Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 26 May 2015
IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
CIV-2014-425-000077 [2015] NZHC 1041
UNDER
|
the Judicature Amendment Act 1972
|
IN THE MATTER
|
of a decision made pursuant to the
Resource Management Act 1991
|
BETWEEN
|
OWEN GEORGE NASH Plaintiff
|
AND
|
QUEENSTOWN LAKES DISTRICT COUNCIL
First Defendant
WOODLOT PROPERTIES LIMITED Second Defendant
|
Hearing:
|
4 February 2015
|
Appearances:
|
G Todd and K Pfeffer for plaintiff N Whittington for first defendant N
Soper for second defendant
|
Judgment:
|
18 May 2015
|
JUDGMENT OF CLIFFORD J
Table of Contents
Introduction ..........................................................................................................[1]
Facts.......................................................................................................................[2] The planning context..........................................................................................[10] The Challenged Non-notification Decisions.....................................................[25] The errors asserted by Mr Nash .......................................................................[28] Illegality – misapplication of permitted baseline and the receiving
environment ................................................................................................[30]
Unreasonableness
.............................................................................................[104]
Delay
..................................................................................................................[107]
Result
.................................................................................................................[108]
NASH v QUEENSTOWN LAKES DISTRICT COUNCIL [2015] NZHC 1041 [18 May
2015]
Introduction
[1] This is an application to declare resource consents for a
multi-unit residential property development near Queenstown
invalid on the
basis that the consent authority, the first defendant the Queenstown Lakes
District Council (QLDC), acted unlawfully
when deciding that the applications
for those consents did not need to be publicly notified.
Facts
[2] Mr Owen Nash, the plaintiff, owns a property above Lake Wakatipu at
Larch Hill Place, near Frankton. Woodlot Properties
Ltd (Woodlot), the second
defendant, is developing a multi-unit residential property on land it owns at
Larch Hill Place (the Woodlot
Development). Neither Mr Nash’s
property nor the Woodlot Development has road access from Larch Hill
Place.
Rather access to those properties is off the nearby Andrews Road
which is, in turn, accessed from SH6A, the Frankton to Queenstown
highway.
[3] Mr Nash is concerned that the Woodlot Development will adversely
affect traffic movement on Andrews Road and, in particular,
at the intersection
of Andrews Road and SH6A.
[4] The Woodlot Development was initially consented, on a non-notified basis, in December 2007.1 Woodlot’s plans were subsequently affected by the adverse economic circumstances that followed the global financial crisis. In response, the development was delayed and Woodlot changed the details of the development on a number of occasions. Since December 2007 QLDC has issued, again each time on a non-notified basis, a further six resource consents for the Woodlot Development reflecting those changes. The following table summarises the details of the various
consents:
1 RM070741 (Queenstown LDC numbers applications for
resource consents and issues resource consents by year and sequentially. Thus
RM070741
refers to the QLDC’s decision in respect of the 741st
resource consent applied for in 2007).
Issue Date
|
No.
|
Nature
|
3 December 2007
|
RM070741
|
Consent for construction of two blocks each containing 6 x 2 bedroom units,
a total of
12 units.
|
25 January 2008
|
RM080009
|
Variation to RM070741 to allow staging.
|
3 December 2008
|
RM081340
|
Consent for construction of two blocks containing a total of 14 units
(6 x 4 bedroom; 8 x 2 bedroom).
|
24 August 2011
|
RM110460
|
Variation to RM081340 to remove one block, subdivide the site and to
increase the number of 2 bedroom units from 8 to 10 in remaining
block.
|
16 October 2012
|
RM120496
|
Consent for construction of two blocks containing a total of 14 units (12 x
2 bedroom and 2 x 7 bedroom).
|
28 November 2013
|
RM130600
|
Consent for construction of two blocks containing a total of 20 units (12 x
2 bedroom and 8 x 2 bedroom).
|
8 October 2014
|
RM140739
|
Variation to RM 130600 relating to outdoor areas and car parks.
|
[5] Mr Nash applies for judicial review of QLDC’s decisions,
under s 95 of the Resource Management Act 1999 (the RMA),
not to publicly notify
the applications which resulted in RM081340 (12 December 2010), RM120496 (16
October 2012) and RM130600 (28
November 2013) (the Challenged Non-notification
Decisions).
[6] Mr Nash says that when making the Challenged Non-notification
Decisions QLDC acted unlawfully in either not considering
adverse traffic
effects or deciding that they were minor or not more than minor. Mr Nash
says this Court should declare the
relevant consents invalid. Recognising,
however, that his challenge is only based on QLDC’s alleged failure to
consider traffic
effects when making the Challenged Non-notification Decisions,
any relief should be fashioned to require QLDC to reconsider the relevant
resource consent applications on a notified basis as regards those effects
alone.
[7] QLDC says it acted lawfully at all times.
[8] Woodlot supports QLDC’s position, but says that if QLDC did
act unlawfully in any way, relief should be denied
due to Mr
Nash’s delay in bringing these proceedings.
[9] By the time this application was heard, the Woodlot
Development was virtually complete. In his affidavit Mr
Broomfield stated it
was on track for completion in late February of 2015. I can only assume that
it is, in fact, now complete.
For some time, however, Woodlot carried
out little or no work at Larchhill Place. By the time of the third
Challenged
Non-notification Decision, in November 2013, Woodlot had undertaken
the majority of the required earthworks pursuant to RM120496.
I was not told
when that work commenced. Construction work began once that non-notification
decision was made and RM130600 was
granted.
The planning context
[10] The planning rules for all of Woodlot’s applications are found
in the current
Queenstown Lakes District Plan (the District Plan).2
[11] The Woodlot Development was originally characterised in accordance
with the District Plan as a residential development located
in the Low Density
Residential Zone. The District Plan establishes rules for that zone on the
basis, among other things, of site
and zone standards. The significance of
site and zone standards is described in the District Plan in the following
terms:3
The District Plan adopts a two-tier system of standards in each zone.
Site Standards are specified in relation to matters which tend to
impact on the use of the particular site or adjacent areas. While these
standards
are important, they are not considered fundamental to the integrity of
an area as a whole and so are specified in a way that if development
does not
comply with these standards the Council will consider the matter of
non-compliance by way of a resource consent for a discretionary
activity. This
enables the Council to consider the implications of non-compliance on the use
and enjoyment of the site involved
and on neighbouring sites.
2 The Queenstown Lakes District Plan was made partially operative in 2003 and fully operative in
2009. While only partially operative in 2007 and 2008, the parts that apply with respect to
RM 07041 and RM 081340 were operative at the time.
3 Queenstown Lakes District Plan DP, r 1.4 [DP].
Zone Standards are standards which are fundamental to environmental
standards or character which are to be attained for a zone or area. Because
of
their importance all activities which fail to meet these standards are non-
complying activities which face a more rigorous assessment
if they are to obtain
a resource consent (as compared with a discretionary activity.
[12] As relevant, a residential development in the Low Density
Residential Zone:
(a) that complies with all relevant zone and site standards, is a permitted
activity;4
(b) that complies with all zone standards but does not comply with one or
more site standards, is a restricted discretionary activity;5
and
(c) that does not comply with one or more zone standards, is a
non-complying activity.6
[13] As first proposed in December 2007 the Woodlot Development, in very
large measure, complied with the zone and site standards
for the Low Density
Residential Zone. It was not, however, a permitted activity. It was a
restricted discretionary activity as
regards two site standards: the extent of
the earthworks required and the size of the blocks’ balconies. It was a
non-complying
activity because at its highest point it exceeded, by 2.31 metres,
the zone standard height limit of seven metres.
[14] As eventually proposed in November 2013, the Woodlot Development was a comprehensive residential development located in the Low Density Residential Zone. It was a comprehensive residential development, rather than simply a residential development, due to a change in the number of units proposed to be built. That change, from 14 to 20, had resulted in the site density (the area of the site divided by the number of units) “increasing” from 533m2 per unit to 320m2 per unit.7
As such the Woodlot Development was a discretionary
activity.8 The Woodlot
4 DP, r 7.5.3.1.
5 DP, r 7.5.3.4(vi).
6 DP, r 7.5.3.5.
8 DP, r 7.5.3.4(v).
Development still exceeded the zone standard seven metre height limit. It
remained, therefore, a non-complying activity.
[15] The District Plan specifies “assessment matters” for
the various zones it creates: these are matters which,
on a non-exclusive
basis, the Council shall have regard to in deciding whether or not to grant
consents or impose conditions. As
relevant for (discretionary) comprehensive
residential developments in the Low Density Residential Zone these
include:9
vi Discretionary Activity – Comprehensive Residential
Development
(a) Any adverse effects of the activity in terms of:
...
(iii) Level of traffic congestion or reduction in levels of traffic safety
which are inconsistent with the classification of the
adjoining road.
...
(v) Any cumulative effect of traffic generation from the activity
in conjunction with traffic generation from other activities
in the
vicinity.
...
[16] Woodlot therefore had to apply to the QLDC for resource consents for
the Woodlot Development. Once an application for a
resource consent is
received, a consent authority has 10 working days to decide whether the
application is to be publicly notified,
or notified to affected parties on a
limited basis.10
[17] Before 1 October 2009, and hence when the first Challenged
Non-notification Decision was made, there was a presumption of
public
notification. Until then s 93(1) of the Resource Management Act 1991 (RMA) had
provided:
93 When public notification of consent applications is
required
(1) A consent authority must notify an application for a resource consent
unless─
(a) the application is for a controlled activity;
or
9 DP, r 7.7.2(vi).
10 Resource Management Act 1991, s 95 [RMA].
(b) the consent authority is satisfied that the adverse effects of the
activity on the environment will be minor.
[18] That is no longer the case. As from 1 October 2009 s 95A of the RMA
has provided:
95A Public notification of consent application at consent authority’s
discretion
(1) A consent authority may, in its discretion, decide whether to publicly
notify an application for a resource consent for an activity.
(2) Despite subsection (1), a consent authority must publicly notify the
application if─
(a) it decides (under section 95D) that the activity will have or is likely
to have adverse effects on the environment that are more
than minor; or
...
[19] Given that the Woodlot Development was a non-complying activity
– albeit by reference to the zone standard height limit
alone – when
making its decision whether to notify Woodlot’s first resource consent
application QLDC was required to,
and did, consider the Woodlot Development as a
whole as a non-complying activity. As relevant, its 27 November 2007
non-notification
decision:
(a) On the height issue, found:
This height intrusion can be absorbed into the existing environment and is
largely an internalised effect. The site forms part of
a gully, and therefore
ground level is lower than some of the surrounding sites, and the height will be
less intrusive than if the
general area was level and flat.
(b) Considered that any risks associated with the non-conforming
earthworks were controlled or mitigated by the terms of
the
proposal.
(c) Concluded the adverse effects of the (slightly) smaller balconies were
less than minor.
[20] On that basis QLDC concluded that notification was not required as regards those issues. RM070741 was based on similar conclusions. Similar conclusions were reached on those matters (height, earthworks, outdoor areas) in the Challenged
Non-notification Decisions. Those matters do not concern Mr Nash, and are
not referred to again.
[21] On the matter of concern to Mr Nash, traffic, the initial 27
November 2007 non-notification decision concluded:
Traffic generation
The proposed development is anticipated to increase the number of vehicle
movements to and from the site and increase the traffic
generated in the
area.
[22] However the adverse effects of this have been considered nil as the
level of the development proposed is anticipated by the
District
Plan.
[23] A similar conclusion was reached as regards building coverage
density:
The subject site is [6400] square meters. The proposal has a site coverage
of approximately 26%, and a site density of 533m2 per unit. This is
well within the permitted allowances for the Low Density zone, therefore the
adverse effects are considered to be
nil.
[24] In other words, QLDC11 concluded that District Plan
allowed for the density of the Woodlot Development, and the associated effects
on traffic, and on that
basis there were no relevant adverse effects to be
considered. Mr Nash does not challenge that decision.
The Challenged Non-notification Decisions
[25] In the first and second Challenged Non-notification Decisions the
possible adverse effects of the Woodlot Development were
assessed by
reference:
(a) first, to the extent of the adverse effects associated with the
Woodlot
Development as previously consented, as part – QLDC reasoned –
of
the “permitted baseline”;
and
11 A number of the decisions challenged in these proceedings were made by delegates of QLDC, including a council-controlled entity, Lakes Environmental Ltd. There is in these proceedings no challenge to any of those delegations and, accordingly, I refer to all decisions as being those of QLDC.
(b) secondly, to the extent of the additional (if any) adverse effects of
the
Woodlot Development as then proposed in terms of: (i) building density/coverage; and
(ii) traffic generation and vehicle movement.
[26] In the third Challenged Non-notification Decision in November 2013,
as regards RM130600, a different approach was taken.
The adverse effects of
the development consented by RM120496 were considered to be already part of the
environment. On that basis,
the adverse effects whose impact were to be
considered were those additional effects “above and beyond those arising
from RM120496”.
[27] QLDC’s approach can be seen from the following brief extracts
from the first and third of those decisions:
First – 3 December 2008
• The development granted under RM070741 and subsequent variation is
considered to form part of the permitted base line and
will be considered in the
assessment of effects, accordingly.
• The effects in terms of building coverage and density have been
previously considered under land use consent RM070741. However,
the internal
layout of the building has been amended such that now there are 14 units instead
of 12 as originally consented under
RM070741. There are no additional adverse
effects over and above what has already been consented.
• Lakes Environmental’s engineer has not raised any other
issues with regard to traffic generation and vehicle movements.
Third – 28 November 2013
• 4.2 FUTURE ENVIRONMENT
The environment which this proposal will be assessed against includes unimplemented resource consent RM120496 that is likely to be implemented. The applicant has undertaken the majority of the required earthworks in accordance with that consent and there is no reason to consider the RM120496 development would not proceed should the current proposal be unsuccessful. The Consent Authority must therefore consider the environment within which this development is proposed to include the currently unimplemented resource consent RM120496. As such only adverse effects that would
arise above and beyond those arising from RM120496 will be considered
below.
• 4.3 ASSESSMENT: EFFECTS ON THE ENVIRONMENT
...
The primary adverse effects arising from the proposed development relate to traffic generation and specifically the effects of the increased traffic on the intersection between Andrews Road and State Highway
6A (SH6A). These are considered to be effects on the environment
(people using the State Highway) and effects on people (the New
Zealand Transport Agency (NZTA) as administrators of the State Highway
and responsible for any required upgrade of the Andrews
Road / SH6A
intersection). The effects on the environment will be discussed here and
effects on people will be discussed later
when effects on persons are being
considered.
The NZTA have provided affected party approval for the development. Therefore
no adverse effects on users of the SH6A will be considered
as the NZTA assessed
effects on the public prior to giving affected party approval.
...
• 5.3 ASSESSMENT: EFFECTS ON PERSONS
...
The NZTA has provided approval for the proposal therefore no effects on that
party will be considered.
In terms of effects on Council roading an assessment was undertaken by
Council’s traffic engineers, MWH, and that report (attached
as appendix 4
of this report) concludes that adverse effects on users of Andrews Road (apart
from the intersection with SH6
discussed earlier) will be less than minor.
This is accepted.
The errors asserted by Mr Nash
[28] As helpfully summarised by Mr Whittington for QLDC, the
essential elements of Mr Nash’s argument are that,
in making the
Challenged Non-notification Decisions:
(a) QLDC erred and acted unlawfully by
(i) failing to apply correctly the “receiving environment”
and “permitted baseline” in its assessment
of the effects of the
various applications;
(ii) failing to conduct its own assessment of traffic effects
beyond NZTA’s affected party approval; and
(iii) failing to base its decisions on adequate information.
(b) QLDC acted unreasonably by failing to consider that there
were special circumstances in terms of s 95(4) of the RMA to justify
notifying the applications.
[29] I now consider the substance of Mr Nash’s application by
reference to each of
those matters in turn.
Illegality – misapplication of permitted baseline and the receiving
environment
[30] Mr Nash’s principal argument is that QLDC wrongly
assessed the significance of the resource consents
which already existed for
the Woodlot Development when it considered the significance of the associated
adverse traffic effects.
That error, he argues, arose because QLDC misapplied
the concepts of the “permitted baseline” and the “receiving
environment” when making those decisions, allowing undesirable
“environmental creep” to occur.
[31] The concepts of permitted baseline and receiving environment
reference the provisions of the RMA under which the Challenged
Non-notification
Decisions were made.
[32] At the time the first of those decisions was made ss 94A and 94B, as
relevant, provided:12
12 Emphasis added.
94A Forming opinion as to whether adverse effects are minor or more
than minor
When forming an opinion, for the purpose of section 93, as to
whether the adverse effects of an activity on the environment will be
minor or more than minor, a consent authority─
(a) may disregard an adverse effect of the activity on the environment if the plan permits an activity with that effect; and
...
94B Forming opinion as to who may be adversely affected
(1) Subsections (2) to (4) apply when a consent authority is forming
an opinion, for the purpose of section 94(1), as
to who may be
adversely affected by the activity.
...
(3) A person—
(a) may be treated as not being adversely affected if, in relation to
the adverse effects of the activity on the person, the
plan permits an activity
with that effect;
...
[33] At the time of the second and third Challenged Non-notification
Decisions, ss 95D and 95E provided to equivalent effect:13
95D Consent authority decides if adverse effects likely to be more
than minor
A consent authority that is deciding, for the purpose of section
95A(2)(a), whether an activity will have or is likely to have adverse effects
on the environment that are more than minor─
...
(b) may disregard an adverse effect of the activity if a rule or
national environmental standard permits an activity with that effect;
...
95E Consent authority decides if person is affected person
(1) A consent authority must decide that a person is an affected
person, in relation to any activity, if the activity’s
adverse effects on
the person are minor or more than minor (but are not less than minor).
(2) The consent authority, in making its
decision,—
13 Emphasis added.
(a) may disregard an adverse effect of the activity on the person if a
rule or national environmental standard permits an activity
with that
effect;
...
[34] Those concepts also reference the provisions in s 104 of the RMA, which
governs the substantive decision as to whether or not
a consent should be
granted.
[35] Prior to the 2009 amendments s 104 provided, again as
relevant:14
104 Consideration of applications
(1) When considering an application for a resource consent and any
submissions received, the consent authority must, subject to
Part 2, have regard
to─
(a) any actual and potential effects on the environment of allowing the
activity; and
(b) any relevant provisions of─
(i) a national policy statement:
(ii) a New Zealand coastal policy statement:
(iii) a regional policy statement or proposed regional policy statement:
(iv) a plan or proposed plan; and
(c) any other matter the consent authority considers relevant and reasonably
necessary to determine the application.
(2) When forming an opinion for the purposes of subsection (1)(a), a
consent authority may disregard an adverse effect of the activity on the
environment if the plan permits an activity with that effect.
Section 104 now, as relevant, provides:
104 Consideration of applications
(1) When considering an application for a resource consent and any
submissions received, the consent authority must, subject to
Part 2, have regard
to─
(a) any actual and potential effects on the environment of allowing
the activity; and
(b) any relevant provisions of─
(i) a national environmental standard: (ii) other regulations:
(iii) a national policy statement:
(iv) a New Zealand coastal policy statement:
(v) a regional policy statement or proposed regional policy statement:
14 Emphasis added.
(vi) a plan or proposed plan; and
(c) any other matter the consent authority considers relevant and
reasonably necessary to determine the application.
(2) When forming an opinion for the purposes of subsection (1)(a), a
consent authority may disregard an adverse effect of the activity on the
environment if a national environmental standard or the plan permits an
activity with that effect.
...
[36] The concept of permitted baseline is reflected in the
“may disregard” provisions of ss 95D(b) and
104(2), and in
the similar provisions of the old ss 94(A)(a) and 104(2). The concept of
the receiving environment is essentially
a reference to “the
environment” as referred to in those provisions.
[37] The concept of the permitted baseline, and the “may
disregard” provisions, have their origins in the Court
of Appeal
decision of Bayley v Manukau City Council.15 In order
to assess Mr Nash’s arguments, I have found it necessary to consider
Bayley, and the various decisions which have followed it, in some
detail.
[38] Bayley involved an appeal from a decision of the High Court
refusing to grant judicial review of a decision made by the Manukau City Council
not to notify a resource consent application. The application was to undertake
a multi-unit terraced housing complex in a business
area. The complex was a
restricted discretionary activity, due to the extent it encroached on the side
yard that was required for
a compliant business use. The Court of Appeal found
that the Council had failed to consider the possibility of consequential effects
arising from the way in which the site layout may have been made possible by the
use of the side yard in a non- complying way.
[39] The Court recognised that, for a restricted discretionary activity,
the words
“activity for which consent is sought” in what was then s 94(2)
did not:16
... extend to an activity which is able to be undertaken without that consent
and, more importantly, is unable to be considered by
the Council. ... Under the
proviso to s 105(1)(6) the authority may refuse consent or impose conditions
only on the basis of those
matters. It would make little sense to require a
consent authority to notify an application because it may involve
15 Bayley v Manukau City Council [1999] 1 NZLR 568 (CA).
16 At 577 lines 33-42.
effects which the authority must then disregard at the hearing of the
application. That would provide false hope for objectors and
be wasteful of
time and money.
[40] But, the Court of Appeal reasoned, the restriction on the
Council’s discretion was expressed in very broad terms.
Under that
restriction the consent authority was obliged by its rules to consider and
assess:17
Whether the site layout ensures a relationship of buildings and other
structures on the site, carparking, access, manoeuvring, and
landscape elements
which is as satisfactory as the relationship envisaged by the yard rule.
Whether the site layout is compatible
with the site development of adjoining
residential, public open space and future development zones.
[41] Moreover it was possible that:18
... by designing a structure intruding into space which the plan requires to
be a yard, an applicant may have been able to utilise
other portions of the
property in a manner which in itself complies with the plan but actually has a
greater impact on the environment
of the neighbourhood because, for example, it
is a more intense use than could have been achieved on the site without the yard
intrusion.
In other words, in this case by taking up part of the yard the
applicant may have gained a consequential advantage
detrimental to the
neighbours and their enjoyment of their properties even by comparison with such
commercial activity as is permissible
as of right.
[42] The Court found that, as a matter of fact, the Council had not
considered those types of consequential effects when making
its non-notification
decision. Accordingly that decision was invalid.
[43] It was in that context that the Court of Appeal
observed:19
Before s 94 authorises the processing of an application for a
resource consent on a non-notified basis the consent authority
must satisfy
itself, first, that the activity for which consent is sought will not have any
adverse effect on the environment which
is a more than minor effect. The
appropriate comparison of the activity for which consent is sought is with what
either is being
lawfully done on the land or could be done there as of
right.
[44] Activities that were “being lawfully done on the land or could
be done there
as of right” came to be known as the “permitted
baseline”.
17 At 578 lines 1-5.
18 At 576 lines 29-37.
19 At 576 lines 1–6.
[45] In Smith Chilcott Ltd v Auckland City Council the Court of
Appeal held that the Bayley permitted baseline approach could be applied
to substantive grant decisions, as well as non-notification
decisions.20
[46] The activities which formed part of the permitted baseline were
qualified by the Court of Appeal in Smith Chilcott so that permitted, but
fanciful, development possibilities were to be
excluded.21
[47] In Arrigato Investments22 the Court of Appeal
considered whether baseline activities extended to activities permitted by
unimplemented consents. In
that context, the Court described the permitted
baseline in the following way:
[29] Thus the permitted baseline in terms of Bayley, as
supplemented by Smith Chilcott Ltd, is the existing environment overlaid
with such relevant activity (not being a fanciful activity) as is permitted by
the plan. Thus
if the activity permitted by the plan will create some adverse
effect on the environment, that adverse effect does not count in the
ss 104 and
105 assessments. It is part of the permitted baseline in the sense that it is
deemed to be already affecting the environment
or, if you like, it is not a
relevant adverse effect. The consequence is that only other or further adverse
effects emanating from
the proposal under consideration are brought to
account.
[48] The Court first reasoned unimplemented consent, by
definition, did not reflect activities which could be undertaken
as of
right23 – and hence did not come within the Bayley
permitted baseline by dint of the decision in Bayley itself.24
The Court went on:
[34] There remains, however, the second issue, whether Bayley
should be extended so as to include unimplemented resource consent
activities within the permitted baseline. Mr Brabant argued that
following the
granting of a resource consent, the holder has an equal right to do what is
allowed as would have been the case had
the plan allowed it. That is so but,
as Mr Burns and Mr Loutit submitted, there is a material difference between what
is allowed
under a plan and what is allowed under a resource consent. The plan
represents a consensus, usually after very extensive community
and regional
involvement, as to what activities should be permitted as of right in the
particular location. There is therefore
good reason for concluding, as was
done in Bayley, that any such permitted activities should be treated as
part of the fabric of the particular environment.
20 Smith Chilcott Ltd v Auckland City Council [2001] NZCA 210; [2001] 3 NZLR 473 at [24].
21 At [26].
22 Arrigato Investments v Auckland Regional Council [2001] NZCA 329; [2002] 1 NZLR 323, [2001] 7 ELRNZ 193.
23 For if they were, no consent would have been required.
24 At [33].
[49] On the particular question of unimplemented consents the Court
reasoned:
[35] Resource consents are capable of being granted on a non-notified as
well as a notified basis. Furthermore, they relate
to activities of differing
kinds. There may be circumstances when it would be appropriate to regard the
activity involved in an
unimplemented resource consent as being part of the
permitted baselines, but equally there may be circumstances in which it would
not be appropriate to do so. For example implementation of an earlier resource
consent may on the one hand be an inevitable
or necessary precursor of
the activity envisaged by the new proposal. On the other hand the unimplemented
consent may be inconsistent
with the new proposal and thus be superseded by it.
We do not think it would be in accordance with the policy and purposes of
the Act for this topic to be the subject of a prescriptive rule one
way or the other. Flexibility should be preserved
so as to allow the consent
authority to exercise its judgment as to what bearing the unimplemented resource
consent should have on
the question of the effects of the instant proposal on
the environment.
[50] The Court of Appeal also commented on the phenomenon of
“environmental creep”, which – as noted – Mr
Nash
asserts has happened here:
[37] We have given careful attention to the submissions made in respect
of what was described as “environmental creep”.
This expression
describes a process whereby having achieved a resource consent for a particular
building or activity, a person may
seek consent for something more and try to
use their existing consent, as yet unimplemented, as the base from which the
effects of
the additional proposal are to be assessed. In physical terms
consent might be obtained for a 10 storey building and then before
any work is
done an application made for 2 extra floors. On the basis posited by Arrigato
[the appellant] effects would be limited
on the second application to the extra
2 floors, rather than to the whole building comprising 12 floors. Mr Burns and
Mr Loutit
expressed concern about the position consent authorities would
be in if the 10 floor structure had become part of the permitted
baseline. Mr
Brabant argued that if such tactics became prevalent, consent authorities could
amend their plans or reject the second
application as going too far.
[38] Reflecting on the competing contentions in this area has reinforced
us in the view that there should be no rigid rule of
law either way. That
conclusion should relieve consent authorities of the anxieties expressed by
counsel while also allowing
applicants for consent to seek a factually
realistic appraisal. What is permitted as of right by a plan is deemed to be
part
of the relevant environment. But, beyond that, assessments of the
relevant environment and relevant effects are essentially
factual matters not to
be overlaid by refinements or rules of law. ...
[51] The enactment in 2003 of the former s 94A(a) and (b) modified and partially codified the effect of the Arrigato decision. That is:
(a) It provided that, as relevant, a consent authority may, rather than
must, regard activities “permitted by the plan”
as part of the
permitted baseline. After Arrigato, that approach had been regarded as
mandatory.
(b) It did not, however, as the Court of Appeal had done in
Arrigato, allow such a discretion as to activities permitted by
unimplemented consents, but rather limited the scope of the permitted baseline
to what is “permitted by the plan”.
[52] Aspects of the new provisions were considered in a number of subsequent High Court and Environment Court cases.25 As a result a degree of confusion arose, including as to the status of effects of activities permitted by non-implemented consents, and the relationship between the permitted baseline (activities whose effects had been “accepted” by the plan) and the environment on which the impact of the other effects of the proposed activity were to be assessed (sometimes described
as the “receiving environment”).
[53] The Court of Appeal considered these issues in Queenstown Lakes District Council v Hawthorn Estate Ltd,26 a case about a consent given by QLDC for a subdivision of 32 residential lots in Queenstown. The proposed subdivision was in an area where there were unimplemented resource consents for significant development. Consent was required as the subdivision was a non-complying activity under the district plan and a discretionary activity under the proposed district plan. The key issue for the Court was whether the Council, when considering whether to grant consent, had been obliged to restrict its consideration of effects to effects on
the environment as the environment existed at the time of the decision, or whether the Council had been right – as it had done – to consider the future state of the
environment as it might be affected as and when those consents were
implemented.
25 Rodney District Council v Eyres Eco-Park Ltd [2006] NZHC 217; [2007] NZRMA 1 (HC); Tairua Marine Ltd v Waikato Regional Council HC Auckland CIV-2005-485-1490, 29 June 2006; O’Connell Construction Ltd v Christchurch City Council [2003] NZRMA 216 (HC); Wilson v Selwyn District Council [2005] NZRMA 76 (HC); Freilich v Tasman District Council [2005] NZRMA
410 (Env C); Queenstown Lakes District Council v Hawthorn Estate Ltd [2006] NZCA 120; [2006] NZRMA 424 (CA).
26 Queenstown Lakes District Council v Hawthorn Estate Ltd, above n 25.
[54] Having reviewed the definition of the word “environment”
in, and the overall structure of, the RMA, the Court
of Appeal concluded that
the Council had been right to take a “futuristic” approach. In
doing so it said:27
[57] In summary, all of the provisions of the [RMA] to which we have
referred lead to the conclusion that when considering the
actual and potential
effects on the environment of allowing an activity, it is permissible, and would
often be desirable or even
necessary, for the consent authority to consider the
future state of the environment, on which such effects would occur.
...
[84] ... In our view, the word “environment” embraces the
future state of the environment as it might be modified
by the utilisation of
rights to carry out permitted activity under a district plan. It also includes
the environment as it might
be modified by the subsequent implementation of
resource consents which have been granted at the time a particular application
is
considered, where it appears likely that those resource consents will be
implemented.
[55] It did not, however, extend to include the effects of resource
consents that might in the future be granted. The Council’s
approach had
earlier been upheld in both the Environment Court and the High Court, on the
basis however that such future effects
could be considered as part of the
permitted baseline. In that context, the Court of Appeal in Hawthorn
observed:
[27] One of the questions that has been raised on the appeal concerns
the adequacy of the Environment Court’s consideration
of the application
of what has come to be known as the “permitted baseline”. Although
that expression was used by Fogarty
J in [74], we doubt that he was using the
term in the sense that it is normally used, that is with reference to
developments that
might lawfully occur on the site subject to the resource
consent application itself. Rather, Fogarty J appears to have used the
expression to refer to the likely developments that would take place beyond the
boundary of the subject site, utilising existing
resource consents.
Nothing turns on the label that the Judge used to refer to lawfully authorised
environmental change beyond
the subject site. However, it would be
prudent to avoid the confusion that might result from using the term other than
in
its normal sense, addressed in Bayley v Manukau City Council, Smith
Chilcott Ltd v Auckland City Council and Arrigato Investments Ltd v
Auckland Regional Council. As we will emphasise later in this judgment the
“permitted baseline” is simply an analytical tool that excludes from
consideration certain effects of developments on the site that is subject to a
resource consent application. It is not to be applied
for the purpose of
ascertaining the future state of the environment beyond the
site.
27 At [57].
[56] The Court later said:28
It is as well to remember what the “permitted baseline” concept
is designed to achieve. In essence, its purpose is to
isolate, and make
irrelevant, the effects of activities on the environment that are permitted by a
district plan, or have already
been consented to. Such effects cannot then be
taken into account when assessing the effects of a particular resource consent
application.
[57] What is clear from the earlier passage is that, where at [65] the
Court refers to “effects of activities on the environment”,
it is
referring to the effects from activities that occur or may occur on the
“subject site”. What is also to be remembered
is that, by the time
of the Court of Appeal’s decision in Hawthorn, Parliament had
– through the way in which s 104 had been enacted – confirmed that,
for want of better words, what can
be described as the “permitted
baseline” approach was discretionary, and not mandatory.
[58] These issues were further considered by the Court of Appeal in
Far North District Council v Te Runanga-a-iwi o Ngāti Kahu,29
a case challenging non-notified consents to subdivide land in respect of
which a land use consent had already been granted to build
residential
units.
[59] In the High Court, the relevant issue was whether the Environment
Court was correct in law when it held that it was obliged to include the
effects of the consented residential units on the future environment. The
Environment Court had found that it was.
It said:30
[98] We consider that it is clear from Hawthorn that we are
required to make a factual determination as to whether or not it is likely
that effect will be given to an unimplemented resource consent [the land use
consent]. If we determine that it is likely then the
environment against which
we assess the effects of a proposal will include the environment as it might be
modified by implementation
of the unimplemented resource consent in question.
We do not consider that we have a discretion to ignore that factual finding as
to the future state of the environment.
[60] The High Court was of the view that that conclusion was an error of
law, reasoning that because the adverse effects of the
consented residential
units were
28 At [65].
29 Far North District Council v Te Runanga-a-iwi o Ngāti Kahu [2013] NZCA 221.
30 Te Runanga-a-iwi o Ngāti Kahu v Far North District Council [2010] NZEnvC 372.
within the “subject site”, they were part of the permitted
baseline. As such, the High Court found the Environment Court
had – as
confirmed by s 104D(1) – a discretion whether to consider those effects or
not.31 But it was not required to do so. That distinction
mattered because the Environment Court had recorded that if it did not have to
include the adverse effects of the residential units in the permitted baseline,
it would have concluded that the proposal would have
been contrary to the
relevant statutory objectives and policies, and would therefore have allowed the
appeal.
[61] The Court of Appeal rejected that approach. In doing so it adopted
the reasoning of Arrigato set out at [47] above. As the Court had done
in Hawthorn, it emphasised the exclusionary nature of the permitted
baseline test and confirmed that the statutory purpose of the “may
disregard” formulation was to vest a consent authority with a discretion
to ignore the permitted baseline where previously
it had been a mandatory
consideration.32 It did so in the following terms:
[88] We do not accept this distinction. The qualification noted by
this Court in Hawthorn was in the context of pointing out the limitation
of the permitted baseline test to the site itself where the appellant had
attempted
to give it a more expansive application. What is decisive is the
exclusionary nature of the permitted baseline test. In essence,
as this Court
observed in Arrigato:
[29] Thus the permitted baseline ... is the existing environment
overlaid with such relevant activity ... as is permitted
by the plan. Thus, if
the activity permitted by the plan will create some adverse effect on the
environment, that adverse effect
does not count in the ss 104 and 105
assessments. It is part of the permitted baseline in the sense that it is
deemed to be already
affecting the environment or, if you like, it is not a
relevant adverse effect. The consequence is that only other or further
adverse effects emanating from the proposal under consideration are brought
to account.
[62] Having emphasised the discretionary power as regards whether or not
effects permitted by the plan are taken into account
or not it went on to
observe:
[91] In the RMA context, the environment and the permitted baseline
concepts are critically different. Both are discrete statutory
considerations.
The environment refers to a state of affairs which a consent authority must
determine and take into account when
assessing the effects of allowing an
activity; by contrast, the permitted baseline provides the authority with an
optional means
of measuring – or more appropriately excluding –
adverse effects of that activity which would otherwise be inherent in
the
proposal.
31 Te Runanga-a-iwi o Ngāti Kahu v Far North District Council (2011) 16 ELRNZ 708 at [105].
32 Far North District Council v Te Runanga-a-iwi o Ngāti Kahu [2013] NZCA 221 at [88]–[90].
[63] The High Court has, in a number of recent decisions,
emphasised the importance of the overall approach of the
Court of Appeal in
Hawthorn, and the need to place the observation in [84] of that decision
– relating to the significance of resource consents that might
be granted
in the future – in context.33 In declining leave to appeal
one of those decisions, the Court of Appeal has recently
said:34
[16] As noted earlier, the High Court dismissed the applicant’s
appeal from the Environment Court. The High Court Judge,
Fogarty J, warned
against treating the observation of this Court in Hawthorn at [84] as if
it were legislation, and highlighted the need to consider the whole of
the decision in Hawthorn, rather than just the summary contained at [84].
He determined that the Environment Court had concluded that a coal mining
licence
was not equivalent to a permitted activity under a District Plan. We
agree that that is the case. He also concluded that the Environment
Court’s alternative analysis based on Hawthorn turned on its
finding of fact that the possibility of Solid Energy using its coal mining
licence at the Sullivan Block was speculative.
He found, correctly in our
view, that that was a finding of fact that was not amenable to appeal in a
jurisdiction in which the
appellate court is limited to revisiting only matters
of law. He found no error by the Environment Court in its application for
Hawthorn, and determined that its findings of fact were not amenable to
appeal. (footnotes omitted)
[64] In my view the rule is that what is permitted as of right by a plan may be considered by a consent authority to be part of the permitted baseline. By the same token, a consent authority might decide not to adopt that approach: it might do so, for example – to adopt the phraseology from Smith Chilcott – where developments were permitted but, in the reality of the situation, fanciful. Beyond that, the assessment of the relevant environment and relevant effects are essentially factual matters, not to be overlaid by refinements or rules of law. That factual assessment, as acknowledged in the Far North Council case, is one that is required as a matter of law to be undertaken taking account of the future state of the environment, including as affected by other resource consents that the consent authority is satisfied are likely
to be put into effect.35 That assessment is, of course, to be
undertaken applying the
effects-based approach fundamental to the
RMA.
33 For example, Royal Forest and Bird Society of New Zealand Inc v Buller District Council [2013] NZHC 1324, [2013] NZRMA 273 at [20]- [23]; Queenstown Central Ltd v Queenstown Lakes District Council [2013] NZHC 817.
34 Royal Forest and Bird Protection Society of New Zealand Inc v Buller District Council & Anor
[2013] NZCA 496 (footnotes omitted).
35 Far North District Council v Te Runanga-a-iwi o Ngāti Kahu [2013] NZCA 221 at [94].
[65] Moreover, when that exercise is undertaken, there may not
be a lot of difference between considering a particular
adverse effect as
part of the permitted baseline or as part of the receiving environment. If, as
a part of the permitted baseline,
the adverse effect is disregarded when
assessing the effects of a proposed activity on the receiving environment,
it is difficult
to see how, in practice, a different result would arise
if that adverse effect were considered already to be part of the receiving
environment. After all, taking that approach would again simply mean that that
effect was not one that had to be counted as impacting
“on the
environment”.
[66] The Court of Appeal in Arrigato recognised that
possibility:36
There are two possible ways of looking at the issue. The first is to ask
what effects qualify as adverse and the second is to inquire
what comprises the
relevant environment. Adverse effects already inherent in an unimplemented
resource consent can be argued to be
irrelevant because they are effects which
the holder of the consent already has a right to impose on the environment. On
the approach
which inquires what comprises the environment, Arrigato’s
proposition is that the environment is already in substance subject
to any
adverse effects inherent in the granting of a resource consent. In practical
terms it is unlikely to matter which of these
approaches are taken. They are
both apt to lead to the same conclusion.
[67] Using the Far North factual situation as an example,
and accepting the emphasis in that case on the centrality of the plan, not
resource consents,
to the permitted baseline approach, nevertheless if the
Council and the Environment Court had considered the effects of the
unimplemented
land use consent as part of the permitted baseline, then the
effects of the dwellings would have been ignored just as they were by
reason of
the fact that that consent was considered as part of the receiving environment.
An alternative way of expressing that
proposition is that if a consent
authority does not exercise its discretion to ignore permitted base
line effects, it
may well nevertheless have to consider the environment as
having been impacted by those effects. Were it not to do so, it could
fail to
make its decision by reference to the appropriate factual context.
[68] Against that background I consider Mr Nash’s illegality
arguments.
36 Arrigato Investments & Ors v Auckland RC & Others, above n 22, at [26].
[69] The essential point here is that, to a large extent, the Woodlot
Development is a permitted activity. Possible adverse effects
on traffic of the
increased density of dwelling units in the Low Density Residential Zone that
might arise when compliant, and
hence permitted, residential
developments are built have already been determined acceptable in the
process of setting
the District Plan in place. The purpose of district plans
is to assist territorial authorities to carry out their functions in
order to
achieve the purpose of the RMA. The preparation of a district plan therefore
requires consideration and application of
the Part 2 purposes and principles of
the RMA.
[70] Because the Woodlot Development was from the outset both non-complying (height) and restricted discretionary (outdoor areas and earthworks), resource consents were necessary. In assessing whether to notify those consents, what I think the Council was required to do was to consider whether, as regards the otherwise complying aspects of the proposal, the matters which meant resource consent was required might have consequentially increased any adverse effects of the proposal. That is the approach taken in Bayley to the significance of the intrusion into the side yard. It was also the approach taken by the Court of Appeal in the slightly different context of overlapping consents in Body Corporate 97010 v Auckland City
Council.37
[71] There is no suggestion here that those matters had or were likely to
have any flow-on effects on the issue that is of concern
to Mr Nash, namely site
density and associated traffic generation.
[72] Putting aside the question of the significance of previously granted
consents, for each of RM070741, RM081340 and RM110460
the density of the
proposed development met the relevant zone standard. On that basis, I do not
see how there can be a challenge
to QLDC’s decision that possible traffic
effects did not mean that the applications needed to be publicly
notified.
[73] For Mr Nash, Mr Todd submitted that, when considering the question
of notification and consent, the Council should not only
consider the matters
that led to
37 Body Corporate 97010 v Auckland City Council [2000] NZCA 168; [2000] NZRMA 529.
consent being required, but all the effects of the activity, to determine whether they were not more than minor. Mr Todd referred me to the discussion in Bayley at pages
576 and 577, where the decision of Cooke J in Locke v Avon Motor Lodge Limited and that of Salmon J in Arley v North Shore City Council are discussed, and to the decision of the High Court in McPherson v Napier City Council. In effect, and as I understood it, Mr Todd was arguing that Locke was, as so discussed by the Court of Appeal, authority under the Resource Management Act for the same proposition that it had been authority for under the old Town and Country Planning Act. So, in this instance, QLDC was required to determine whether the traffic effects of the Woodlot proposal as a whole were “not more than minor”, even though they were – as the Council realised – anticipated and accepted by the District Plan. I am not persuaded by that argument. In Bayley the Court of Appeal acknowledged that the approach taken in Locke may be inappropriate under the RMA albeit, I acknowledge, in
assessing restricted discretionary activity.38 More
significantly, I am guided by the
conclusion of the Court of Appeal in Arrigato, referred to at [50]
above, that:
What is permitted as of right by a plan is deemed39 to be part of
the relevant environment.40 But, beyond that, assessments of the
relevant environment and relevant effects are essentially factual matters not to
be overlaid
by refinements or rules of law.
[74] Here, the fact is that the District Plan anticipated and accepted the traffic density consequences of residential developments up to a certain density, as measured by the area of the site divided by the number of proposed units. Moreover, in making that provision the District Plan can be seen as reflecting an anticipation that that level of development is likely to occur. Those are essentially factual assessments and fact conclusions. It is that type of assessment that, in my view, Arrigato and Far North recognised a consent authority was required to make. As the
authors of Environmental and Resource Management Law
observe:41
[I]f a proposed non-complying activity is likely to generate the same amount
of traffic as would a permitted activity, then the effects
of that traffic
generation may be disregarded in assessing whether the effects of the proposed
activity are more than minor.
38 Bayley v Manukau City Council, above n 15, at 577 lines 45-46.
39 Now, “may be deemed by a consent authority”.
40 That is, somewhat confusingly, within the permitted baseline.
[75] For essentially
similar reasons, I do not think it can be argued – as it was for Mr Nash
– that the Council did
not have adequate information when it made those
decisions.
[76] The situation would be different, including for the non-challenged
initial consent RM070741, if those non-complying and restricted
discretionary
aspects of the Woodlot Development could reasonably have been seen as possibly
causing consequential effects on density
and associated traffic generation. If
that were the case, then those matters should have been considered in the
context of RM070741.
In that context, I think QLDC’s conclusion that
the Woodlot Development was “likely to be implemented” is
one that
was open to it, in terms of its factual assessment of the receiving environment,
if not, as a matter of law, as regards
its discretionary assessment of the
permitted baseline.
[77] The real issue here is whether traffic effects were properly
considered when that was no longer the case, as occurred in
late 2013 when the
number of units in the Woodlot Development increased from 14 to 20.
[78] In that context, and as recognised by QLDC, the increased density of
the
2013 Woodlot Development was capable – by definition – of generating traffic effects that were greater than those anticipated by the District Plan. It was for that very reason it had become a discretionary activity not, significantly I note, a restricted discretionary activity. On that basis, QLDC was required to assess whether the adverse traffic effects of the proposed development – at the point the
non-notification decision was made – were not “more than
minor”.42 Rule 7.7.2(vi)
of the District Plan explicitly confirms that.
[79] In assessing the legality of the third Challenged Non-notification
Decision, and on the basis of the Far North decision, I cannot accept Mr
Nash’s argument that
42 I have not considered in this decision whether the provisions which now give consent authorities discretion whether to publicly notify an application have any material effect on the way a non-notification decision may be made. The case was argued on the basis that the relevant legislative changes had had no material effects. The Court of Appeal in Coro Mainstreet v Thames District Council [2013] NZCA 665; [2013] NZRMA 73 has questioned that assumption. I have taken the point no further.
the Council was not correct when it regarded “the environment” as
including the then unimplemented RM120496.
[80] But, as I said, the real issue is whether those possible adverse
traffic effects were properly, that is in this context lawfully,
considered.
[81] QLDC had three sources of information when it made its
assessment:
(a) the traffic generation assessment report prepared for
Woodlot by
Bartlett Consulting;
(b) the similar report prepared for QLDC by MWH New Zealand
Ltd;
and
(c) the “affected persons’ approval” letter from
the New Zealand
Transport Agency (NZTA).
[82] Bartlett Consulting concluded that the traffic effects of the 20
apartment development would, by comparison with the previous
14 unit
development, have less than minor increased traffic effects or, in fact, reduced
traffic effects. It is not clear, however,
that QLDC relied on the Bartlett
Consulting reasoning, as that reasoning was doubted by its own advisers
MWH.
[83] MWH Ltd, the Council’s advisors, took a different approach.
They said:
While the calculation by Bartlett Consulting has merit, the traffic
generation in the approved resource consent is the correct base
for comparison
of the proposal.
The previously consented base traffic generation is 112 [vehicles per day],
comprised of Block One having 12 apartments and Block
Two 2 apartments and each
generating eight vehicles per apartment per day.43
43 MWH had earlier commented:
Traffic generation for the permitted Block One activities are calculated with reference to the NZ Transport Agency research report 453 appendix C, which is appropriate. The Land Use Activity selected as Residential Dwelling (Outer Suburban), which has a generation per unit of
8.2 vehicles per unit per day, and is consistent with clause 3.3.2.1 of the QLDC amendments to the NZS440:2004 that requires assessments of residential traffic loading to be based on eight vehicles per apartment per day and with the previously approved resource consents.
I did not receive any submissions or affidavit evidence explaining these aspects of the information on which QLDC based its decisions.
[84] Comparing consent RM120496 with proposed RM130600, MWH concluded:
It is proposed to modify Block Two by replacing the two apartments each
containing seven bedrooms with the eight apartments each containing
two
bedrooms. Traffic generation has been calculated as per Block One, which is
appropriate, and results with 164 vpd for Block One
and Two combined.
Comparing the base traffic (112 vpd) to the proposal (164 vpd) shows a 43%
increase in daily traffic is expected to be generated by
the total proposal, and
for Block Two the increases from 16 vpd to 64 vpd, an increase of 300%. The peak
hour traffic volume will
increase from 12.6 vph to 18 vph, which is an increase
of 43%.
While the percentage increases are high, the absolute increase in traffic volume over the day and peak hour are unlikely to be noticed by road users. For example, the peak hour traffic increases by 5.4 vph, and assuming an
80/20 out/in trip distribution this calculates as an additional 4.3 vph out of
Andrews Road, or one vehicle every 14 minutes.
Based on the above analysis, the increased traffic generated by the proposal
is considered to be less than minor.
[85] In terms of the effect on the Andrews Road/SH5A intersection, MWH
observed:
Effect on Andrews Road and the Frankton Road intersection
Based on the traffic generation evaluation above there will be a small
traffic volume increase from the proposal that will use Andrews
Road and the
Frankton Road intersection.
The existing movement deficiencies are unchanged, and are summarised
below:
1. Restricted tracking paths for all vehicle types in and out of Andrews
Road.
2. Left turn out of Andrews Road appears to cross onto the Frankton Road
central flush median, with potential for conflict with
right turn in
vehicles.
3. It appears a vehicle cannot turn into Andrews Road if a vehicle is
waiting to exit Andrews Road.
With increased traffic volumes on Andrews Road as a result of currently
permitted activities, the frequency of potential conflicts
will increase and
therefore the likelihood of a crash increases.
The intersection requires improvements to cater for the expected traffic movements anticipated by the current land zoning of all Andrews Road properties.
The impacts on Andrews Road users as a result of this proposal, from the
intersection to cul-de-sac head, are considered to be minor.
The existing
carriageway appears to be 5.0m to 5.5m wide (measured from Google earth) with
parking banned on one side and no footpaths.
This is not compliant with the
QLDC District Plan (DP), however the increase in traffic (including estimating
traffic generation
from all properties on Andrews Road) does not change the
required traffic provisions with reference to Table 3.1 – Road Design
Standards – Urban of the QLDC amendments to the 4404:2004.
It is expected that the NZTA will be contacted regarding the proposal for
their comment as an effected party.
[86] NZTA’s consent letter was to the point. It read:
Woodlot properties Limited – Residential Units – SH 6A –
Frankton
Thank you for forwarding details of the above-mentioned land use proposal for our consideration and comment. We understand the applicant proposes to increase the number of residential units in an approved apartment block (Block 2) at Andrews Road, Queenstown. The proposal seeks to alter the internal configuration from the approved
2 apartments containing 7 bedrooms to 8 apartments containing 2
bedrooms.
We are satisfied that the proposed activity is unlikely to have an adverse
effect on the safety and functionality of the State highway
adjacent to the
subject site. Accordingly, please find enclosed the NZTA’s written
approval for your information and further
action.
[87] As can be seen, both MWH and NZTA compared the effects associated
with RM130600 with those associated with RM120496.
That is, they
assessed the adverse effects associated with the increment, or increase, of
adverse effects of RM130600’s
20 units as opposed to RM120496’s 14
units. The issue is, therefore, whether that approach was lawfully correct or
whether
QLDC was required to consider whether the overall effect of the
increased traffic associated with the Woodlot Development on the
environment was
“more than minor”. That is the proposition that, in a variety of
ways, Mr Nash advances.
[88] There is, I accept, some support for that proposition in the wording
of the
District Plan, where relevant assessment matters are specified.
Section
7.7.2(vi)(a)(v) refers to the adverse effects of “Any cumulative effect of traffic generation from the activity in conjunction with traffic generation from other activities in the vicinity”. Section 7.7.2(vi)(c) refers to “Any adverse effects of the proximity or bulk of the buildings, in terms of visual dominance by buildings of the
outlook from adjoining sites and buildings, which is out of character with
the local environment”. That “assessment
matter” can be
compared with that specified in Section 7.7.2(vi)(h): “The extent to which
the increased building coverage would have any adverse effect on
adjoining properties in terms of dominance by buildings, loss of privacy, access
to sunlight and daylight and loss of opportunities or views”. Although the
relevant provisions of the District Plan were not
addressed during oral
argument, and Mr Nash’s written submissions did not refer to them at all,
it can clearly be argued that
“any adverse effects” means what it
says, as confirmed by the reference to “increased” building
coverage.
[89] In my view, however, and by reference not only to the concepts of permitted baseline and environment, as developed by the Court of Appeal subsequent to the Bayley decision, but also to the overall scheme of the RMA, I think the approach taken by QLDC was a legally correct one. As a matter of principle, district plans, agreed for a district following the processes of public consultation called for by the RMA, and fitting within the hierarchy of planning documents found in the RMA as most recently discussed by the Supreme Court in Environmental Defence Society Inc
v New Zealand King Salmon Company Ltd,44 reflect
a given community’s
assessment of how to give effect to the purposes and principles of the RMA.
Thus, s 9(3) of the RMA provides:
(3) No person may use land in a manner that contravenes a district rule
unless the use—
(a) is expressly allowed by a resource consent; or
(b) is allowed by section 10; or
(c) is an activity allowed by section 10A.
[90] Where, following that process, various uses and activities are provided for as complying activities those uses and activities have been accepted as being “appropriate”. That collective decision has been reached pursuant to a public process in which the Part 2 purposes and principles will have been applied. If the approach called for by Mr Nash was required, it would – in effect – call that assessment into question. That is, the increased traffic generated by a complying
activity may well have an effect on the environment that is “more
than minor”. But
that effect, or the reasonable
possibility of it, has been agreed to. But if those (accepted) effects have to
be included in the
“adverse effects” by reference to which the
“not more than minor” determination is to be made, that acceptance
would have to be revisited, or at least notice given on the basis that it could
be. But, as Tipping J explained in Arrigato:45
Thus, if the activity permitted by the plan will create some adverse effect
on the environment, that adverse effect does not count
in the ss 104 and 105
assessment. It is part of the permitted baseline in the sense that it is deemed
to be already affecting the
environment or, if you like, it is not a relevant
adverse effect. The consequence is that only other or further adverse effects
emanating from the proposal under consideration are brought to
account.
[91] Furthermore, with reference to the various matters
specified in Section 7.7.2(vi) of the District
Plan, the adverse
effects of the Woodlot Development, in terms of the minimum site density
for a complying development,
have been determined to be not incompatible with
the levels acceptable in a low density residential environment, not out of
character
with the local environment and not incompatible with the scale of
other buildings in the surrounding area.
[92] The Judge-made concept of permitted baseline activities and the “may disregard” provisions of the RMA are confirmation, in my view, of that basic principle. Therefore when – as here – an activity is discretionary on the basis, among other things, that it allows for a density of development greater than that permitted as of right, the adverse effects to be assessed are those which arise consequentially because of and to the extent of that “greater” density. Specifically, the District Plan represents a decision as to an acceptable level of development within the Queenstown area. That acceptable level of development is reflected in the
District Plan in the minimum site density (450m2) for
complying residential
development. The discretionary status of comprehensive residential development reflects the fact that, beyond that a decision of acceptability has not been made. In my view, therefore, what QLDC had to assess was, as it did, whether the increase in density associated with the proposal could have adverse effects that, by comparison to the adverse effects associated with a complying development, were not more than
minor.
45 Arrigato Investments Ors v Auckland Regional Council and Ors, above n 22, at [29].
[93] The factual matters at issue here are quite different to the
Arrigato example of a consented 10 storey building, to which it is
proposed to add two storeys. In that situation what has to be assessed
is
not the incremental two storeys, but the difference between the height of
the development the plan would have allowed (if
any) as of right. Moreover,
that difference also has to be assessed in the context of the specific terms of
the relevant district
plan. A height limit may be set to expressly balance the
need for development against the need to preserve existing amenity values.
By
definition almost, in that context, any higher development than that permitted
as of right could have a more than minor effect.
In my view, however, the
density rules at issue here are not of that type. The increased traffic effects
caused by complying residential
developments have not been calibrated in that
way. Rather, they represent an acceptable level of traffic density for the
local environment.
The “more than minor” decision in this context
is, in my view, properly made therefore by reference to the incremental
effect
on traffic that the density of a comprehensive residential development as a
discretionary activity will have.
[94] I conclude, therefore, the approach taken by the Council was one
lawfully available to it.
[95] There is, I recognise, a proper concern with the phenomenon of “environmental creep”. But I think that concern is addressed by the Court of Appeal in Arrigato. What is permitted by law (i.e. the plan, as subsequently emphasised in Far North) may, under the Judge made rubric of the “permitted baseline” approach, as now legislated by s 104(5), be disregarded by a consent authority when making non-notification or consent decisions. Beyond that, what is required are factual assessments made against the background of the relevant District Plan and a proper, futuristic, assessment of the environment. In that context, it is one thing to start with a proposed development that will, as regards a particular matter, have effects that the plan regards as acceptable. It is another to obtain a consent for an activity which has effects which are not anticipated by the District Plan, and then to apply for a further consent which adds to those unanticipated effects. In my view, the flexibility provided by the Arrigato approach as confirmed by the Court of Appeal in the Far North case, enables that type of concern to be addressed.
[96] An example of the application of that approach is described by the
Court of
Appeal in Hawthorn in the following terms:
[79] The Environment Court dealt with the implications of the existing
resource consents in the present case in a manner that
was consistent with that
approach. It will always be a question of fact as to whether or not an existing
resource consent is going
to be implemented. If it appeared that a developer
was simply seeking successively more intensive resource consents for the same
site there would inevitably come a point when a particular proposal was properly
to be viewed as replacing previous proposals. That
would have the consequence
that all of the adverse effects of the latter proposal should be taken into
account, with no “discount”
given for consents previously granted.
We are not persuaded that the prospect of “creep” should
lead to the
conclusion that the consequences of the subsequent implementation of
existing resource consents cannot be considered as part of the
future
environment.
[97] Again, I think this emphasises the essentially factual nature of the
inquiry called for. The effect of the decision
in Far North
is to confirm the non- discretionary nature of that
inquiry.46
[98] I also consider QLDC did have adequate information in terms of the MWH report and the NZTA consent letter. Mr Nash argued, on the basis of the Court of Appeal decision in Royal Forest and Bird Protection Society of New Zealand Inc v Kapiti Coast District Council, that QLDC should not have regarded the NZTA consent as “signing off” on the adverse impacts on traffic at the Andrews Road/
SH6A intersection.47 In Royal Forest and Bird the Court
of Appeal, reflecting the
approach it had taken in Arrigato in commenting on the risk of environmental creep, observed that ss 94A(c) and 104(3)(b) required a purposive – necessarily nuanced –
approach, including as to the significance of affected party consents
given to a
46 The Supreme Court has granted leave to appeal from the
decision of the Court of Appeal in the Far North decision (Te
Rūnanga- Ᾱ-Iwi O Ngāti Kahu v Far North District Council
[2013] NZSC 134). One of the questions to be determined is:
In relation to the subdivision consent application, whether or not the
unimplemented land use consent should have been taken into
account, when
determining the application for the subdivision consent, as part of: (i) The
“environment” under s 104(1)
of the Resource Management Act 1991; or
(ii) The permitted baseline under s 104(2).
The issues discussed in this judgment about the relationship of the permitted baseline, the receiving environment and environmental creep may therefore be considered by the Supreme Court in the relatively near future.
47 Royal Forest and Bird Protection Society of New Zealand Inc v Kapiti Coast District Council
[2009] NZCA 73, [2009] NZRMA 302.
particular proposal.48 The Court did not hold, as Mr Nash
submitted, that an affected party approval from the administrator of a
particular environment
was not a substitute for a consent authority’s
own assessment of effects on that environment. Rather, it held that, “a
particular piece of land may be of such importance in terms of Part 2 that it
would be inappropriate to treat the current owner or
administrator of it as the
sole arbiter of the effects on that piece of land”.49 There
is a considerable difference between the two propositions.
[99] Mr Nash further submitted that the State Highway network fell within
the scope of matters protected by Part 2 of the RMA,
in that it was fundamental
to the enablement of people and communities to provide for their social and
economic wellbeing,50 and for the efficient use of resources and
energy.51 QLDC therefore needed to make its own assessment of the
effects of RM130600 on SH6A. It also needed to consider the effects on the
Andrews Road intersection as they impacted on itself.
[100] Those rather conclusory submissions were not supported by any
analysis of the role of NZTA under the Land Transport Management
Act 2003, and
the relationship of that act to the RMA.
[101] For QLDC, the submission was that the position of the Department of
Conservation in the Royal Forest and Bird case was quite different to
that of NZTA in this case. Here the matter involved a technical issue on which
NZTA plainly (again a
conclusionary proposition) has unique expertise (traffic
generation on its own highways). Those considerations, it was submitted,
distinguish this case from Royal Forest and Bird.
[102] Both the Land Transport Management Act and the Government Roading Powers Act 1989 establish what are, on the basis of my brief review, complex legislative schemes. In that context, and unwilling to embark unguided on what is
plainly a complicated statutory interpretation, I have nevertheless
briefly considered
48 At [26].
49 At [27].
50 RMA, s 5(2).
51 RMA, s 7(b)–(ba).
the provisions of the Land Transport Management Act, and NZTA’s statutory role. I note that it is the function of NZTA “to manage the State Highway system, including planning, funding, design, supervision, construction, and maintenance and operations, in accordance with this Act and the Government Roading Powers Act
1989”.52
[103] In these circumstances, I am not prepared to conclude that QLDC
acted unlawfully when it concluded that NZTA’s affected
persons’
consent meant it could be satisfied that the adverse effects of the Woodlot
Development of 20 residential units on
the Andrews Road/SH5 intersection were
not more than minor.
Unreasonableness
[104] Mr Nash argues that QLDC acted unreasonably by failing to give
active consideration to whether the applications for RM120496
and RM130600
should have been notified on account of there being special circumstances under
s 95A(4) of the RMA. That section provides:
Despite subsection (3), a consent authority may publically notify an
application if it decides that special circumstances exist in
relation to the
application.
[105] On each occasion, QLDC decided that special circumstances did not
exist. Mr Nash submits that QLDC merely stated that conclusion,
and did not
actively engage itself in the necessary consideration.
[106] He argued particularly that the history leading to RM130600 was that the developer applied for resource consent for a succession of gradually more intensive developments on the same site relying on the previous consents, though none had been implemented. I do not accept that submission as made. There was not, in my view, a material “intensification” up until the 20 unit RM130600 proposal. Then, and as I have analysed above, QLDC acted lawfully when it considered adverse effects. It therefore follows that I do not consider it acted unreasonably in deciding
not to notify under s 95A(4).
52 Land Transport Management Act 2003, s 95(1)(c).
Delay
[107] The other argument that received some attention before me was whether, if Mr Nash succeeded in establishing that QLDC had acted unlawfully, relief should nevertheless be denied because of the delay in bringing these proceedings. I do not need to consider that argument now. However, I note that if Mr Nash had so succeeded, I do not consider that delay would have been a reason to grant him relief. The 20 unit proposal arose relatively late in the overall history. My reading of the affidavits suggests that, once that proposal was on the table and consented, Mr Nash
– and I take it others – raised the concerns which led to these
proceedings. In many ways, the overall delay that is
the successive iterations
of the proposal and the period of time that elapsed from the first consent
granted in 2007 has been of
Woodlot’s making. In that context, any delay
that may have been associated with the issue of these proceedings is not, in
my
view, material.
Result
[108] I therefore decline Mr Nash’s application for judicial
review of the
Challenged Non-notification Decisions.
[109] I did not receive submissions on costs. However, I see no reason why
costs should not follow the event on a 2B basis. If
the parties cannot agree,
brief submissions may be filed no later than four weeks from the date of this
judgment.
[110] I make a final comment. As MWH acknowledged, there is a sound basis for Mr Nash’s concerns – the implications of the Woodlot Development aside – with the safety of the Andrews Road/SH6A intersection. To the extent that Mr Nash attempted, through these proceedings, to have that matter addressed immediately in the context of consents applied for for the Woodlot Development, he has not
succeeded. But that does not mean that matter will not have to be considered by
QLDC, and NZTA, in a timely fashion in terms of their relevant
statutory obligations.
Clifford J
Solicitors:
GTODD Law, Queenstown for the plaintiff. Meredith Connell, Auckland for the first defendant.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/1041.html