Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 18 April 2014
IN THE HIGH COURT OF NEW ZEALAND BLENHEIM REGISTRY
CIV-2014-406-000008 [2014] NZHC 639
BETWEEN
|
NOPERA LOG HOUSE LIMITED
Applicant
|
AND
|
MICHELLE ELIZABETH GODSIFF Respondent
STUART LEONARD GODSIFF Second Respondent
|
Hearing:
|
25 March 2014
|
Appearances:
|
N R Campbell QC for Applicant
Q A Davies and D P Neild for Respondents
|
Judgment:
|
2 April 2014
|
JUDGMENT OF ASSOCIATE JUDGE MATTHEWS
Background
[1] On 29 November 2013 the respondents, Mr and Mrs Godsiff (the
Godsiffs) agreed to sell their property in the Marlborough
Sounds to Mr K
Radzik. The agreement was subject to one condition only, in the following
terms:
18.0 Due Diligence
This agreement is entirely conditional on the Purchaser approving (in the
Purchaser’s sole and unfettered discretion) all matters
that the Purchaser
considers may touch, concern or affect the property or the commercial viability
of the transaction within twenty
(20) complete working days after the date of
this agreement being signed by both parties.
[2] The agreement was later varied in three material
respects:
NOPERA LOG HOUSE LTD v M E & S L GODSIFF [2014] NZHC 639 [2 April 2014]
(a) On 6 December the parties agreed to the contract being subject to
consent being granted under the Overseas Investment Act 2005
(OIA) by 31 March
2014.
(b) On 18 December 2013 the parties agreed to the date for confirmation
under the due diligence condition being 31 January 2014.1
(c) On 20 January 2014 Mr Radzik nominated Nopera Log House Limited
(Nopera), the applicant, as purchaser under the agreement.
[3] Nopera did not confirm the due diligence condition by 5.00 pm on 31
January
2014. At 5.15 pm that day the Godsiffs cancelled the contract, on the ground
that the due diligence condition had not been confirmed.
By that point, Nopera
had not lodged an application for consent under the OIA. Nor had it paid the
deposit which was required
to be paid on 31 January.
[4] On 12 February 2014 Nopera lodged a caveat against the titles to the property claiming an interest in the land as nominated purchaser pursuant to the agreement for sale and purchase which I have described. On 25 February Land Information New Zealand gave notice to Nopera that the Godsiffs had applied to lapse the caveat. On
10 March Nopera filed this application for an order that the caveat not
lapse.
The issues
[5] It is common ground that, depending on the circumstances, a purchaser under a conditional agreement for sale and purchase of land may have an equitable interest in that land capable of sustaining a caveat prior to confirmation.2 The test is whether equity can compel a vendor to transfer the estate or interest to the purchaser. If so, this gives that purchaser the equitable estate or interest which will support a caveat.
The equitable interest obtained, however, is always conditional upon the
purchaser
2 Bevin v Smith [1994] 3 NZLR 648 (CA); McDonald v Isaac Construction Co Ltd [1995]
3 NZLR 612 at 619 (HC).
performing the contract, so the interest of a purchaser under a conditional
contract ceases if the contract is avoided for failure
of the
condition.3
[6] In this case Nopera says that it has an equitable interest in the
property as the Godsiffs have wrongly cancelled the contract,
and that it is
therefore entitled to an order that the caveat remain on the title. The Godsiffs
say, however:
(a) The contract was subject to a due diligence condition, that condition
was not confirmed by the due date for confirmation, and
they were entitled to
terminate the contract.
(b) A contract conditional on the granting of consent under the Overseas
Investment Act 2005 does not pass an equitable interest
and therefore signing
the contract Nopera did not receive an interest in the land capable of
sustaining a caveat.
[7] The issues in this case reflect these two propositions.
Rules governing the lapse of a caveat
[8] The principles to be applied by the Court were recently summarised
by the Court of Appeal in Botany Land Development Ltd v Auckland
Council.4 The Court said:
[23] As this Court has previously held, applications under provisions such
as s 145A of the Land Transfer Act are “quite
unsuitable to determine the
rights of the parties”. This is particularly so where there are disputed
questions of fact. That
said, there is no dispute between the parties as to the
applicable principles.
[24] The onus is on the caveator to demonstrate that it holds an interest
in the land which is sufficient to support a caveat.
The caveator must put
before the Court a reasonably arguable case to support the interest it claims.
An order for the removal of
a caveat will only be made if it is clear that there
was either no valid ground for lodging it in the first place or, alternatively
that such ground as then existed has now ceased to exist. There is a residual
discretion, once a reasonably arguable case has
been established as to
whether to make an order removing the caveat. This will be exercised only
cautiously, for example,
where the Court finds there is no practical
advantage to maintaining a caveat and the caveator will not be
prejudiced.
3 Bevin v Smith above.
4 Botany Land Development Ltd v Auckland Council [2014] NZCA 61.
The facts
[9] It is common ground that Nopera required consent under the Overseas
Investment Act 2005 in order to complete its intended
purchase.5
Nopera’s intended purchase was an overseas investment in sensitive
land, within the definition set out in the Act.6
[10] Consent must be obtained for such a transaction before an
overseas investment is given effect under the transaction
in question,7
but entering a contract to acquire a property that is conditional on
consent being obtained under the Act is exempted from that
requirement.8
[11] Nopera was required to make the application for
consent.9 Certain information must be provided in support of
an application. In this case, some of that information was held by the
Godsiffs,
and they accept that it was necessary for them to make this
information available to Nopera before it could file its application
for
consent.
[12] On Thursday, 9 January 2014 the solicitor for Nopera emailed the solicitor for the Godsiffs asking for certain information to be provided. At that date there were 5610 working days before the agreed deadline for consent to be obtained, 31
March. I will explain the relevance of this figure shortly. The solicitor
for Nopera said:
Timewise, we are working towards making the application towards the end of
next week, so something by then would be great.
[13] The following week ended on 17 January. The information was not to hand, nor had the application been filed. On Monday, 20 January the solicitor for Nopera wrote to the Godsiffs’ solicitor again advising that the application was drafted but he still required information from the Godsiffs, as well as information which had been
sought from the real estate agent and some information from a third
party. He asked
5 Overseas Investment Act 2005, section 10.
6 Section 12 and Part 1 of Schedule 1.
7 Section 11.
8 See definition of “give effect to an overseas investment” in s 6.
9 Section 22.
10 This figure is my calculation and differs from that contained in the respondents’ chronology.
when the Godsiffs’ information would be available. The same day the Godsiffs’ solicitor advised Nopera’s solicitor that the information had been prepared, and he expected to receive it by post the following day, or the day after. The next day (21
January) he advised that the information would be sent to him by post the following day and he would be in touch once he had received it and reviewed it. There were
48 working days to the consent confirmation deadline.
[14] On Thursday, 23 January Nopera’s solicitor emailed the
Godsiffs’ solicitor again noting that he was nearly ready
to submit the
application but one of the missing components was the vendor information. He
asked that it be provided once the Godsiffs’
solicitors received it. That
solicitor responded the same day advising that the Godsiffs had advised that it
would be “at
least tomorrow” before the information was in his
hands. Nopera’s solicitor responded:
Ok thanks Rob – no worries – we’ll plan to get Appn
completed & filed next week.
At that point there were 46 working days until the deadline for consent to be
granted.
[15] The next week started on Monday, 27 January. That morning the
solicitor for the Godsiffs wrote to Nopera’s solicitors
advising
that his instructions were to forward the information required for the
consent application to him after Nopera had
confirmed the due diligence
condition. Nopera’s solicitor advised in response that:
The ongoing delay in providing the relatively simple Vendor information will
delay OIO consent. 90% of category 2 OIO applications
are assessed within 50
[working days]. We are assuming 60 [working days] as a worst case. 60 [working
days] from 1 February takes
us to 4th May 2014.
Before our client pays the $19,544 OIO application fee, please confirm your
client will agree to this revised OIO consent date. This
is a [due diligence]
matter.
At that point there were 44 working days to the agreed consent
deadline.
[16] On 29 January an extension of that deadline was declined. On the same day the solicitor for the Godsiffs emailed to Nopera’s solicitor a letter to the Overseas Investment Office and advised the original would be posted for inclusion with the application. He asked whether any further information was required, and in relation
to due diligence noted that he had responded to Nopera’s most recent
inquiries and asked if there were any other issues which
still required an
answer.
[17] At 5.15 pm on 31 January, 15 minutes after the deadline for
confirmation of the due diligence condition by Nopera, the solicitor
for the
Godsiffs advised in a letter sent by facsimile that as the due diligence term
had not been confirmed he was instructed to
cancel the agreement, which was then
at an end. At that time 40 working days remained until the agreed deadline for
consent.
[18] The undisputed evidence before the Court is that the Overseas
Investment Office website records that the office has a target
of assessing 90%
of consent applications, within the category which would apply in this case,
within 50 working days of active consideration
by the office. Further, in the
second half of 2013 the office met that target in 98% of cases. There is no
evidence of how many
days an application for consent in this case, or in any
given case, would in fact take. Nonetheless, in an affidavit sworn in support
of
this application, Mrs A G Takacs, a director of Nopera, gives the following
explanation for Nopera not having confirmed the due
diligence condition on 31
January:
18. On 31 January 2014, Nopera and Radzik were unwilling to risk OIO
non-refundable application fee of $19,544 because the remaining
40 working days before the OIO condition date provided (in both Nopera and its solicitor’s judgment) a significant risk that there would be insufficient time available to obtain OIO consent before 31 March
2014. Had the vendors supplied the requested information by
23 January 2014, Nopera and Radzik would have been comfortable to proceed
with the OIO Application.
19. As at 31 January 2014 the only matter preventing Nopera from
confirming the DD condition was that there was not enough
time to obtain OIO
consent by the OIO consent date, because of delay by the vendor in providing
information.
[19] Apart from reference to the information on the OIO website which I have referred to, there is no other evidence before the Court on why there was assessed to be a significant risk that the application would not be determined within 40 working days. There is no evidence of the percentage of consents decided within 40 days, which was the time remaining on 31 January, or 46 days, the time remaining on
23 January, the date which would have left Nopera “comfortable to proceed”.
[20] No other reason is given for Nopera not confirming the due
diligence condition.
[21] Clause 9.8 of the contract provides, to the extent
relevant:
9.8 If this agreement is expressed to be subject either to the above or
to any other condition(s), then in relation to each such
condition the following
shall apply unless otherwise expressly provided:
(1) The condition shall be a condition subsequent.
(2) The party or parties for whose benefit the condition has been included
shall do all things which may reasonably be necessary
to enable the condition to
be fulfilled by the date for fulfilment.
(3) Time for fulfilment of any condition and any extended time for
fulfilment to a fixed date shall be of the essence.
(4) The condition shall be deemed to be not fulfilled until notice of
fulfilment has been served by one party on the other party.
(5) If the condition is not fulfilled by the date for fulfilment, either party may at any time before the condition is fulfilled or waived avoid this agreement by giving notice to the other. ...
(6) ... 11
First issue – were the Godsiffs entitled to cancel the contract when
Nopera failed to confirm it by 5.00 pm on 31 January?
[22] Mr Campbell accepts that the due diligence condition was not fulfilled by the required time, but says that the Godsiffs cannot rely on non-fulfilment of a condition, and then cancel the contract on that ground, where non-fulfilment was caused by its own default. He says that due diligence conditions cannot be satisfied where information is required from the other party to the contract, and that information is not provided. He says that the Godsiffs failed to respond in a timely way to Nopera’s request for relevant information to support its application for consent under the OIA, information first requested on 9 January 2014. He relies on the events which I have summarised above in relation to requests for information and responses
to them. He notes that while these exchanges were taking place the
Godsiffs had
11 The contracts between Nopera and the Godsiffs is on the 9th edition of the standard agreement for sale and purchase of real estate approved by the Real Estate Institute of New Zealand and the Auckland District Law Society. Page 1 of the general terms of sale, which contains clause 1 from clause 1.0 to 1.3(4)(e), was omitted from the copy of the agreement which was produced in evidence. Nonetheless counsel agreed that the page is included in the contract, and a copy of the page was available for my consideration as it was contained within the contract by which the Godsiffs sold the property to another party, which was exhibited to the first affidavit of Mr S L Godsiff.
entered a backup agreement for sale of the property to an unrelated third
party which was subject to the cancellation or termination
of the contract of
sale to Nopera immediately the Godsiffs became lawfully entitled to do
so.
[23] Mr Campbell then says that by the time the information was provided
on
30 January, there was a significant risk that an OIA application
would not be processed in time to meet the OIA condition
date of 31 March,
that Nopera was unwilling to risk the non-refundable OIA application fee,
and these were both matters
that Nopera considered affected the commercial
viability of the transaction, in terms of the due diligence clause. Thus, he
says,
there is an arguable case that the Godsiffs’ delay in providing the
required OIA information prevented Nopera from fulfilling
the due diligence
condition by 31 January.
Discussion
[24] Whilst the principle relied upon by Mr Campbell is not challenged,
there are a number of difficulties with its application
in this
case.
[25] First, Nopera wishes to proceed with its contract of purchase, but it did not confirm the due diligence condition, nor did it waive the condition. It did not seek an extension of time for confirmation of the due diligence clause beyond 5.00 pm on
31 January. Apart from noting in an email to the Godsiffs’ solicitors
that it regarded the failure to provide the information
required for the OIA
consent in a timely way as a due diligence issue, it did nothing
further.
[26] The wording of the due diligence clause which is relevant
to Nopera’s argument is this:
This agreement is entirely conditional on [Nopera] approving (in
[Nopera’s] sole and unfettered discretion) all matters that
[Nopera]
considers may touch, concern or affect ... the commercial viability of the
transaction ...
[27] Nopera argues that the possible wastage of the OIA consent fee due to the lateness of the application for consent is an issue relevant to the commercial viability of the transaction, within this condition.
[28] In my view, however, that is not the case. On its ordinary
meaning, the commercial viability of a transaction involving
the sale and
purchase of a property will not usually involve the risk of losing a consent
application fee, where it is inherent in
entering the agreement in the first
place that a consent application fee will be incurred. There is no suggestion
that Nopera finds
that the transaction is not commercially viable because of
the extent of fees which must be incurred; its position is
based on the
proposition that a risk of losing a fee affects the viability of the
transaction.
[29] Even if I am wrong in that conclusion, the evidence on the element
of risk relied on by Nopera is, in my view, insufficient
to show an arguable
case that any responsibility for Nopera’s decision not to confirm the due
diligence clause lies at the
feet of the Godsiffs.
[30] I have summarised the information which led Nopera to the contrary
view earlier in this judgment. It is a statement by the
OIO of its intentions
in relation to deciding applications which are made under the OIA. It does not
follow from that statement
of intention that any given application is at risk of
not being decided until some point late in the 50 working day period. Some
might be; equally some might be decided in a much briefer period. At 31 January
when there were 40 working days available prior
to 31 March, there may have been
a level of risk that the application would not be processed by the latter date,
as the office does
not aspire to deciding all applications within a 40 day
period. It is not possible, however, on the evidence produced to the Court
on
this application to assess whether there was any significant element of risk in
relation to this application. There is no evidence
about the turnaround in the
OIO at the time, or the time then being taken to process applications of this
kind.
[31] Further, even if there is sufficient evidence for the Court to find that there was a real risk of the consent fee being wasted if the application was not made by a date 50 working days prior to 31 March, Nopera has not established an arguable case that responsibility for the loss of time between 50 working days in advance of that date, and 40 working days in advance of that date, is the responsibility of the Godsiffs.
[32] On 9 January, which was 56 working days before the deadline relied
on by Nopera, its solicitor first emailed the solicitor
for the Godsiffs in
relation to the OIA application. After setting out certain required information,
he said:
If we could have something from you or your clients covering off these areas
that would be appreciated.
Timewise, we are working towards making the application towards the end of
next week, so something by then would be great.
[33] This email was written on Thursday, 9 January; if one assumes that
the vague phrase “towards the end of next week”
referred to perhaps
Thursday, 16 January, by that point there would have been just 51 working days
available before the consent deadline.
No element of urgency was expressed
which reflects the degree of reliance now placed on the 50 working day reference
on the OIO
website.
[34] On 23 January, 46 working days out, the same solicitor advised the Godsiffs’ solicitor that he was nearly ready to submit the application but “one of the missing components” was the information sought from the Godsiffs. Later the same day, in response to a reply to this email, indicating that it would not be available until the following day at the earliest, Nopera’s solicitor commented “No worries” and indicated that he would “plan to get the application completed and filed next week” which, at the earliest, could only have been a reference to Monday, 27 January,
44 days out from the deadline.
[35] On 27 January Nopera’s solicitor sought an extension of time
for the OIO consent date, this being the first indication
that Nopera’s
solicitor recognised any adverse significance in the diminishing time period
before the consent confirmation
date.
[36] Nopera places responsibility for its decision not to confirm the due diligence condition, for the reasons I have outlined, squarely on the delay between 27 January and 31 January, but at no point prior to 27 January did Nopera’s solicitor indicate any element of urgency for a response to his requests for information – in fact on
23 January, just two working days earlier, his indication was quite the reverse.
[37] The period of four days between 27 January and 31 January, which
Nopera now says is the responsibility of the Godsiffs, requires
further
consideration too. First, as Monday, 27 January was the first day on
which Nopera’s solicitor considered
there was now a real element of
haste required, it is relevant that the respective solicitors were in different
cities (Blenheim
and Nelson). An original document containing the
vendor’s information had to be filed by the purchaser’s solicitors.
Even if despatched to them on Monday, 27 January by post, it would not be
received until Tuesday, 28 January. On the day a level
of urgency was
expressed, there was inevitably a further day to be lost in the provision of the
information, unless an immediate
form of delivery was arranged, such as delivery
by courier or in person, but Nopera’s solicitor did not suggest, let alone
arrange, this. That leaves just three days during which, viewing the matter as
favourably as possible from Nopera’s perspective,
there might have been an
element of delay on the part of the Godsiffs. That does not, however,
materially assist Nopera’s
position – there is no evidence of how
much difference this three day period might have made to the likelihood of
consent being
granted by 31 March. Put another way, the evidence does not
establish an arguable case that this period of time materially affected
the
prospect of consent being granted in time or therefore, as Nopera would have it,
the commercial viability of the transaction.
[38] For these reasons I find that Nopera has not established an arguable case that the Godsiffs caused it to be unable to confirm the due diligence clause on 31 January
2014. Rather, it elected not to confirm the due diligence condition by the
required deadline, and the Godsiffs were entitled to cancel
the
contract.
Second issue – does a contract subject to consent under the Overseas
Investment Act 2005 pass an equitable interest to the
purchaser?
[39] Given the decision I have reached on the first issue it is not
necessary to discuss the second issue at length. However,
because counsel
presented detailed arguments in relation to this issue, and because it does not
appear to have been decided previously.
I will briefly express my
view.
[40] Section 10 of the OIA provides that a transaction requires consent if it will result in an overseas investment in sensitive land. A transaction is defined in s 6 as
the entering into or the giving of effect to a provision in a contract or
arrangement. Section 12 provides that an overseas investment
in sensitive land
is the acquisition of an interest in land, and s 6 defines interest to include a
legal or equitable interest.
[41] It follows from these definitions that the acquiring of an equitable
interest in sensitive land, which amounts to an overseas
investment, requires
consent. Consent need not, however, be obtained before a contract is entered
which is conditional on such consent
being granted. This is because although s
11 provides that consent must be obtained before the overseas investment is
given effect
to under the transaction, the definition of giving effect to an
overseas investment, in s 6, excludes an acquisition which is conditional
on
consent being obtained under this Act.
[42] Therefore in this case consent was not required before the contract
between
Nopera and the Godsiffs was entered.
[43] Apart from this being, in my view, the correct interpretation of the
sections to which I have referred, it is also
consistent with s 29,
which provides that a transaction entered into without consent is neither
illegal nor void but may
be cancelled in certain circumstances, and s 25(1)
which provides that consent may be granted retrospectively. Further, s 42 sets
out certain offences in relation to transactions without consent, but relates
only to giving effect to an overseas investment, which
as I have said excludes
the entering of a contract which is conditional on the granting of
consent.
[44] In Bevin v Smith,12 the Court said:
There will be some conditional contracts, particularly those subject to true
conditions precedent, where the parties cannot be regarded
as intending that
equitable title will pass to the purchaser until the condition is waived or
fulfilled.
[45] As noted above,13 the condition in this contract
was expressed to be a condition subsequent.
12 Bevin v Smith, [5] above.
13 At [21].
[46] In McDonald v Isaac Construction Co Ltd,14 Tipping
J said:
In the usual case where the parties intend to be bound and to remain bound
subject to the fulfilment of the condition, equitable interests
in land can
arise by means of such a conditional contract.
[47] Based on this, the learned authors of Principles of Real
Property Law15
express the view that:
Applying this test it will no doubt be found that most conditional contracts
are intended to pass the equitable title to the purchaser
and hence give the
purchaser a caveatable interest.
[48] Applying this principle, and having regard to the structure of the
OIA which I have outlined, and the express contractual
provision that conditions
in this contract were conditions subsequent, it is my view that Nopera as
purchaser obtained an equitable
interest in the land on entering the contract,
and that equitable interest was held subject to consent being granted. It was
capable
of supporting a caveat, accordingly.
[49] Had this case fallen to be decided on this issue alone, I would have
made an order sustaining the caveat.
[50] Counsel for the Godsiffs referred me to a passage in McMorland Sale of Land.16 At paragraph 6.09 the learned author stated that although a conditional contract normally passes an equitable, and therefore a caveatable, interest a contract conditional on the grant of consent under the OIA does not pass an equitable interest and therefore is not caveatable. Unfortunately, the learned author does not give a reason for this conclusion. With respect, I differ from this view for the reasons
given.
Outcome
[51] The application to sustain the caveat is
dismissed.
14 McDonald v Isaac Construction Co Ltd [1995] 3 NZLR 612 at 619.
16 D W McMorland Sale of Land (3rd ed, Cathcart Trust, Auckland 2011).
[52] The respondent is entitled to costs which I award on a 2B
basis plus
disbursements to be fixed, if necessary, by the
Registrar.
J G Matthews
Associate
Judge
Solicitors:
Radich Law, Blenheim. Gascoigne Wicks, Blenheim.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2014/639.html