Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 28 October 2014
IN THE HIGH COURT OF NEW ZEALAND TIMARU REGISTRY
CIV-2013-476-000311 [2014] NZHC 2616
BETWEEN
|
FEDERATED FARMERS OF NEW ZEALAND (INC) MACKENZIE BRANCH
Appellant
|
AND
|
MACKENZIE DISTRICT COUNCIL Respondent
|
Hearing:
|
25 and 26 June 2014
|
Appearances:
|
M Casey QC and J Derry for Appellant
D C Caldwell and Ms McCallum for Respondent
J Maassen for Meridian Energy Ltd
|
Judgment:
|
23 October 2014
|
JUDGMENT OF GENDALL
J
FEDERATED FARMERS OF NEW ZEALAND (INC) MACKENZIE BRANCH v MACKENZIE DISTRICT COUNCIL [2014] NZHC 2616 [23 October 2014]
Table of Contents
Para No
Introduction
|
[1]
|
|
Background
|
[4]
|
|
|
The Mackenzie District Plan
|
[7]
|
|
Plan Change 13 (PC13)
|
[20]
|
|
Submissions on PC13 and the Commissioner’s decision
|
[32]
|
|
Appeals from the Commissioner’s decision
|
[42]
|
Environment Court decisions
|
[64]
|
|
|
First Interim Decision
|
[64]
|
|
Sixth Decision
|
[73]
|
|
Seventh Decision
|
[82]
|
|
Eighth Decision
|
[88]
|
The three appeals
|
[91]
|
|
|
Appeal against the Sixth Decision
|
[92]
|
|
Appeal against the Seventh Decision
|
[95]
|
|
Appeal against the Eighth Decision
|
[97]
|
The issues
|
[101]
|
|
Legislative regime
|
[103]
|
|
|
Appeals
|
[103]
|
|
Substantive provisions
|
[104]
|
Discussion
|
[105]
|
|
|
Introduction
|
[105]
|
|
Plan Changes generally
|
[107]
|
Issue (a) – The ability to delete a notified issue
|
[113]
|
|
Issue (b) – The obligation under s 290A
|
[117]
|
|
Issue (c) – Jurisdiction pursuant to s 293
|
[119]
|
|
|
Interpretation of the Statute
|
[124]
|
|
The plain meaning of s 293
|
[128]
|
|
In light of the purpose
|
[131]
|
|
The role of the Environment Court on appeal
|
[136]
|
|
The test for determining whether a submission is “on” a Plan
Change
|
[139]
|
|
Jurisdiction under s 293
|
[144]
|
|
Summary of findings
|
[156]
|
Issue (d) – Interrelationship between ss 290 and 293
|
[160]
|
|
Result
|
|
[161]
|
Costs
|
|
[168]
|
Relief
|
|
[169]
|
Introduction
[1] The appellant (Federated Farmers) appeals against three decisions of
the Environment Court dated 1 November 2013 (Sixth Decision),1
5 November 2013 (Seventh Decision),2 and 23 December
2013 (Eighth Decision).3 All of these decisions concern, to
a greater or lesser extent, decisions made by the respondent in respect of Plan
Change 13 (PC13)
to its Mackenzie District Plan (the District Plan) pursuant to
the Resource Management Act 1991 (RMA).
[2] Though the Mackenzie District Council (the Council) is described as
the respondent in this appeal and Mr Caldwell appeared
as its counsel
throughout, in essence it is not challenging major aspects of the substance of
these appeals. Simply put, it takes
the position that it supports the appeals
insofar as it wishes the Environment Court decisions to be correct
jurisdictionally, although
it does take issue with some aspects of those
appeals.
[3] Meridian Energy Limited (Meridian) originally opposed these appeals
in part. However, shortly before the hearing (but after
filing submissions)
Meridian advised that it no longer opposed the appeals and that it would abide
the decision of this Court. At
Meridian’s request, its submissions have
not been considered and play no part in this judgment. For completeness I
simply
observe that although Meridian withdrew, Mr Maasen nevertheless appeared
before me as its counsel throughout the hearing, simply
with a watching
brief.
Background
[4] The background facts in this case and the planning history concerning the District Plan and PC13 are complex. It is useful here to set these out in some detail. They will assist in understanding the issues facing the Council with its District Plan
and the extent of change to the then-existing position proposed by
PC13.
1 Federated Farmers of New Zealand (Inc) Mackenzie Branch v Mackenzie District Council
(No 6) [2013] NZEnvC 257, (2013) 17 ELRNZ 402 [Sixth Decision].
2 Federated Farmers of New Zealand (Inc) Mackenzie Branch v Mackenzie District Council
(No 7) [2013] NZEnvC 258 [Seventh Decision].
3 Federated Farmers of New Zealand (Inc) Mackenzie Branch v Mackenzie District Council
[2013] NZEnvC 304 [Eighth Decision].
[5] The District Plan promulgated by the Council became operative on 24
May
2004. The proposed Plan Change in question, PC13, relates to the Mackenzie
Basin subzone of the District Plan. The Mackenzie Basin
subzone comprises a
large area of central South Island high country from the Northern Shores of Lake
Ohau in the south, to the mountains
north of Lake Tekapo in the north, and from
the Southern Alps including Aorangi/Mt Cook to the west to the small towns of
Twizel
and Tekapo in the east. Within the subzone are 25 farms and stations
which are the major proportion by far of its occupied land.
Of these farms and
stations, 22 are members of the appellant Federated Farmers Mackenzie
Branch.
[6] Special zoning in the District Plan within the Mackenzie Basin also
accommodates major hydro electric operations owned by
Meridian and Genesis
Energy Limited including dams, storage areas, lakes, power stations and an
extensive canal and road network.
The Mackenzie District Plan
[7] As the genesis of the present appeals before this Court lies in the
District Plan and PC13 it is useful to review the provisions
of these
instruments in some detail.
[8] The District Plan came into force on 24 May 2004. Section 7 of the
District Plan covers the rural zone. It included under
“Issue 7 –
Landscape Values” a comment that the landscapes of the Mackenzie District
are of significant value.
The District is said to contain three basic
landscape units. These are essentially the mountainous chain of the main
divide, vast
tussock grasslands of the Mackenzie Basin and the more intensively
farmed and settled farmland east of the Two Thumb, Albury and
Dalgety
Ranges.
[9] The majority of the Mackenzie Basin is described as being regionally
outstanding. On this aspect, Issue 7 in the District
Plan records that:
The challenge is to find an appropriate balance between land uses
and activities and the maintenance of outstanding landscape
qualities.
[10] The District Plan also emphasised under “Rural Objective 3
– Landscape
Values" the need for:
Protection of outstanding landscape values, the natural character of the
margins of lakes, rivers and wetlands and of those natural
processes and
elements which contribute to the District’s overall character and
amenity.
[11] Appropriate development particularly in the high country and the
Mackenzie Basin was to have an overriding regard to these
wider visual and
landscape considerations.
[12] A range of other relevant policies were included in the
District Plan. Amongst other things these covered concerns
to avoid or mitigate
the effects on lakeside landscapes by controlling the scale, appearances and
location of buildings, concerns
as to earthworks in the Basin, attempts
to limit structures and tall vegetation within scenic viewing areas, to
avoid or mitigate the effects of subdivision, uses or development which
might impinge on aspects including important landscapes,
concerns to control the
spread of wilding trees in the District, to generally encourage guidelines
for siting and design of
buildings, structures, tracks, roads and the like
and agreed colour schemes, and to encourage land use activities which sustain
or
enhance the ecosystem functions and natural values of the High
Country.
[13] The Council through its District Plan, had thus identified a range
of landscape issues and endeavoured to address these through
objectives and
policies in the Plan. However, it seems some of the rules in the District Plan
were permissive, with buildings in
the rural zone generally permitted, as long
as they achieved a number of minimum standards.
[14] With regard to subdivision, there were no specified minimum allotments in the rural zone, with allotment size (in relation to the ability to provide onsite sewage disposal) being the only element of control. In essence therefore, as long as onsite sewage disposal could be achieved without adverse effects, there was no practical limit on allotments that could be created in the rural zone and therefore no real limit on how dense residential or built development could potentially become in most areas of this zone.
[15] Mr Caldwell for the Council noted that, while the District Plan did
recognise that houses could be built within the rural
area, the Council did not
anticipate the recent scale of lifestyle development which has occurred within
the Mackenzie Basin and
particularly the growth of retirement and holiday
homes.
[16] It had become apparent he said that the controlled activity
status for subdivisions and the permitted activity
for dwelling houses was now
not appropriate to ensure the protection of landscape values generally. Thus,
after obtaining reports
and recommendations, in June 2006 a decision was made by
the Council to prepare a Plan Change. This resulted in PC13, the pertinent
provisions of which are annexed hereto marked “A”.
[17] The District Plan had remained in force since its inception, until
the Council made this decision that steps needed to be
taken to alter the Plan.
The reason for this was outlined in a report of Mr Graham Densem, dated November
2007:
1.10 The Operative Mackenzie District Plan incorporates various
measures for managing development and conservation in
the Mackenzie Basin.
These were extensively discussed between residents, interested parties and the
Council during the Plan review,
and were either accepted by them or at least are
an agreed balance between the various interests.
1.11 However problems have developed for the Council in the
unforeseen numbers of applications for subdivision and housing in rural parts of
the
Basin, and further pending applications it is aware of. Also, the
unforeseen number of tenure review applications that potentially
could change
the balance established under the existing Plan mechanisms, which were
established generally with the leasehold farming
system in mind. The
Council therefore is considering what measures it may need to add to or amend in
the Plan in view of these changes.
1.12 The Council recognises the existing Plan represents a considerable
energy input of [sic] from various groups and individuals.
It has not embarked
on the current review lightly. However it is satisfied that the magnitude of
the pressures justifies the further
effort.
(emphasis added)
[18] Similarly, in a document entitled “Public Notice of Proposed Change 13 (Rural Zone – Mackenzie Basin) to the Mackenzie District Plan”, dated 19
December 2007, Mr Craig Lyon and Mr Glenn Innes (on behalf of the Council),
stated as follows:
The Mackenzie District Council has prepared Proposed Plan Change 13
Rural Zone – Mackenzie Basin to the Mackenzie District Plan. The primary purpose of this Plan Change is to provide greater protection of the
landscape values of the Mackenzie Basin from inappropriate subdivision,
development and use. To achieve this greater acknowledgment of outstanding natural landscapes and features within the District is provided through objectives, policies and rules, particular [sic] as they apply to the Mackenzie Basin.
(emphasis added)
[19] The ‘preamble’ to the proposed Plan Change of the same
date states:
The Council is aware that the Mackenzie Basin contains values found nowhere
else in New Zealand and that retaining those values is
important to the long
term economy of the region as well as being a responsibility under the Resource
Management Act 1991. There has been considerable subdivision and
development pressure for the past five or so years, particularly for residential
purposes
and particularly within the Mackenzie Basin. Currently the District
Plan provides little or no control over such development, creating
considerable
potential for adverse effects of sporadic subdivision to occur.
...
The Plan Change is therefore based on the general principle that
residential use and subdivision should follow the current land use
patterns of
the Basin...The Plan Change also addresses the visual impact of
irrigation structures and covered feed in the vicinity of roads by proposing
guidelines
for landowners.
(emphasis added)
Plan Change 13 (PC13) (as notified)
[20] On 19 December 2013 the Council publicly notified PC13. It is
helpful to set out in full that part of the notified version
dealing with the
primary purpose of PC13 which stated:
The primary purpose of this Plan Change is to provide greater protection of the landscape values of the Mackenzie Basin from inappropriate subdivision, development and use. To achieve this, greater acknowledgment of outstanding natural landscapes and features within the District is provided through the objectives, policies and rules, particularly as they apply to the Mackenzie Basin. The landscape assessment of the Mackenzie Basin recently undertaken, which also draws on previous assessments, acknowledges the outstanding natural landscape values of the Basin. It also
assesses the characteristics of the landscape that have resulted from its use
for pastoral farming including the placement of
homestead and farm
buildings within that landscape. The assessment concludes that the homestead
clusters or nodes of farm buildings
are generally well located and fit into the
landscape, being relatively inconspicuous due to topography, set- back or
screening.
They are also limited in number within the general landscape areas
of the Basin, such that they do not adversely affect the overall
character of
those areas.
The Plan Change is therefore based on the general principle that residential
use and subdivision should follow the current land use
patterns of the Basin,
namely being limited to either existing towns or existing clusters of
buildings usually associated
with homesteads. Provision is also made for the
establishment of new clusters where they meet stringent standards and have the
ability
to replicate existing clusters or nodes. The Plan Change also addresses
the visual impact of irrigation structures and covered feed
in the vicinity of
roads by proposing guidelines for landowners.
(emphasis added)
[21] PC13 introduced an additional statement under the section
“Rural Issue 7 – Landscape Values”. This identified
a concern
that, if rural lifestyle and residential development around existing towns was
too extensive or in the wrong location,
it could have the potential to alter the
wide open character offered by much of the Mackenzie Basin. It recognised
also that
breaking up of farmland through subdivision could result in
loss of the former high county ethos and landscape pattern
and might result
in more intensive use of the remaining farmed areas. The particular landscape
values which could be degraded by
inappropriate development were described.
These were to include visual openness, a sense of naturalness, a sense of
landform continuity,
the existence of small well separated towns and spectacular
views such as iconic lake views particularly at Tekapo and Pukaki and
the loss
or degradation of views from iconic tourist highways. Significantly, this
additional wording in PC13 also noted another
issue concerning retaining of the
values of the Mackenzie Basin. This was a concern described specifically as the
extent to which
additional irrigation will “green” the Mackenzie
Basin and change land use patterns.
[22] PC13 also deleted Objective 3 in the District Plan relating to landscape values. Instead, it added two new objectives – Objective 3A which focused on outstanding natural landscapes and Objective 3B which addressed landscape values.
[23] Objective 3A dealing with “Outstanding Landscapes”
provided that its intention was:
To protect and sustain the outstanding natural landscapes and features of the
District for present and future generations.
[24] The explanation to this Objective 3A noted the obligations on the
Council under s 6 of the RMA to recognise and provide for
the protection of
Outstanding Natural Features and Landscapes. It went on to note that it was
appropriate that development particularly
in the Mackenzie Basin should have an
overriding regard to wider visual and landscape considerations.
[25] PC13 also introduced a new Policy 3A which related to recognition of
the natural landscape of the Mackenzie Basin. It stated
specifically that this
was:
To recognise the Mackenzie Basin as an Outstanding Natural Landscape and
through the Mackenzie Basin Sub zone within the Rural Zone,
to protect the Basin
from inappropriate subdivision, use and development.
[26] The explanations regarding Policy 3A recognised the distinctive
Mackenzie Country character and stated that virtually the
entire Mackenzie Basin
remained outstanding in terms of landscape values because of its uniqueness and
the natural and visual qualities
of the entire environment, its lakes,
landforms, extensive and dramatic vistas, its land use, community and the
general Mackenzie
identity. It noted further that this uniqueness was to be
protected from inappropriate subdivision, use and development.
[27] PC13 also introduced a suite of policies additional to Policy 3A
which were broadly described as follows:
(a) Policy 3B – Economy, Environment and Community:
To encourage a healthy productive economy, environment, and community within,
and maintain the identity of, the Mackenzie Country.
(b) Policy 3C – Adverse Effects of Sporadic
Development:
To avoid the adverse effects on the environment of sporadic development and subdivision.
(c) Policy 3D – Adverse Impacts on Buildings and
Earthworks:
To avoid the adverse impacts on the outstanding natural landscape and
features of the Mackenzie Basin, in particular from buildings,
domestication,
structures, earthworks, tracks and roads.
(d) Policy 3E – Limitations on Residential Subdivision and
Housing:
To only provide for residential subdivision and housing development within
the identified urban areas of the Basin (Twizel and Lake
Tekapo) and within
identified or approved building nodes.
(e) Policy 3F – Landscape Carrying Capacity
To recognise the diversity of physical settings and landscapes within the
Mackenzie Basin and the varying capacity of these to absorb
built
development.
(f) Policy 3G – Approved Building Nodes
New building modes will only be granted as “approved building
nodes” where the Council is satisfied of a detailed range
of
requirements.
(g) Policy 3H – Extensions to Existing Identified Nodes
Extensions to existing identified building nodes will only be granted where
the Council is satisfied that all matters listed in Policy
3G are satisfied
other than items 8 and 13, and that there is no longer sufficient land
available within the identified
node for the operational
requirements of the property.
(h) Policy 3I – Farm and Non-Residential Buildings
Farm and other non-residential buildings, other than farm buildings that
require a remote location, are required to locate within
identified or approved
building nodes.
(i) Policy 3J – Remote Farm Buildings
To recognise that some farm buildings are required because of their function to locate away from building nodes and to provide for these buildings subject to location, design and external appearance control.
(j) Policy 3K – Lakeside Areas
To avoid adverse impacts of buildings, structures and uses on the landscape
values and character of the Mackenzie Basin lakes and
their margins.
(k) Policy 3L – Subdivision
(a) To provide for subdivision of land for non-residential
purposes only where this subdivision does not have the potential
to impact on
the landscape values and character of the immediate and wider area, and will not
diminish the sustainability of existing
and likely future productive use of farm
buildings.
(b) To only provide for subdivision for residential purposes
within identified or approved building nodes.
(l) Policy 3M – Manuka Terrace – Rural Residential
Zone
To manage the adverse effects of existing and further subdivision and
development on Manuka Terrace, Lake Ohau through the Rural Residential
Manuka
Terrace zone.
(m) Police 3N – Design and Appearance of Buildings
To control the design, appearance and location of all buildings
within the Mackenzie Basin, to avoid or mitigate adverse
impacts on landscape
values of the Basin Sub Zone.
(n) Policy 3O – Views from Roads
To manage landscape change so that the outstanding natural landscape
values and features are protected and the screening of
distinct views is avoided
when viewed from public roads.
[28] As to policy 3O above, the specific explanations and reasons for
this policy identified that structures such as large irrigators
and storage on
farms of polythene- wrapped feed, amongst others, could impact on views and the
experience of road users. It was
therefore appropriate to encourage sensitive
placement of structures including setbacks from road frontages, particularly
state highways.
Implementation methods for this were provided at page 12 of
PC13 with the following words:
To encourage placement of various temporary farm structures such as irrigators and wrapped feed back from roads and state highways, through preparation and distribution of guidelines to landowners and managers.
[29] PC13 as notified also introduced a new Rural Objective, 3B which
provided:
Objective 3B – Landscape Values
Protection of the natural character of the landscape and margins of lakes,
rivers and wetlands and of the natural processes and elements
that contribute to
the District’s overall character and amenity.
[30] PC13 provided for a number of permitted activities including farm
accessory buildings located within approved building nodes,
subject to
compliance with certain standards. It introduced a new controlled activity
relating to remote farm accessory buildings
in the Mackenzie Basin zone and a
restricted discretionary activity status for non-farm buildings within
identified building nodes,
subject again to compliance with
standards.
[31] It also introduced as a category of non-complying activities,
non-farming buildings not within an identified or approved building
node and
certain other farm accessory buildings. In addition it introduced controlled
activity status in relation to earthworks
and tracking and provided
for discretionary activities for the establishment of approved building
nodes and the
like.
Submissions on PC13 and the Commissioners’ decision
[32] Following public notification of PC13, 134 submissions were received by the Council. Hearing of submissions took place over some eight days in September and November 2008 and May 2009 before Commissioners appointed by the Council for this purpose pursuant to s 34A of the RMA. Following these hearings, the Commissioners issued their recommendations, adopted by the Council on
1 September 2009 and publicly notified shortly thereafter.
[33] The Commissioners’ decision incorporated a number of changes
to PC13 as notified. PC3 as amended by the Commissioners,
is generally set out
at annexure B of this judgment However, the key changes included the
following:
(a) The activity “approved building nodes” was removed and renamed as “Farm Base Areas” and provided for all buildings within those areas as permitted activities and subdivisions as controlled activities.
(b) Outside these Farm Base Areas, the decision made all farm buildings
controlled activities, non-farming buildings discretionary
activities,
subdivision for farming purposes restricted discretionary activities, and
subdivision for non-farming purposes discretionary
activities.
(c) They included residential units and accommodation for farm
workers
and their families within the definition of “farm
buildings”.
(d) They provided specifically for farming type buildings.
(e) They reintroduced the lakeside protection area with non-complying
status for buildings and subdivision.
(f) They removed certain areas to the west and south of Twizel from
the
Mackenzie Basin sub zone.
[34] In addition the Commissioners made certain amendments to the wording
of
Objective 3A to now read:
Objective 3A – Distinctive and outstanding landscapes
To protect and sustain the distinctive and outstanding natural
landscapes and features of the District for present and future
generations from subdivision and development that would
detract from those landscapes.
[35] In addition, Policy 3A was amended to read:
Policy 3A – Recognition of the Mackenzie Basin
To recognise the Mackenzie Basin as having a distinctive and highly
valued landscape containing an outstanding natural
landscapes and through the Mackenzie Basin Sub zone within the Rural Zone, to
protect the Basin from inappropriate
subdivision, use and
development.
[36] The Commissioners also amended certain explanations and
reasons with respect to Policy 3A and introduced further
explanations in
relation to the integrity of the values associated with the Mackenzie
Basin.
[37] The Commissioners then introduced Policy 3B – Landscape Diversity. This read as follows:
To recognise the diversity of physical settings and landscapes within the
Mackenzie Basin and the varying capacity of these to absorb
further subdivision,
buildings and domestication, and in particular to recognise the suitability of
existing farm base areas to accommodate
and absorb additional
buildings.
[38] A further policy change was made to “Policy 3O – Views from
Road” noted
at [27](n) above. This was to the effect that it was now to read:
To require buildings to be set back from roads, particularly state highways,
and to encourage the sensitive location of structures
such as large irrigators
to avoid or limit screening of views of distinctive and outstanding landscapes
of the Mackenzie Basin.
[39] And, the Commissioners referred to concerns raised by some
farmer submitters that PC13 might inhibit diversification
of farming and
held:
bac kgr ound l andsc ape assess ment t hat t he “ greening” of t he Bas in i s
seen as undesirable in landscape terms. That may be the case, but in
the face of strong evidence that diversification is necessary for the viability
of the total farming systems, including
the control of rabbits, wilding
trees, and soil loss through wind erosion, we consider some detriment to
the landscape
may have to be accepted. As Mr John Murray noted when summing up
for Federated Farmers, negative effects of farming activities on
the landscape
may be the “lesser of two evils”.
(emphasis added)
[40] In addition, at para 184 the Commissioners, I understand in dealing with
a submission seeking that dairying be prohibited or
made a discretionary
activity, said:
can be addressed through this
Plan Change and therefore recommend that these submissions be
rejected.
(emphasis added)
[41] Consistent with these comments, and in accordance with a request
made in submissions by a Federated Farmers High Country
Industry Group, the
Commissioners deleted the proposed final sentence of the Statement of Issues
before it, para 1.1, being the sentence
that read:
Another issue associated with retaining values of the Basin is the extent to
which additional irrigation will “green”
the Basin and change land
use patterns.
Appeals from the Commissioners’ decision
Introduction
[42] Following the release of the Commissioners’ decision, multiple
appeals were filed in the Environment Court. Nine notices
of appeal were put
before the Court. They are summarised below. The importance of these appeals,
and what they disclose, will become
apparent later in this judgment.
High Country Rosehip Orchard Ltd and Mackenzie Lifestyle Ltd
[43]
of the
|
Thi
Comm
(a)
|
s notice of appeal, dated 6 October 2009, was concerned with the decision
issioners in its entirety. In essence, the appeal asserts:
The refusal by the Commissioners to rezone the appellants’ land
and
|
|
|
the comments of the Commissioners stating that there is insufficient
evidence to warrant rezoning the land.
|
|
(b)
|
The decision of the commissioners refusing the appellants’
submission that PC13 and the s 32 RMA analysis were flawed and
|
|
|
should be redrafted.
|
|
(c)
|
Generally failing to give effect to the appellants’
submissions
|
|
|
(primarily concerning zoning of the appellants’ land).
|
[44] It sought relief relating specifically to its own land or,
alternatively, abandonment of PC13 altogether.
Mackenzie Properties Ltd
[45] This notice of appeal, dated 16 October 2009, appeals
against:
Those parts of the decision that relate to the boundaries for the Manuka
Terrace Rural Residential Zone.
The grounds relied on are:
(a) Prior to PC13 being notified, the appellant applied to subdivide
part of land it owns (the Ohau Block) into 49 residential
lots and a balance.
This application was a non-controlled activity and was therefore non- notified.
A decision has not been provided
at the time the appeal was filed. PC13 will
alter the status of subdivision of that land. The appellant claims that it is
not a
sustainable use of resources for there to be a possibility that consent
will be refused.
(b) It is inequitable for a plan change to frustrate the use of land granted
by a resource consent (here a subdivision) by altering
the use to which that
land may be put (i.e. restricting building activities). Further, that the Ohau
Block does not sit well within
the Manuka Terrace Rural Residential
Zone.
(c) And generally, that the s 32 report is inadequate and that the
decision upon the appellant’s original submission is
contrary to Part 2 of
the RMA.
[46] Mackenzie Properties Ltd sought relief relating specifically to its land, and rezoning in particular.
Meridian Energy Ltd
[47] This notice of appeal, dated 19 October 2009, sought to
appeal against Objective 3A, Policy 3A, Policy 3C,
Policy 3D and
Policy 3(H)(X). The generalised “crux” of Meridian’s
concern, as identified by it, is that:
...PC13 appears to have gone further than intended, by seeking to control all
“non-farming” uses, and failing to
appropriately recognise
that utilities would also fall within the category of “non-farming”
uses. Utilities should
simply not be subject to the same issues, objectives,
policies and rules as residential and domestic activities. Importantly, no
consideration has been given to, or assessment made of, the effects arising from
applying such provisions to utilities and the Waitaki
Hydro-Electric Power
Scheme (HEPS) in particular.
[48] Meridian further detailed its grounds of appeal in the body of its
notice of appeal, and, with more specificity, in a schedule
annexed to the
appeal.
[49] Meridian sought wide ranging relief, and other relief consequential
to that. For present purposes, the precise nature of
that relief sought does not
need to be further detailed.
Mount Gerald Station Ltd
[50]
appea
|
This l, whi
(a)
|
notice of appeal, dated 19 October 2009, disclosed various grounds of ch
are generalised as follows:
Not all areas of the Mackenzie Basin meet the definition of
|
|
|
“outstanding natural landscape” in terms of the RMA
definition.
|
|
(b)
|
Mount Gerald, at a general level, recognises the need to
control
|
|
|
sporadic subdivision but, at the same time, has concerns regarding
the
Commissioners’ decision. In particular, the scope of the
background
|
|
|
reports were inadequate, all matters identified in ss 5 – 7 RMA have
not been appropriately weighed, and the recommendations
and
amendments are inconsistent with the RMA.
|
[51] The notice of appeal then sets out proposed amendments to PC13 as
recommended by the Commissioners, along with reasons for
the course proposed by
the appellants.
[52] The relief sought here was framed by reference to specific objectives
and policies raised in its appeal, and other relief
as may be necessary
consequential to that specific relief sought. Again, it is not necessary to set
this out in any detail here.
Federated Farmers of NZ Mackenzie Branch
[53] This notice of appeal, dated 20 October 2009, sought to appeal the whole of the Commissioners’ decision. However, it particularly focused on (but was not limited to) five discrete aspects of PC13 as amended by the Commissioners. The
grounds on which the notice of appeal proceeded can be summarised as
follows:
|
(a)
|
The objectives and policies contained within the amended PC13 were not
justified and did not accord with ss 5 and 6 RMA.
|
(b)
|
In submissions, Federated Farmers sought less controls and restrictions on
farm buildings and their location, and the protections
|
|
|
sought to be imposed by PC13 were said to be too wide ranging and unduly
restrictive on the farming community.
|
|
(c)
|
PC13 was ambiguous and the s 32 report upon which
the
Commissioners’ decision proceeded was inadequate.
|
|
(d)
|
The Commissioners’ decision failed to give adequate reasons
for either accepting or rejecting various submissions.
|
|
(e)
|
Federated Farmers claimed a more flexible approach to wilding trees and
reflectivity restrictions imposed on structures was required.
|
|
[54]
|
Fed
|
erated Farmers sought specific relief to give effect to these discrete |
concerns.
Fountainblue Ltd, Southern Serenity Ltd and Pukaki Downs Tourism Holdings
Partnership
[55] This notice of appeal, dated 21 October 2009, sought to appeal
against the Commissioners’ decision in its entirety and,
more
specifically, “those parts of the decision that either specifically or
effectively reject Fountainblue’s submissions
and relief sought.”
The (abridged) reasons for the appeal are set out below:
(a) The Commissioners erred in finding that PC13 should not be
abandoned.
(b) The Commissioners erred in not taking account of
Fountainblue’s existing application for a controlled activity
subdivision consent, which must eventually be granted.
(c) The Commissioners erred in rejecting an expanded
‘existing farm base’ at Pukaki Downs Station. Fountainblue
alleges
that its proposed existing farm base has not been treated equally by the
Council.
(d) The Lakeside Protection Zone should not have been reinstated by the
Commissioners as it represents an “undue restriction
on
Fountainblue’s use of Pukaki Downs Station”.
(e) Overall, PC13 is not the most appropriate forms of achieving the
aims of the Council.
[56] These appellants also sought quite specific relief but, in
the alternative, sought the withdrawal of PC13 so a
new investigation could be
conducted and a new plan change notified.
Haldon Station
[57] This notice of appeal, dated 22 October 2009, appealed against the whole of the commissioners’ decision. Quite relevantly, the notice of appeal states that the “appeal also relates to all consequential and related aspects of the plan, which may affect, or be affected by, this appeal.” Haldon then stated that it “sought that various
changes be made to the Plan to reflect its interests particularly in respect
to property it owns at Haldon Station.” It then
stated it
sought:
(a) Expansion of the ‘node’ that applies to its
land, to ensure it incorporates any and all buildings
that comprise
Haldon’s activities. It also desired to create an additional
node.
(b) That ancillary farm buildings be permitted to be located outside of nodes
where they are a component of a primary activity of
a property.
(c) To oppose the requirement that consent may be required to maintain
or upgrade farm tracks or roads, the requirement that
farm buildings were to be
a minimum of 100 metres from non-farm buildings other than homesteads, and
certain other requirements.
[58] Haldon too sought relief specific to its complaints, and other
consequential relief.
Rhoborough Downs Ltd, Robert Preston, Roberta Preston and Sarah
Preston
[59] This notice of appeal, dated 22 October 2009, appealed against the whole
of the decision of the Commissioners, but in particular
it appealed
against:
(a) The amendments to Objective 3A and associated policies and
methods of implementation.
(b) The removal of provision for identified building nodes.
(c) Blanket discretionary activity status for all buildings other than
farm buildings outside of existing farm base areas.
(d) The inclusion of inappropriate assessment criteria associated with discretionary activities.
(e) Non-complying activity status for all buildings or extensions to
buildings within the Lakeside Protection Areas.
(f) The failure to include special provision for land owned by the
appellant.
(g) The deletion of an “Are for lifestyle subdivisions (no
nodes)”.
(emphasis added)
[60] The grounds for the appeal were several and need not be traversed in
any detail here. However, for completeness, they included breach of
natural justice through the appellant not being heard, PC13 not being the most
appropriate means of achieving the purpose
of the RMA, PC13 being not the
optimal planning solution, PC13 incorporating excessive regulation which is
inefficient and ineffective,
the landscape analysis underpinning the
Commissioners’ decision said to be inadequate, insufficient
acknowledgement of landowners’
need to provide for their economic
well-being, and inadequate reasons given for the amendments proposed by the
Commissioners. As
to this last point, the appellants expressly stated:
This is particularly inappropriate when changes have been made to a number of
objectives and policies including, for example, Objective
3A, Policy 3A and
Policy 3B without any apparent jurisdiction.
[61] The Rhoborough Group sought that PC13 be abandoned in its entirety.
Alternatively, they sought that further analysis and investigation
be undertaken
and amendments made. They also sought any necessary consequential
relief.
The Wolds Station Ltd
[62] This notice of appeal appealed against the whole of the decision of
the Commissioners. However, it was particularly addressed
towards three points:
(a) the aspects of the decision concerning reflectivity; (b) the decision
concerning amenity tree planting;
and (c) the decision to leave out part of the
appellants’ property from the farm base area. The grounds advanced
included:
(a) The landscape assessment was incomplete and flawed.
(b) The RMA had been incorrectly applied, which included an incorrect
s
32 analysis.
(c) The Commissioners failed to give adequate reasons for rejecting
submissions.
(d) The reflectivity standard was too high, and the tree planting policies
were too onerous.
[63] The Wolds Station sought specific relief, abandonment of PC13
or:
...such further or other relief as may be rational and applicable having
regard to all the circumstances and to achieve a rational zone
change.
Environment Court decisions
First Interim Decision
[64] This decision (Interim Decision) issued on 14 December 2011
is somewhat of a tome, running to just shy of 500 paragraphs, and over 170 pages
(including annexures).4 However, the Interim Decision is
not the subject of this appeal. Indeed, it has previously been the subject
of an earlier
appeal to this Court by the appellants in this proceeding,
Federated Farmers.5 That appeal was heard in this Court by
Williams J and is referred to herein as the Interim Decision
Appeal.
[65] I do not propose to consider the Interim Decision in any detail here. However, a cursory review is prudent as it does form part of the essential background to these proceedings in their entirety. First, it is useful to set out the issues which the Environment Court saw to be outstanding in the then extant
appeals:6
The remaining appeals by the named appellants raise issues about:
The existence and extent of outstanding natural
landscapes within the Mackenzie Basin subzone;
5 Federated Farmers of New Zealand (Inc) Mackenzie Branch v Mackenzie District Council
[2013] NZHC 518 [Interim Decision Appeal].
6 Interim Decision, above n 4 at [11].
The Rural objective(s) as to landscape;
The implementing policies and landscape; Hazard provisions;
Some of the implementing rules in section 7 of the
district plan, especially in relation to reflectivity and wilding trees;
Land use practices and sustainability; Specific farm base areas and/or rules;
Proposed new Rural-Residential and Tourist Resort
zones.
[66] Next, and helpfully for present purposes, the judgment
included a “conclusions and outcome section”.7 It is
from this section I now replicate certain aspects:
8. Conclusions and outcome
8.1 Summary
[458] The basic fact underpinning this decision is that the
Mackenzie Basin is one huge open tussock-dominated landscape
surrounded by
mountains including Aoraki... The elected representatives of the district
notified Plan Change 13 on the foundation
that the Mackenzie Basin was an
outstanding natural landscape. Applying a high standard of
“outstandingness” we
have found on the evidence that is
correct.
[459] As we have pointed out the operative district plan and PC13 between
them identify a number of issues (the place of buildings,
exotic wildings,
intensive agriculture) in respect of sustainable management... However, the
district plan and PC13 between them
only purport to settle objectives and
policies for one of them – buildings in the landscape and zone. The other
important
issues are left hanging. That is of real concern because not only are
there matters of national importance involved, but several
of the core elements
of sustainable management are also.
8.2 The problems with PC13
[460] The fact that these proceedings are about an outstanding natural
landscape is crucial because recognising and protecting it
from inappropriate
development is stated by Parliament to be a matter of national
importance...
[461] It appears to us that all ... [the matters referred above at [460]]
should have been addressed by the Mackenzie District
Council because they all
relate to or are “on” the subject of PC13 – the landscape of
the Mackenzie Basin. However,
the amended and/or additional policies and
methods we have proposed in the evidence probably go beyond the submissions and
do go
further than the appeals on the plan change. Consequently those
changes
7 At [458] – [494].
cannot be made without giving both the parties and other potentially
interested persons an opportunity to be heard...
8.3 T he cour t’s powers to amend district
plans
[462] The Environment Court has powers to amend subordinate legislation
contained in a district plan. The justification for these
powers appears to be
in one of the very few exceptions to the cornerstone principle that legislation
should be enacted by elected
representatives...
...
8.4 Can and should we exercise our powers under section
293?
[471] We consider we have jurisdiction to consider the issues raised but
not dealt with by PC13(C) – as we have pointed out
they all relate to the
protection of the outstanding natural landscape which is the Mackenzie
Basin from inappropriate subdivision,
use and development.
...
8.5 Outcome
[484] This decision in [sic] final in respect of our
finding that the Mackenzie Basin as a whole (excluding Twizel and Tekapo
townships, Mr Densem’s landscape
unit 54 west of Twizel, and the Dobson
river catchment) is an outstanding natural landscape. All other determinations
or judgments
are interim...
[67] The above is not, and does not purport to be, anything but the most
cursory of overviews of what is a very thorough judgment.
Annexed hereto marked
“C” is a copy of the changes proposed to be made in the
Interim Decision, (as outlined in the Schedule to the Interim Decision)
which
were expressly stated not to be final.
[68] It is also worthwhile pausing for a moment to consider the
Interim Decision Appeal of Williams J referred to at [64] above. This
too informs the procedural history of these proceedings in their entirety and,
more
relevantly, how the present appeals came to exist. In that Interim
Decision Appeal, Williams J observed first that the Environment
Court’s
Interim Decision had proposed to introduce new controls relating to the
following matters:8
(a) pastoral intensification (greening, cultivation and large
farm buildings) made possible by the introduction of large
scale
irrigation;
(b) on farm retirement subdivisions;
8 Interim Decision Appeal, above n 5 at [2].
(c) restrictions on the location of “farm bases” to address
potential inundation hazards arising from the presence
within the district of
hydroelectric infrastructure owned by Meridian Energy Limited; and
(d) the spread of wilding pines. (footnotes omitted)
Federated Farmers and others had appealed to the High Court among other matters challenging the way in which the Environment Court had proposed to rely on s 293
RMA to introduce these controls.
[69] Williams J acknowledged that the Environment Court’s decision “does not purport to be final”, but noted that it does record that the Environment Court was “strongly of the inclination” that it ought to invoke s 293 of the RMA.9 Williams J
then stated:10
In my view, the most important question in this appeal is how far an interim
decision can go before it loses that character and becomes,
in substance, a
final decision.
[70] After discussing the background to the appeal,11 Williams J turned to consider the appeal itself, which advanced four points.12 However, it was noted that shortly before the hearing, Federated Farmers and Meridian filed a consent memorandum which settled one of the grounds of appeal which was, perhaps
ironically, the only aspect of the interim decision expressly stated to be
final. This was the finding of the Environment Court that
the Mackenzie Basin
subzone is, in its entirety, an outstanding natural
landscape.13
[71] From that point forward Williams J identified, correctly in my view, that the primary issue that remained on foot before the Court was whether the Interim Decision was appealable at all.14 Williams J discussed this issue in some detail,15
before he reached the conclusion
that:16
9 At [5].
10 At [6].
11 At [7] – [14].
12 At [15].
13 At [18] – [20].
14 At [22] – [23].
15 At [24] – [39].
16 At [40] – [41], [43], [45], [48].
|
In my view, the inevitable conclusion is that no appealable decisions have
yet been made in respect of the issues still in play and
the appeal is therefore
not properly brought.
|
|
Just as in the AMP case, the best that can be said for the appellant
is that the Environment Court might make an error or errors of law if it
continues along the path that it has signalled...
|
|
|
...
|
|
|
That said, I have some sympathy for the position Federated Farmers find
themselves in. The Environment Court in this case has gone
much further in
setting out a potential final view on the issues promoted than any Environment
Court or Planning Tribunal decision
brought to my attention in argument. Not
only has that court communicated its strong inclination to use s 293, but it has
also drafted
its proposed changes both in relation to policies and some
rules...
|
|
|
...
|
|
|
I am, in short, not prepared to find that, in breach of natural justice and
contrary to its own protestations, the Environment Court
has predetermined the
outcome in this case.
|
|
|
...
|
|
|
I am, however, prepared to reaffirm that no aspect of the interim judgment
is final except that relating to the spatial extent of
the Mackenzie Basin as an
outstanding natural landscape, and that all remaining matters involving
substantive merits or jurisdiction
must be approached by that court with a
genuine open mind as to outcome...
|
|
|
[72]
|
In my view the Interim Decision Appeal very clearly
highlights
|
the
|
difficulties which not only the parties, but also this Court, were having
with the strongly phrased Interim Decision, a decision which it might be
said was heading towards a final determination of the matter. Williams J had
some concerns with the
jurisdiction of the Environment Court to tread the path
it signalled it would and remitted the matter back to the Environment Court.
It
is to the subsequent decisions of the Environment Court which found this appeal,
and which address these very issues, I now turn.
Sixth Decision
[73] In this decision the Environment Court began with the
following:17
17 Sixth Decision, above n 1, at [1] – [2].
This decision is about the jurisdiction of the Environment Court to make the
orders proposed in the First (Interim) Decision of the
court in these
proceedings. The proceedings concern the Mackenzie District Council’s
Plan Change 13 (“PC13”)
which was notified on 19 December 2007. The
history of PC13 is described in the First (Interim) Decision.
Various appellants have raised issues as to the court’s jurisdiction
under the Resource Management Act 1991 (“the RMA”
or “the
Act”). A further hearing was held to resolve those and some
consequential issues. The questions are:
(1) are the remedies proposed by the court ‘on’
PC13?
(2) what are the normal powers of the court after hearing appeals on plans
and plan changes?
(3) are the proposals in the First (Interim) Decision within the section
290 jurisdiction?
(4) what are the court’s powers under section 293 of the RMA as
amended in 2005? And
(5) do any (further) proposals of the court come within those powers? Questions (4) and (5) are separate and consequential so I will deal with those
in a further decision.
[74] The Court then briefly discussed PC13,18 which was
followed by an essay of some relevant submissions. On the submissions
it had received the Court observed:19
The court has always regarded the submission and appeal by The Wolds as key
documents because they raise three important issues –
first, how much of
(and where are) the outstanding natural landscapes of the Mackenzie Basin;
second, that policies (including their
“controls” in the language of
the Wolds’ documents) should distinguish different areas in the Basin
rather than
apply uniformly across the whole of the Mackenzie subzone; and
thirdly, that questions of fairness to all parties and to persons
not before the
court are very important.
And, on the submissions generally, the Court
remarked:20
The court always needs to bear in mind (even if not expressed specifically)
that granting relief on any one set of appeals might have
effects on the others.
A feedback loop is implicit in the court’s suggested orders in the First
(Interim) Decision...
18 At [6] – [9].
19 At [15].
20 At [23].
[75] Following this the Court began reviewing the “scheme of
the RMA” in relation to preparation of plan
changes, submissions on plan
changes, and appeals from decisions in respect of plan changes.21
This review was substantial. I do not propose to set out that discussion
in any detail. Rather, I outline below what I see to be
pertinent points
elucidated from that discussion:
(a) Schedule 1 of the RMA contains provision for the “preparation and change” of plans and proposed plans. Schedule 1, cl 6 enables the persons identified in sch 1, subcls (2) to (4) to make submissions that are “on” a proposed plan change. This is important as “[a] territorial
authority can choose the scope of its own plan
changes.”22
(b) After receiving submissions and any further submissions (pursuant to sch
1, cl 8) the local authority is bound to issue a decision
in accordance with sch
1, cl 10. Schedule 1, cl 11 provides for notification of
decisions.
(c) Schedule 1, cl 14 provides for appeals to the Environment
Court against decisions issued pursuant to sch 1, cl 10.
Schedule 1, cl 15 then
sets out some mechanics of the hearings by the Environment Court. Subclause (2)
states that “if the
court gives directions (under s 293(1) RMA) to the
local authority, then the local authority must comply.” No other direct
powers are given to the Environment Court in relation to amending district plans
or changes under Schedule 1.
(d) Section 290 sets out the “[p]owers of [the] Environment Court in regard to appeals and inquiries”. By s 290(1) the Environment Court has “the same power, duty, and discretion in respect of a decision appealed against” as the local authority. In the Sixth Decision it was
noted that this “has both substantive and procedural implications”.23
Section 290(2) enables the Environment Court to “confirm, amend or
cancel a decision to which an appeal relates”. The
meaning of
subs
21 At [24] – [51].
22 At [24] – [25].
23 At [34].
(2) was the subject of consideration by the Environment
Court.24
Section 290(4) states that nothing in s 290 affects “any specific power
or duty” of the Environment Court. The Court
stated it would return to s
290(4) later.25
(e) Section 290A “requires the Environment Court to have regard
to the decision of the local authority”.26
(f) The Court expressly recorded that it would discuss the “meaning and
application” of s 293 in more detail in the next
decision.27
However, it was recorded that the s 293 powers appear to be discretionary
and complementary to the s 290 powers.28
[76] The Court then provided a summary in the following
terms:29
The effect of the 2005 Amendment Act appears to be that there is now a two
stage process:
(1) the court decides whether to confirm, amend, or cancel the
decision or the provision or matter appealed. Cancellation
appears to have the
effect of reinstating the council’s notified provision or
of inserting a provision sought by a submission, and appeal, or of deleting a
provision as sought by a submission and appeal. As
a part of that the court may
be able to exercise a clause 10(2) power to amend a local authority
decision?
(2) if the court decides that the outcome of the first stage is not
the most appropriate provision under section 32, then it
may exercise its
discretion under s 293 to direct the council to come up with amendments that
are. Such directions are
not necessarily alternatives to the
section 290 orders but may be supplementary to it.
[77] The Court next turned its mind to consider whether the “objectives and policies proposed in the First (Interim) Decision [were] ‘on’ PC13”.30 In its analysis,
the Court referred to several decisions promulgating what it termed
“[t]he legal
24 At [35] – [38].
25 At [39].
26 At [41].
27 At [44].
28 At [44].
29 At [50].
30 At [52] – [79].
tests” before engaging in the substantive discussion.31 The Court then turned to consider what aspects of Objective 3B, as proposed by the Interim Decision,32 are
‘on’ PC13. Objective 3B as proposed is set out in Annexure
“D” for convenience.
[78] In terms of this, the Court held that Objectives 3B(1), (2) and
(3)(a) to (c) are
‘on’ PC13, as they are all consequential and implementing
policies, except those related to the spread of wilding pines.
The Court then
held that objective 3B(3)(d) however is not ‘on’ PC13.
[79] The Court went on to consider whether it ought to utilise
its discretion pursuant to s 290 to amend or cancel
the decision of the
Commissioners, or any aspect thereof.33 In this respect, the Court
addressed the issue of ‘greening’ which is, of course, of central
import to Federated Farmers’
appeal against this decision. The Court
stated:34
I shortly turn to itemise what orders the court can and should make under s
290 of the Act. However, before I do, there is a preliminary
point. The
Commissioners’ Decision purported to amend PC13(N) by deleting some words
in the statement of issues which read:
Another issue associated with retaining values of the Basin is the extent
to which additional irrigation will “green”
the Basin and change
land use patterns.
I hold that the decision of the Commissioners to amend the statement of issues is ultra vires. An issue once notified ... cannot ... be added to or deleted from a notified plan change. That is because the public relies on the statement of issues (when identified) when making decisions as to whether or not to lodge submissions. Accordingly the statement of issues in PC13(N) should be reinstated. The court has power to make that change under section
290(2) or (possibly) 292 of the RMA.
[80] This finding lead the Court to make an order (order 6A) which
recorded:
Under section 290(2) of the Resource Management Act 1991, the Environment
Court cancels the decision of the Mackenzie District Commissioners at its
Annexure C paragraph 1 where it purported to delete from Plan Change
13 the
words:
32 Interim Decision, above n 4, at [151].
33 Sixth Decision, above n 1, at [80] – [92].
34 At [84].
Another issue associated with retaining values of the basin is the extent to
which additional irrigation will “green”
the Basin and change land
use patterns...
– to the effect that those words are reinstated in the plan
change.
[81] I have in this section outlined a relatively large portion of the
decision. This is because the entirety of the decision
forms the narrative of
this proceeding. Of course, the appeal is really against order 6A (and
the relevant aspects of
the judgment set out above), and it is on those
aspects of the decision that the discussion below will focus.
Seventh Decision
[82] Federated Farmers appeals against the Seventh Decision in its
entirety. The Court in its judgment rather helpfully sets out what
this decision intended to resolve:35
This decision considers the various submissions on the jurisdiction
and merits of the proposed orders under section
293 of the
Resource Management Act 1991 as outlined in the First (Interim) Decision of the
Court in these proceedings. The
questions to be decided here are:
(1) do the remaining orders proposed in the First (Interim) Decision come
within section 293 and, if so:
(2) should the court exercise such powers?
[83] After again briefly setting out the background to the
proceeding,36 the Court turned to consider the interpretive issue in
earnest.37 This discussion is not fully traversed here, other than
to note that the following observations of broad application were
made:
(a) Because PC13 was notified in 2007, this proceeding fell to be considered pursuant to the provisions of the RMA after it was
amended in 200538 but before it was amended again
in 200939 and
35 Seventh Decision, above n 2, at [2].
36 At [4] – [6].
37 At [8] – [46].
38 Resource Management Amendment Act 2005.
39 Resource Management (Simplifying and Streamlining) Amendment Act 2009.
2013.40 I note here that this interpretation of the transitional
nature of the 2009 and 2013 amendments has not been raised by counsel and
this
judgment proceeds on the basis that that interpretation is
correct.41
(b) By the Interpretation Act 1999, the primary guide to interpretation is
the words of the relevant sections themselves in their
immediate context, along
with the purpose of the section in which they are couched. Resort to other
guides as to meaning may be
had where appropriate.42
[84] Rather, the summary provided by the Court, as replicated below, is
relied upon:43
[47] The primary jurisdiction – to make orders under section 290
– arises if there has been compliance with clause
14 of Schedule 1. That
is, a person can only appeal on a matter or provision that meets the criteria
listed in clause 14(1), and
if they referred to that matter or provision in
submission. Further, as I set out in the Sixth Decision, in the case of a plan
change
the submission must have also been ‘on’ the plan change:
Clearwater Resort Ltd v Christchurch City Council and Option 5 Inc v
Malborough District Council.
[48] Section 293 gives the court powers to resolve the situations where
if, after considering all the relevant factors,
it becomes apparent on
the evidence and/or on the face of the local authority’s decision
that:
in order to achieve the purpose of the RMA an objective not sought in any appeal is the most appropriate objective in terms of section 32
RMA because that objective recognises and provides for a section 6 matter of national importance or takes account under section 8 of the
principles of Te Tiriti o Waitangi;
a policy not sought by any appeal is most appropriate
in order to implement an objective having regard to its efficiency and
effectiveness compared with the alternatives including the status
quo;
an objective may have been amended under section 290(2)
but then consequential amendments to policies and methods (not sought
by any
submission but related to it) may be found by the court to be the most
appropriate solutions under section 32 of the Act.
40 Resource Management Amendment Act 2013.
41 Seventh Decision, above n 2, at [7].
42 At [9].
43 At [47] – [55].
Usually the answer is that a differently worded objective or policy will come
within the range of possibilities permissible under
the “fair and
reasonable in all the circumstances” principle set out by the Full Court
in Countdown Properties (Northlands) Ltd v Dunedin City Council and
extended slightly with the addition of clause 10(2) to the RMA in 1996. But the
section 293 powers are very useful especially
where there are concerns over the
fairness of the process.
[49] Another situation where section 293 may be used is where the local
authority has made an error of law or has substantially
failed to carry out one
of its duties under the RMA or under a statutory instrument. Examples of such
an error or failure might
be:
failure to consider a relevant National Policy
statement (or any of the other instruments referred to in section 293(2));
or
misapplication of section 32 by comparing incorrect
options (e.g. not comparing the effects of the proposed change’s
provision
with the effects of the status quo).
[50] If the court calls for and receives submissions on the issue and is
persuaded that there is indeed such an error or failure,
does the fact that the
error of law has not been raised in any appeal mean that the court can give no
directions under section
293 as to how to fix the problem? One
possibility is to recommend that the local authority pursue a variation under
clause
16A. I consider section 293 provides another.
[51] When section 293 is read as a whole in the scheme of the RMA, I
hold that there is also a limited jurisdiction given to
the Environment Court
where the court identifies, or finds, that a duty of the local authority in
respect of a relevant issue has
not been adequately complied with. In that
case, provided there is a rational connection between the issue which is the
subject
of the plan provision or the plan change and the matter identified by
the court, the court has jurisdiction under section 293 to
give directions about
the matter, notwithstanding that it was not raised in an appeal.
...
[54] In summary, the tests for whether directions are within
jurisdiction are:
(0) in the case of a plan change are the directions about
amending the provision ‘on’ the issue(s) raised
by the plan change?
And
(1A) do the directions fairly and reasonably address a matter or provision
which is the subject of an appeal (and the submission
on which it is based)?
Or
(1B) do the directions address a “consequential alteration arising out of ... any other matters the court considered relating to matters raised in submissions raised in submissions? Or
(1C) do the directions fairly and reasonably flow from a direct breach of
a nationally important statutory duty or a departure
from a higher statutory
instrument? And
(2) are fairness and participation issues fairly and reasonably resolvable by
consultation and notification?
(citations omitted)
[85] After this, the Court turned its mind to consider whether pursuant
to s 293 it had jurisdiction to make the alterations to
the policies and
objectives as proposed in the Interim Decision. In this respect, the
thrust of the judgment here, appears to contain a finding that Objectives 3B(1),
(2) and (3)(a) – (c),
as proposed in the Interim Decision, are
within the scope of the appeals and that there is a sufficient nexus between
those appeals and PC13 as notified.44
[86] An express finding was made that objective 3B(3)(d), which related
to exotic wildings, was beyond jurisdiction.45 The Court then
considered the policies it proposed (attached to this judgment as Annexure C)
and commented:
(a) Suggested policy 3B1 is within jurisdiction except to the extent
that the words “or carbon forestry under an Emissions
Trading
Scheme” should be deleted from 3B1(a).46
(b) Suggested policy “3B(5)” is beyond
jurisdiction.47
(c) Suggested policy 3B8(c) and (d) are within the jurisdiction of s 293 due to the operation of s 6(b) RMA, (as matters of national
importance relating to the protection of outstanding natural
44 At [59] – [65].
45 At [66].
46 At [70].
47 At [71] – [72]. I note that suggested policy 3B5 as set out in the Interim Decision does not relate
to Wilding Trees. In fact, there is no policy “3B(5)” in the Interim Decision. There is a policy
3B5, which relates to development in farm base areas. Additionally, there is a policy 3B15, which deals with Wilding Trees. In light of this confusion, I am unable to ascertain precisely what was being referred to. However, given that the discussion centres on Wildings, I am inclined to the view that this discussion was a reference to policy 3B15, but express no definitive view one way or another.
landscapes) while policies 3B8(a) and (b) are “within the basic scope
of section 292”.48
(d) Suggested policy 3B12 is within
jurisdiction.49
o
48 At [79].
49 At [82].
50 At [83] – [84].
51 At [87].
52 At [88].
53 At [106].
(b) Policy 3B8: the Council should write and consult on policies
which: (i) avoids building or growing structures adjacent to State Highway 8;
(ii) requires buildings to be set back from roads (particularly State Highway
8); and (iii) manages the sensitive location of structures
which detract from
the landscape.54
(c) Policy 3B12: the Council should write a new policy
“encouraging traditional pastoral farming so as to maintain tussock
grasslands”,
subject to Policy 3B8 (as developed by the Council in
accordance with the above directions).55
(d) Policy 3B13: The Council should write a policy for farm buildings
which avoids farm buildings in lakeside areas, scenic viewing areas and along
tourist roads, whilst managing farm buildings elsewhere in terms of location,
design and placement.56
(e) Policy 3B16: It would be useful for the Council to consider
a policy dealing with non-encouragement of subdivision, except in specified
areas,
and specifying a minimum lot size of 200 hectares (except in farm base
areas).57
(f) Policy 3B14: proposed policy 3B14(1) is too general and probably
unhelpful and policy 3B14(2) is beyond the scope of PC13. However, policy
3B14(3) would be a useful backstop, and the Council should prepare a policy
along its lines.58
Eighth Decision
[88] The relevant point emerging from this decision can be addressed
via reference to two paragraphs of this Eighth
Decision:59
54 At [111].
55 At [112].
56 At [113].
57 At [115].
58 At [119].
59 Eighth Decision, above n 3, at [35] – [36].
The court could order that Objective 3B(1) and (2) should be considered under
section 293, but that would be to waste a huge amount
of effort on the only
substantive matter that was actually decided in the First Decision – that
the greater part of the (upper)
Mackenzie Basin is an outstanding natural
landscape which should be recognised and protected as a matter of national
importance.
If this issue was fairly and reasonably before the court and on the
plan change – and I have held it was both – then
there should be
some finality to the litigation on this issue at least (subject to the
qualifications in the Sixth Decision about
variations).
Exercising the court’s powers under section 290, I consider that the
court should cancel the decision of the Mackenzie District
Council’s
Commissioners and should substitute Objective 3B(1) and (2) as set out above
because they are the most appropriate
objectives for achieving the purpose of
the Act for the reasons stated in the First (Interim) Decision.
[89] The orders then made had the effect, inter alia, of deleting
Objective 3B in the Commissioners’ decision and substituting
in its stead
the following replacement objective 3B:60
Objective 3B – Activities in Mackenzie Basin’s outstanding natural
landscape
(1) Subject to (2)(a), to protect and enhance the outstanding natural
landscape of the Mackenzie Basin subzone in particular
the following
characteristics and/or values:
(a) the openness and vastness of the landscape; (b) the tussock grasslands;
(c) the lack of houses and other structures;
(d) residential development limited to small areas in clusters;
(e) the form of the mountains, hills and moraines, encircling and/or
located in, the Mackenzie Basin;
(f) undeveloped lakesides and State Highway 8 roadside;
(2) To maintain and develop structures and works for the Waitaki Power
Scheme:
(a) within the existing footprints of the Tekapo-Pukaki and
Ohau Canal Corridor, the Tekapo, Pukaki and Ohau Rivers,
along the existing
transmission lines, and in the Crown- owned land containing the Lakes
Tekapo, Pukaki, Ruataniwha and Ohau
and subject only (in respect of landscape
values) to the objectives, policies and methods of implementation within Chapter
15 (Utilities)
except for management of exotic tree species in respect of which
all
60 At Order 8C.
objective (1) and all implementing policies and methods in this section
apply;
(b) elsewhere in the Mackenzie Basin subzone so as to achieve objective (1)
above.
[90] For completeness, the Eighth Decision also deleted objective
3A in the Commissioners’ decision and renamed objective 3C to be new
objective 3A, the first six words
of which now read:61
3A Landscape Values
Protection of the outstanding landscape values...
The three appeals
[91] I turn now to consider the grounds advanced by Federated Farmers
with respect to each of the three appeals that are before
me. The appeals are
broad with ten alleged errors of law advanced.
Appeal against the Sixth Decision
[92] In respect of this decision, Federated Farmers appeals
against:
The decision of the Environment Court (as set out in Order 6A) of the Sixth
(Procedural) Decision to cancel the decision of the Mackenzie
District
Commissioners to delete from PC13 the following words:
Another issue associated with retaining values of the Basin is the extent
to which additional irrigation will “green”
the Basin and change
land use and patterns [(“Greening
Issue”)].
To the effect that those words are reinstated in the plan change.
[93] The errors of law said to found this appeal are outlined in the
Notice of
Appeal as follows:
3. The Environment Court erred in law in deciding that an issue once
notified cannot be deleted from a notified plan or plan
change. (First Error of
Law)
4. The Environment Court erred in failing to have regard to
the decision of the Mackenzie District Commissioners
to delete the Greening
Issue from the Statement of Issues... (Second Error of Law)
61 At Order 8B.
[94] The grounds advanced by Federated Farmers for the appeals in respect
of each error of law are addressed below:
First Error of Law
1991). The submissions included a request that the final sentence of
the paragraph to be added to Rural Issue 7 – Landscape Values be
deleted (i.e. the “Greening Issue”). The Commissioners
accepted
this request and deleted the Greening Issue. As this relief was accepted in a
submission, the decision to make this deletion
from the Statement of Issues
was within the jurisdiction of the Commissioners.
Second Error of Law
Appeal against the Seventh Decision
[95] In respect of this decision, Federated Farmers appeals against the
decision in its entirety. The errors of law claimed to
found this appeal as
outlined in the Notice of Appeal are several:
9. The Environment Court erred in law in determining that objective
3B(1) and 3B(3)(a) – (c) are fairly and reasonably within the scope of the appeals, and sufficiently connected to PC13 as notified.
(Seventh Error of Law)
10. The Environment Court erred in law in determining that the policies
3B1 and 3B8 are within jurisdiction on the basis that they implement
Objective 3B. (Eighth Error of Law)
11. The Environment Court erred in law in determining that Policies
3B1, 3B8, 3B12 and 3B13 respond to the submissions and appeals. (Ninth Error
of Law)
[96] The grounds of appeal for each of these alleged errors of law are
replicated below:
Third Error of Law
Fourth Error of Law
Because the issue of “...the extent to which additional irrigation will ‘green’ the Basin and change land use patterns’ [sic] was specifically raised, I hold that objective
3B(3)(a) was ‘on’ PC13 under the first limb of the
Clearwater test.”
Fifth Error of Law
Sixth Error of Law
Seventh Error of Law
32. The Court was wrong in law to find that:
32.1 Objective 3B(1) and 3B(3)(a) – (c) are fairly and reasonably
within the scope of appeals;
32.2 Objective 3B(3)(a) – (c) was responsive to appeals that were
concerned that the objective was to apply in an undifferentiated
way to the
Mackenzie Basin zone as a while [sic]; and
32.3 That objective 3B(3)(b) is a “logical consequence” of the
submissions and appeals by The Wolds Station Limited and
Fountainblue and
others.
Eighth Error of Law
Ninth Error of Law
36. The Court was wrong in law to find that:
36.1 Policies 3B1, 3B8 and 3B12 are within jurisdiction because they respond
to the submissions and appeals, such as the appeal by
The Wolds which seeks that
undifferentiated policies not be applied to the whole Mackenzie Basin.
36.2 Directions along the lines of Policy 3B13 are consequential relief in
that they meet the differentiation principle sought by
The Wolds.
Appeal against the Eighth Decision
[97] In respect of this decision, Federated Farmers appeals
against:
...The decision to cancel the decision of the Commissioners in respect of
Objective 3B of Plan Change 13 (Decision 8A); and to amend
the District Plan by
deleting Objective 3B in the Commissioner’s version of PC13; and
substituting this with a new Objective
3B(1) (Decision 8C) in reliance on
section 290 of the Resource Management Act 1991.
[98] The error of law said to found this appeal is that:
The Environment Court erred in law in confirming Objective 3B(1) in reliance
on section 290 in advance of any process to be followed
pursuant to section 293
to introduce objectives, policies and rules in relation to pastoral
intensification? [(Tenth Error of Law)].
[99] The ground on which this appeal is based is that:
[Tenth Error of Law]
[100] I have read and received the submissions of both
parties in full. I do not propose to replicate significant tracts of those
submissions in a discrete section. Rather, as I discuss each of the four issues
identified below, I will refer to the submissions
of counsel as and when
appropriate.
The issues
[101] It seems to me that the crux of this appeal requires resolution of
four discrete interpretive issues. As I perceive the pleadings,
these
are:
(a) Can an issue, once notified, be deleted from a plan change? Or does
sch 1, cl 10 of the RMA, which requires a decision to
be made on each matter
raised in submissions, confer upon the Commissioners the power to so
delete?
(b) To what extent is the Environment Court required to have regard to the
decision of the Council/the Commissioners pursuant to s
290A?
(c) What is the Environment Court’s jurisdiction pursuant to s
293 – in other words, what is the scope of its statutory
power under s
293? And, on this question, is the Court required to address when an issue will
be considered to be “on”
a Plan Change?
(d) Can the Environment Court, in reliance on s 290, cancel a decision of the
Council/the Commissioners in advance of following the
process contemplated by s
293?
And I am satisfied here that the central issue as outlined at (c) above
relates also to the extent (if any) that the Environment Court
might be
constrained by the appeals before it when invoking s 293, especially where the
Court considers the planning instrument before
it fails to satisfy a duty it has
under s 6 RMA.
[102] I now turn to consider the legislative regime applicable to this appeal before returning to a discussion of the above issues. The resolution of these four issues and
particularly the questions outlined at [101](c) above will ultimately inform
the outcome of the ten claimed errors of law.
Legislative regime
Appeals
[103] The approach of this Court to appeals from the Environment Court is
well rehearsed. It was traversed in my earlier judgment
Simons Hill Station
Ltd v Royal Forest & Bird Protection Society of New Zealand Inc,62
which I repeat below:63
This appeal is governed by s 299 of the RMA, which provides:
299 Appeal to High Court on question of law
(1) A party to a proceeding before the Environment Court under this Act or
any other enactment may appeal on a question of law to
the High Court against
any decision, report, or recommendation of the Environment Court made in the
proceeding.
(2) The appeal must be made in accordance with the High Court Rules, except
to any extent that those rules are inconsistent with sections
300 to
307.
Therefore, if an appeal discloses no discernible question of law, it is not
to be entertained by this Court. The principles applicable
to RMA appeals can
be summarised as follows:
(a) Appeals to this Court from the Environment Court under s
299 are limited to questions of law.
(b) The onus of establishing that the Environment Court erred in law rests on the appellant: Smith v Takapuna CC (1988)
13 NZTPA 156 (HC).
(c) In Countdown Properties (Northland) Ltd v Dunedin City Council [[1994] NZRMA 145 at 153] it was said that there will be an error of law justifying interference with the decision of the Environment Court if it can be established that the Environment Court:
(i) applied a wrong legal test;
(ii) came to a conclusion without evidence or one to which, on
evidence, it could not reasonably have come;
63 At [18] – [19].
(iii) took into account matters which it should not have taken into account;
or
(iv) failed to take into account matters which it should have taken into
account.
(d) The weight to be afforded to relevant considerations is a question for
the Environment Court and is not a matter available for
reconsideration by the
High Court as a question of law: Moriarty v North Shore City Council
[1994] NZRMA 433 (HC).
(e) The Court will not engage in a re-examination of the merits of the case under the guise of a question of law: Sean Investments Pty Ltd v Mackellar (1981) 38 ALR
363; Murphy v Takapuna CC HC Auckland M456/88, 7
August 1989.
(f) This Court will not grant relief where there has been an error of law unless it has been established that the error materially affected the result of the Environment Court’s decision: Royal Forest & Bird Protection Society Inc v W A Habgood Ltd (1987) 12 NZTPA 76 (HC) at 81 – 82; BP Oil NZ Ltd v Waitakere City Council [1996] NZRMA
67 (HC).
Substantive provisions
[104] This appeal involves several provisions of the RMA (as it stood in
2007). For convenience at this point I replicate what
I see as the most
important aspects of the provisions below:
5 Purpose
(1) The purpose of this Act is to promote the sustainable management
of natural and physical resources.
(2) In this Act, sustainable management means managing the use,
development, and protection of natural and physical resources
in a way, or at a
rate, which enables people and communities to provide for their social,
economic, and cultural wellbeing and for
their health and safety
while—
(a) Sustaining the potential of natural and physical resources
(excluding minerals) to meet the reasonably foreseeable
needs of future
generations; and
(b) Safeguarding the life-supporting capacity of air, water, soil, and ecosystems; and
(c) Avoiding, remedying, or mitigating any adverse effects of
activities on the environment.
6 Matters of national importance
In achieving the purpose of this Act, all persons exercising functions and
powers under it, in relation to managing the use,
development, and
protection of natural and physical resources, shall recognise and provide for
the following matters of national
importance:
...
(b) The protection of outstanding natural features and landscapes
from inappropriate subdivision, use, and development:
(c) The protection of areas of significant indigenous vegetation and
significant habitats of indigenous fauna:
...
31 Functions of territorial authorities under this Act
(1) Every territorial authority shall have the following functions for
the purpose of giving effect to this Act in its district:
(a) The establishment, implementation, and review of
objectives, policies, and methods to achieve integrated
management of the
effects of the use, development, or protection of land and associated natural
and physical resources of the district:
(b) the control of any actual or potential effects of the use,
development, or protection of land...
32 Consideration of alternatives, benefits, and costs
(1) In achieving the purpose of this Act, before a proposed
plan, proposed policy statement, change, or variation
is publicly notified, a
national policy statement or New Zealand coastal policy statement is notified
under section 48, or a regulation
is made, an evaluation must be carried out
by—
...
(c) the local authority, for a policy statement or a plan (except for plan changes that have been requested and the request accepted under clause 25(2)(b) of Part 2 of Schedule 1); or
(d) the person who made the request, for plan changes that have been requested and the request accepted under clause
25(2)(b) of Part 2 of the Schedule 1.
(2) A further evaluation must also be made by—
(a) a local authority before making a decision under clause 10 or
clause 29(4) of the Schedule 1; and
...
(3) An evaluation must examine—
(a) the extent to which each objective is the most appropriate way to
achieve the purpose of this Act; and
(b) whether, having regard to their efficiency and effectiveness, the
policies, rules, or other methods are the most appropriate
for achieving the
objectives.
(3A) This subsection applies to a rule that imposes a greater prohibition
or restriction on an activity to which a national environmental
standard applies
than any prohibition or restriction in the standard. The evaluation of such a
rule must examine whether the prohibition
or restriction it imposes is justified
in the circumstances of the region or district.
(4) For the purposes of the examinations referred to in subsections (3)
and (3A), an evaluation must take into account—
(a) the benefits and costs of policies, rules, or other methods;
and
(b) the risk of acting or not acting if there is uncertain
or insufficient information about the subject matter
of the policies, rules, or
other methods.
(5) The person required to carry out an evaluation under subsection
(1) must prepare a report summarising the evaluation and
giving reasons for that
evaluation.
(6) The report must be available for public inspection at the same
time as the document to which the report relates is publicly
notified or the
regulation is made.
73 Preparation and change of district plans
(1) There shall at all times be one district plan for each district
prepared by the territorial authority in the manner set
out in Schedule
1.
(1A) A district plan may be changed by a territorial authority in the manner set out in Schedule 1.
(1B) A territorial authority given a direction under section 25A(2) must
prepare a change to its district plan in a way that implements
the
direction.
(2) Any person may request a territorial authority to change a district plan, and the plan may be changed in the manner set out in Schedule
1.
(3) A district plan may be prepared in territorial sections.
(4) A local authority must amend a proposed district plan or district
plan to give effect to a regional policy statement, if—
(a) the statement contains a provision to which the plan does not give
effect; and
(b) 1 of the following occurs:
(i) the statement is reviewed under section 79 and not changed or replaced;
or
(ii) the statement is reviewed under section 79 and is changed or
replaced and the change or replacement becomes operative;
or
(iii) the statement is changed or varied and becomes operative.
(5) A local authority must comply with subsection (4)—
(a) within the time specified in the statement, if a time is
specified; or
(b) as soon as reasonably practicable, in any other case.
74 Matters to be considered by territorial authority
(1) A territorial authority shall prepare and change its district plan in accordance with its functions under section 31, the provisions of Part
2, a direction given under section 25A(2), its duty under section 32, and any
regulations.
(2) In addition to the requirements of section 75(3) and (4),
when preparing or changing a district plan, a territorial
authority shall have
regard to—
(a) Any—
(i) Proposed regional policy statement; or
(ii) Proposed regional plan of its region in regard to any matter of regional significance or for which the regional council has primary responsibility under Part 4; and]
(b) Any—
(i) Management plans and strategies prepared under other Acts;
and
(ii) Repealed.
(iia) Relevant entry in the Historic Places Register; and
(iii) Regulations relating to ensuring sustainability, or the
conservation, management, or sustainability of fisheries resources
(including
regulations or bylaws relating to taiapure, mahinga mataitai, or other non-
commercial Maori customary fishing),—
to the extent that their content has a bearing on resource
management issues of the district; and
(c) The extent to which the district plan needs to be consistent with
the plans or proposed plans of adjacent territorial authorities.
(2A) A territorial authority, when preparing or changing a district plan,
must—
(a) take into account any relevant planning document
recognised by an iwi authority and lodged with the territorial
authority, to the
extent that its content has a bearing on resource management issues of the
district; and
...
(3) In preparing or changing any district plan, a territorial authority must
not have regard to trade competition.
75 Contents of district plans
(1) A district plan must state—
(a) the objectives for the district; and
(b) the policies to implement the objectives; and
(c) the rules (if any) to implement the policies. (2) A district plan may state—
(a) the significant resource management issues for the district;
and
(b) the methods, other than rules, for implementing the policies for the district; and
(c) the principal reasons for adopting the policies and methods;
and
(d) the environmental results expected from the policies and methods;
and
(e) the procedures for monitoring the efficiency and effectiveness
of the policies and methods; and
(f) the processes for dealing with issues that cross territorial authority
boundaries; and
(g) the information to be included with an application for a
resource consent; and
(h) any other information required for the purpose of the
territorial authority's functions, powers, and duties under
this Act.
(3) A district plan must give effect to—
(a) any national policy statement; and
(b) any New Zealand coastal policy statement; and
(c) any regional policy statement.
(4) A district plan must not be inconsistent with—
(a) a water conservation order; or
(b) a regional plan for any matter specified in section 30(1).
(5) A district plan may incorporate material by reference under Part 3 of
Schedule 1.
290 Powers of Environment Court in regard to appeals and
inquiries
(1) The Environment Court has the same power, duty, and discretion in
respect of a decision appealed against, or to which an
inquiry relates, as the
person against whose decision the appeal or inquiry is brought.
(2) The Environment Court may confirm, amend, or cancel a decision to
which an appeal relates.
(3) The Environment Court may recommend the confirmation,
amendment, or cancellation of a decision to which an inquiry
relates.
(4) Nothing in this section affects any specific power or duty the Environment Court has under this Act or under any other Act or regulation
290A Environment Court to have regard to decision that is subject of
appeal or inquiry
In determining an appeal or inquiry, the Environment Court must
have regard to the decision that is the subject of the appeal
or
inquiry.
(1) After hearing an appeal against, or an inquiry into, the
provisions of any policy statement or plan that is before the
Environment Court,
the Court may direct the local authority to—
(a) prepare changes to the policy statement or plan to address any
matters identified by the Court:
(b) consult the parties and other persons that the Court directs about
the changes:
(c) submit the changes to the Court for confirmation. (2) The Court—
(a) must state its reasons for giving a direction under subsection
(1); and
(b) may give directions under subsection 1 relating to a matter that
it directs to be addressed.
(3) Subsection (4) applies if the Environment Court finds that a
policy statement or plan that is before the Court departs
from—
(a) a national policy statement:
(b) the New Zealand coastal policy statement: (c) a relevant regional policy statement:
(d) a relevant regional plan:
(e) a water conservation order.
(4) The Environment Court may allow a departure to remain if
it considers that it is of minor significance and does
not affect the general
intent and purpose of the policy statement or plan.
(5) In subsections (3) and (4), departs and departure
mean that a policy statement or plan—
(a) does not give effect to a national policy statement, the New Zealand coastal policy statement, or a relevant regional policy statement; or
(b) is inconsistent with a relevant regional plan or water
conservation order.
Schedule 1
Preparation, change, and review of policy
Statements and plans
...
Part 1
Preparation and change of policy statements
And plans by local authorities
...
14 Appeals to Environment Court
(1) A person who made a submission on a proposed policy statement or
plan may appeal to the Environment Court in respect of—
(a) a provision included in the proposed policy statement or plan;
or
(b) a provision that the decision on submissions proposes to
include in the policy statement or plan; or
(c) a matter excluded from the proposed policy statement or plan;
or
(d) a provision that the decision on submissions proposes to
exclude from the policy statement or plan.
(2) However, a person may appeal under subclause (1) only if
the person referred to the provision or the matter in
the person's submission on
the proposed policy statement or plan.
(a) the person referred to the provision or the matter in the
person's submission on the proposed policy statement
or plan; and
(b) the appeal does not seek the withdrawal of the proposed policy
statement or plan as a whole.
(3) The following persons may appeal to the Environment Court against
any aspect of a requiring authority's or heritage protection
authority's
decision:
(a) any person who made a submission on the requirement that referred
to that matter:
(b) the territorial authority.
(4) Any appeal to the Environment Court under this clause must be in the prescribed form and lodged with the Environment Court within
30 working days of service of the notice of decision of the local authority under clause 11 or service of the notice of decision of the
requiring authority or heritage protection authority under clause 13, as the
case may be.
(5) The appellant must serve a copy of the notice in the prescribed
manner.
15 Hearing by the Environment Court
(1) The Environment Court shall hold a public hearing into
any provision or matter referred to it.
(2) If the Environment Court, in a hearing into any provision
of a proposed policy statement or plan (other than
a proposed regional coastal
plan), directs a local authority under section 293(1), the local authority must
comply with the Court's
directions.
(3) Where the Environment Court hears an appeal against a provision of
a proposed regional coastal plan, that appeal is an
inquiry and the Environment
Court—
(a) Shall report its findings to the appellant, the local authority
concerned, and the Minister of Conservation; and
(b) May include a direction given under section 293(1) to the regional
council to make modifications to, deletions from, or
additions to, the proposed
regional coastal plan.
(emphasis added)
Discussion
Introduction
[105] I need to make it abundantly clear at the outset that I am not here
concerned with any factual findings made by the Environment
Court to the extent
that they do not disclose an error of law. This is an appeal on questions of
law alone.
[106] I intend to resolve the four discrete issues I have identified above at [101] and then apply those resolutions to the ten grounds of appeal raised by Federated Farmers. However, the reality is that the issues raised herein are, for the most part, interpretive issues bearing upon the jurisdiction of the Environment Court and its constituent Judge(s) and Commissioner(s).
Plan changes generally
[107] Given that this entire proceeding concerns, to varying degrees, the
roles of the Council and the Courts in respect of changes
to district plans, it
is appropriate to briefly discuss the plan change regime under the RMA. An
appropriate starting point is
to repeat the purpose of the RMA, as set out in s
5:
5 Purpose
(1) The purpose of this Act is to promote the sustainable management
of natural and physical resources.
(2) In this Act, sustainable management means managing the use,
development, and protection of natural and physical resources in a way, or at a
rate, which enables people
and communities to provide for their social,
economic, and cultural wellbeing and for their health and safety
while—
(a) Sustaining the potential of natural and physical resources
(excluding minerals) to meet the reasonably foreseeable
needs of future
generations; and
(b) Safeguarding the life-supporting capacity of air, water, soil, and
ecosystems; and
(c) Avoiding, remedying, or mitigating any adverse effects of
activities on the environment.
[108] Sections 6 – 8 set out respectively, “matters of national
importance” (which includes the protection of
outstanding natural features
and landscapes), “other matters” and the “Treaty of
Waitangi”. The matters
identified in those sections are afforded
particular status by the RMA, which inform the purpose in s 5. I note for
clarity that
ss 5 – 8 collectively comprise Part 2 of the RMA.
[109] The “functions, powers, and duties of local authorities”
are set out at ss 30 –
36AA of the RMA. Section 31 is relevantly set out above, which sets out the
functions of a territorial authority, the purpose of
which being to give effect
to the RMA.64 Section 32 imposes certain obligations upon a local
authority to prepare evaluative reports when proposing an activity for which
such
a report is required. Sections 39 – 42 then set out the “powers
and duties in relation to hearings”.
[110] The purpose of district plans is described by s
72:
64 Resource Management Act 1991, s 31(1)(a) and (b).
72 Purpose of district plans
The purpose of the preparation, implementation, and administration of
district plans is to assist territorial authorities
to carry out their functions
in order to achieve the purpose of this Act.
[111] By s 73, the local authority is obliged at all times to have a
district plan, prepared in accordance with schedule 1,65 which may be
changed in the manner prescribed by the same.66 A district
plan may also be prepared in territorial sections.67 When
preparing or changing a district plan, a local authority must do so in
accordance with:68
(a) its functions under section 31; and
(b) the provisions of Part 2; and
(c) a direction given under section 25A(2); and
(d) its obligation (if any) to prepare an evaluation report in accordance
with section 32; and
(e) its obligation to have particular regard to an evaluation report
prepared in accordance with section 32; and
(f) any regulations.
In addition, it must have regard to, inter alia, proposed regional policy
statements, proposed regional plans, management plans and
strategies prepared
under other acts, relevant entries in the historic places register and certain
regulations.69
[112] The contents of district plans are governed by s 75, which mandates,
as noted above at [104], that the district plan is to
state the objectives for
the district, the policies to implement the objectives and the rules (if
any) to implement the
policies.70 There are also the range of
permissible matters that a district plan may state:71
(a) the significant resource management issues for the district;
and
65 Section 73(1).
66 Section 73(2).
67 Section 73(3).
68 Section 74(1)(a) – (f).
69 Section 74(2).
70 Section 75(1).
71 Section 75(2).
(b) the methods, other than rules, for implementing the policies for the
district; and
(c) the principal reasons for adopting the policies and methods; and
(d) the environmental results expected from the policies and methods;
and
(e) the procedures for monitoring the efficiency and effectiveness of the
policies and methods; and
(f) the processes for dealing with issues that cross territorial authority
boundaries; and
(g) the information to be included with an application for a resource
consent; and
(h) any other information required for the purpose of the
territorial authority's functions, powers, and duties under this
Act.
A district plan is also required not to be inconsistent with certain other
planning documents.72 By section 76 a local authority is also
empowered to make certain rules to accompany the district plan.
Issue (a) – ability to delete a notified issue
[113] In my view this issue can be disposed of expeditiously. Federated
Farmers and the Council are in general agreement on this
point. They say that
the Environment Court has formed an erroneous view of the law, and has sought to
impose an artificial limit
on the powers of Commissioners in circumstances such
as this. I agree. This approach, quite simply, is unfounded in terms of
both the statutory provisions and prior case law.
[114] This point of law in my view could be disposed of on the sole ground that the provisions of the RMA are not qualified in the manner contended for by the Environment Court. The mandatory and permissible contents of district plans are set out in s 75. A statement of significant resource management issues may be included.73 By sch 1, cl 6 of the RMA a person is permitted to make submissions on the proposed plan as notified. This is expressed in unqualified terms and, in the
absence of clear language or Parliamentary intent to the contrary, there
is no need to
72 Section 75(3) – (4).
73 Section 75(2)(a).
read into this qualifications as to the scope or content of submissions.
Finally, by a combination of sch 1, cls 8B and 10 the local
authority is
required to hold a hearing into those submissions and provide a decision with
reasons for accepting or rejecting such
submissions (again in their entirety).
The logical result is that the Council (and its Commissioners) are not only
permitted to
consider submissions on such ‘issue statements’, but
are obliged to give reasons for accepting or rejecting such
submissions.
[115] In addition, counsel for both Federated Farmers and the
Council have directed me to authorities in which the precise
course of action
described as “ultra vires” by Judge Jackson has been pursued
by the Courts, and thereby implicitly endorsed.74 While these are
all Environment Court decisions, they are entirely consistent with the view I
have formed in relation to this matter
and therefore reinforce my
conclusion.
[116] Federated Farmers succeed on their first error of law. I find that
the Environment Court was wrong to hold that “an
issue once notified
cannot be deleted from a notified plan or plan change”. This however in
my view is not the death knell
of the greening issue. The finding on this
ground simply records that the specific method used to achieve reinsertion was
unavailable
as a matter of statutory construction. Whether other means may be
available, or indeed whether this is a real concern here to any
major extent,
are other matters. As will appear later in this judgment, my finding on this
question does not affect substantively
the ultimate outcome of this
appeal.
Issue (b) – the obligation under s 290A
[117] Section 290A RMA is mandatory and requires the Environment Court in determining an appeal to have regard to the decision appealed against. Issue (a) noted at [113] above related to the decision of the Environment Court with respect to
‘greening’. Namely, Federated Farmers sought to question the
Sixth Decision of the
Environment Court in reinstating the reference to ‘greening’
in the issues statement.
74 Minister for the Environment v Hurunui District Council EnvC Christchurch C110/99, 15 June
1999; Cammack v Kapiti Coast District Council EnvC Wellington W082/2009, 16 October
2009; Carter Holt Harvey Forests Ltd v Tasman District Council [1998] NZEnvC 47; (1998) 4 ELRNZ 93 (EnvC).
The present issue concerning s 290A also relates solely to that aspect of the
Sixth Decision concerning ‘greening’. Because of the
decision reached above in respect of issue (a), and the decision that is to
follow
on issue (c) (discussed below at [119] and following) I need not reach a
conclusion on this, and do not do so. I do however make
several observations
of general application concerning the s 290A obligation:
(a) The decision that is the subject of the appeal must be given genuine attention and thought, and accorded weight as is appropriate. However, such consideration does not mean the appellate body is in any way beholden to the decision appealed from; it is entitled to
depart when appropriate.75 It has been said that the decision
under
appeal is not “some sort of arresting anchor point” and that it
is “a counsel of efficiency rather than
obedience”.76
(b) There is no presumption that the Environment Court on appeal will follow
the decision appealed from.77 Commonsense dictates that if that
were the case it would be quite antithetical to the de novo role of the
Environment Court on
appeal. Similarly, the requirement, imposed as it
is on the Environment Court, the appellate body, places no onus on the appellant
to demonstrate the first instance decision was not correct.78 It is
trite law however, that a de novo appeal has never warranted an appellate body
proceeding in ignorance of the decision appealed
from.79
(c) The appellate body is not obliged to give reasons for departure from the decision appealed from, though the requirement expressed at [117](a) above would normally be manifest in a requirement that an
explanation be given as to why the Environment Court is
so
75 Man O’War Station Ltd v Auckland Regional Council [2011] MZRMA 235, (2011) 16 ELRNZ
475 (HC) at [65].
76 Horticulture New Zealand v Manawatu-Wanganui Regional Council [2014] NZHC 2492 at [40].
77 Blueskin Bay Forest Heights Ltd v Dunedin City Council [2010] NZEnvC 177 at [53];
Waterfront Watch Inc v Wellington City Council [2012] NZEnvC 74 at [146].
79 Waitakere City Council v Estate Homes Ltd [2006] NZSC 112, [2007] 2 NZLR 149 at [29].
departing.80 As a matter of practice, reasons for departure
from the first instance decision should be given.
[118] The s 290A obligation is not onerous. The first instance decision
simply assumes the mantle of another element of the factual
matrix which the de
novo decision of the Environment Court must take into account in reaching its
determination. Many previous decisions
purport to fulfil this obligation via a
single paragraph which simply records that the Environment Court has had regard
to the decision
appealed against. While this may fulfil the requirement of
having regard (or at least making it clear that such regard has been had),
the
obligation to provide reasons for departure must still be borne in
mind.
Issue (c) – Jurisdiction pursuant to s 293
Introduction
[119] As I have previously signalled, this question formed the central issue
for determination in this appeal. Perhaps more importantly,
this is an issue of
some moment in terms of jurisdictional limits and the extent to which the
Environment Court may theoretically
assume a planning role. However, because of
the conclusion I have reached in respect of issue (a) above the importance of
this issue
might be said perhaps to have reduced to some extent. This is
because from one perspective it could be argued that the Environment
Court might
only be able to exercise its jurisdiction in terms of s 293 as a result of its
finding that the deletion of the greening
issue was ultra vires. That finding
as I have noted above was incorrect. It could be argued therefore it naturally
follows that,
to whatever extent the jurisdiction under s 293 relied upon the
reinsertion of the greening issue, at least on the basis of vires,
the decision
to give effect to that statement through objective 3B was equally
flawed.
[120] But, for present purposes I disagree with that proposition, for reasons which I
will now outline regarding s 293. I leave that aspect on one side and turn
to consider the fundamental purpose of s 293 here. On
its face, section 293 is
broadly worded.
80 At [67], citing H B Land Protection Society Inc v Hastings District Council EnvC Wellington
W57/2009, 28 July 2009.
It contains no statutory restrictions on the Court’s discretion to
direct that changes be prepared to a local authority’s
district plan to
address “any matters” identified by the Court. The fundamental
purpose of s 293 is to give the Court
power to direct changes to a proposed plan
(or plan change), which are not otherwise within the Court’s jurisdiction
due to
the scope of the appeal before it.
[121] But the Courts have consistently held that this power is
not unlimited. Section 293 is to be exercised cautiously
and sparingly
as:
(a) It deprives potential parties or interested persons of the right to be
heard by the local authority;
(b) The Court is to discourage careless submissions and references;
and
(c) The Court has to be careful not to step unnecessarily into the planning
arena.
[122] The discretion must be exercised in a manner
consistent with the Environment Court’s role as a judicial
body with
appellate jurisdiction given it by statute.
[123] In Mawhinney v Auckland City Council,81 Wylie J
stated:
I must however express reservations about the process followed by the
Environment Court. The Court’s jurisdiction on an appeal
under cl 14 of
the Act is not unlimited. As is noted in “Environment and Resource
Management Law”, the Court is primarily a judicial body with appellate
jurisdiction. It is not a planning authority with executive functions.
When it
is dealing with an appeal in relation to a plan change, it must consider whether
any proposed amendment goes beyond what
is reasonably and fairly raised in the
original submission and the notice of appeal. After hearing the appeal, the
Court may,
instead of allowing or disallowing the appeal, exercise its
discretion under s 293 to direct the local authority to prepare
changes to the
plan to address matters identified by the Court. It cannot go beyond
that.
81 Mawhinney v Auckland City Council [2011] NZHC 1300; (2011) 16 ELRNZ 608 at [111].
Interpretation of the Statute
[124] The starting point must of course be the plain words of s 293,82
as informed by the plain words of the RMA, read in light of its
purpose.83 In addition, it is permissible to refer to
“indications” in the enactment to further inform the ascertainment
of meaning
where appropriate.84 I pause here for a
moment to consider the proper approach to this interpretive
exercise.
[125] In Parris v Television New Zealand Ltd,85
Baragwanath J stated:86
The exercise [of statutory interpretation] begins with the language used by
Parliament in enacting the particular measure and consideration
of the facts in
its light. Where that yields no clear answer the Court will have recourse to
well-settled techniques of statutory
interpretation. Their purpose is to
determine what result best squares with the policy of the measure insofar as
that can be deduced
from any pointers provided by Parliament, including the
specific measure, the Interpretation Act 1999, and if necessary analogous
legislation and the presumptions of the common law. With their aid the
Court’s function is to make a practical judgment as
to how the
classification is to be made.
[126] In the context of the RMA, but in relation to s 322, the decision of
Greig J in
Zdrahal v Wellington City Council,87 is
helpful:88
The provisions of s 322 are to be given a fair, large and liberal
construction to ensure the object and the purposes of the Act as
a whole and it
is not to be narrowly construed as by a pedantic grammarian.
This passage followed the replication of the oft-cited passage of Greig J in
another
RMA context from NZ Rail Ltd v Malborough District
Council:89
[Part 2]...of the Act expresses in ordinary words of wide meaning the overall
purpose and principles of the Act. It is not, I think
a part of the Act which
should be subjected to strict rules and principles of statutory construction
which aim to extract a precise
and unique meaning from the words used. There is
a deliberate openness about the language, its meanings and its connotations
which
I think is intended to allow the application of policy in a
82 A-G v Associated Newspapers Ltd [1994] 1 all ER 556 (HL) at 561; CIR v Alcan NZ Ltd [1994]
3 NZLR 439 (CA) at 443.
83 Interpretation Act 1999, s 5(1).
84 Section 5(2).
85 Parris v Television New Zealand Ltd [1999] NZCA 244; (1999) 14 PRNZ 172 (CA).
86 At [11].
87 Zdrahal v Wellington City Council [1995] 1 NZLR 700 (HC).
88 At 706.
89 NZ Rail Ltd v Malborough District Council [1994] NZRMA 70 (HC) at 86.
general and broad way. Indeed, it is for that purpose that the Planning
Tribunal, with special expertise and skills, is established
and appointed to
oversee and to promote the objectives and the policies and the principles under
the Act.
[127] I therefore repeat that the starting point is always the plain words.
Where there is no ambiguity, there is little issue.
However, it is vital that
the plain words are still cross-checked against the purpose of the Act “in
order to observe the
dual requirements of s 5.”90 I now turn
to consider the plain words of s 293, the purpose of the RMA Act and previous
case law.
The plain meaning of s 293
[128] On its face s 293 seems to establish a bipartite regime. The first
aspect consists of subss (1) and (2) and permits the
Environment Court, after
hearing the appeal (or inquiry) into the provisions of the plan, to direct the
local authority to prepare
changes to the plan to address “any
matters” identified by the Court, “to consult the parties and other
persons
that the court directs about the changes”, and to require the
local authority to “submit those changes back to the Court
for
confirmation”. Reasons must be given for such a direction. However,
there is no indication that the s 293 jurisdiction
can only be invoked at the
behest of a party to an appeal (or hearing), as opposed to the Court which
happened here.
[129] The second aspect of s 293 is comprised of subss (3) – (5). In
essence, this regime permits minor departures from
various national
planning documents to remain if the minor departure does not affect the
general intent and purpose of the plan.
[130] Without more, the first aspect of s 293 appears to confer upon the Environment Court a power to assume a quite significant planning role.91 The power to direct changes is qualified only by the fact that the matters directed must be “identified by the Court”. The issue in the present case, as contended for by both
Federated Farmers and the Council, is whether that broad prima facie
jurisdiction is
90 Commerce Commission v Fonterra Co-operative Group Ltd [2007] NZSC 36, [2007] 3 NZLR
767 at [22].
curtailed by either or both of (a) the subject of the appeals
to the Environment Court;
or (b) the subject of the Plan Change.
In light of the purpose
[131] First, the purpose of the Act, here the RMA, is plainly set out by s
5 which I
have outlined at [107] above.
[132] This purpose is informed and guided by ss 6 – 8, which detail
matters to which the Court must have regard. This relationship
was recently
framed in succinct terms by the Supreme Court in Environmental Defence
Society Inc v New Zealand King Salmon Company Ltd:92
[26] Section 5 sets out the core purpose of the RMA — the promotion of sustainable management of natural and physical resources. Sections 6, 7 and
8 supplement that by stating the particular obligations of those administering the RMA in relation to the various matters identified. As between ss 6 and 7,
the stronger direction is given by s 6 — decision-makers “shall recognise and provide for” what are described as “matters of national importance”, whereas s 7 requires decision-makers to “have particular regard to” the
specified matters. The matters set out in s 6 fall naturally within the concept of sustainable management in a New Zealand context. The requirement to
“recognise and provide for” the specified matters as “matters of national importance” identifies the nature of the obligation that decision-makers have in relation to those matters when implementing the principle of
sustainable management. The matters referred to in s 7 tend to be more abstract and more evaluative than the matters set out in s 6. This may explain
why the requirement in s 7 is to “have particular regard to” them
(rather than being in similar terms to s 6).
...
[28] It is significant that three of the seven matters of national
importance identified in s 6 relate to the preservation or
protection of certain
areas, either absolutely or from “inappropriate” subdivision, use
and development (that is, ss
6(a), (b) and (c)). Like the use of the words
“protection” and “avoiding” in s 5, the language of ss
6(a),
(b) and (c) suggests that, within the concept of sustainable management,
the RMA envisages that there will be areas the natural characteristics or
natural features of which require protection from the adverse
effects of
development. In this way, s 6 underscores the point made earlier that
protection of the environment is a core element of sustainable
management.
(Emphasis added)
[133] Next, the purpose of district
plans is expressly stated in s 72 of the RMA:
The purpose of the preparation, implementation, and administration of
district plans is to assist territorial authorities
to carry out their functions
in order to achieve the purpose of this Act
(Emphasis added).
[134] So, the ultimate purpose of district plans is to achieve the purpose of the RMA, as set out above. As a matter of logic, if a district plan is not achieving the purpose of its existence, then it would be absurd to let that plan (or plan change) stand undisturbed by the limited planning role explicitly conferred upon the Environment Court. However, I also accept that the plan change regime created by the RMA is such that it was originally envisaged that substantive decisions relating to planning documents are to be subject to the regimented processes constituted by
the RMA,93 not amenable to alteration at the whim of the
Environment Court for the
present time sitting.
[135] A purposive analysis does little to narrow the ambit of the prima
facie broad powers conferred on the Environment Court on
appeal, or to resolve
the apparent tension between these two principles which might be seen to be in
conflict. I turn now to review
the role of the Environment Court on
appeal.
The role of the Environment Court on appeal
[136] It is trite law that the Environment Court’s role is a judicial one, and does not ordinarily intrude into the realm of planning, a domain generally the sole occupation of the local authority.94 This is important as it highlights the benefit of having matters of wide ranging import subject to the regimented and rigorous processes constituted by the RMA,95 being attended to by the ‘at source’96 authority, rather
than a Court divorced from the minutiae of public sentiment and
consciousness. In
93 Re Thames-Coromandel District Council EnvC Wellington W034/09, 15 May 2009 at [17].
94 Mawhinney v Auckland City Council [2011] NZHC 1300; (2011) 16 ELRNZ 608 (HC) at [11]; Auckland Council v
Byerley Park Ltd [2013] NZHC 3402 at [21].
95 Re Thames-Coromandel District Council EnvC Wellington W034/09, 15 May 2009 at [17].
fact, it has been expressly stated that s 293 does
not entitle the Environment Court to shed itself of its appellate role and step
into a planning role.97
[137] In a slightly different context, the Supreme Court, in Waitakere
City Council v Estate Homes Ltd,98 said:99
The legislation envisages that the Environment Court will consider
the matter that was before the Council and its decision
to the extent that it is
in issue on appeal. Legislation providing for de novo appeals has never been
read as permitting the appellate
tribunal to ignore the opinion of the tribunal
whose decision is the subject of appeal. In the planning context, the decision
of
the local authority will almost always be relevant because of the
authority's general knowledge of the local context in
which the issues
arise.
[138] However, as I have noted above, there is a clear tension
between these judicially enunciated principles concerning
the dichotomy between
appellate judicial functions and planning functions, and the plain fact that
Parliament has vested in the Environment
Court, as an appellate body, what
appears at first blush to be broad planning powers. What therefore falls for
determination is
how these two concepts come together to ensure the
interpretation afforded to s 293 is congruent with clear judicial comment and
an
equally clear statutory provision enacted by Parliament. I consider this
interplay in the discussion on the s 293 jurisdiction
below. However, because
this issue was raised before me as having some relevance here, I first set out
the test for determining
whether a submission is ‘on’ a plan
change.
The test for determining whether a submission is ‘on’ a Plan
Change
[139] This issue was recently the subject of detailed consideration by Kós J in
Palmerston North City Council v Motor Machinists Ltd.100
His Honour broke the analysis down into a review of the leading
cases,101 which was followed by a
98 Waitakere City Council v Estate Homes Limited [2006] NZSC 112, [2007] 2 NZLR 149.
99 At [29].
100 Palmerston North City Council v Motor Machinists Ltd [2013] NZHC 1290 at [46] – [83].
101 These included Clearwater Resort Ltd v Christchurch City Council HC Christchurch AP34/02,
14 March 2003; Option 5 Inc v Malborough District Council [2009] NZHC 1348; (2009) 16 ELRNZ 1 (HC); Halswater Holdings Ltd v Selwyn District Council [1999] NZEnvC 114; (1999) 5 ELRNZ 192 (EnvC). In addition the decision in Naturally Best New Zealand Ltd v Queenstown Lakes District Council EnvC Christchurch C49/2004, 23 April 2004 was considered and discounted by Kós J as being
detailed discussion. The following broad principles can be elucidated from
His
Honour’s decision and the cases cited therein:
(a) From the Clearwater discussion:102 the
question of whether a submission is ‘on’ a plan change is one of
“apparently irreducible simplicity but
which may not necessarily be easy
to answer in a specific case”. The approach adopted by William Young J
was one that focuses
on the extent to which the variation in question alters the
proposed plan. In adopting this approach William Young J adopted a two-pronged
framework:
(i) A submission is only ‘on’ a variation “if it is
addressed to the extent to which the variation changes the pre-existing
status
quo”.
(ii) If the effect of regarding a submission as “on” a variation
would be to permit a planning instrument to be appreciably
amended without real
opportunity for participation by those potentially affected, that will be a
“powerful consideration”
militating against a finding that the
submission was truly ‘on’ the plan change.
(b) From the Halswater discussion:103 Kós J noted here that William Young J drew on Halswater in formulating the above test in Clearwater. The crux of Halswater is the comment to the effect that if a submitter seeks a remedy that is much beyond what is contemplated by the plan change, they will have to resort to alternate avenues to achieve that remedy. The Environment Court in that case made the specific comment that “submissions on a plan change cannot seek a rezoning ... if a rezoning is not contemplated by a plan
change.”
incorrect to the extent it sought to depart from Clearwater.
102 Palmerston North City Council v Motor Machinists Ltd [2013] NZHC 1290 at [48] – [57].
103 At [58] – [65].
(c) From the Option 5 discussion:104 the
proposition put forward in this case is reducible to the principle that simply
because a matter is proposed in a plan change does
not mean that a submission
seeking to extend that proposal will be ‘on’ a plan change. In
Option 5 it was said that an approach such as this would be “too
crude” and that ultimately the Clearwater test needs to be
applied.
[140] Ordinarily this issue will arise where a party is attempting
to make submissions on a plan change which are beyond
the scope of what was
intended by the local authority. In such cases, the submissions are moot
because they seek to address an
issue which was not ‘live’. I take
it that Federated Farmers and the Council here are making the related point that
the Environment Court cannot invoke the s 293 jurisdiction of its own motion to
equally address an issue that is not live. However,
that does ignore the prima
facie position that the raison d'être of s 293 is, to some extent, to
alter the initial reference
by directing that changes be made. Implicit in this
concept is the possibility that an issue that was once not ‘live’,
could so become as a result of the jurisdiction.
[141] I would be willing to accept as a proposition of general, but not
universal, application that the s 293 jurisdiction should
ordinarily be invoked
only to address live issues, and not to create them. However, at least to a
significant extent, that distinction
can be put to one side. I am of the view
that in the present case this issue, is to a large degree, a question of fact,
not one
of law. I accept for the purposes of this present appeal that the issue
of greening (and thereby pastoral intensification) was ‘on’
PC13 for
the following reasons:
(a) PC13 as notified made express and unequivocal reference to the
issue of greening as associated with increased irrigation.
This reference was
introduced at the behest of the local authority and marked a clear deviation
from the status quo.
(b) The purpose of PC13 was stated to be to protect the
“Mackenzie
Basin from inappropriate subdivision, development and use.”
Quite
104 At [66] – [68].
clearly issues associated with farming (including pastoral intensification)
are capable of falling within the scope of that purpose.
(c) Submitters were alive to this issue as the Commissioners saw fit to
pass comment on the matter on the basis of submissions
on point. There is
therefore no question that this was not an issue ventilated and contemplated by
either the parties making submissions
or the Commissioners.
[142] Having made express reference to these issues in PC13, the local
authority cannot subsequently seek to disavow itself of the
implications in this
proceeding. I am reinforced in this view by the general pragmatism adopted by
the Courts in determining whether
a matter has been disclosed by a
submission,105 which is applicable by analogy to the approach taken
to what a plan change itself (or an appeal) discloses.
[143] It therefore follows that Federated Farmers are not successful in
terms of its
Fourth error of law.
Jurisdiction under s 293
[144] The principles applicable to jurisdiction pursuant to s 293 are well
rehearsed. However, their application is not so simple
in this case as the
Environment Court has invoked the jurisdiction of its own motion, rather than
following the receipt of an application
to do so would be more
typical.
[145] As best I can tell, before me there was no real dispute between the
parties as to the correct approach to be taken to s 293,
so I record the
principles succinctly:
(a) The primary purpose of s 293 is, in appropriate cases, to expand
the
“nature and extent of relief sought beyond the scope of the
reference”,
though such relief must be referable to, and arise from, the
original
reference.106 It has
been said that “there must be a nexus between the reference itself and the
changed relief sought”.107 Put simply, the matters must be
within the scope of the plan change.
(b) Where the use of s 293 would have substantial consequences on
persons who would have a “vital interest”,108 resort
ought not to be had to the section lightly. This issue is particularly acute
where the invocation of s 293 would have impacts
on geographical regions outside
the original contemplation of the plan change109 or on subject
matters not within its original contemplation.110 In the latter
two situations, it is likely that granting such relief would be beyond its
jurisdiction.111
(c) Though the power conferred upon the Environment Court by s 293 is
prima facie very broad, it does not confer a general discretion;
it must be
exercised judicially in accordance with the overall regime created by the RMA,
and does not entitle the Environment Court
to make planning decisions where it
simply disagrees with decisions made by a planning
authority.112
(d) In the case of s 293 relief sought by a party to an appeal, that relief must relate to the subject matter of the appeal and the original relief sought “as a matter of discretion”.113 Though the jurisdiction “is not limited to the express words of the reference”, the relief sought must
be a foreseeable consequence of the changes proposed in
the
106 Hamilton City Council v New Zealand Historic Places Trust/Pouhere Taonga [2005] NZRMA
145 (HC) at [25].
107 At [25].
108 Day v Manawatu-Wanganui Regional Council [2012] NZEnvC 182 at [5-76].
110 At [468]. See too Friends of Nelson Haven and Tasman Bay (Inc) v Tasman District Council
EnvC Auckland A078/08, 16 July 2008 at [25].
111 Queenstown Airport Corporation Ltd v Queenstown Lakes District Council [2013] NZEnvC
224, citing General Distributors Ltd v Waipa District Council [2008] NZHC 2104; (2008) 15 ELRNZ 59 (HC) at [32]
and [65].
112 Auckland City Council v Byerley Park Ltd [2013] NZHC 3402, [2014] NZRMA 124 at [21].
113 Gardez Investments Ltd v Queenstown Lakes District Council EnvC Queenstown C95/05, 4 July
2005 at [56]
reference.114 The overarching consideration is one of
procedural fairness.115
(e) Even where the Court has jurisdiction to resort to s 293, that does
not mean it should so resort; it is a power that should
be used
sparingly.116
(f) Where the discretion is exercised, the Court cannot go beyond
directing the local authority to prepare changes to the
plan to address the
matters identified by the Court.117
[146] The vast majority of cases contemplate the situation in which a party
to an appeal invites the Court to invoke s 293
as a method of
altering the original reference. However, in the present case, it seems that
the Environment Court has invoked
the jurisdiction of its own motion. This
might be somewhat unusual, but nonetheless it is a situation contemplated by s
293.
[147] In this light, I am satisfied that it was open to the Environment
Court to utilise s 293 in the way it did. Though I agree
with this approach in
substance, I am not in agreement with the test that was formulated by
the Environment Court. Though
I need not record a final position on this,
aspects of a potentially correct test require that the matter(s) sought to be
addressed
with s 293 must ordinarily:
(a) be ‘on’ the plan change.
(b) be within the scope of submissions to the local authority (and
therefore form part of its decision).
(c) be within the scope of the appeals and the relief
sought.118 In determining whether this requirement has been met,
the Court will
114 Westfield (NZ) Ltd v Hamilton City Council [2004] NZRMA 556 (HC) at [73].
115 At [74].
117 Mawhinney v Auckland Council [2011] NZHC 1300; (2011) 16 ELRNZ 608 (HC) at [111].
118 Briggs v Christchurch City Council EnvC Christchurch C045/08, 24 April 2008 at [253].
take a broad and pragmatic approach, unbridled by legal nicety. However, an unduly broad approach is equally inappropriate. Any
‘matter’ identified must be within the general tenor of the
appeal.119
[148] However, there may be some narrow exceptions to this general approach
in circumstances including but not limited to situations
where there
is:
(i) an inadequate s 32 report.
(ii) a failure to comply with s 74 (including preparation in
accordance with the provisions of Part 2).
(iii) a more than minor deviation from one of the matters referred to in s
293(3), whether or not raised on appeal.
[149] Any exception would normally be a condition precedent to validity of a plan change. In these situations, where the failure has a material bearing on the plan change, I am of the view that there would “be some appropriate basis for the Court to determine to exercise its discretion.”120 Moreover, in circumstances falling within that narrow exception it would be inappropriate to hold that the Environment Court did not have jurisdiction to redress a failure at planning level to comply with a
mandatory obligation. In my view, this is a case falling within such an
exception. The reasons for this finding are:
(a) There has been a positive and unchallenged final decision that the Mackenzie Basin is an outstanding natural landscape. This is a finding from PC13. Section 6(b) RMA not only requires, but mandates, that all persons exercising functions and powers under the Act shall recognise and provide for the “protection of outstanding natural features and landscapes from inappropriate subdivision, use,
and development.”
120 Thacker v Christchurch City Council EnvC Christchurch C026/09, 6 May 2009 at [91].
(b) Quite apart from the issue of greening, at a minimum, Policy 3A of PC13
recorded that one of its purposes was to recognise
the Mackenzie Basin
as an outstanding natural landscape and to protect the zone from
inappropriate subdivision, use and development. These words are verbatim
replications of the s 6 test. Broad protection was
therefore squarely at the
fore in PC13.
(c) Similarly, the intention of Objective 3A was to “protect and
sustain the outstanding natural landscapes and features
of the district for
present and future generations”.
[150] The issue therefore seems to be that the Mackenzie District Council
saw fit to embark on a course of action with a substantially
broad remit, but
arguably it failed to specifically implement that broad aim. Put simply, the
broad purpose was to protect the Mackenzie
Basin. The specific policies and
objectives crafted to meet that aim, it could be said, were inadequate. In
large part they sought
to deal principally with housing and other related
development. Arguably, that is not congruent with the wider purpose of
seeking to recognise the region as an outstanding natural landscape. This
recognition has since occurred. Once that did
happen, the Environment Court was
required by the mandatory direction in s 6, to recognise and provide for its
protection.
[151] I am reinforced in this conclusion by the wide ranging nature of the
appeals which were lodged here against the Commissioners’
decision. In
many cases the appeals were said to be against the entirety of the decision.
Where a party drafts broadly in this
manner, but actually may intend only to
appeal certain parts, then there can be no complaint that its imprecise language
has led
to an unintended consequence. In this regard, I note that the prayer
for relief in the Wolds’ appeal recorded, inter alia:
Such further or other relief as may be rational and applicable having regard
to all the circumstances and to achieve a rational zone
change.
[152] This is extremely broad. It must be remembered, that the Environment Court, on appeals from local authorities, can face wide-ranging contentions, between which
it must seek to do justice. I am therefore inclined to the view that the
notices of appeal were sufficiently broad to confer upon
the Environment Court
jurisdiction to consider matters in the round, including the deleted
issue.
[153] While I am in significant agreement with the general substantive
outcome reached by the Environment Court, there are still
cogent objections to
the manner in which it deployed the s 293 jurisdiction here. On this aspect I
find:
(a) The Environment Court may have stepped beyond its role pursuant to
s 293 by drafting the proposed changes. The jurisdiction
is to direct that
changes be made, not to make the changes and direct that they be
implemented.
(b) The Court was ill-equipped to carry out the s 32 analysis of the
proposed changes given their extent. Further, where
significant changes are
proposed by the Environment Court, the Council should be directed to publicly
notify the changes so comment
is sought and received on each issue.
[154] In my view, this is a case where the changes proposed by the
Environment Court were so wide ranging and of such import that
I consider the
summary process adopted by the Court for dealing with the proposed changes was
inadequate. Thus, I think the appropriate
course here is to refer the matter
back to the Environment Court with the following directions:
(a) Given that the main issue here is a failure to consider specific
policies and objectives for addressing the broad prohibition
on inappropriate
subdivision, use and development contained in both PC13 and s 6(b) RMA, it is
this broad failure that must be addressed
by the Council. The specific changes
proposed by the Environment Court should assume the position of
recommendations.
(b) A new s 32 report will be necessitated in order to enable
full
consideration of when the “most appropriate” threshold will be met.
This is particularly so in light of the finding that the Mackenzie Basin is
an outstanding natural landscape.
(c) Any changes prepared by the Council should be publicly notified.
These are matters of vital importance to the region, which need to be engaged
by the public. In fact, once the changes are made,
the entire plan change
should again be notified.
[155] The practical result of the findings I have reached on this issue
resounds across almost all grounds of appeal. In fact,
in many ways it is a
substantial resolution to them, For that reason, as is reflected in my
conclusions on each claimed error
of law, I need not specifically address each
error.
Summary of findings
[156] This has been a complex issue. For brevity, I record the most
important aspects of my findings on the s 293 jurisdiction.
First, I
have found that the orthodox test is that the matter sought to be addressed
must be ‘on’ the plan change,
within the scope of submissions to the
council, and be within the scope of the appeals to the Environment Court
and the relief
there sought. However, this orthodox position is not
without exception.
[157] Applied to the present case, I have reached a view that quite apart
from the deletion of the ‘greening’ issue,
PC13 is broader in scope
than that contended for by either party. It sought to protect what is, now
certainly, an outstanding natural
landscape from inappropriate subdivision, use
and development. The failure here was by the Council to not include sufficient
policies
and objectives to meet that aim. Not only was this an aim of PC13, but
doing so is rendered obligatory by s 6(b) RMA. There are
also a suite of
provisions which require the Council to consider s 6. I consider they failed
properly to do so here.
[158] Moreover, apart from that basis for my findings, I am satisfied that the appeals to the Environment Court were sufficiently broad to enable it to pursue the course it ultimately elected.
[159] Notwithstanding my agreement with the substantive decision reached by
the
Environment Court, there were procedural deficiencies that require
rectification.
Issue (d) – Interrelationship between ss 290 and 293
[160] It is my understanding that this issue was effectively abandoned by
counsel for the parties at the hearing before me. I do
not therefore need to
consider this issue further. However, if I am wrong as to this aspect, I
reserve leave to the parties to file
memoranda, and I will deal with this issue
on the papers as an addendum to this judgment.
Result
First error of law
[161] Federated Farmers succeeds on this ground of appeal. The
Environment Court was incorrect to hold that an issue, once notified,
cannot be
deleted from a plan change. It therefore follows that, on this basis, the
Environment Court had no jurisdiction to address
the issue of greening of the
Mackenzie Basin.
Second error of law
[162] I reach no conclusion on this ground of appeal as the practical effect
of Federated Farmers succeeding on the first ground
of appeal renders this
ground redundant.
Third error of law
[163] Federated Farmers fails on this ground of appeal. This is a rare
case where the Environment Court was, broadly speaking,
entitled to pursue the
course of action it did.
Fourth error of law
[164] Federated Farmers fails on this ground of appeal. The legal test it advocates for is not directly transferrable to the issue in question. In any event I find that the
Environment Court was entitled, as a matter of fact, to find that the issue
of greening
(and thereby pastoral intensification) was ‘on’ PC13.
Fifth, sixth, seventh, eighth and ninth errors of law
[165] Because of the findings I have reached in terms of the third claimed
error of law, these grounds of appeal almost wholly fall
away. These matters
will again be addressed by the Environment Court and the Council in accordance
with the directions to the Environment
Court that will accompany this
decision.
[166] In addition, on many of the remaining claimed errors of law, there
were either mixed issues of law and fact, or wholly factual
disputes.
Tenth error of law
[167] At the hearing this ground of appeal was effectively
abandoned and I therefore do not need to consider it further.
If I am wrong
on this aspect as I have noted, I reserve leave to the parties to file further
submissions on this point and I will
determine it on the papers.
Costs
[168] Though there was no substantial contradictor in this case, each party
has had some measure of success on appeal. I am inclined
to the view that costs
should lie where they fall. If the parties disagree and costs are sought, then
I direct:
(a) The party or parties claiming costs shall file and serve
submissions within twenty working days of this judgment being
released.
(b) The other party shall file and serve response submissions within
fifteen working days following receipt of the other
party’s
submissions.
(c) I will then deal with the issue of costs on the papers.
Relief
[169] While I acknowledge that this Court is seized of the ability, in
appropriate circumstances, to substitute the decision that
should have been made
by the Environment Court,121 this is not in my view, such a case.
That is particularly so given the allegations of inadequacy in terms of s
32.122 This is a case where it is appropriate to refer the matter
back to the Environment Court for determination in light of the findings
made
here on the points of law.123
[170] I therefore make the following orders–
(a) The appeal against the Sixth Decision is allowed. The
decision of the Environment Court is quashed to the extent it found that the
deletion of the ‘greening’
issue was ultra vires.
(b) The appeal against the Seventh Decision is substantively
dismissed, though procedurally it succeeds to a limited point. I therefore
quash the Seventh Decision and refer it back to the Environment Court for
reconsideration with the following directions:
(i) Section 293 was able to be utilised. A more appropriate test is set out
in this judgment.
(ii) The directions to the Council should be to prepare changes, not to
implement already prepared changes.
(iii) In light of the Environment Court’s finding that the true scope of PC13 is determined to be much broader than originally thought by the Council, a new s 32 Report is required and will need to be commissioned by the Council to address the
changes and matters identified by the Environment
Court.
121 Landrover Owners Club (Otago) Inc v Dunedin City Council (1998) 4 ELRNZ 252 (HC).
122 Taylor v Hahei Holidays Ltd [2005] NZCA 248; [2006] NZRMA 15 (CA).
(iv) The entire varied plan change
should again be publicly notified by the Council to enable the community to
be consulted
and to engage with what is being proposed.
(v) Following consultation, the Council should submit the final changes to
the Environment Court for confirmation.
...................................................
Gendall J
Solicitors:
Duncan Cotterill, Christchurch
Tavendale and Partners, Christchurch
Cooper Rapley, Lawyers, Palmerston North
Annexure A
Objective 3A – Outstanding Landscapes
To protect and sustain the outstanding natural landscapes and
features of the
District for present and future generations.
Policy 3A – Recognition of Mackenzie Basin
To recognise the Mackenzie Basin as an outstanding natural landscape and
through the Mackenzie Basin Subzone within the Rural Zone,
to protect the Basin
from inappropriate subdivision, use and development.
Policy 3B – Economy, Environment and Community
To encourage a healthy productive economy, environment, and community
within, and maintain the identity of, the Mackenzie Country.
Policy 3C – Adverse Effects of Sporadic Development
To avoid the adverse effects on the environment of sporadic
development and subdivision.
Policy 3D – Adverse impacts of Buildings and Earthworks
To avoid adverse impacts on the outstanding natural landscape and features
of the Mackenzie Basin, in particular from buildings,
domestication,
structures, earthworks, tracks and roads.
Policy 3E – Limitations on Residential Subdivision and
Housing
To only provide for residential subdivision and housing
development within identified urban areas of the Basin (Twizel and
Lake Tekapo)
and within identified or approved building nodes.
Policy 3F – Landscape Carrying Capacity
To recognise the diversity of physical settings and landscapes within the
Mackenzie
Basin and the varying capacity of these to absorb built
development.
Policy 3G – Approved Building Nodes
New building nodes will only be granted as “approved building
nodes” where the
Council is satisfied [of various matters].
Policy 3H – Extensions to Existing Identified Nodes
Extensions to existing identified building nodes will only be granted
where the Council is satisfied that all the matters listed above
in Policy 3G
are satisfied other than items 8 and 13, and that there is no longer sufficient
land available within the identified
node for the operational requirements of
the property.
Policy 3I – Farm and Non-Residential Buildings
Farm and other non-residential buildings, other than farm buildings that
require a remote location, are required to locate within
identified or approved
building nodes.
Policy 3J – Remote Farm Buildings
To recognise that some farm buildings are required because of their
function to locate away from building nodes and to provide for
these buildings
subject to location, design and external appearance controls.
Policy 3K – Lakeside areas
To avoid adverse impacts of buildings, structures and uses on the
landscape values and character of the Mackenzie Basin lakes and
their
margins,
Policy 3L – Subdivision
(a) To provide for subdivision of land for non-residential purposes
only where this subdivision does not have the potential to
impact on the
landscape values and character of the immediate wider area, and will not
diminish the sustainability of existing and
likely future productive use of farm
holdings.
(b) To only provide for subdivision for residential purposes within
identified or approved building nodes.
Policy 3M – Manuka Terrace Rural-Residential Zone
To manage the adverse effects of existing and further subdivision and
development on Manuka Terrace, Lake Ohau through the Residential
– Mauka
Terrace Zone.
Policy 3N – Design and Appearance of Buildings
To control the design, appearance and location of all buildings within the Mackenzie Basin to avoid or mitigate adverse impacts on the landscape values of the Basin Subzone.
Police 3O – Views from Roads
To manage landscape change so that the outstanding natural landscape
values and features are protected and the screening of distinct
views is avoided
when viewed from public roads.
Objective 3B – Landscape Values
Protection of the natural character of the landscape and margins of lakes, rivers and wetlands and of the natural processes and elements that contribute to the District’s overall character and amenity.
Annexure B
Objective 3A – Distinctive and Outstanding Landscapes
To protect and sustain the distinctive and outstanding natural
landscapes and features of the District from subdivision
and development that
would detract from those landscapes.
Policy 3A – Recognition of Mackenzie Basin
To recognise the Mackenzie Basin as having a distinctive and
highly valued landscape containing outstanding natural landscapes,
and through
the Mackenzie Basin subzone within the Rural Zone, to protect the Basin from
inappropriate subdivision, use and development.
Policy 3B – Landscape Diversity
To recognise the diversity of physical settings and landscapes within the
Mackenzie Basin and the varying capacity of these to absorb
further subdivision,
buildings and domestication, and in particular to recognise the suitability of
existing farm base areas to accommodate
and absorb additional
buildings.
Policy 3C – Adverse impacts of Buildings and Earthworks
To avoid adverse impacts on the outstanding natural landscape and features
of the Mackenzie Basin, in particular from residential,
buildings,
domestication, structures, earthworks, tracks and roads.
Policy 3D – Adverse Effects of Sporadic Development
To control non-farming buildings and subdivision in the Mackenzie Basin
(outside of existing farm base areas) to ensure adverse effects
on the
environment of sporadic development and subdivision are avoided and to sustain
existing and likely future productive use of
farm holdings.
Policy 3E – Limitations on Residential Subdivision and
Housing
To provide for residential subdivision and housing development in the Mackenzie Basin only within identified urban areas of the Basin (Twizel and Lake Tekapo), within the special zone for a possible small settlement at Lake Pukaki and within identified farm base areas.
Policy 3F – Design and Appearance of Buildings
To control the design, scale, appearance and location of residential
buildings, and other buildings where reasonable, with regard
to the purpose of
the buildings, within the Mackenzie Basin to avoid, remedy or mitigate adverse
impacts on the landscape and heritage
values of the Basin Subzone.
Policy 3G – Lakeside areas
To avoid adverse impacts of buildings, structures and uses on the
landscape values and character of the Mackenzie Basin lakes and
their
margins.
Policy 3H – Views from Roads
To require buildings to be set back from roads, particularly state
highways, and to encourage the sensitive location of structures
such as large
irrigators to avoid or limit screening views of distinctive and outstanding
landscapes of the Mackenzie Basin.
Policy 3I – Manuka Terrace Rural-Residential Zone
To avoid, remedy or mitigate the adverse effects of existing and further
subdivision and development on Manuka Terrace, Lake Ohau
through the Rural
Residential – Manuka Terrace Zone.
Policy 3J – Renewable Energy
To recognise and provide for the use and development of
renewable energy generation and transmission infrastructure and
operations
while, as far as practicable, avoiding, remedying or mitigating significant
adverse effects on the outstanding natural
landscapes and features of the
Mackenzie Basin.
Objective 3B – Economy, Environment and Community
To encourage a healthy productive economy, environment, and community
within, and maintain the identity of, the Mackenzie Country.
Policy 3K – Farming Buildings and Subdivision
To enable productive use of the land of the Mackenzie Basin and in particular farming use, by providing for farming buildings and subdivision to facilitate farming, while limiting their potential adverse impacts on important landscape values.
Objective 3C – Landscape Values
Protection of the natural character of the landscape and margins of lakes,
rivers and wetlands and of the natural processes and elements
that contribute to
the District’s overall character and amenity.
Policy 3L – Important Landscapes and Natural Features
To limit earthworks on steeper slopes, high altitude areas, and on land
containing geopreservation sites to enable the landforms
and landscape
character of these areas to be maintained.
Policy 3M – Scenic Viewing Areas
To limit structures and tall vegetation within scenic viewing areas to
enable views of the landscape to be obtained within and from
these
areas.
Rural Policy 3N – Impacts of Subdivision Use and
Development
Avoid or mitigate the effects of subdivision, uses or development which
have the potential to modify or detract from areas with a
high degree of
naturalness, visibility, aesthetic value, including important landscapes,
landforms and other natural features.
Policy 3O – Tree Planting
To control the adverse effects of siting, design and potential wildling
tree spread of tree planting throughout the District, to enable
forestry to be
integrated within rural landscapes and to avoid screening of distant
landscapes.
Rural Policy 3P – In Harmony With The Landscape
To encourage the use of guidelines for the siting and design of buildings
and structures, tracks, and roads, tree planting, signs
and fences.
To encourage the use of an agreed colour palette in the choice of external materials and colours of structures throughout the district, which colours are based on those which appeal in the natural surroundings of Twizel, Tekapo and Fairlie.
Annexure C
A : SCHEDULE OF POLICIES 3B1 TO 3B16
Policy 3B1 – Recognition of the Mackenzie Basin’s distinctive
characteristics
To recognise that within the Mackenzie Basin’s outstanding natural
landscape there
are:
(a) some areas where different types of development and use (such as
irrigated pastoral farming or carbon forestry under
an Emissions Trading
Scheme) and/or subdivision are appropriate, and to identify these areas;
and
(b) many areas where use and development beyond pastoral activities on
tussock grasslands is either generally inappropriate or should
be
avoided.
– while encouraging a healthy productive economy, environment, and
community within, and maintaining the identity of, the Mackenzie
Country.
Policy 3B2 – Adverse Impacts of Buildings and Earthworks
To avoid adverse impacts on the outstanding natural landscape and features of
the Mackenzie Basin, in particular from residential
buildings, domestication,
structures, earthworks, tracks and roads except in particular areas under
policies below, and to remedy
or mitigate the adverse effects of farm buildings
and fences.
Policy 3B3 – Adverse effects of Sporadic Subdivision and
Development
To control buildings and subdivision in the Mackenzie Basin Subzone (outside
of approved farm base areas and other than for
activities provided for
in [the Renewable Energy] Policy 3B9 and subject to lesser controls on
buildings and subdivision in
areas of lower visual vulnerability) to
ensure adverse effects, including cumulative effects, on the environment of
sporadic
development and subdivision are avoided or mitigated and to sustain
existing and likely future productive use of land.
Policy 3B4 – Limits on subdivision and housing
(1) Subject to (2) below, to enable residential or rural residential subdivision and housing development in the Mackenzie Basin Rural subzone only within identified farm base areas;
(2) To encourage new residential or rural residential subzones in areas of
low or medium vulnerability provided:
(a) objectives 1, 2, 4, 7, 8 and 11 of the Rural chapter are achieved;
and
(b) the new subzones satisfy policy 3B6 below;
(3) To strongly discourage residential units elsewhere in the Mackenzie
Basin.
Policy 3B5 – Development in farm base areas
(1) Subdivision and development of farm base areas which are in areas of high
vulnerability to development shall maintain or enhance
the significant and
outstanding natural landscape and other natural values of the Mackenzie Basin
by:
(a) confining development to areas where it is screened by topography or
vegetation or otherwise visually inconspicuous, particularly
from public
viewpoints and from views of Lakes Tekapo, Pukaki and Benmore provided that
there may be exceptions for development of
existing farm bases at Braemar,
Tasman Downs and for farm bases at the stations along Haldon Road
(b) integrating built form and earthworks so that it nestles within
the landform and vegetation
(c) planting of local native species and/or non-wilding exotic species and
management of wilding tree spread
(d) maintaining a sense of isolation from other development
(e) built development, earthworks and access having a low key
rural character in terms of location, layout and development,
with particular
regard to construction style, materials and detailing
(f) mitigating, the adverse effects of slight spill on the night sky.
(g) avoiding adverse effects on the natural character and
environmental values of waterbodies, groundwater and sites of natural
significance
(h) installing sustainable systems for water supply, sewage treatment and disposal, stormwater services and access;
(2) Subdivision and development in farm base areas which are in areas of low
or medium vulnerability to development shall:
(a) restrict planting to local native species and/or non-wilding
exotic species
(b) manage exotic wilding tree spread
(c) maintain a sense of isolation from other development
(d) mitigate, the adverse effects of light spill on the night sky
(e) avoid adverse effects on the natural character and environmental
values of waterbodies, groundwater and sites of natural
significance
(f) install sustainable systems for water supply, sewage treatment and
disposal, stormwater services and access.
3B6 – Potential residential and visitor accommodation activity subzones
(1) To mitigate the effects of past subdivision on landscape and visual
amenity values and to encourage appropriate rural residential
activities in the
Mackenzie Basin by identifying, where appropriate, alternative specialist zoning
options (such as Rural-Residential)
in areas of low or medium vulnerability to
development where there are demonstrable advantages for the environment;
(2) where such subzones are located wholly or partly in areas of
medium vulnerability then any development within shall
maintain or enhance the
significant and outstanding natural landscape and other natural values of the
Mackenzie Basin by:
(1) confining development to areas where it is visually inconspicuous,
particularly from public viewpoints and from views up Lakes
Tekapo and Pukaki
provided that there may be exceptions for development of existing farm bases at
Braemar, Tasman Downs and for farm
bases at the stations along Haldon Arm
Road
(2) integrating built form and earthworks so that it nestles within the landform and vegetation
(3) planting of local native species and/or non-wilding exotic species and
management of wilding tree spread
(4) maintaining a sense of isolation
(5) built development, earthworks and access having a low key rural
character in terms of location, layout and
development, with
particular regard to construction style, materials and detailing
(6) mitigating, the adverse effects of light spill on the night sky
(7) avoiding adverse effects on the natural character and environmental
values of waterbodies, groundwater and sites of natural significance
(8) installing sustainable systems for water supply, sewage treatment and
disposal, stormwater services and access
Policy 3B7 – Lakeside protection areas
(c) To recognise the special importance of the Mackenzie Basin’s lakes,
their
margins, and their settings in achieving Objective 3B.
(d) Subject to (c), to avoid adverse impacts of buildings, structures and
uses on the landscape values and character of the Mackenzie
Basin lakes and
their margins.
(e) To avoid, remedy or mitigate the adverse impacts of further
buildings and structures required for the Waitaki Power Scheme
on the landscape
values and character of the Basin’s lakes and their margins.
(Note: Policy (c) has different objectives to achieve dependent on whether
Rural
Objective (7)3B or Utilities objective (Section 15)3 is being
implemented.)
Policy 3B8 – Views from State Highways and Tourist Roads
(a) To avoid all buildings other structures, exotic trees and fences in
the scenic grasslands listed in Appendix X and in the
scenic viewing areas shown
on the planning maps;
(b) To Require buildings to be set back from roads particularly state highways, and to manage the sensitive location of structures such as large irrigators to avoid or limit screening of views of the outstanding natural landscape of the Mackenzie Basin.
(c) To avoid clearance, cultivation or oversowing of all
tussock grasslands adjacent to and within the foreground of
views from State
Highways and the tourist roads;
(d) To minimise the adverse effects of irrigation of pasture adjacent to the
state highways or the tourism roads.
Policy 3B9 – Renewable Energy
To recognise and provide for the use and development of renewable energy generation and transmission infrastructure and operations within the footprint of current operations or on land owned by infrastructure operators as at 31 October
2011 while, as far as practicable, avoiding, remedying or mitigating
significant adverse effects on the outstanding natural landscape
and features of
the Mackenzie Basin.
Policy 3B10 – Reverse sensitivity
To avoid, remedy or mitigate adverse reverse sensitivity effects of non-farm
development on rural activities such as power
generation, transmission
infrastructure, state highways and the Tekapo Military Training Area.
Policy 3B11 Hazards
To avoid hazards caused by activities such as power generation; and water
transport by canal and aqueduct on non-farm development
and activities.
Policy 3B12
Traditional pastoral farming is encouraged so as to maintain tussock
grasslands, subject to achievement of the other Rural objectives
and to policy
3B8.
Policy 3B13 Farm Buildings
(1) Farm buildings should be avoided in lakeside areas, scenic viewing areas
and scenic grasslands.
(2) Elsewhere in the Mackenzie Basin subzone farm buildings should be managed in respect of location, density of buildings, design, external appearance and size except in areas of low visual vulnerability where only density and size are relevant.
Policy 3B14 Pastoral intensification
(1) To ensure areas in the Mackenzie Basin which are proposed for pastoral
intensification meet all the other relevant objectives
and policies for the
Mackenzie Basin subzone (including Rural Objectives 1, 2 and 4 and implementing
policies);
(2) To link management of new areas of pastoral
intensification with management of wilding exotic trees and other
weeds;
(3) To avoid pastoral intensification in sites of natural
significance, scenic viewing areas and scenic grasslands.
3B15 Wilding trees
To manage wilding tree spread by:
(a) confining it to areas of low or medium vulnerability as showing on Map [-]; (b) requiring landowners to remove wildings of identified tree species from their
land (outside of areas identified in (a) before they seed.
3B16 Landscape aspects of subdivision
(1) In order to minimise its adverse effects, subdivision in the Mackenzie
Basin
Rural subzone will not be encouraged except:
in farm base areas;
in areas of low visual and/or ecological
vulnerability;
(2) there should be a minimum lot size of 200 hectares (except in farm
bases);
(3) further subdivision of lakeside protection areas (except for existing
farm bases), scenic viewing areas and scenic grasslands
will not be
allowed;
(4) all lots in a subdivision shall be linked by mutually enforceable
convenants and conditions (also enforceable by the Council)
to remove exotic
wildings from each other lot unless the trees are in an approved forest
area;
(5) All subdivision should have regard to topographical and ecological restraints.
Annexure D (proposed objective 3B)
Objective 3B – Activities in Mackenzie Basin’s outstanding
natural landscape
(1) Subject to (2)(a), to protect and enhance the outstanding natural
landscape of the Mackenzie Basin subzone in particular
the following
characteristics and/or values:
(a) the openness and vastness of the landscape; (b) the tussock grasslands;
(c) the lack of houses and other structures;
(d) residential development limited to small areas in clusters;
(e) the form of the mountains, hills and moraines, encircling
and/or located in, the Mackenzie Basin;
(f) undeveloped lakesides and State Highway 8 roadside;
(2) To maintain and develop structures and works for the Waitaki Power Scheme: (a) within the existing footprints of the Tekapo-Pukaki and Ohau Canal
Corridor, the Tekapo, Pukaki and Ohau Rivers, along the existing transmission
lines, and in the Crown-owned land containing Lakes
Tekapo, Pukaki, Ruataniwha
and Ohau and subject only (in respect of landscape values) to the objectives,
policies and methods of
implementation within Chapter 15 (Utilities) except for
management of exotic tree species in respect of which all objective (1) and
all
implementing policies and methods in this section apply;
(b) elsewhere within the Mackenzie Basin subzone so as to achieve
objective (1) above.
(3) Subject to objective (1) above and to rural objectives 1, 2 and
4:
(a) to enable pastoral farming while limiting buildings, fencing and
shelterbelts;
(b) to enable pastoral intensification including cultivation and/or direct
drilling and high intensity (irrigated) farming in
appropriate areas
south and east of State Highway 8 except adjacent to, and in the foreground of
views from, State Highways and
tourist roads;
(c) to enable rural residential subdivision, cluster housing and farm buildings preferably around existing homesteads (where they are outside hazard areas) or in the areas of low visual vulnerability shown on map Z in the district plan;
(d) to enable carbon forests and production forests in:
The Twizel River landscape unit;
The area between Hayman Road east to approximately 650 masl contour on the Mary Range;
Mid and lower Tekapo and Pukaki River flats; Around
identified existing farm bases
– whilst ensuring exotic wildings do not escape from those areas and managing a transfer to non-weed species.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/2616.html