Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 17 December 2014
IN THE HIGH COURT OF NEW ZEALAND NELSON REGISTRY
CIV-2014-442-28 [2014] NZHC 3187
BETWEEN
|
MONACO MANAGEMENT LIMITED
Plaintiff
|
AND
|
HANDY 4 LIMITED First Defendant
MARGARET BARTLETT and ALAN BARTLETT Second Defendants
2210 DEVELOPMENTS LIMITED Third Defendant
MICHAEL EDMONDS and ANGELA WINTER Fourth Defendants
VAUGHAN WORKMAN Fifth Defendant
MARIANO BOFFA Sixth Defendant
ZEZORA HOLDINGS LIMITED Seventh Defendant
PETER and AUDREY HEAVEN Eighth Defendants
MICHAEL BOUTLE and ROBIN WHALLEY Ninth Defendants
MICHAEL and INGA COTTON Tenth Defendants
ALROD LIMITED Eleventh Defendant
DAVID SCOTT Twelfth Defendant
BODY CORPORATE 334302
Thirteenth Defendant
|
Hearing:
|
On the papers
|
Judgment:
|
12 December 2014
|
MONACO MANAGEMENT LTD v HANDY 4 LTD [2014] NZHC 3187 [12 December
2014]
COSTS JUDGMENT OF CLIFFORD J
Introduction
[1] The plaintiff, Monaco Management Ltd (Monaco), seeks costs against
each of the first thirteen defendants, on a joint and
several basis, with
respect to a without notice interlocutory injunction granted to it restraining
the defendants from re- entering
possession of the units at 6 Point Road,
Nelson, pending orders for specific performance or under s 261 of the Property
Law Act 2007
providing for renewal.
[2] Each of the defendants objects.
[3] As Monaco submitted, it is appropriate to deal with this matter on the papers. [4] Monaco is the lessee of the Grand Mercure Monaco Hotel at 6 Point Road
Nelson. Each of the defendants is either, as an investor, the
owner of units comprising the hotel or in the case of
the third and thirteenth
defendants, a body corporate which owns common areas and whose members are, I
assume, investors. Monaco’s
lease was for an original period of ten years,
ending 26 May 2014, with two rights of renewal of ten years each. Provided
Monaco
was not in breach of the lease, it was entitled to renew the lease by
giving at least three calendar months’ written notice
before the end of
the first term of the lease to the lessors: that is, written notice was required
by 27 February 2014.
[5] Monaco did not give written notice by the time required. Rather,
on 17 April
2014, almost two months late, it gave notice to the lessors of
the hotel units, including each of the defendants, in
the following
terms:
NOTICE OF RENEWAL
A By lease (“the lease”) dated 27th April 2004 comprised in unique identifier 162353 Unit [ ] Deposited Plan 334302 (“premises”) was leased on the terms and conditions contained in the lease.
B The lessee and the lessor are currently the respective lessee and
lessor under the lease.
C The term of the lease expires on 26 May 2014 with two rights to
renewed terms of the lease for ten (10) years each, the
first being exercisable
on the renewal date of 27 May 2014.
NOW TAKE NOTICE:
1. The lessee hereby gives you written notice to renew the lease for
a further term of ten (10 years from the renewal date
of 27 May 2014.
DATED 17th day of April 2014.
[6] On 22 May, not having received it says responses to its late notice
of renewal, Monaco sent each of the defendants the following
email:
Dear [ ]
On 17 April 2014 we sent you a Notice of Renewal in relation to your lease of
Hotel unit [ ]. You have not responded to this Notice.
Your failure to respond is a breach of the Property Law Act 2007. Unless we receive a response from you by 3.00 pm Saturday 24 May 2014 we will take your failure to respond as a refusal to renew the lease and we will instruct our solicitors to apply to the Court for a renewal of the lease. If that is required, we will be seeking legal costs against you as well due to your breach of the Property Law Act.
We look forward to hearing from you. pp Scott Sanders
Monaco Management Limited
[7] As I understand matters, the other lessors of hotel units had
responded to the late notice to renew, indicating their agreement.
[8] The defendants replied to that email in a variety of ways, or not
at all.
[9] On 26 May 2014, just two days later, the plaintiff applied without notice for its interim injunction. That injunction was granted by this Court. Subsequently agreement has been reached between the plaintiff and the defendants for renewal of the leases.
[10] These matters occurred against the background of ongoing disputes
between the defendants and Monaco relating to the
operation of the
hotel. Whilst of contextual significance, that is not directly relevant to
the question I must decide.
[11] Monaco says that it was, in effect, forced to take legal action to
protect its position given the responses or lack of responses
from the
defendants to its notice of renewal and later email.
[12] The defendants, the minority of whom were represented by solicitors
for this purpose, the majority of whom wrote directly
to the Court, have
responded in a variety of ways, generally to the effect that it was
Monaco’s actions in giving notice of
renewal late that occasioned these
circumstances and that the legal action taken by Monaco was, in reality,
unnecessary or precipitate.
[13] Having considered those submissions, and the circumstances more
generally, I am clear that an award of costs to Monaco is
not appropriate. My
reasons are:
(a) Monaco was late in giving notice to renew.
(b) On that basis, Monaco’s remedy was an application under s 261 of
the
Property Law Act.
(c) In the circumstances, Monaco’s “Notice of
Renewal” did not, as might have helped matters, refer
to the fact that
it was out of time, nor that – provided there was no breach of the lease
–Monaco would generally be
entitled to renew were it to apply under s 261
to be relieved from the consequence of failure to give notice in
time.
(d) Responses are not required to a notice to renew a lease. Rather, ss 261 - 264 of the Property Law Act reflects the requirement that a lessee who does not consent to a renewal must give notice of that fact to Monaco, who must then, in turn, give a notice under s 262.
(e) Monaco’s email of 22 May 2014 wrongly stated that the
defendants’ “failure” to respond to the late
notice of 17
April 2014 was a breach of the Property Law Act 2007. It was not.
(f) Given the short period of time that expired between the despatch of
that email, and the application for an interim injunction,
it is not surprising
that, facing a threat of legal action, the defendants did not immediately
co-operate with Monaco.
[14] Thus, and as defendants generally submitted, it was the way Monaco conducted itself that has resulted in it taking legal action. Moreover, the email of
22 May was legally wrong and verged on intimidation.
[15] In this, I acknowledge that the position of the tenth defendants,
Michael and
Inga Cotton, might be seen as being somewhat different, in that they replied
on
10 May 2014 to the plaintiff, declining to agree to the renewal and giving
notice of an exercise of their rights under the Property
Law Act. But, by the
time Monaco came to apply without notice for its interim injunction, Mr and Mrs
Cotton had agreed not to re-enter
their unit pending resolution of the issue of
the renewal of the lease. In their case, that is, in fact, an additional and
conclusive
reason why Monaco is not entitled to costs.
[16] Monaco’s application for costs is declined
accordingly.
“Clifford J”
Solicitors:
Saunders Robinson Brown, Christchurch for plaintiff. Pitt & Moore, Nelson for eleventh defendant.
Morgan Coakle, Auckland for twelfth and thirteenth defendants.
Copy to all other defendants.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/3187.html