Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 15 April 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-3593 [2014] NZHC 304
BETWEEN
|
WAIORA TRADING LIMITED
Plaintiff
|
AND
|
GREGORY LAURENCE O'SULLIVAN First Defendant
IGOR ALEXANDROVICH M IKITASOV Second Defendant
|
Hearing:
|
26 February 2014
|
Appearances:
|
R C Mark for plaintiff
No appearance for first defendant (abides decision of Court) No appearance
for second defendant
|
Judgment:
|
27 February 2014
|
JUDGMENT OF LANG J
[on application for judicial review]
This judgment was delivered by me on 27 February 2014 at 10.30 am,
pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date...............
WAIORA TRADING LIMITED v O'SULLIVAN & MIKITASOV [2014] NZHC 304 [27 February 2014]
[1] Mr Mikitasov owns a house property in Paihia. In June 2009, he
arranged for Mr John Nicholas to carry out urgent repairs
to his property. Mr
Mikitasov was not satisfied with the standard of workmanship of the repairs, and
he also considered that he
had been significantly overcharged in relation
to them. This has led to a protracted dispute between Mr Mikitasov
and
Mr Nicholas that remains on foot nearly five years later.
[2] In May 2010, Mr Mikitasov issued proceedings in the District Court.
He named both Mr Nicholas and the plaintiff, Waiora
Trading Limited
(“Waiora”), as defendants. Mr Nicholas and his wife are
the directors of Waiora. Those
proceedings became protracted, and on 30
May 2013 Mr Mikitasov changed tack. Rather than proceed to trial in the District
Court,
he issued an adjudication claim against both Waiora and Mr Nicholas
under the provisions of the Construction Contracts
Act 2002 (“the
Act”). The first defendant, Mr O’Sullivan, was appointed to
adjudicate the claim.
[3] Mr Nicholas and Waiora both defended the claim. Waiora contended
that it has nothing to do with Mr Nicholas’ building
activities, and that
it was therefore never a party to the construction contract between Mr Mikitasov
and Mr Nicholas.
[4] Mr O’Sullivan released his determination on 21 June 2013. He
held that Mr Mikitasov was entitled to be paid the sum
of $30,362 inclusive of
GST. He said that that sum was to be payable “by the respondent”.
The adjudicator did not address,
however, Waiora’s defence based on the
assertion that it was not a party to the construction contract.
[5] Waiora now seeks judicial review of the adjudicator’s
determination. It contends that the adjudicator erred
in law in several
respects when he failed to deal with its defence to the claim by Mr Mikitasov.
Waiora asks the Court to set the
adjudicator’s determination aside to the
extent that it purports to render Waiora liable to Mr Mikitasov.
[6] The adjudicator abides by the decision of the Court. Mr Mikitasov took no steps to defend the application for judicial review, and the proceeding was
accordingly set down for hearing on a formal proof basis. Two days before
the hearing, Mr Mikitasov filed an affidavit in opposition
to the application,
but he did not appear when the application was called on 26 February
2014.
Scope of judicial review in this context
[7] There has been some debate regarding the extent to which judicial
review is available to challenge a determination made
by an adjudicator under
the Act. The issue was effectively settled, however, by the decision of the
Court of Appeal in Rees v Firth.1 In that case, the Court of
Appeal held that judicial review is not restricted to situations where the
applicant alleges that the adjudicator
has acted outside his or her
jurisdiction. The Court of Appeal emphasised, however, that Judges should be
careful not to allow judicial
review proceedings to cut across the scheme of the
Act and thereby undermine its objectives. In this context the Court
said:2
[27] The courts must be vigilant to ensure that judicial review of
adjudicators’ determinations does not cut across the scheme
of the CCA and
undermine its objectives. But this does not mean that judicial review should be
limited to instances of “jurisdictional
error”. In principle, any
ground of judicial review may be raised, but an applicant must demonstrate that
the court should
intervene in the particular circumstances, and that will not be
easy given the purpose and scheme of the CCA. Indeed, we consider
that it will
be very difficult to satisfy a court that intervention is necessary. As an
example, given that an important purpose
of the CCA is to provide a
mechanism to enable money flows to be maintained on the basis of preliminary and
non-binding assessments
of the merits, it is unlikely that errors of fact by
adjudicators will give rise to successful applications for judicial review.
In
the great majority of cases where an adjudicator‘s determination is to be
challenged, the appropriate course will be for
the parties to submit the merits
of the dispute to binding resolution through arbitration or litigation (or, of
course, to go to
mediation).
Decision
[8] The adjudicator reached his decision in the present case based on the documents filed by the parties. These squarely raised the issue that lies at the heart of the present application. Mr Mikitasov’s claim contained the following
paragraphs:
1 Rees v Firth [2011] NZCA 668.
2 Ibid.
4. In early March 2009, Mr Mikitasov and his family intended to live in
another part of New Zealand for a few months. During
the time that Mr Mikitasov
was to be out of the property, he appointed a property manager Mr SG
Seed.
...
6. On 14 June 2009, the Mr Seed informed Mr Mikitasov that he had
engaged Mr Nicholas trading as J Nicholas Builders to carry
out the
investigations and provide the quote.
7. On 19 June 2009, after the investigation was completed, Mr Mikitasov received an estimate of costs from Mr Nicholas for repairs of around
$30,000 (including materials). The estimate was in respect of the remedial works specified in the Report and included the cost for the
additional repairs, investigated by Mr Nicholas.
...
9. On 25 June Mr Mikitasov entered into a contract (the Contract) with
Mr Nicholas. A cash advance payment of $5,000 was paid
to Mr Nicholas through
Mr Seed. The Contract indicated that Mr Nicholas was the builder who would do
the required remedial work
and any other work Mr Mikitasov requested of
him as directed by Mr Mikitasov (the Work).
...
14. Until this point, interim payments for the Work had been
made through Mr Seed. Mr Seed now said that all future
payments for the Work
should be paid directly to Mr Nicholas’ company and provided an encoded
bank deposit slip for Waiora
trading.
15. At this point Mr Nicholas told Mr Mikitasov that the work undertaken
by him was undertaken on behalf of Waiora Trading Limited
– his company
and that his wife would deal with the accounting aspects.
[9] The response filed on behalf of Mr Nicholas and Waiora
contained the following passage:
4. In the claimant’s description of the dispute at the commencement of the adjudication claim, it is alleged that during the term of the contract Mr Nicholas variously represented himself as acting in his own right and trading as J Nicholas Builders, or as a director and shareholder of Waiora Trading Limited. Mr Nicholas has never represented himself to Mr Mikitasov as acting in the capacity as director and shareholder of Waiora Trading Limited. Waiora Trading Limited is an entirely separate business, providing tourist accommodation in Paihia and is operated by Mr Nicholas’ wife. Mr Nicholas simply requested that Mr Mikitasov pay Mr Nicholas by depositing funds in the Waiora bank account. The reason for this was that Mrs Nicholas could then administer the payments and pay Mr Seed and suppliers for material.
Mr Nicholas also provided the adjudicator with copies of invoices he had
rendered in respect of the repairs. These were rendered by
“J L Nicholas
Builder”.
[10] Section 45(c) and (d) of the Act require an adjudicator to consider
both the adjudication claim and any response filed in
relation to it. As noted
above, however, the adjudicator’s determination made no reference at all
to the issue of whether Mr
Nicholas had entered into the construction contract
on behalf of Waiora. An affirmative answer to that question was obviously
required
if the adjudicator was to impose liability on Waiora under the
contract. If Waiora was not a party to the contract, it could not
be liable to
Mr Mikitasov under it.
[11] The adjudicator’s failure to address this issue was obviously
an error, and it could be described in a number of ways.
First, it went to the
question of jurisdiction. The adjudicator had no jurisdiction to find Waiora
liable under the construction
contract unless he first found that it was a party
to that contract. It could also be argued that the adjudicator failed to
take into account a relevant consideration, namely the facts raised by
Waiora in support of its defence.
[12] One possible interpretation of the determination is that the
adjudicator held that Waiora was a party to the contract.
If that is the case,
however, he gave no reasons for reaching that decision. Failure to give
reasons in relation to a critical
contested issue of fact may also render the
decision amenable to review.3 The fact that the adjudicator
referred throughout his decision to Mr Nicholas and Waiora as “the
respondent” suggests,
however, that he never turned his mind to this
critical issue. He appears to have proceeded on the basis that Waiora and Mr
Nicholas
were one and the same legal entity, when that was patently not the
case.
[13] Regardless of how the adjudicator’s error is described, it is potentially amenable to review by the Court. The only remaining issue to be determined is whether relief should be granted. This requires the Court to consider whether the granting of relief in the present context would undermine the objects and purposes of
the Act.
[14] Two factors are relevant in this context. The first is that this particular construction contract is now at an end. The cash flow considerations referred to in the passage cited above from Rees v Firth therefore do not arise.4 The second arises out of the fact that a conclusion reached in an adjudication under the Act can properly be regarded as provisional, in the sense that both parties are free to challenge it through subsequent litigation or arbitration. As the Court of Appeal recognised in Rees v Firth in the same passage, the scheme of the Act anticipates that these will usually be the most appropriate means by which to challenge the
preliminary and non-binding conclusions reached by an
adjudicator.
[15] There is, of course, nothing to prevent Waiora from issuing
a fresh proceeding in the District Court or High Court
seeking a declaration
that it was not a party to the construction contract with Mr Mikitasov. I do
not consider, however, that
it would cut across or undermine the objects and
purposes of the Act if the Court was to make an order in the present
proceeding
requiring the adjudicator to determine that issue. This is
particularly so given the fact that the adjudicator ought to have
considered and
determined it as part of his original adjudication.
[16] I have therefore concluded that the issue of Waiora’s
liability should be remitted to the adjudicator for determination.
Counsel for
Waiora agrees that this is appropriate. It would be wrong for the Court to go
further and endeavour to decide a contested
factual issue of this nature on the
basis of the material on the Court file. That should properly be the task of the
adjudicator,
who has the ability to test and weigh the arguments for both
parties. In particular, the adjudicator will need to reach a view one
way or
another as to whether Mr Nicholas told Mr Mikitasov that he was undertaking the
work on Waiora’s behalf. That issue
cannot realistically be determined
in the context of the present proceeding.
Result
[17] The application is granted. The adjudicator’s determination is set aside to the extent that it purports to render Waiora liable to Mr Mikitasov. The issue of whether
Waiora is liable to Mr Mikitasov is remitted to the adjudicator for
determination.
4 Rees v Firth, above n 1.
Costs
[18] Counsel for Waioroa does not seek an award of costs in his
client’s favour. Costs will accordingly lie where they
fall.
Lang J
Solicitors:
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/304.html