![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 17 December 2014
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2014-404-001388 [2014] NZHC 3090
IN THE MATTER OF
|
a statutory demand issued under s 289 of
the Companies Act 1993
|
BETWEEN
|
LEIGHTON CONTRACTORS PTY LIMITED
Applicant
|
AND
|
SHARP CONCRETE CUTTERS & DRILLERS LIMITED
Respondent
|
Hearing:
|
29 September 2014
|
Appearances:
|
A E Murray for Applicant
E St John for Respondent
|
Judgment:
|
5 December 2014
|
JUDGMENT OF ASSOCIATE JUDGE OSBORNE
as to statutory demand
This judgment was delivered by me at 9.00 am on 5 December 2014 pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar
LEIGHTON CONTRACTORS PTY LIMITED v SHARP CONCRETE CUTTERS & DRILLERS
LIMITED [2014] NZHC 3090 [5 December 2014]
Introduction – Sharp’s demand on payment
claims
[1] The applicant (Leighton) applies for an order setting aside a
statutory demand issued by the respondent (Sharp).
[2] The demand arises out of a construction contract dated 11 September
2012 which is subject to the Construction Contracts
Act 2002 (the Act). The
estimated completion date was April 2013; the work was in fact completed in July
2013.
[3] Sharp’s demand is stated to represent the balance of payment claims issued under the Act in response to which, it alleges, Leighton failed to provide payment schedules in accordance with the Act. Leighton accepts that each invoice issued by Sharp constituted in terms of s 20 of the Act a valid payment claim. The parties agree as to the dates on which the payment claims were made. With the exception of two claims of 1 July 2013, the timing of the claims and responses are such that the statutory demand either entirely stands or entirely falls, depending upon which
party’s argument succeeds.1 (The invoices are
listed in Table 1 at [16] below
together with other details relating to them).
[4] It is common ground that, regardless of the Court’s determination on the parties’ arguments, the statutory demand requires adjustment (in relation to the 1 July
2013 claims). It is also common ground that the cash payment schedules
issued on the dates referred to in Table 1 at [16] below constituted
valid
payment schedules under s 21 of the Act.
The issue
[5] The issues in this proceeding are as to the effective date of each payment claim. Leighton asserts that the claims became effective on the 25th day of the
month. Sharp asserts that the effective date was 20 working days from
service.
1 See below at [16]–[17].
[6] Counsel agree that to resolve that issue, the Court must answer two
questions:
(a) did the contract provide a payment claim/payment schedule regime in
place of the default regime under the Act?
(b) to the extent that the contract purports to include such a regime,
were the terms of the contract invalid as being in conflict
with mandatory
provisions of the Act?
[7] Two other grounds of opposition were not pursued by Ms
Murray for Leighton. First, Leighton abandoned an argument
that the statutory
demand had not adequately identified the debt. Secondly, Ms Murray did not rely
on a ground which had asserted
that a statutory demand should not be used to
recover a debt. Had that ground been pursued, I would have rejected it.
Although
older authorities can be found to support such a broad proposition, it
is no longer good law in relation to debts which are indisputably
owed.
Payment claims and payment schedules – the statutory
regime
[8] Section 20 of the Act provides for payment claims and s 21 provides
for payment schedules.
[9] Section 22 makes the payer liable to pay the claimed amount in the
following circumstances:
22 Liability for paying claimed amount
A payer becomes liable to pay the claimed amount on the due date for the
progress payment to which the payment claim relates if—
(a) a payee serves a payment claim on a payer; and
(b) the payer does not provide a payment schedule to the payee
within—
(i) the time required by the relevant construction contract; or
(ii) if the contract does not provide for the matter, 20 working days after the payment claim is served.
[10] Section 23(2) of the Act provides that when the payer becomes liable
under s 22 of the Act, the payee may recover in any
Court as a debt due the
unpaid portion of the claimed amount and the actual and reasonable costs of
recovery awarded by the Court.
[11] The Court of Appeal has very recently, in Watts & Hughes
Construction Ltd v Complete Siteworks Co Ltd referred to “the
Draconian consequences ... of not serving a Payment Schedule [in
time]”.2 In doing so, the Court adopted passages from two
earlier cases which had identified the “pay first/argue later”
philosophy
of the Act and emphasised the “absolute and irreversible
consequences” which result from not providing a compliant payment
schedule.3
The contract
[12] The form of contract adopted by Leighton is entitled “Minor
Works and/or Services Contract” and appears to
be a standard form
of contract adopted by Leighton for what it calls minor works and
services.4 The contract expressly refers to a number of Acts of
Parliament but does not refer to the Construction Contracts Act.
[13] Leighton relies on cl 12 of the contract for the proposition that
the contract provides its own procedure in relation to
invoices and payments
which ousts the default provisions of the Act. Clause 12 provides:
12 Progress Claims and Payments
12.1 ...
12.2 Progress claims shall be submitted in a form acceptable to Leighton
on or before the time for submission of claims for payment
stated in the
Annexure or, if no time is stated, on the last business day of each month
(relevant time). If the Contractor submits
a progress claim earlier than the
relevant time, the Contractor agrees that the progress claim shall not be taken
to have been submitted
until the relevant time and that the early submission of
the progress claim shall not require Leighton to make a determination or
payment
in respect of
2 Watts & Hughes Construction Ltd v Complete Siteworks Co Ltd [2014] NZCA 564 at [33].
3 Salem Ltd v Top End Homes Ltd CA 169/05, 12 December 2005 at [22] and Marsden Villas Ltd v
Wooding Construction Ltd [2006] NZHC 569; [2007] 1 NZLR 807 (HC) at [111].
4 It is described by Leighton as “Document No. D-PR-4102 Rev 14”.
the progress claim any earlier than would have been the case if the
Contractor had submitted the progress claim at the relevant time.
12.3 Progress payments shall be made within the period for payment
stated in the Annexure for Leighton’s determination
of the value of the
matters referred to in clause 12.1 less the amount paid in previous
progress payments.
Leighton may, at its discretion, provide a statement to the Contractor of its
determination of the amount payable in respect of a
progress claim submitted by
the Contractor at any time prior to the time for payment of the claim. The
statement may take any form.
12.4 At Leighton’s discretion, payment shall be made by electronic
funds transfer or by cheque. The date of the payment
shall be regarded as the
date on which the funds are cleared by Leighton for payment, the funds being
available to the Contractor
within 2 business days thereafter.
12.5 The Contractor shall not submit a claim for payment to Leighton
unless:
(a) Its employees and subcontractors have been paid all amounts due
and payable to them;
(b) It has paid all workers compensation insurance premiums due and
payable by the Contractor in connection with the Works
and/or Services;
(c) It has paid all payroll tax due and payable in respect of wages
paid or payable to employees engaged in connection with
the Works and/or
Services; and
(d) It has complied with all statutory obligations in connection with
the Works and/or Services.
12.6 Leighton may, at any time and as a condition precedent to payment,
require the Contractor to provide it with evidence to
Leighton’s
satisfaction of the Contractor’s compliance with clause 12.5.
[14] The “Annexure” referred to in cl 12 provides:
Payment Terms
(clause 12)
(a) Time for submission of claims for payment:
(Cross the applicable box and complete (i) if applicable) (i) 25th day of month
(ii) alternative Fridays
(b) Period for Payment: 30 days
[If (a)(i) applies the period for payment shall be the Friday following the
number of days stated in (b) from the last day of the
month in which claims are
submitted.
If (a)(ii) applies the period for payment shall be the Friday following the
number of days stated in (b) from the time for submission
of claims (in this
case, the period for payment to be stated in (b) should be 14 days).
Claims not submitted in time shall default to the next claim
period.]
Sharp’s invoices and Leighton’s payment
schedules
[15] The invoices which are the subject of Sharp’s statutory demand
cover the
period 1 April 2013 to 16 July 2013. [16] Table 1 which follows sets out:
(a) the date of invoice;
(b) the effective date of invoice if the 20th working day from
service
(Sharp’s case) is adopted;
(c) the effective date of invoice if the 25th day of the month
(Leighton’s
case) is adopted;
(d) the due date for a payment schedule if Sharp’s case is
accepted;
(e) the due date for a payment schedule if Leighton’s case is
accepted;
and
(f) the date on which Leighton issued a payment
schedule.
Table 1
|
Date of Invoice
|
Effective date if 20th
working days from service
|
Effective date if 25th
working day of month
|
Date Sharp alleges PS
due
|
Date
Leighton alleges PS due
|
Payment
Schedule issued
|
April
Invoices
|
01/04/2013
01/04/2013
02/04/2013
14/04/2013
16/04/2013
|
30/04/2013
30/04/2013
01/05/2013
13/05/2013
15/05/2013
|
25/04/2013
25/04/2013
25/04/2014
25/04/2013
25/04/2013
|
20/05/2013
20/05/2013
20/05/2013
20/05/2013
20/05/2013
|
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
|
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
|
June Invoices
|
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
31/05/2013
01/06/2013
05/06/2013
07/06/2013
11/06/2013
|
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
01/07/2013
03/07/2013
05/07/2013
09/07/2013
|
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
25/06/2013
|
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/06/2013
20/07/2013
20/07/2013
20/07/2013
20/07/2013
|
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
02/08/2013
|
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
24/07/2013
|
July
|
01/07/2013
01/07/2013
16/07/2013
|
29/07/2013
29/07/2013
13/08/2013
|
25/07/2013
25/07/2013
25/07/2013
|
20/08/2013
20/08/2013
20/08/2013
|
30/08/2013
30/08/2013
30/08/2013
|
24/07/2013
24/07/2013
26/08/2013
|
[17] The entries in Table 1 in relation to the two invoices of 1 July
2013 indicate that Leighton has no ground to contest the
fact that those
invoices represent debts due and owing – Leighton’s payment
schedules in relation to them in time whichever
party’s case as to the
effective date of claim is accepted.
Leighton’s position
[18] For Leighton, Ms Murray submitted generally that there is a substantial dispute as to whether the sums invoiced by Sharp became, by operation of the Act, debts due and owing.
[19] For that general proposition, Ms Murray submitted that the contract
provided a payment claim/payment schedule regime, which
excluded the default
regime under the Act.
Sharp’s position
[20] For Sharp, Mr St John submitted that Leighton cannot dispute the
fact that the sums invoiced by Sharp are due and owing because:
(a) the contract did not provide a payment claim/payment
schedule regime, with the result that the default regime under
the Act applied;
and
(b) to any extent (which is denied) that the contract purported to
include a regime, that regime was invalid as being in conflict
with mandatory
provisions of the Act.
The test to be applied in relation to setting aside a statutory
demand
[21] Leighton does not have to satisfy the Court of the
correctness of its arguments. The applicable test under
s 290(4)(a)
Companies Act 1993 is that the Court must be satisfied that there is a
substantial dispute whether or not the debt is
owing or is due. In the way the
test is frequently put, Leighton as applicant must show that there is arguably a
genuine substantial
dispute as to the existence of the debt.
Issue 1 – did the contract provide a Payment Claim/Payment Schedule
regime in place of the default regime under the Act?
[22] Clause 12 of the contract5 is headed “Progress Claims and Payments”. With repeated reference to “progress claims” it provides a mechanism by which any progress claims must be submitted. Through cl 12 incorporating the Annexure to the
contract,6 the time for submission of any progress
claim under cl 12 is the 25th day
5 Above at [13].
6 Set out above at [14].
of the month. (That period is to be contrasted with “20 working days
after the payment claim is served” under the default
regime provided in s
22(b)(ii) of the Act).
[23] For Leighton, Ms Murray relies upon the following provisions of the
Act:
14 Parties free to agree on progress payment provisions in
construction contract
The parties to a construction contract are free to agree between themselves
on a mechanism for determining—
(a) the number of progress payments under the contract: (b) the interval between those payments:
(c) the amount of each of those payments:
(d) the date when each of those payments becomes due.
20 Payment claims
(1) A payee may serve a payment claim on the payer for each progress
payment,—
(a) if the contract provides for the matter, at the end of the
relevant period that is specified in, or is determined in accordance
with the
terms of, the contract; or
(b) if the contract does not provide for the matter, at the end of the
relevant period referred to in section 17(2).
21 Payment schedules
(1) A payer may respond to a payment claim by providing a payment schedule to
the payee.
(2) A payment schedule must—
(a) be in writing; and
(b) identify the payment claim to which it relates; and
(c) indicate a scheduled amount.
(3) If the scheduled amount is less than the claimed amount, the
payment schedule must indicate—
(a) the manner in which the payer calculated the scheduled
amount; and
(b) the payer's reason or reasons for the difference between the scheduled amount and the claimed amount; and
(c) in a case where the difference is because the payer is withholding
payment on any basis, the payer's reason or reasons for
withholding
payment.
22 Liability for paying claimed amount
A payer becomes liable to pay the claimed amount on the due date for the
progress payment to which the payment claim relates if—
(a) a payee serves a payment claim on a payer; and
(b) the payer does not provide a payment schedule to the payee within—
(i) the time required by the relevant construction contract; or
(ii) if the contract does not provide for the matter, 20 working
days after the payment claim is served.
[24] Ms Murray submits that at least arguably the parties exercised their
freedom to determine details in relation to progress
payments (under s 14 of the
Act). In particular, she says that the combination of cl 12.3 and the Payment
Terms in the Annexure
represent a contractual provision for the date when each
payment would become due.
[25] Ms Murray submits that Sharp was permitted, in terms of s 20, to
serve a payment claim for each progress payment at the end
of the period
specified in the contract. By the combined effect of cl 12.2 and the Payment
Terms under the annexure, that meant
the 25th day of the month. Clause 12.2 of
the contract, by its terms, means that any progress claim (for a progress
payment) submitted
earlier than the 25th day of the month is taken to have been
submitted on that day.
[26] Ms Murray submits that it is arguable that the default regime for
progress claims under the Act was replaced in this case
by the contractual
provisions.
[27] Mr St John, for Sharp, submits that the 20 working day (default) requirement of payment under s 22 of the Act applies in this case because there are no relevant contractual provisions to replace it. Mr St John submits that the contract refers only to progress claims and not to payment claims. He notes the express reference to payments but not to payment schedules. He submits that the contract does not restrict the date by which payment claims can be made and the date on which they become effective.
Discussion
[28] The contract expressly makes provision in cl 12.3 for progress
payments, requiring that they be made within the period for
payment stated in
the Annexure (“30 days”). The annexure also provides that the
claims for payment are to be submitted
on the “25th day of month”.
That is a mechanism for determining (in terms of s 14(b) of the Act) the
interval between
payments.
[29] When it comes to service of a payment claim, (which s 20(1) of the
Act expressly provides a payee may serve for each
progress payment)
Leighton’s reliance is upon cl 12.2 which speaks in terms of
“progress claims”.
[30] The effect of Mr St John’s submission is to suggest that the
Court should conclude that when the parties provided for
progress claims in
relation to progress payment entitlements, the parties were not speaking of the
same concept as that of “payment
claims” under s 20 of the
Act.
[31] I find it at least arguable that what the parties set out in the contract was a regime whereby payment claims were submitted for each progress payment. Although in cl 12.2 the parties referred to “progress claims” rather than “payment claims”, they equally referred (in cl 12.5) to “a claim for payment”. An indication that those involved in the industry are likely to have contemplated that progress claims would fall within the concept of “payment claims” under the Act can be found in the text by Geoff Bayley and Tómas Kennedy-Grant, A guide to the Construction Contracts Act at where the authors note that the term “payment claim” is defined in s 5 of the Act simply as “the claim referred to in s 20”. They go on to
observe in relation to progress claims:7
Within the construction industry interim claims for payment have generally
been described as “progress claims” while the
last claim has been
described as the “final claim”. The description “payment
claim” introduced by the Act
will cover both types of claim.
[32] I do not find that it is clear beyond argument that the particular
wording used
in the contract in relation to payments on progress claims
(whether “progress
payments” or “a claim for payment”) was
intended to be something other than the
“payment claim” provided for in s 20 of the Act.
[33] Mr St John also submitted that there is a legal difficulty in
treating the progress claims as payment claims under the Act.
Mr St John
submits that the effect of cl 12.2 of the contract is to deem a claim to have
been served on a date after the date
on which it was in fact served. Mr St John
submitted that to allow the parties to “deem” alternative dates
would undermine
the purpose of the Act as if deeming provisions were valid there
would be no reason why a clause could not equally deem a payment
claim to have
not been made, say until the end of the contract.
[34] I do not find that argument compelling. The key issue is whether the contractual arrangement for progress payments represents a mechanism for determining the matters which s 14 of the Act gives the parties freedom to determine. It is arguable in this case that what cl 12.2 provides is an interval between payments, being the calendar month interval which follows from the stipulation of the 25th day of each month as the date for submission of claims. In turn, the parties have agreed that claims submitted at that interval are then due for payment 30 days after the 25th day of the month. The interval between claims and payments and the due date of payments under cl 12.2 of the contract fits comfortably with the Act’s first purpose, namely to facilitate regular and timely payments between the parties to a
construction contract.8 Recognising as valid or arguably valid
the cl 12 provision for
regular and timely payments in this case does not undermine the purpose of
the Act. But a provision which deemed claims to have been
made or payments due
at the end of a contract might well do so. The employer in Mr St John’s
counterfactual would be stipulating
for a contract without intervals between
payments or, put another way, would not be providing for progress payments at
all.
Overall conclusion
[35] I find it arguable that the contract validly provided a payment
claim/payment schedule regime which excluded the default
regime under the
Act.
8 Construction Contracts Act 2002, s 3(a).
Outcome
[36] Given my finding, Leighton’s application must succeed.
[37] Costs and disbursements must follow the event. A 2B award is
appropriate.
Orders
[38] I order:
(a) The statutory demand issued by the respondent on 27 May 2014 is set
aside; and
(b) The respondent is to pay the applicant’s costs on a 2B basis
together
with disbursements to be fixed by the Registrar.
Solicitors:
Simpson Grierson, Auckland
Franklin Law, Auckland.
Counsel: E St John, Barrister, Christchurch
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/3090.html