Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 15 December 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2009-404-6868 [2014] NZHC 2794
BETWEEN
|
BODY CORPORATE 172108
Plaintiff
|
AND
|
J M MEADER & ORS
First to Forty Eighth Respondents
|
Hearing:
|
13 October 2014
|
Appearances:
|
T Allan/ T Gavigan for the Plaintiff
M C Smith for the First Respondent
|
Judgment:
|
11 November 2014
|
JUDGMENT OF THOMAS J
This judgment was delivered by me on 11 November 2014 at 4.00 pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date:...............................
Solicitors:
Grove Darlow & Partners, Auckland. Gilbert Walker,
Auckland.
BODY CORPORATE 172108 v MEADER [2014] NZHC 2794 [11 November 2014]
Introduction
[1] The applicant in respect of the interlocutory application for
orders as to discovery is the 37th respondent in the proceedings,
Manchester
Securities Limited (MSL). The respondent to the application is the plaintiff in
the proceeding, Body Corporate 172108.
[2] MSL owns the top floor of a 12 story unit title development in
Hobson Street, Auckland (the Building).
[3] While the Building is a unit title development, the legal structure is somewhat unusual in that the exterior walls of levels 1 – 11 are common property but the entire
12th floor structure including the exterior walls and roof is the separate
property of MSL (save for some items of common property
such as the lift shaft,
stairwells and ducts).
[4] The Building suffers from weathertightness defects, primarily in
levels 1 – 11 but also affecting level 12. The nature
and extent of the
work required to level 12 is somewhat different from the remainder of the
Building, level 12 having been added
at a later date and constructed of
different materials using different methods.
[5] In 2009 the Body Corporate obtained a building consent to reclad the whole Building including all of level 12. The Body Corporate successfully applied to the High Court for the work to be carried out pursuant to a scheme settled under s 48
Unit Titles Act 1972 (the Scheme). There was a dispute between the Body
Corporate and MSL as to the proportion of the costs of the
works to be borne by
MSL.
[6] There were, it seems, a number of High Court decisions. The end result is that the High Court approved the Scheme. The work to level 12 was to be carried out by MSL at its cost. The High Court capped MSL’s liability at 11.88 per cent (its ownership interest share) of the costs of repairs to the Building. If the level 12 works cost less than 11.88 per cent of the total, MSL will make a top up contribution towards the costs of the works to levels 1 – 11.
[7] The Body Corporate work commenced in July 2012. In February 2014
it received code compliance. The work to level 12 started
in September 2012 and
is not yet complete. It is apparent that the cost of the level 12 work is
likely to exceed the 11.88 per cent
cap, meaning MSL will not have to contribute
towards the costs of repairing the rest of the Building.
[8] The main proceedings concern the application by the Body Corporate
for orders changing the costs sharing terms of the Scheme
which would result in
MSL paying a greater share of the overall costs. The application is opposed by
MSL.
The discovery application
[9] MSL disputes the costs of the works to levels 1 – 11 as
alleged by the Body
Corporate. It also disputes that the Body Corporate is entitled to include
within the
2010 costs sharing formula the additional costs of closing in the balconies
to levels 1
– 11 of the Building instead of undertaking the work covered by the
Scheme and for which building consent had been obtained.
[10] On 16 April 2014 the High Court made discovery orders by consent. At
issue is whether the Body Corporate has fully
disclosed the agreed
categories of documents required pursuant to the order as follows:
(a) Documents relating to the decision to close in the balconies,
including copies of engineering reports and correspondence
with engineers and
other consultants involved in making and implementing that decision; minutes of
the Body Corporate; and communications
between members of the Body Corporate
Committee and Secretary relating to that decision.
(b) Contractors’ instructions and variation advice notices, and related
architectural design, engineering and other consultants’ reports.
[11] MSL does not accept that the disclosure of documents relating to the closing in of the balconies and the number of variations to the construction contract is complete. It has refined its request for variations to those enumerated in the
schedule attached to counsel’s submissions. It has reduced by four
the number of items sought in the original application
as a result of
explanations given on behalf of the Body Corporate.
[12] MSL also now seeks discovery of documents relating to the claim
against Auckland Council by the Body Corporate, which settled.
It requests
discovery of the fifth amended statement of claim and the document evidencing
the terms on which the proceeding was
settled.
Disclosure principles
[13] The Body Corporate commenced the proceeding by way of an originating
application under Part 19 of the High Court Rules.
Although discovery is
not ordered as a matter of course in such proceedings, orders can be made where
a case for discovery is made
out. As the High Court has
noted:1
...there is reluctance to order discovery [in a Part 19 proceeding], except
in a narrow band of marginal cases where the court has
genuine difficulty in
determining whether a party has made out its case, and where there is
substantial reason to believe that discovery
would or might well assist that
determination.
[14] MSL claims that there are good reasons why discovery is appropriate
here:
(a) MSL is a member of the Body Corporate whose role is to serve the
interests of all owners;
(b) the Body Corporate has duties under the Scheme to exercise
its powers fairly;
(c) given that the Body Corporate has applied to the Court to vary the costs sharing terms settled more than four years ago, it should be prepared to substantiate its own expenditure by making disclosure;
and
1 Katavich v Meltzer HC Auckland CIV-2006-404-5968, 29 May 2009 at [15].
(d) there is substantial reason to believe that the discovery would or might
well assist in determining the application.
Balcony work
[15] The Scheme related to the works covered by the building consent
which had been obtained at the time the Scheme was approved.
That showed the
balconies being repaired on a like for like basis. Some time after that the
Body Corporate decided to close in
the balconies. MSL says the additional costs
of closing in the balconies should not be taken into account in determining the
costs
of the works to levels 1 – 11 because the costs are betterment
rather than remediation.
[16] While the Body Corporate has disclosed the engineering calculations
and specifications it has not disclosed the advice on
which the Body Corporate
based its decision to approve the variation despite consenting to the discovery
orders set out under paragraph
10. The decision resulted in a variation costing
approximately $1.1 million. It required resource consent and amended building
consent. MSL says that in those circumstances it cannot be disputed that the
variation was a material one and there must have been
advice from the
professionals to the Body Corporate setting out the advantages and disadvantages
of proceeding with the variation.
[17] MSL refers to a newsletter from the Body Corporate’s manager,
Ms Barreto,
dated 7 November 2012 which states:
Structural Steel supporting some balconies was discovered to be allow [sic]
too much flex or “bounce” on the balcony.
This only is an issue
only [sic] if (as we are) glazing in with new ranch sliders – this up and
down movement would crush
or otherwise break the ranchslider frames and
certainly make them non-weathertight and compliant. A new structural steel
system has
had to be designed for these balconies to ensure that this movement
does not happen, and as such has created some delay for these
units progress
[sic].
[18] Attached to the newsletter was the progress report supplied to the
Body Corporate consultants by the building contractor.
The building contractor,
Bronsan Construction Limited, described the work to the balconies as
follows:
The cantilevered balconies to the type A and B apartments have been found to have an excessive amount of deflection within them (Bounce). This creates significant complications when trying to clad the building as
typically cladding should be installed on the basis of little to no movement
within the building. To alleviate this issue structural
steel is having to be
erected to the underside of each balcony so that this movement is mitigated and
the cladding can then be completed.
Although this only effects the B and D
apartments it does mean unfortunately that the scaffold and shrinkwrap
does need
to remain up longer than intended across all of the north and south
elevations.
[19] MSL points to the discrepancy between the advice the Body Corporate
gave to the owners and Brosnan’s explanation.
The Body Corporate says by
an affidavit from the project manager and engineer that Ms Borretto was mistaken
in her understanding
and that the work to strengthen the balconies was required
in any event, the thickness of the balconies not being to code and there
being a
concern about the transfer effect on the performance of the whole cladding by
what was believed to be excessive deflection
in the cantilevered
balconies.
[20] The project manager in his affidavit sets out three reasons why the
decision to close the balconies was made.
[21] MSL’s position remains that it seeks disclosure of the reports
connected with the decision to close in the balconies
so it can ascertain the
scope and costs of the alterations in relation to the work approved under the
Scheme.
[22] The Body Corporate agreed to disclose documents relating to the
decision and that was ordered by the Court. I am at a loss
as to why the Body
Corporate now appears to be recanting from its agreement, asserting that certain
work was required regardless.
Not only was disclosure ordered but MSL
is entitled to have the necessary information to determine the ramifications
of the changes to the Scheme. It appears that the specification for the
work has been disclosed but not the documents
relating to the decision.
The wording in the affidavits from the Body Corporate manager, the engineer, Mr
Holding, and the project
manager is the same, stating that:
There are no other “reports” or “letters” or
“emails” containing a formal editorialised report of advice.
(emphasis added)
[23] Quite what is meant by those words I am not sure. The Body Corporate is required to make disclosure in accordance with the order to which it consented.
Variation items
[24] The same consideration applies to this head of the disclosure. The
affidavits on behalf of the Body Corporate purport
to give the
experts’ opinion on the substantive issue, that is, whether the costs
incurred would have been required in
any event. That is the matter for trial
and MSL is entitled to have the information sought so its own experts can
investigate.
I appreciate that the Body Corporate has offered a meeting between
its experts and those of MSL. There is some disagreement between
the parties as
to how genuine the offer was and in any event, MSL’s position is that it
would like its experts to view the
documents prior to any such
meeting.
[25] Mr Cummins, director of MSL, points to two examples where, on the
face of it, the assertions made by the Body Corporate’s
experts that the
costs were required in any event are not supported by documented evidence. For
example, in connection with the
deck sprinklers, the fire engineer’s
advice of 25 March 2013 indicates sprinklers were required because the decks
were being
closed in. Another example is the change from single to double
glazing which had a cost implication which must be relevant to MSL’s
liability.
[26] In those circumstances I am not satisfied that MSL should be
prepared to rely on the assertions by the Body Corporate experts
as to whether
matters are or are not relevant. The Body Corporate had agreed to provide
details of the variations and disclosure
should be made.
[27] The Body Corporate has raised the issue of disproportionality, that is, whether the costs of disclosure are out of all proportion to the claim. It points out that significant costs have been incurred by the Body Corporate to date by reason of it and its experts having to work through thousands of documents to isolate those sought. They have also spent time considering which documents are relevant. I accept the submission from MSL that, had disclosure been made as agreed rather than the experts purporting to determine what was and was not relevant, quite some cost could been avoided. In any event, the assessment is that some $5,000 will be required in order to complete the Body Corporate’s disclosure obligations. I am not
satisfied that is disproportionate in the context of the overall cost of the
Scheme, notwithstanding that MSL is obliged to contribute
a portion only of that
cost.
[28] In making these decisions it is relevant to note the obligations of
the parties pursuant to the Scheme. The Scheme deals
with the repair of the
Building. By definition “repair” does not cover the works required
to close in the balconies
as it is work not included in the original building
consent. It may lead to a better result for a number of reasons but it was not
the work the Scheme was designed to cover. The work has a cost implication.
The costs in respect of which MSL has a liability are
the costs relevant to the
repair. MSL is entitled to the information it seeks in order to assess the
impact on its liability of
the work to close in the balconies and indeed any
other variations to the works included in the Scheme.
[29] Relevant too is the fact that, in undertaking the works pursuant to the Scheme, the Body Corporate’s decision is final except if five or more owners’ objections in monetary value exceed $30,000 or one unit owner’s objection exceeds
$10,000. In that case the dispute goes to arbitration. That is an
indication of the level of materiality in contemplation at the
time the Scheme
was approved. It is also relevant to note the provisions concerning the works
to be undertaken by MSL whereby MSL
is under an obligation to be transparent
from the outset and to give information to and consult with the Body Corporate
in respect
of its decisions and prices.
Settlement agreement
[30] What was not covered by the discovery order is the second category
of documents sought by MSL. This relates to the basis
on which a claim against
the Auckland Council filed by the Body Corporate was advanced and settled. MSL
had received a copy of the
fourth amended statement of claim. It seeks the
fifth amended statement of claim and the document evidencing the terms on which
the proceeding was settled.
[31] This is opposed by the Body Corporate on the basis that the documents were not covered by the order for tailored discovery; they are not relevant to the proceeding, being one commenced by an originating application; and the application
is in fact an attempt to obtain discovery of the settlement document without
complying with proper procedure. In any event,
the Body Corporate
asserts privilege or confidentiality over the documents.
[32] The Body Corporate’s claim against the Auckland Council was in
negligence seeking damages for the costs of repairing
the common property.
While most of the unit owners joined the proceeding to sue for the costs of
repairing their unit property,
MSL did not. Indeed, MSL purchased level 12
being on notice of the weathertightness issues as is confirmed in correspondence
from
Mr Cummins to the Council supplied as part of this proceeding.
[33] It appears that the fourth amended statement of claim did not
exclude MSL’s share of the common property from the Body
Corporate’s
claim, although MSL says it sought and received assurances that its share of the
common property would not be included
in the Body Corporate’s claim. MSL
then says that it is probably safe to assume that the settlement agreement under
which
a substantial payment was made by the Council encompasses MSL’s
share of the common property. The settlement proceeds have
been distributed
amongst the owners who joined the litigation personally and no part of the
proceeds have been accounted for to MSL.
[34] MSL says that the settlement of the Body Corporate’s claim is
relevant to the issue before the Court in the application
to vary the Scheme.
It says that, regardless of whether MSL is entitled to a share of the settlement
proceeds, it is relevant to
the Court’s assessment of the Body
Corporate’s application.
[35] Any claim which MSL might have against the Auckland Council would appear to be out of time and indeed, as noted, MSL purchased with knowledge of weathertightness issues. I accept the Body Corporate’s submission that any claim MSL might have against the Body Corporate for a share of the proceeds of any settlement of the Body Corporate’s claim against the Council would need to be brought by way of an ordinary proceeding rather than somehow being part of the Body Corporate’s application made by way of an originating application. There is no real connection between the application before the Court and any claim MSL might have in respect of the settlement.
[36] I agree with the Body Corporate that MSL is effectively trying to
conflate two issues, that is the amount MSL should properly
pay towards the
repairs of the Building and how MSL would pay its share. Any part of the
settlement to which MSL might be entitled
is relevant to the second of those
questions. MSL elected not to be part of the claim against the Auckland
Council.
[37] Although, cases such as LV Trust Holdings Ltd v Body Corporate
considered whether a scheme under s 74 of the Unit Titles Act 2010 could
provide for payment of compensation, this is not the issue
in this
case.2
[38] I accept that determination of what sum MSL ought to be
required to contribute to common property repairs is
separate from whether MSL
might have a claim to the settlement proceeds in the proceedings between the
Body Corporate and the Auckland
Council.
Result
[39] For the reasons given the Body Corporate is to make full disclosure
in respect of items A and B of the application but is
not required to make
disclosure of items C and D.
[40] In the circumstances, the parties may decide costs should lie. If there is not agreement, costs will be dealt with by me on the papers upon the filing of memoranda, required from MSL within 21 days and from the Body Corporate within
28 days of this
decision.
Thomas J
2 LV Trust Holdings Ltd v Body Corporate 114424 [2012] NZHC 3578, (2012) 14 NZCPR 344.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/2794.html