Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 17 February 2015
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV2014-404-001608 [2014] NZHC 3128
BETWEEN
|
NEW CORE PROPERTIES LIMITED
Plaintiff
|
AND
|
GANELLEN CONSTRUCTION LIMITED
Defendant
|
Hearing:
|
17 November 2014
and On the papers
|
Appearances:
|
R J Hooker for the Plaintiff
R G Smedley for the Defendant
|
Judgment:
|
10 December 2014
|
JUDGMENT OF ASSOCIATE JUDGE
CHRISTIANSEN
This judgment was delivered by me on
10.12.14 at 4:30pm, pursuant to
Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date...............
NEW CORE PROPERTIES LIMITED v GANELLEN CONSTRUCTION LIMITED [2014] NZHC 3128 [10
December 2014]
Hearing
[1] This matter was only partly heard when the hearing concluded after
6:00pm and when it was clear that further time would
be required to hear the
reply submissions on behalf of the plaintiff. At that time the hearing was
adjourned and counsel were requested
to submit final submissions in
writing.
[2] Those submissions have now been received.
Background
[3] The plaintiff, New Core Properties Limited (New Core) owned central
city commercial property which, following the Christchurch
earthquake, it wished
to develop. Discussions were entered into with the defendant Ganellen
Construction Limited (Ganellen) a building
contractor.
[4] In issue between the parties is whether a contract was concluded.
Ganellen says there was a concluded Contract. On 8
May 2014 it, by its
solicitor issued a notice of default and later on 28 May 2014 issued a notice of
cancellation. It has made demand
upon New Core for payment of damages in the
sum of $2,939,309.
[5] Ganellen’s position is that the parties entered into a
Contract or otherwise agreed to the resolution of any disputes
by
arbitration.
[6] New Core denies any contract was concluded. By its proceeding
filed on 30
June 2014 New Core seeks an order declaring the parties did not
enter into a Contract for the construction of a commercial
building. It
also seeks an order declaring it has not agreed to arbitrate on any dispute
between the parties.
[7] Ganellen has in response filed an appearance under protest to jurisdiction. Its position is that New Core and Ganellen are parties to a Contract agreement (the Contract) that was executed and dated 2 May 2014; and that the general conditions of the Contract are NZS 3910-2003 (3910) which provides that contractual disputes or differences are to be dealt with by the dispute resolution provisions of the Contract.
[8] In response to Ganellen’s protest, New Core has filed
an application to dismiss the appearance under protest
to jurisdiction. It is
that application which is for consideration by this Court at this
time.
[9] If the Court agrees the appearance under protest should be
dismissed then it will be because New Core has satisfied the
Court that the
parties did not conclude a construction Contract on 2 May 2014 or at any
other time and therefore the
arbitration agreement contained within the
terms of the construction Contract cannot exist. It follows that if the Court
was of
the view the Contract agreement did exist then the Court should find that
the arbitration agreement exists also. If the Court determines
there is a
Contract then it should stay New Core’s proceedings and refer the parties
back to arbitration, an arbitration which
Ganellen submits has already
commenced.
[10] Ganellen says this Court should strike out New Core’s
proceeding under Rule
15.1 of the High Court Rules, or by use of its inherent jurisdiction, on the
basis that
New Core’s cause of action cannot by any possibility be
maintained.
Issues
[11] It is not in issue that the Contract, if it existed, contains an
agreement to arbitrate. Rather, it is New Core’s
position that although
contractual terms were negotiated a Contract was not concluded and therefore did
not come into existence.
[12] In issue is a document dated 2 May 2014. It records that Ganellen
shall construct, complete, deliver and maintain the works
and that New Core
would pay Ganellen $18,142,400. The signature page refers to the Contract
documents comprising, as well, a Contract
agreement, and special conditions of
Contract and general conditions of Contract which incorporated the general
conditions of Contract
under 3910.
[13] The Contract was signed by Jun Sil Ahn (Mr Ahn) as director of New Core.
[14] Mr Ahn signed the Contract on 2 May 2014 at the offices of New
Core’s
solicitors, Jackson Russell.
[15] There is a difference of view between the parties regarding the
significance of that document. Evidence on behalf of New
Core indicates Mr Ahn
may not have understood its purpose.
[16] Ganellen’s position is that the document dated 2 May 2014 is
evidence to
show that a contract containing an arbitration agreement exists because
clause 2.7 of
3910 provides:
Unless and until the contract agreement is executed by the parties, the
tender or other offer and its acceptance between the contract
and principal
shall, together with other documents intended to form part of the
contract, constitute a contract between
them.
[17] However, if the Court did not accept the document dated 2 May 2014
as evidence of the Contract, Ganellen submits sufficient
other evidence can be
found in the offer of Ganellen and the acceptance of New Core communicated by
the parties’ respective
agents on 1 March 2014.
[18] An examination of various communications made on that date would be
required. On behalf of New Core it is submitted
that those
communications contained no meeting of minds, or that there was
insufficient certainty about essential terms.
In addition there are some
suggestions that the evidence provided in that regard for this Court by Mr Doig,
the commercial director
of Ganellen, ought to be viewed with
caution.
[19] Also there will be some discussion about what was sufficient in terms of communications made, for a contract to have formed. It is clear from clause 2.7 of
3910 that emails may constitute evidence of a contract even before the formal contract document was signed. Indeed, clause 2.7.3 of 3910 provides that “failure by either party to execute the contract agreement within the time provided shall be a default under Section 14”. In short the failure to execute the contract is a default of that contract. Therefore for Ganellen it is submitted that even if New Core had failed
to execute the Contract, that would not have changed the fact that the
parties were already bound by it if the existence of same is
clearly
evidenced.
[20] The case on behalf of Ganellen relies in part on an email from New
Core’s solicitor to Ganellen’s Mr Doig
on 29 April which
enclosed the construction Contract which was said to have been approved by New
Core. That email noted that
Ganellen’s solicitors would prepare the
construction Contract for signing and in that regard noted Mr Ahn and his wife
would
be travelling abroad on 6 May 2014.
[21] Ganellen says that following execution of the document on 2 May 2014
by Mr Ahn a copy of the duly executed document was delivered
to Ganellen by New
Core’s agent Mr Lee on 8 May 2014.
[22] The Court will review claims by Ganellen that a contract was earlier
agreed when its tender price was accepted on 1 March
2014. Then the Court will
review the evidence relating to claims of a contract executed on 2 May
2014.
[23] In conclusion there will also be brief discussion about whether in
any event it is appropriate for an arbitrator to have
jurisdiction to rule on
the existence of a contract. In that regard it is submitted for New Core that
the Court’s jurisdiction
is ousted by arbitration only if it is satisfied
that a Contract was entered into. That proposition is not accepted by
Ganellen.
Counsel for Ganellen submits Article 8 of the Arbitration Act 1996
provides that a Court shall, in a proceeding brought in a matter
which is
subject to an arbitration agreement, and if a party requests, stay those
proceedings and refer the parties to arbitration
unless it finds the agreement
is null and void, inoperative, or incapable of being performed.
Requirements of a Contract agreement
[24] There must be a “meeting of minds” that is an acceptance
of terms proposed
by an offer or counter offer. As Gresson J in Reporoa Stores Ltd v
Trevloar said:1
A reply constituting the acceptance of an offer must be read with the offer; to bring about a binding contract the offer and the reply accepting must be of
1 [1958] NZLR 117 at 177.
and in respect of precisely the same terms. The offeree must unreservedly
assent to the exact terms proposed by the offeror. If,
while purporting to
accept the offer as a whole, he introduces a new term which the offeror has not
had the chance of examining,
he is in fact making a counter-offer. Was the
offer accepted or not? If there was anything equivocal in the notice
exercising
the option, no binding contract could result.
The tender contract – 1 March 2014
[25] Ganellen claims that a contract was entered into when its tender was
accepted by New Core. New Core submits that any acceptance
was subject to
certain other works being included. Also it is the evidence of Mr Ahn that at
the relevant time the negotiation was
limited to price and was not concerned
with the terms or scope of work.
[26] By the written authority of New Core a Mr Marshall and a Mr Lee were
authorised to communicate on its behalf. Mr and Mrs
Ahn are Korean nationals
and their English language capabilities were limited.
[27] Mr Doig deposes that in about July 2013 Ganellen and New Core
entered into a memorandum of understanding to ensure good faith,
contact and
consultation and for the purpose of identifying respective obligations pre
contract. Later Mr Doig prepared a tender
proposal which was submitted to New
Core via Mr Marshall and Mr Lee on 28 February 2014 at 5:58pm.
[28] It referred to a tender sum of $18,368,218 (excluding GST) and noted
the Contract was to be a modified version of 3910 before
modifications being
mutually agreed before entering into the Contract. Mr Doig says many of the
modifications had already been negotiated
beforehand.
[29] At 6:17pm 28 February Mr Lee emailed Mr Doig to say the Ahns wanted
to reduce that cost to an equivalent of $3,450 per m2.
[30] On 1 March 2014 at 4:29pm Mr Doig emailed Mr Marshall with a revised tender offer of $18,242,068 (ex GST). It noted the tender sum was conditional upon execution of a New Zealand standard main construction contract under acceptable
terms to both. The revised tender noted it was provided in accordance with
the terms and conditions noted in the tender proposal submitted
the previous
day.
[31] At 5:42pm on 1 March 2014 Mr Marshall responded with a
counter-offer:
Mr and Mrs Ahn have said they will agree and sent confirmation that they will
go ahead with the construction if the price is $18,142,400.
Can you please
speak to the directors and let us know today. Jun (Mr Lee) is waiting with the
Ahns now”.
[32] Mr Doig says he then discussed the counter-offer with
Ganellen’s directors and then responded to Mr Marshall at 5:57pm
on 1
March 2014 with an email which stated that he had:
Been authorised to confirm the tender sum of $18,142,400 (excluding GST) as
noted below, in accordance with terms and conditions of
our original tender
submission.
[33] At 6:17pm on 1 March 2015 Mr Lee replied stating:
We are here to confirm on behalf of director (Jun Sil Ahn), New Core
Properties Ltd of $181,142,400 [sic] (exc GST) which
is a fixed sum
contract based on the original architectural drawings and external works
including landscape, security gates and
fences.
Thank you for business and we are looking forward to working with you on this
project as a main contractor.
Congratulation and thanks for all your hard work.
[34] The email clearly contained a typographical error in the contract
sum noted.
[35] Mr Hooker submits Mr Lee’s email was not an
unequivocal acceptance because it introduced the term ‘fixed
price
Contract’ and because it included “external works including
landscapes, security gates and fences etc.”.
[36] Mr Ahn deposed that he had no intention of entering into a contract
with this exchange of emails. He deposed that it was
a negotiation only about
price.
[37] Mr Hooker submits Mr Doig’s 1 March 5:57pm email was not an unconditional acceptance of New Core’s counter-offer; that it was in fact a counter- offer by Ganellen because Mr Doig introduced new terms and conditions which did
not form part of its conditional offer made at 4:29pm or in New Core’s
counter-offer made a 5:42pm.
Considerations
[38] New Core says the only term agreed was the price; that
Ganellen’s email of
5:57pm recorded all modifications were to be mutually agreed before entering
into the Contract. It follows submits Mr Hooker that
there was no intention at
that point in time to enter into a contract. Besides, Mr Ahn said he had no
intention of entering into
a contract as at that time it was only concerned
about price.
[39] The prerequisites to formation of a contract are, inter alia an
intention to be immediately bound, and agreement expressly
or by implication on
every term which was legally essential to the formation of the
bargain.2
[40] In the Court’s view a contract was agreed as at 5:57pm on 1
March 2014.
[41] The Court agrees with Mr Smedley’s assessment that the 6:17pm
email is an acceptance accompanied by a clarification
(not new terms) that the
Contract “is a fixed lump sum contract based on the original
drawings and external works
including landscapes, security gates and fences
and etc.”.
[42] Nor does the Court accept the emails concern a negotiation of price
only. Can it be said that price was agreed when the scope
of works was not. It
does not make sense.
[43] Further, it is clear from the Contract signed on 2 May 2014 that the
3910 general conditions of contract were not altered.
Contract of 2 May 2014
[44] On 5 March 2014 Mr Doig emailed New Core’s solicitor Mr
Davies-Colley
attaching copies of the initial tender submission and “the emails
containing the
2 Fletcher Challenge Energy Ltd v Electricity Corporation of NZ Ltd [2001] NZCA 289; [2002] 2 NZLR 433.
revised tender offer, counter-offer and acceptance that had been exchanged on
1
March 2014...”
[45] Subsequently there was an exchange of emails during which Mr Doig
says minor details were negotiated but none essential
to the Contract
that had been entered into. No evidence has been provided by Mr Davies-Colley
challenging Mr Doig’s
account of these things. Nor is there challenge to
Mr Doig’s account that until 29 April 2014 that negotiations resulted
in
clarification but no changes of significance.
[46] On 29 April Mr Davies-Colley emailed Mr Doig a copy of the
construction
Contract for execution by Ganellen. He wrote:
...Further to our recent conversation, please see attached the construction
contract and agreement for consultant services which have
been approved by our
client.
We note your earlier advice that you will prepare the construction
contract... Once that is done, please sign both the construction
contract and
the consultancy agreement, then courier them to us for signing...
[47] On 30 April 2014 Mr Doig emailed Mr Lee that the Contract agreement
duly executed by Ganellen would be couriered to Mr Davies-Colley
for execution
by New Core.
[48] The clear and acceptable evidence is that Mr Ahn signed the Contract agreement at the offices of his solicitors Jackson Russell on 2 May 2014. Indeed, and subsequently, Mr Lee provided Mr Doig with a copy of the signed contract. On
8 May Mr Lee informed Mr Doig that the Ahns did not intend to proceed with
the Contract. Ganellen then issued a notice of default
and subsequently on 26
May gave notice cancelling the Contract.
[49] In support of submissions that there was no concluded agreement, Mr
Hooker has submitted that no acceptance of the Contract
had been communicated by
the Ahns, New Core or its solicitor Mr Davies-Colley.
[50] Mr Hooker relies on the text Law of Contract in New Zealand 4th
ed. Mr
Hooker refers to Chapter 3.4:
3.4 Communication of acceptance
Even if the offeree has made up his or her mind to a final
acceptance, the agreement is not yet complete. The normal
position is that
there must be an external manifestation of assent, some words spoken or act done
by the offeree or by his or her
authorised agent which the law can regard as the
communication of the acceptance of the offeror. And insufficiently communicated
assent is not effective as an acceptance.
[51] Mr Hooker refers to Mr Ahn’s evidence that he went to his
solicitor’s office on 2 May and there received advice
about the Contract.
Mr Ahn does not say he signed it. Mr Hooker submits that what took place in the
office is legally privileged.
He says there is no evidence that there was any
communication to Ganellen that the Contract had been accepted. Mr Doig does not
claim there was communication of acceptance by New Core’s solicitors. He
did telephone Mr Ahn on 5 May and asked to confirm
the Contract had been signed.
He asked for a copy of the Contract.
[52] Mr Davies-Colley has sworn an affidavit. He refers to his office
receiving a telephone message from Mr Doig saying that
Mr Doig had understood
the Contract had been signed and executed. Mr Davies-Collier responded by email
advising Mr Doig that Jackson
Russell did not have instructions to confirm the
Contract was accepted.
[53] Regarding advice being received by Mr Doig from Mr Lee that the
Contract was signed and witnessed Mr Hooker submits the Court
ought to be wary
about accepting the quality of that evidence because it contained hearsay.
Further it is suggested Mr Lee did
not have authority at that time to provide
any information in that regard. Mr Hooker submits there may be good reason to
challenge
the authenticity of the email from Mr Lee to Mr Doig suggesting Mr
Doig should check his mobile phone messages. The reason for this
submits Mr
Hooker is because of the formatting of the emails that had been printed and
attached to Mr Doig’s affidavit.
Considerations
[54] Unquestionably communicated acceptance is required for there to be a binding Contract between the parties.
[55] The Court has already accepted Ganellen’s position that the
offer and the communicated acceptance that constitutes
the Contract between the
parties was contained within email correspondence on and before 1 March
2014.
[56] Ganellen’s backup position is that evidence of a Contract can
be found also in the email of New Core’s solicitor
agents on 29 April 2014
which attached the final revised construction contract and the agreement for
consultant services. That letter
by its terms and because of its request that
Ganellen’s solicitors should prepare the documents ‘for
signing’ contained
New Core’s offer.
[57] Ganellen says its acceptance was communicated by Mr Doig on 30
April
2014 in an email to which he attached executed copies of the Contract
agreement –
which contained an arbitration clause.
[58] Ganellen’s position is that communication of the fact that New
Core had executed the Contract was not required but
that execution was
communicated to him when Mr Marshall told Mr Doig on 2 May 2014 that Mr Ahn had
executed the Contract and also
when Mr Lee on 3 May 2014 told Mr Doig (in a
telephone message) that Mr Ahn had signed the Contract.
[59] A copy of that document which Mr Doig refers to having received was,
he says, given to him by Mr Lee on 8 May 2014.
[60] Critical to New Core’s case is its claim that acceptance of
the Contract was not communicated to Ganellen. But, that
position ignores the
communication made by Mr Lee and Mr Marshall on New Core’s
behalf.
[61] Subsequent conduct does assist the Court in adopting the position that the Contract came into existence when signed by Mr Ahn, even if it had not come into existence earlier. In Fletcher Challenge Energy Limited3 Blanchard J for the
majority held:
3 Supra.
It is permissible when considering contract formation... to look
at subsequent conduct of the parties towards one another,
including what they
have said to each other after the date of the alleged contract.
[62] In this case there is evidence of correspondence
between solicitors subsequently to show that the existence
of a Contract has
really only been challenged since New Core’s statement of claim was filed
in early July 2014.
[63] On 28 May 2014 New Core’s solicitors wrote to Ganellen’s
solicitors by email noting they were instructed to accept
service of notices and
correspondence pursuant to the Contract. They also advised that from that time
Mr Lee [and Mr Marshall]
were no longer authorised to act as agent for New Core
or Mr and Mrs Ahn.
[64] At all times prior it is clear Mr Lee and Mr Marshall were appointed
as New Core’s representatives each having the
authority to exercise any of
New Core’s powers or duties. Indeed Ganellen was instructed to
communicate directly with Mr Lee
and Mr Marshall.
[65] On 9 June 2014 New Core’s new solicitors wrote stating that
they understood Ganellen had cancelled the Contract and
that had been done on
the basis of an illegal repudiation of Contract. The lawyer requested
information for the basis on which Ganellen’s
lawyers considered Ganellen
was entitled to cancel the Contract. They asked whether Ganellen had cancelled
the Contract at common
law or under the terms of the Contract. The lawyer
suggested Ganellen had terminated any right to arbitration because of its
cancellation
of the Contract. Further, the lawyers purported to give notice
under clause 13.3.2 of the Contract. They invited a response to
the proposal
for mediation in accordance with the Contract.
[66] The unchallenged evidence of Mr Doig is that only on 23 June 2014
was it suggested for the first time that there was no Contract.
[67] The Court agrees with Mr Smedley’s submission that it would be
incredible
that if New Core genuinely believed it had not accepted the Contract that it would
have instructed its solicitors to correspond in the manner they did. Only
latterly has it been suggested that the Contract had not
been accepted or
executed.
[68] In the Court’s view Mr Davies-Colley’s 29 April email
and its acceptance is
clear evidence of consensus of the parties having been reached on all
essential terms.
[69] Mrs Ahn has provided evidence suggesting there were changes
in the Contract which Mr Doig has exhibited as having
been provided to him by
Mr Lee, and the copy which Ms Ahn has. Indeed there are some changes although
it appears they are not of
consequence. Also the copy Ms Ahn has exhibited was
not signed. It is reasonable to assume that it was a draft of that which was
concluded and executed on 2 May 2014.
Conclusions
[70] An enforceable Contract and arbitration agreement exists between the parties. [71] This matter was brought to the Court upon the application to dismiss
Ganellen’s appearance under protest to jurisdiction.
[72] Two options are available to the Court. One of those is to stay the
plaintiff’s proceeding and to refer the parties
back to the arbitration
proceeding which has already been initiated by Ganellen. The other option is to
strike out the proceeding
because the only relief sought by it is for orders
declaring there is neither a contract nor an arbitration agreement, and
requesting
the issue of an injunction to restrain the appointment of the
arbitrator who has already been appointed.
[73] In the Court’s view the proceeding should merely be stayed at
this time. Further the Court directs the parties refer
their issues back to the
arbitration proceeding.
Judgment
[74] The application to dismiss the protest to jurisdiction is dismissed.
[75] There is an order referring the parties back to the arbitration
proceeding that has been initiated.
[76] Costs are reserved. Submissions on behalf of New Core are to be filed and served no later than 10 working days after the submissions of Ganellen have been filed and served. A decision on the papers will follow. The Court certifies hearing
time of 1.25 days.
Associate Judge Christiansen
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/3128.html