pleadings has been settled. Further, given the complexity of the expert evidence, this may well be a case where issues of relevance are more appropriately dealt with at trial. At a pre-trial stage the Court would necessarily have to take a very cautious approach to determining that any particular expert evidence could not possibly be relevant at trial.
Summary and conclusion
[40] The guiding principle in civil litigation is that the parties should
have every opportunity to ensure that the real controversy
goes to trial, so as
to secure the just determination of the proceedings. The High Court Rules
provide a framework aimed at achieving
this outcome in a way that is as just,
economical and prompt as the circumstances allow.
[41] To ensure that the real issues proceed to trial, both the pleadings
and the evidence will need to be revised to ensure
that they are properly
focussed and presented in a way that is accurate, clear and intelligible. This
requires that a new close
of pleadings date be set and new timetable directions
made.
[42] The consequence of this approach is that the plaintiffs will be
entitled to further amend their pleadings, without leave,
until the new close of
pleadings date. They have foreshadowed their intention to do so. In such
circumstances, rather than attempt
a line by line critique of the current
pleading, I have endeavoured to provide general guidance as to the issues that
will need to
be addressed in any amended pleading. I have found that a number
of SML’s concerns with the current pleading are well founded.
[43] In relation to the evidence application, I decline to make the
orders sought by SML, for the reasons I have outlined. The
exclusion of
potentially relevant evidence would undermine the prospects of the real
controversy being determined when the claims
against SML proceed to trial.
Given the recent settlement and the subsequent lengthy adjournment, the
appropriate course is to make
timetable directions that will enable each party
to appropriately rationalise and re-work their evidence to attempt to ensure
that
the real issues in dispute are addressed in a clear and logical manner, and
that SML has a proper opportunity to respond to the plaintiffs’
evidence.
[44] SML has been largely successful in its pleadings application (although I have taken a somewhat more global approach than that advocated by SML). On the other hand, SML has failed in its evidence application. In such circumstances my preliminary view is that costs should lie where they fall. Given, however, that I have not heard from the parties on costs issues, leave is reserved to file memoranda if
either party has a different view or costs cannot be otherwise agreed. Any
such memoranda are to be filed by 17 October 2014, with
any memoranda in reply
to be filed by 31 October 2014.
Directions
[45] I direct as follows:
(a) The new close of pleadings date is 19 December 2014.
(b) The parties are to provide any updated additional discovery
by
7 November 2014.
(c) The plaintiffs are to file and serve an amended statement of claim, addressing the matters identified at [24] to [26] and [28] above, by
7 November 2014.
(d) SML is to file a defence to the amended statement of claim
by
28 November 2014.
(e) The plaintiffs are to file a reply by 12 December 2014.
(f) The plaintiffs’ revised briefs of evidence are to be
served by
20 February 2015. Such briefs are to amalgamate the
plaintiffs’ existing briefs (both initial and reply) to the extent
appropriate and include any further relevant evidence (including updating
evidence) that the plaintiffs wish to rely upon at trial.
(g) SML’s revised briefs of evidence are to be served by 27 March
2015.
(h) The plaintiffs’ briefs of evidence in reply are to be served by 17
April
2015.
(i) A case management teleconference is to be scheduled on the first available date after 2 February 2015 to review compliance with the timetable and
address any other issues that may
arise.
Katz J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/2306.html