Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 21 August 2015
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV 2014-485-11253 [2015] NZHC 1991
UNDER
|
the Resource Management Act 1991
|
IN THE MATTER
|
of an appeal under s 149V(1) of the Act against the Report and Decision of
the Board of Inquiry into the Basin Bridge Proposal dated
29 August 2014
|
BETWEEN
|
NEW ZEALAND TRANSPORT AGENCY
Appellant
|
AND
|
ARCHITECTURAL CENTRE INCORPORATED & ORS
Parties to the appeal under s 302(1)
of the Act
|
Hearing:
|
20-24, 27-31 July 2015
|
Counsel:
|
M Casey QC, A F D Cameron, F Wedde and A Cameron for
Appellant
K M Anderson and E Manohar for Wellington City Council
(Interested Party)
P Milne for Architectural Centre Incorporated (Interested Party) T Bennion
for Mount Victoria Historical Society
(Interested Party)
M S R Palmer QC for Save the Basin Campaign (Interested Party) and Mount
Victoria Residents Association (Interested Party)
|
Judgment:
|
21 August 2015
|
JUDGMENT OF BROWN
J
NZ TRANSPORT AGENCY v ARCHITECTURAL CENTRE INC & ORS [2015] NZHC 1991 [21 August 2015]
Table of Contents
Paragraph No.
Overview [1] Scope of appeal [7] “A question of law” [12] Section 171 [27]
Section 171(1)(c)
[30]
Original form of s 171(1)
[32]
1993 Amendment
[33]
2003 Amendment
[41] Sections 171(1) and 104(1) compared
[45] The relevance of King Salmon
[48]
Sequence of consideration of the Issues [50]
The meaning of “having particular regard to” in s 171
[56] “have regard to”
[59] “having particular regard to”
[64] Did the Board adopt the correct approach?
[69]
The effect of the phrase “subject to Part 2” in s 171
[83] The relocation of the phrase within s 171(1)
[86] The implications of King Salmon
[99]
Consideration of alternative options – an overview
[119] Chronology
[123] The Board’s general approach
[125]
Subissue 1A: Relating the measure of adequacy to the
adversity of effects [129]
Q 4(a): Does s 171(1)(b) of the Act require a more careful consideration of alternatives where there are
more significant adverse effects of allowing the requirement?
[136]
Subissue 1B: The requirement to consider all non-suppositious
options with potentially less adverse effects [145]
Q 7(a): Does s 171(1)(b) require the requiring authority to fully evaluate every non-suppositious alternative with
potentially reduced environmental effects? [152]
Q 7(b)(i): Is the case one in which the true and only reasonable conclusion contradicts the determination
that BRREO was a non-suppositious option?
[160]
Q 7(b)(ii): Is the case one in which the true and only reasonable conclusion contradicts the determination that Option X was an option with potentially less
adverse effects?
[165]
Q 7(b)(iii): Is the case one in which true and only reasonable conclusion contradicts the determination
that a long tunnel option was a non-suppositious option?
[172]
Subissue 1C: Interpreting adequacy as requiring transparency
and replicability
[175] Context
[175] The transparency and replicability of the option evaluation
[179] The issue
[180]
Subissue 1D: Requiring the assessment methodology to incorporate
Part 2 weightings [188] Subissue 1E: Conflation of s 171(1)(b) and (c) considerations [201]
Subissue 1F: Finding that adequate consideration was not given to
alternatives following the Government’s decision to underground
Buckle Street [208] Context [208] Issues [209]
Q 19(a) [recast]: Is this a case in which the true and
only reasonable conclusion contradicts the determination that the review of alternatives carried out in July 2012
was cursory?
[211]
Q 19(b): In order for the consideration of alternatives to be relevant must the consideration be completed before
the application documentation is well advanced?
[215]
Q 19(d) [recast]: Is this a case in which the true and only reasonable conclusion contradicts the determination that adequate consideration was not given to alternatives
following the Government’s decision?
[219]
Q 19(c): Is a requiring authority required to prepare a
“feasible option type assessment” when the environment
changes? Or is it entitled to rely on earlier work? [222] Subissue 1G: Adequacy of the consideration [225]
Issue 2: Inquiring as to the outcome rather than the process
of considering alternatives [232]
Issue 3: Misapplication of s 171(1) [240]
Issue 4: Incorrect approach to assessment of enabling benefits [245]
A stand-alone project [245] Effects and benefits – terminology and meaning [249] The Board’s Decision [254] The parties’ positions [259]
31(a): Is a project’s enabling benefit an effect in terms of s 3 that can and should be taken into account under
s 171(1) and/or s 5? [261]
31(b): Where a project’s enabling benefits are consistent with a programme of infrastructure development that is recognised in relevant documents under s 171(1)(a) and (d), should those enabling benefits be given considerable
weight as an effect of the project under s 171(1) and/or s
5? [267]
31(c): In order to be taken into account, must a project’s
enabling benefits be unique to that project, guaranteed and
go ahead, and able to be quantified? [268]
31(d): Does the definition of the future environment constrain the ability of a decision-maker to consider the enabling
benefits of a project? [270]
31(e): In order for the positive effects of a future development to be taken into account must the approvals for that development be sought at the same time as
(or in advance of) the project? [278]
31(f): Is it consistent with sustainable management (in terms of s 5) to approve an infrastructure project because it is necessary to facilitate future developments; and does it make a difference if the project is primarily necessary to facilitate those future infrastructure
developments? [283]
31(g): In the alternative, given its conclusion that the Proposal was necessary primarily to enable future roading projects, did the Board err in law by failing to
consider conditions to address this concern? [288] Issue 5: Assessment of transportation benefits – an overview [289]
Subissue 5A: Standard of proof required to demonstrate
transportation benefits [293]
Q 36(a): Is a higher standard of proof required to demonstrate the transportation benefits of a project where it will have adverse effects that are more
than minimal? [297]
Q 36(b): If the Board applied the wrong standard of proof, were the Board’s findings regarding the transportation benefits of the Proposal ones that the Board could
reasonably have come to on the evidence? [302]
Subissue 5B: Assessment of immediate transportation benefits [303]
Q 39(a): Did the Board fail to take into account a relevant matter in failing to have regard to the immediate
transportation benefits of the Proposal? [307]
The meaning of Q 39(b)? [311]
Subissue 5C: Requiring the Proposal to demonstrate benefits
that go beyond the requiring authority’s objections [313]
Mode shift [314]
The issue of a long-term solution [322] Issues 6, 7 and 8: Questions of law relevant to heritage and amenity [329] The refinement of the questions of law [329]
Q 45A: When assessing the heritage or amenity effects
on the environment under s 171(1), must the decision-maker
do so ‘through the lens’ of the relevant plans under
s 171(1)(a) and, if relevant, s 171(1)(d) documents?
That is, should the effects be assessed ‘through the lens’
of the recognition and protection provided by those plans
and/or documents? [333] The planning framework [334] The Board’s decision [337] The parties’ contentions [343] Analysis [351]
Q 45B: Further, should the Board have assessed the effects having particular regard to its finding at [1230] that the works were reasonably necessary to achieve
the objectives under s 171(1)(c)? [356]
Q 45C: When there is no ‘invalidity, incomplete coverage or uncertainty of meaning’ in the relevant plans
under s 171(1)(a), is it appropriate for a decision-maker to assess effects against s 6(f) (for historic heritage) and
s 7(c) (for amenity values)? [361]
Q 45D: Did the Board correctly apply the definition
of ‘historic heritage’ under s 2? [367]
The parties’ contentions [369]
Analysis [374]
Q 45E: What is the correct approach to the application
of the test of ‘inappropriateness’ in s 6(f) [should the Court consider resort to Part 2 of the RMA was available to the
Board in the circumstances of this case]? [384]
Issue 8: Failure to consider options within the scope of the application to address amenity and heritage related effects to
the Gateway Building [393] Summary [399] Disposition [400]
Overview
[1] On 17 June 2013 the appellant (NZTA) lodged a Notice of
Requirement (NoR) and applications for incidental resource
consents for what is
commonly referred to as the Basin Bridge Project (Project). The Project was to
construct, operate and maintain
a two lane one-way bridge on the north side of
the Basin Reserve in Wellington City as part of State Highway 1 between Paterson
Street
and Taranaki Street.
[2] The key aspects of the Project were summarised in NZTA’s
submissions in
this way:
(a) The Basin Reserve is a key transport node within the Wellington
network. [NZTA’s] assessment is that the Project
area is subject to
congestion, delay and journey time variability, particularly during peak periods
and weekends, and also has a
high accident rate. These problems are predicted
to get worse in the future as travel demand grows in the area for all transport
modes, and changes in land use occur in the immediate vicinity (Adelaide Road)
and the wider Wellington area (Wellington airport
and the
southern/eastern suburbs).
(b) The Project provides essential infrastructure by grade separating
the westbound traffic movements at the Basin
Reserve. Grade
separation would be provided by way of a bridge (the Basin Bridge), located in
the north of the Basin Reserve.
The Basin Bridge would carry westbound traffic
from the Mt Victoria tunnel to Buckle Street/Arras Tunnel. This would remove
that
traffic from the roads around the Basin Reserve, which frees up capacity on
those roads for public transport improvements and north-south
local
traffic.
(c) The Project also includes a dedicated pedestrian/cycling path and
enables improvements for those transportation modes
around the Basin
Reserve by reducing conflict between those modes and vehicular
traffic.
[3] On 7 July 2013 the Minister for the Environment referred the Proposal to a Board of Inquiry appointed under s 149J of the Resource Management Act 1991 (RMA) to hear and determine the merits of the application. The Minister’s reasons for directing the Proposal to a Board of Inquiry were as follows:
National significance
I consider the matters are a proposal of national significance
because:
• The proposal is adjacent to and partially within the
Basin Reserve Historic Area and international test cricket
ground; in the
vicinity of other historic places including the former Home of Compassion
Crèche, the former Mount Cook Police
Station, Government House and the
former National Art Gallery and Dominion Museum; and is adjacent to the National
War Memorial Park
(Pukeahu). The proposal is likely to affect recreational,
memorial, and heritage values associated with this area of national significance
(including associated structures, features and places) which contribute to New
Zealand’s national identity.
• The proposal is likely to result in significant and irreversible
changes to the urban environment around the Basin Reserve.
In particular, the
proposed elevating of westbound traffic on SH1 [State Highway 1] is likely to
compete with the open space aspect
that exists for the current ground level
layout of the Basin Reserve roundabout.
• The proposal has aroused widespread public interest regarding its
actual or likely effects on the environment, including
on heritage values and
experiential values associated with the Basin Reserve. This includes on-going
media and public attention
on the options for traffic improvement around the
Basin Reserve, including local, national and international coverage.
• The proposal is intended to reduce journey time and
variability for people and freight, thereby facilitating
economic
development. The proposal is also likely to provide for public
transport, walking and cycling opportunities;
reduce congestion and accident
rates in the area; and improve emergency access to the Wellington Regional
Hospital. If realised,
these benefits will assist the Crown in
fulfilling its public health, welfare, security, and safety functions.
• The proposal relates to a network utility operation (road) that,
although physically contained within the boundaries
of Wellington City,
as a section of the Wellington Northern Corridor Road of National Significance
will affect and extend to
more than one district and region in its
entirety.
[4] Section 149P(1) provides that the Board of Inquiry must have regard
to the Minister’s reasons for making a direction
to refer the Proposal to
the Board for decision.
[5] The scope of the hearing was described by the Board in its Final
Report in this way:
[79] The hearing took place in Wellington. It commenced on
3 February 2014 and finished on 4 June 2014. The hearing took 72 sitting days over four months. The length of the hearing was occasioned by the
volume of material and the strength and perseverance of the opposition to the
Project. No stone was left unturned. We make no apology
for the length of the
hearing. It was necessary to give the Applicant and the Parties the
opportunity to fully present their cases.
[6] Having released a Draft Decision on 22 July 2014 in accordance with s 149Q(1) of the RMA, the Board released its Final Report and Decision on
29 August 2014 (Decision). The essence of the determination of the majority
of the
Board1 is captured in the final few paragraphs:
[1324] In the final outcome, we are required to evaluate the significant
adverse effects taken together with the significance of
the national and
regional need for and benefit of the Project. In carrying out this evaluation,
we are conscious of the dicta of
the Privy Council in McGuire that
relevantly Sections 6 and 7 are strong directions to be borne in mind, and if an
alternative is available that is reasonably
acceptable, though not ideal, it
would accord with the spirit of the legislation to prefer that.
[1325] This tension between the anticipated benefits and the anticipated
adverse effects is the crux of the issues that have been
debated before us. It
reflects the tensions in Part 2. It reflects the tensions inherent in the
statutory documents.
[1326] We are conscious of our findings as to the manner in which the
Project would be consistent with the integrated planning instruments
and
documents relating to transportation. We are also conscious of our findings on
adverse effects, which are contrary to the themes
in the planning instruments on
heritage, landscape, visual amenity, open space and amenity. As the planners
agreed, the statutory
instruments give no guidance on how this conflict should
be resolved.
[1327] While the RMA does not require that an (sic) NoR must set out to
achieve the best quality outcome, in our view, there
are compelling
landscape, amenity and heritage reasons why this Project should not be
confirmed. The Basin Bridge would be around
for over 100 years. It would thus
have enduring, and significant permanent adverse effects on this
sensitive urban landscape
and the surrounding streets. It would have adverse
effects on the important symbol of Government House and the other
historical
and cultural values of the area.
[1328] Government House, like the Basin Reserve, has the important
quality of rarity (there is only one such main residence
of the Crown in New
Zealand). The sensitivity of the area derives not just from Government House
and the Basin Reserve but the overall
national significance of the whole area
from Taranaki Street to Government House.
[1329] The adverse effects are occasioned by the dominance of the Basin
Bridge, resulting from its bulk and scale in relation to
the present
environment, and the future environment, which does not anticipate such
a
substantial elevated structure in this
significant open space. The carefully crafted design of the Basin Bridge,
together with the
meticulously crafted landscape and amenity measures, while
offering some offset, do not mitigate the bulk and scale of the Basin
Bridge,
exacerbated by the Northern Gateway Building.
[1330] The ultimate criterion is whether confirming the NoR for the Project
would promote the sustainable management purpose of the
RMA. On that criterion,
we judge that, even with its transportation and economic benefits, confirming
the NoR would not promote
the sustainable management purpose described in
Section 5. It follows that the requirement should be cancelled. The resource
consents,
being ancillary to the requirement, are declined.
Scope of appeal
[7] A right of appeal to the High Court against the Board’s
decision is provided
in s 149V “but only on a question of law”.
[8] NZTA filed an appeal on 24 September 2014 and the following
parties (the respondents) gave notice under s 301 of
the RMA of their wish to
appear on the appeal:
(a) the Architectural Centre Inc (TAC);
(b) Mt Victoria Historical Society Inc (MVHS);
(c) Mt Victoria Residents’ Association Inc (MVRA);
(d) Save the Basin Campaign Inc (STBC); and
(e) Wellington City Council (WCC).
[9] As noted in a Minute of MacKenzie J dated 12 November 2014, some of
the respondents contended that aspects of the appeal
were not focused on
questions of law but related to factual conclusions or the weight which the
Board had placed on certain evidence.
Although NZTA did not accept those
criticisms, it elected to review its notice of appeal in the light of the
matters raised. MacKenzie
J directed:
[9] ... The appellant should be given an opportunity to consider the issues raised by the respondents and, if thought appropriate, to amend the notice of appeal. If the parties are then still at odds over whether the issues
raise (sic) in the appeal do all involve questions of law, a hearing on that
question might assist in focusing the issues on appeal,
in a way which could
potentially save considerable time at the hearing itself.
Timetable directions were made for the filing of an amended notice of appeal
and an interlocutory application challenging the scope
of the notice of
appeal.
[10] On 27 November 2014 NZTA filed an amended notice of appeal together
with a memorandum summarising the changes in tabular
form. Although the
respondents continued to have concerns about the appropriateness of what
they described as the “extensive
factual related grounds”, they
advised that they would not be pursuing an interlocutory application because of
their limited
resources as local community groups.
[11] The scope of the appeal is conveyed in the first paragraph of the
amended notice of appeal which divides the appeal into
eight issues:
Issue 1: Misapplication of s 171(1)(b) of the Act (adequacy of consideration
given to alternatives);
Issue 2: Inquiring as to the outcome rather than the process of considering
alternatives;
Issue 3: Misapplication of s 171(1) of the Act (requirement to have
particular regard to matters in paragraphs (a) to (d));
Issue 4: Incorrect approach to the assessment of enabling
benefits;
Issue 5: Incorrect approach to the assessment of transportation
benefits;
Issue 6: Failure to have particular regard to s 171(1)(a) and (d) matters
in assessing heritage and amenity effects;
Issue 7: Incorrect approach to the assessment of the environment; and
Issue 8: Failure to consider options within the scope of the application to
address amenity and heritage related effects of the
Northern Gateway
Building.
Issue 1 is divided into seven subissues and Issue 5 is divided into three
subissues. In total 34 questions of law were specified
in the amended notice of
appeal. However each specified question of law was preceded by alleged
“errors of law” and
followed by “grounds of appeal”. As
a consequence of cross-references to those other parts, the number of questions
of law expanded.
“A question of law”
[12] As noted above, the right of appeal provided by s 149V is
“only on a question of law”. Hence this appeal is
not a general
appeal. It is not the role of the High Court to conduct a rehearing of the
application to the Board or to undertake
an “on the merits”
consideration of whether the Board’s conclusion was correct. Nor is it
the role of the High
Court to determine whether or not the Project would be the
best outcome to address the congestion problem at the Basin Reserve.
[13] To adapt the observation of Blanchard J in Vodafone New Zealand
Ltd v
Telecom New Zealand Ltd the questions for this Court are the more
limited ones of:2
(a) has the Board misinterpreted what was required of it by the RMA and in
particular under s 171?
(b) if not, are the Board’s conclusions nevertheless so misconceived
that they are unlawful conclusions?
[14] The nature of that more limited role was explained by the Supreme
Court in
Bryson v Three Foot Six Ltd:3
[24] Appealable questions of law may nevertheless arise from the
reasoning of the Court on the way to its ultimate conclusion.
If the Court
were, for example, to misinterpret the requirements of s 6 – to
misdirect
3 Bryson v Three Foot Six Ltd [2005] NZSC 34, [2005] 3 NZLR 721.
itself on the section, which incorporates the legal concept of contract of
service – that would certainly be an error of law
which could be corrected
on appeal, either by the Court of Appeal or by this Court ...
[25] An appeal cannot, however, be said to be on a question of law where
the fact-finding Court has merely applied law which
it has correctly understood
to the facts of an individual case. It is for the Court to weigh the relevant
facts in the light of
the applicable law. Provided that the Court has not
overlooked any relevant matter or taken account of some matter which is
irrelevant
to the proper application of the law, the conclusion is a matter for
the fact-finding Court, unless it is clearly insupportable.
[26] An ultimate conclusion of a fact-finding body can sometimes be so
insupportable – so clearly untenable – as
to amount to an error of
law: proper application of the law requires a different answer. That will be
the position only in the rare
case in which there has been, in the well-known
words of Lord Radcliffe in Edwards v Bairstow, a state of affairs
“in which there is no evidence to support the determination” or
“one in which the evidence
is inconsistent with and contradictory of the
determination” or “one in which the true and only reasonable
conclusion
contradicts the determination”. Lord Radcliffe preferred the
last of these three phrases but he said that each propounded
the same test
...
[27] It must be emphasised that an intending appellant seeking to assert
that there was no evidence to support a finding of the
Employment Court or that,
to use Lord Radcliffe’s preferred phrase, “the true and only
reasonable conclusion contradicts
the determination”, faces a very high
hurdle. It is important that appellate Judges keep this
firmly
in mind. Lord Donaldson MR has pointed out in Piggott Brothers
& Co Ltd v Jackson the danger that an appellate Court can very easily
persuade itself that, as it would certainly not have reached the same
conclusion,
the tribunal which did so was certainly wrong:
“It does not matter whether, with whatever degree of certainty, the
appellate court considers that it would have reached a different
conclusion.
What matters is whether the decision under appeal was a permissible option. To
answer that question in the negative
in the context of employment law, the
appeal tribunal will almost always have to be able to identify a finding of fact
which was
unsupported by any evidence or a clear self-misdirection in law
by the Industrial Tribunal. If it cannot do this, it should re-examine with the
greatest
care its preliminary conclusion that the decision under appeal was not
a permissible option ...”
[28] It should also be understood that an error concerning a particular fact which is only one element in an overall factual finding, where there is support for that overall finding in other portions of the evidence, cannot be said to give rise to a finding on “no evidence”. It could nonetheless lead or contribute to an outcome which is insupportable.
[15] In Vodafone, after reference to Bryson, Blanchard J
elaborated on the point with particular reference to the nature of the
interpretative problem:4
[54] The nature of the interpretative problem in the present
circumstances and the caution which must be exercised before it
can be said that
an interpretation is in error, or before it can be said that a statutory
provision has been misapplied, is well
illustrated in the judgment of Lord
Mustill, speaking for the House of Lords in R v Monopolies and
Mergers Commission, ex parte South Yorkshire Transport Ltd. What was in
issue was much less complicated than “net cost” in the present case.
It was the construction of the words
“a substantial part of the United
Kingdom” in statutory criteria applying to the investigation of
mergers of
transport services. Lord Mustill drew attention to the
“protean nature” of the word “substantial”, ranging
from “not trifling” to “nearly complete”. He
cautioned against taking an inherently imprecise word
and “by redefining
it thrusting on it a spurious degree of precision”. Accordingly, he
concluded that the area referred
to as “a substantial part” must
only be “of such dimensions as to make it worthy of consideration for the
purposes
of the Act”. Applying that test (the criterion) to the facts
involved asking, first, whether the Monopolies Commission had
misdirected
itself, and, second, whether its decision could be overturned on the
facts.
[55] His Lordship said that it was quite clear that the Commission had
reached an appreciation of “substantial” which
was “broadly
correct”. Speaking generally about how a question of the nature
of the second question should
be approached, his Lordship said:
Once the criterion for a judgment has been properly understood, the fact that
it was formerly part of a range of possible criteria
from which it was difficult
to choose and on which opinions might legitimately differ becomes a matter of
history. The judgment
now proceeds unequivocally on the basis of the criterion
as ascertained. So far, no room for controversy. But this clear-cut approach
cannot be applied to every case, for the criterion so established may itself be
so imprecise that different decision-makers, each
acting rationally, might reach
differing conclusions when applying it to the facts of a given case. In such a
case the court is
entitled to substitute its own opinion for that of the
person to whom the decision has been entrusted only if the decision
is so
aberrant that it cannot be classed as rational: Edwards v Bairstow
[1955] UKHL 3; [1956] AC 14.
Lord Mustill said that South Yorkshire was such a case:
Even after eliminating inappropriate senses of “substantial” one
is still left with a meaning broad enough to call for
the exercise of judgment
rather than an exact quantitative measurement. Approaching the matter in
this light I am quite satisfied
that there is no ground for interference by
the court, since the conclusion at which the commission arrived was well
within
the permissible field of judgment.
4 Vodafone New Zealand Ltd v Telecom New Zealand Ltd, above n 2.
[56] The issue about “net cost” involves an imprecise
criterion where “different decision-makers, each acting
rationally, might
reach differing conclusions when applying it to the facts of a given
case”.
[57] Some guidance is also to be obtained from this Court’s
decision in Unison Networks Ltd v Commerce Commission. That case was
about a statutory regime for controlling electricity line companies. The
Commission’s task was to set thresholds
for declarations of control. It
differs from the present case because it involved the use of a broadly expressed
power designed
to achieve economic objectives, rather than, as here, the
calculation of an amount of net cost. But it was alleged in Unison that
the Commission had misconstrued the requirements of Part 4A of the Commerce Act
1986 and applied the wrong legal test when exercising
its power. As to that,
this Court said that the statute contemplated that the Commission, as a
specialist body, would exercise
judgment in constructing the thresholds. That
requirement, the Court said, could have been lawfully tackled in one of two
ways.
Both approaches were within the terms of the provisions in the relevant
subpart of Part 4A. The Commission chose one of them and
that was lawful.
Importantly, it can be added that if the Commission had chosen the other,
it too would have been lawful.
[58] So there are two stages. First, whether the Commission has
misinterpreted the language of the statute. This in part turns
on its
appreciation of the function of the word “unavoidable”. And,
secondly, whether, if its interpretation was correct,
it has nonetheless
exercised its judgment about what was “net cost” in a way that
contradicts the true and only reasonable
conclusion available on the facts and
has thereby committed an error of law in terms of Edwards v
Bairstow.
[16] Several of the questions of law in the amended notice of appeal
utilise the formulation whether the Board made findings to
which “it could
reasonably have come on the evidence”.5
[17] I recognise that in identifying the circumstances in which it is permissible to interfere with a tribunal’s decision a number of High Court judgments have included the formula “a conclusion [the tribunal] could not reasonably have come to”.6
However I consider that there is significant potential for confusion when such a formulation is reframed without the inclusion of a negative with the consequence that the question becomes: is the conclusion one to which a tribunal could reasonably
have come on the evidence?
5 For example, the questions of law listed as 4(b), 7(b)(i)–(iii), 19(a) and (d), 22 and 36(b).
6 Countdown Properties (Northlands) Ltd v Dunedin City Council [1994] NZHC 67; [1994] NZRMA 145 (HC); Ayrburn Farms Estate Ltd v Queenstown Lakes District Council [2012] NZHC 735, [2013] NZRMA 126 at [34].
[18] The potential for confusion is compounded when the ground of appeal
is expressed as was ground 5(d) in the amended notice
of appeal:
... the finding that sufficiently careful consideration had not been given to
alternatives was not a reasonable finding on the evidence.
In similar vein in NZTA’s written reply it was contended
that:
A question of law can arise where a decision-maker has reached a finding
without any reasonable evidential foundation.
[19] It is useful, I suggest, to recall why Lord Radcliffe
preferred his third description in Edwards v Bairstow, namely one
in which the true and only reasonable conclusion contradicts the
determination:7
... Rightly understood, each phrase propounds the same test. For my part, I
prefer the last of the three, since I think that it is
rather misleading to
speak of there being no evidence to support a conclusion when in cases such as
these many of the facts are likely
to be neutral in themselves, and only to take
their colour from the combination of circumstances in which they are found to
occur.
[20] In my view paraphrasing the established tests by reference
to “not a reasonable finding on the evidence”
or “without
any reasonable evidential foundation” does not advance the analysis and
has the potential to extend the inquiry
beyond the proper boundary of what
constitutes a question of law.
[21] In the context of an appeal against the exercise of a discretion (which the present appeal is not) it has long been recognised that on the same evidence two different minds might reach widely different decisions without either being appealable.8 The same point has been made employing the word “reasonably”:9
The reason for the limited role of the Court of Appeal in custody cases is
not that appeals in such cases are subject to any special
rules, but that there
are often two or more possible decisions, any one of which might reasonably be
thought to be the best, and
any one of which therefore a judge may make without
being held to be wrong.
7 Edwards v Bairstow [1955] UKHL 3; [1956] AC 14 (HL) at 36.
8 Bellenden v Satterthwaite [1948] 1 All ER 343 (CA) at 345.
9 G v G [1985] 2 All ER 225 (HL) at 228.
[22] However in the third of Lord Radcliffe’s descriptions in
Edwards v Bairstow where “reasonable” appears, it is quite
clear that only one possible conclusion was in contemplation as being
reasonable:
one in which the true and only reasonable conclusion contradicts the
determination.
[23] Consequently, in the interests of clarity, when addressing those
questions of law in NZTA’s amended notice of appeal
which adopt the
“could reasonably have come to on the evidence” formula, I
propose to reframe the question
to align precisely with Lord
Radcliffe’s third description.
[24] From time to time there was reference in the course of NZTA’s submissions to another formula, namely a conclusion “where there is no reliable, probative evidence to support the determination”. Authority for that formula as demonstrating an error of law was said to be found in Chorus Ltd v Commerce Commission.10
Kόs J there remarked:
[177] Thirdly, I find the Commission did not fail to determine what
inferences could reliably be drawn from the benchmark data about
the likely cost
of providing the UBA service in New Zealand. This was very much a tertiary
argument to the two primary arguments.
Had the Commission had reason to believe
that the benchmark evidence was not reliable, probative evidence or that the
proposed
IPP outcome, based on the benchmark evidence and allowing for
consideration of s 18, was irrational and likely to produce an
outcome
substantially removed from the likely ISLRIC found under the FPP, the Commission
would have had a duty to inquire further.
But those were not the circumstances
here. The benchmark evidence was reliable and probative. The IPP outcome was
not evidently
irrational, however unpalatable it may have been to Chorus. The
mechanism to correct the IPP price lay not in further protracted
analysis to
produce a more perfect IPP price. It lay in the statutory mechanism, under s
42, to obtain a full pricing review using
the FPP.
[25] On appeal the Court of Appeal11 endorsed the High Court’s finding that there was no reason to believe that the benchmark evidence that the Commission obtained through its questionnaire was not reliable, probative evidence.12 However I do not
consider that the Court of Appeal’s judgment is to be read as
extending the grounds
10 Chorus Ltd v Commerce Commission [2014] NZHC 690 at [154] and [177].
11 Chorus Ltd v Commerce Commission [2014] NZCA 440. References omitted.
12 At [121].
upon which a judgment may be challenged as wrong in law. Indeed it is
apparent that the Court of Appeal was reiterating the traditional
approach.
[26] The introductory paragraphs bear repeating. Having noted that the
appeal was not a general appeal against the merits of
the Commission’s
determination and that Chorus did not challenge the Commission’s
interpretation of any of the relevant
statutory provisions, the Court
said:
[109] Instead Chorus challenges the Commission’s determination on
the basis that the proper application of the law required
a different answer.
Chorus does this by alleging, in the first five questions of law, that the
Commission made factual errors and
thereby erred in law.
[110] It is well-established, however, that to succeed on the basis of
allegations of this nature Chorus must show that the Commission
has exercised
its judgment about the application of the IPP:
... in a way that contradicts the true and only reasonable conclusion
available on the facts and has thereby committed an error of
law in terms of
Edwards v Bairstow.
[111] This is a high hurdle for Chorus to surmount. It is
well-established that unless the Commission’s application of the
statutory
provisions is factually “unsupportable” it will not have erred in
law. It is for the Commission, as a specialist
body, to exercise judgment in
carrying out the requisite “benchmarking” exercise and in weighing
up the relevant facts
in that context. It will therefore having erred only if
there is no evidence to support the factual findings it made in reaching
its
determination.
[112] In the absence of a right of general appeal, it is not the role of
the Court in an appeal on a question of law to undertake
a broad reappraisal of
the Commission’s factual findings or the exercise of its
evaluative judgments. Care should
also be taken to avoid a technical and
overly semantic analysis of the Commission’s determination in an endeavour
to create
a question of law. In making factual findings it is for
the Commission, and not the Court, to decide what weight should
be given to the
relevant evidence and what inferences, if any, should be drawn from the
evidence. An inference must be logically
drawn from proven facts and not be
mere speculation or guesswork. At the same time, as counsel for the Commission
acknowledged,
if the Commission has made a factual error that makes its
application of the statutory provisions “unsupportable” it
will have
erred in law.
Section 171
[27] The Board was required to consider the NoR under s 149P(4) which provides:
(4) A board of inquiry considering a matter that is a notice
of requirement for a designation or to alter a designation—
(a) must have regard to the matters set out in section 171(1) and
comply with section 171(1A) as if it were a territorial authority;
and
(b) may—
(i) cancel the requirement; or
(ii) confirm the requirement; or
(iii) confirm the requirement, but modify it or impose conditions on it as
the board thinks fit; and
(c) may waive the requirement for an outline plan to be
submitted under section 176A.
[28] Consequently the Board was required to make its decision on the NoR by
applying s 171(1) which provides:
(1) When considering a requirement and any submissions received, a
territorial authority must, subject to Part 2, consider
the effects on the
environment of allowing the requirement, having particular regard
to—
(a) any relevant provisions of—
(i) a national policy statement:
(ii) a New Zealand coastal policy statement:
(iii) a regional policy statement or proposed regional policy
statement:
(iv) a plan or proposed plan; and
(b) whether adequate consideration has been given to alternative
sites, routes, or methods of undertaking the work if—
(i) the requiring authority does not have an interest in the land sufficient
for undertaking the work; or
(ii) it is likely that the work will have a significant adverse
effect on the environment; and
(c) whether the work and designation are reasonably necessary for
achieving the objectives of the requiring authority for which
the designation is
sought; and
(d) any other matter the territorial authority considers reasonably necessary in order to make a recommendation on the requirement.
[29] Issues relating to the interpretation of s 171(1) comprised a
significant part of the appeal. In this portion of the judgment
I briefly
traverse the legislative history of s 171 together with some relevant
authorities. In the course of doing so I identify
a number of the primary
interpretation issues in contest. However it is convenient first to draw
attention to s 171(1)(c), relating
as it does to the objectives of a
requirement.
Section 171(1)(c)
[30] NZTA’s objectives for the Project
were:13
Objective 1: To improve the resilience, efficiency and reliability of
the State network:
(i) By providing relief from congestion on SH1 between
Paterson Street and Tory Street;
(ii) By improving the safety for traffic and persons using this part of the
SH1 corridor; and
(iii) By increasing the capacity of the SH1 corridor between
Paterson Street and Tory Street.
Objective 2: To support regional economic growth and
productivity:
(i) By contributing to the enhanced movement of people and freight through
Wellington City; and
(ii) By, in particular, improving access to Wellington’s CBD
employment centres, airport and hospital.
Objective 3: To support mobility and modal choices within Wellington
City:
(i) By providing opportunities for improved public transport, cycling and
walking; and
(ii) By not constraining opportunities for future transport
developments.
Objective 4: To facilitate improvement to the local road transport
network in Wellington City in the vicinity of the Basin Reserve.
[31] The Board found that the works were reasonably necessary to achieve those objectives.14 The Board also recorded that there was no real dispute that the NoR
(i.e. designation) was reasonably necessary for achieving the
objectives.15
13 Final Decision, at [1225].
14 At [1230].
Original form of s 171(1)
[32] Section 171 as originally enacted in 1991 included Part 2 of the RMA
as one of five matters to which a territorial authority
was required to have
particular regard:
171 Recommendation by territorial authority–
(1) When considering a requirement made under section 168,
a territorial authority shall have regard to the matters
set out in the notice
given under section 168 (together with any further information
supplied under section 169), and
all submissions, and shall also have particular
regard to–
(a) Whether the designation is reasonably necessary for
achieving the objectives of the public work or project
or work for which the
designation is sought; and
(b) Whether adequate consideration has been given to
alternative sites, routes, or methods of achieving the public
work or project or
work; and
(c) Whether the nature of the public work or project or work means
that it would be unreasonable to expect the requiring authority
to use an
alternative site, route, or method; and
(d) All relevant provisions of national policy statements,
New Zealand coastal policy statements, regional
policy statements, regional
plans, and district plans; and
(e) Part II.
Section 104 concerning resource consent applications and s 191
concerning requirements for heritage orders had a similar structure.
1993 Amendment
[33] The reference to Part 2 was relocated in 199316 when the
words “Subject to Part II” were placed at the commencement of
the subsection. An equivalent amendment
was made to both ss 104 and
191.
[34] The 1993 Amendment also introduced s 168A providing for the public notification of requirements. Under s 168A(3) a territorial authority was to have
regard to the matters set out in s 171.
15 At [1218] –[1219].
16 Resource Management Amendment Act 1993, s 87.
[35] The speech of the Minister of the Environment on the second reading of the bill explained the motivation for the amendments. Having noted that the RMA seeks to provide certainty to all parties and that the law must provide a clear framework for the courts and others to work with, the Hon Rob Storey said:17
The Bill, therefore, addresses those sections of the Resource Management Act
in which at present there is a lack of clarity. There
are some who believe that
the Act should be left untouched until case law demonstrates that,
because of ambiguous wording,
Parliament’s intent has not been exactly
converted into the law.
If Parliament intends a particular policy direction, I think that direction
has to be clearly expressed. To do otherwise would be
a dereliction of the
trust placed in us as members of Parliament. It is one thing to use language
that allows a flexibility of outcomes,
when Parliament probably knows what it
intends as the result; it is quite another matter to have language that allows a
variety of
outcomes, when there is meant to be only one.
Sorting out the ambiguities in a legal setting also puts a very large cost on
everybody – citizens, local government, central
government, and
potentially on the environment itself. I think that the House would want to do
better than that, and therefore it
has to remove the necessary ambiguities and
costs.
[36] Specifically in relation to references within the RMA to Part 2, the
Minister said:
As I said, the Bill makes a number of technical amendments and I certainly do
not intend to go through all of them. Part II of the
Resource Management Act
sets out the purpose of the Act. The current references in the Act to Part II
have been in danger of being
interpreted as downgrading the status of Part II.
Amendments in the Bill restore Part II to its proper overarching
position.
[37] The significance of the “subject to” drafting method had been the subject of direct consideration some four years earlier in Environmental Defence Society Inc v Mangonui County Council.18 Section 3 of the Town and Country Planning Act 1977, the predecessor of the RMA, related to matters of national importance which were in particular to be recognised and provided for in the implementation and administration of district schemes. Section 36, which related to the contents of
district schemes, included the phrase “subject to section
3”.
17 (17 June 1993) 535 NZPD 15920.
18 Environmental Defence Society Inc v Mangonui County Council [1989] NZCA 17; [1989] 3 NZLR 257 (CA)
at 260.
[38] With reference to the significance of the inclusion of that phrase
Cooke P
said:
The decision of the Tribunal now in question contains no discussion of the
relationship between s 3 and the other sections, but Chilwell
J observes in his
judgment that the Tribunal has consistently held that the change in
wording making certain sections subject
to s 3 does no more than make explicit
what was previously implicit and that the Waimea decision applies to the
present Act. The High Court Judge also adopted that view and it may fairly be
said, I think, to have been
both an express basis of his decision and an
underlying assumption of the Tribunal’s decision. Read as a whole, their
reasoning
appears to involve an overall balancing of the various considerations
in ss 3 and 4 on the lines approved in the Waimea judgment.
With respect, I am unable to agree that this is a correct view. Rather I agree with the view taken by Dr K A Palmer in his Planning and Development Law in New Zealand (2nd ed, 1984) vol 1 at p 202 that the 1977 change was significant. The qualification “Subject to” is a standard drafting method of making clear that the other provisions referred to are to prevail in the event of a conflict. This Court had occasion to say so expressly in a reported case the year before the 1977 Act: Harding v Coburn [1976] 2
NZLR 577, 582. There was no need nor reason to insert those words in ss 4 and 36 of the 1977 Act if the legislature had intended that the s 3 matters were no more than matters to which regard was to be had, together with district considerations, in preparing a district scheme. The explanation of the insertion of the words that leap to the eye, as it seems to me, is that the argument for the Minister of Works rejected in Waimea was henceforth to prevail. There is an analogy with the legislative guidelines provided by declaring a special object for the amending Act considered by this Court in Ashburton Acclimatisation Society v Federated Farmers of New Zealand Inc [1988] 1 NZLR 78, 87-88; see also per Bisson J at pp 94–
95 and per Chilwell J at pp 97–99.
(emphasis added)
[39] Section 171 in its 1993–amended form was considered in
a number of noteworthy judgments. Delivering the
advice of the Privy Council
in McGuire v Hastings District Council Lord Cooke of Thorndon
said:19
[22] ... By s 171 particular regard is to be had to various
matters, including (b) whether adequate consideration
has been given to
alternative routes and (c) whether it would be unreasonable to expect the
authority to use an alternative route.
...; but, by s 6(e), which their
Lordships have mentioned earlier, [Hastings] is under a general duty to
recognise and
provide for the relationship of Maori with their ancestral lands.
So, too, Hastings must have particular regard to kaitiakitanga
(s 7) and it must
take into account the principles of the Treaty (s 8). Note that s 171 is
expressly made subject to Part II, which includes ss 6, 7 and 8. This means
that
19 McGuire v Hastings District Council [2000] UKPC 43, [2002] 2 NZLR 577.
the directions in the latter sections have to be considered as well as
those in s 171 and indeed override them in the event of conflict.
(emphasis added)
[40] While strictly speaking those observations in relation to the operation of s 171 were obiter dicta, as Auckland Volcanic Cones Society Inc v Transit New Zealand recognised, they were “very strong obiter dicta”.20 The High Court there added:
[59] ... The specific considerations in s 171 (alternative
methods or routes in particular) are subject to Part II of
the RMA. Parties
involved in the administration and application of the RMA are very familiar with
the requirement to have regard
to other considerations subject to Part II. On
an application for resource consent, consent authorities and on appeal the
Environment
Court must have regard to the considerations in s 104 of the RMA.
The s 104 considerations are expressed to be subject to Part II.
There is a
well-established body of case law confirming the primacy of Part II and how that
is applied in relation to the s 104
considerations. The drafting technique
used in s 171 to provide the considerations in that section are subject to Part
II is not
unique to s 171.
[60] In the present case the effect of ss 171 and 174 is to require
Transit and the Environment Court on appeal to have particular
regard to the
matters at s 171(1)(a), (b), (c) and (d) but always subject to Part II of the
RMA.
2003 Amendment
[41] Section 171 was substantially redrafted in the 2003
Amendment.21 One change was the relocation of the reference to
“subject to Part II” from its location at the commencement of the
subsection:
171 Recommendation by territorial authority
(1) When considering a requirement and any submissions received, a
territorial authority must, subject to Part II, consider
the effects on the
environment of allowing the requirement, having particular regard
to–
...
Although a similar change was made to s 104(1), there was no equivalent amendment to s 191(1) and consequently the phrase “Subject to Part 2” remains at
the commencement of that subsection.
20 Auckland Volcanic Cones Society Inc v Transit New Zealand [2003] NZRMA 316 (HC).
21 Resource Management Amendment Act 2003, s 63.
[42] Section 186A(3) was substantially redrafted in terms identical to s
171(1).
[43] One of the contested points of interpretation turns on the
fact of that relocation of the phrase within s 171(1).
Whereas TAC contended
that the phrase continued to render the totality of the consideration of effects
as being subject to Part
2, NZTA argued that the relocation had the consequence
that the phrase related to the consideration of effects rather than to the
(a)
to (d) matters.
[44] Most recently s 171 was considered in Queenstown Airport
Corporation Ltd v Queenstown Lakes District Council.22 Citing
McGuire, Whata J said:
[68] It will be seen that the focal point of the assessment is, subject
to Part 2, consideration of the effects of allowing
the requirement
having particular regard to the stated matters. The import of this is that
the purpose, policies and directions in Part 2 set the frame for the
consideration of the effects
on the environment of allowing the requirement.
Indeed, in the event of conflict with the directions in s 171, Part 2 matters
override
them. Paramount in this regard is s 5 dealing with the purpose
of the Act, namely to promote sustainable management of natural
and
physical resources.
[69] Part 2 also requires that in achieving the sustainable management
purpose, all persons exercising functions shall recognise
and provide for
identified matters of national importance; shall have regard to other matters
specified in s 7 and shall take into
account the principles of the Treaty of
Waitangi.
[70] The reference at s 171(1)(d) to “any other matter” is
qualified by the words “reasonably necessary”.
Given the
Act’s overarching purpose, however, the scope of the matters that may
legitimately be considered as part of the
effects assessment must be broad and
consistent with securing the attainment of that purpose.
(emphasis added)
Sections 171(1) and 104(1) compared
[45] It is convenient at this juncture to note the different
structure of s 104 following the 2003
Amendment:23
23 Section 104(1)(b) was replaced on 1 October 2009 by s 83(1) of the Resource Management
(Simplifying and Streamlining) Amendment Act 2009.
104 Consideration of applications
(1) When considering an application for a resource consent and any
submissions received, the consent authority must, subject
to Part II, have
regard to–
(a) any actual and potential effects on the environment of allowing
the activity; and
(b) any relevant provisions of–
(i) a national policy statement:
(ii) a New Zealand coastal policy statement:
(iii) a regional policy statement or proposed regional policy
statement:
(iv) a plan or proposed plan; and
(c) any other matter the consent authority considers relevant and reasonably
necessary to determine the application.
[46] Two points of difference between ss 104 and 171 material to the
statutory interpretation arguments in this case are:
(a) in s 104 the effects on the environment comprises one of the
matters to which regard is to be had whereas in s 171
it is the focus
of consideration;
(b) s 171 requires that the matters listed are to be the subject
of
“particular” regard.
[47] Having noted what it described as the “subtly different language” in the two sections, the Board concluded that the difference in wording did not require a substantively different approach to considering effects on the environment arising from NoRs from that for determining consent applications.24 That conclusion is also
in issue in contest on this
appeal.25
24 At [194] of the Final Decision.
25 Question 28A: see [72] below.
The relevance of King Salmon
[48] The Supreme Court’s decision in Environmental Defence Society Inc v The New Zealand King Salmon Co Ltd26 was released on 17 April 2014 part way through the hearing before the Board.27 King Salmon involved an application for a change to the Marlborough Sounds Resource Management Plan under s 66 of the RMA. It did not concern s 171. The relevance of King Salmon to the present appeal arises from
the Court’s discussion of Part 228 and the
decision-making process known as the
“overall judgment” approach.
[49] NZTA’s submissions stated that King Salmon has
significantly modified the approach to decision-making under the RMA and
in particular the meaning of “subject
to Part 2”. The
respondents rejoined that the ratio of King Salmon was confined to plan
changes and that the decision was of little moment in relation to
designations.
Sequence of consideration of the Issues
[50] As earlier noted29 the amended notice of appeal grouped
the questions of law under eight broad issues by reference to subject
matter.
[51] In its written submissions NZTA stated that it had “further refined” the questions of law comprised in Issues 3 and 6. Although these submissions were presented as filed, the redefinition provoked some debate which led to NZTA filing a memorandum on the fourth day of the hearing formally recording the intended “restatement” of the questions of law relevant to Issues 3 and 6 and summarising the
principles relating to the Court’s power to amend a notice of
appeal.30
[52] The Issue 3 questions, being Q 28(a), (b) and (c), were
refined as five questions which I will refer to as Q 28A
to 28E. The Issue 6
question, being Q 45
27 At [91] of the Final Decision.
28 A change to a regional plan under s 66 must be “in accordance with [inter alia] the provisions of
Part 2”: s 66(1)(b).
29 At [11] above.
30 Memorandum of counsel for the Appellant in relation to questions of scope and the Court’s
power to amend (if necessary) dated 23 July 2015.
(albeit with the cross-reference to the errors of law listed in para 44 of
the amended notice of appeal), was refined as five questions
which I will refer
to as Q 45A to 45E.
[53] It is convenient to set out the refined Issue 3 questions of
law:
28A Does the difference in wording between s 104 and s 171 require a
substantively different approach to considering effects on
the environment
arising from notices of requirement as that for determining consent
applications?
28B Was the Board in error by considering the effects of the environment
of allowing the requirement without having particular
regard to the matters
listed in s 171(1)(a)–(d)?
28C When considering a requirement under s 171(1) RMA, how are the
words ‘having particular regard’ to be interpreted?
28D When considering a requirement under s 171(1) RMA, how are the words
‘subject to Part 2’ to be applied (in particular,
following the
recent Supreme Court decision in King Salmon)?
28E As a consequence of those errors, did the Board make findings of fact
that it could not otherwise have come to on the evidence?
[54] That “refinement” of the Issue 3 questions of law was
particularly significant as it introduced in an explicit
way as Q 28C
and 28D31 fundamental questions concerning the interpretation of
s 171(1). The answers to, or more accurately the discussion of, those
two
questions has significance for a number of the other specified questions
of law.
[55] Consequently, although the structure of the parties’ submissions helpfully tracked the sequence of the Issues in the amended notice of appeal, I propose to first address the key issues of statutory interpretation and the arguments concerning the implications of King Salmon. Having done so, the judgment will then traverse the
remaining questions of law in the sequence of the identified
Issues.
31 Q 28(a), (b) and (c) in the amended notice of appeal remained as Q 28A, 28B and 28E.
The meaning of “having particular regard to” in s
171
[56] NZTA’s intention to call into question the interpretation of
the phrase “having particular regard to”
was arguably implicit
in Q 28(a) and Q 28(b) in Issue 3. However the issue was squarely raised in
the restated Q 28C:
When considering a requirement under s 171(1) RMA, how are the words
“having particular regard” to be interpreted?
The 23 July 2015 memorandum32 explained that it was necessary to
address Q 28C
when determining the Q 28 questions in the amended notice of
appeal.
[57] The phrase is used not only in s 171(1) (and relatedly in s 168A(3))
but it also appears in 191(1) and notably in s 7 in
Part 2. By contrast what is
usually viewed as the lesser obligation of “have regard to” is
employed in s 104(1) and
in a variety of other
sections.33
[58] A curious interface between the two phrases is highlighted in s 149P which concerns the matters to be considered by a board of inquiry. As noted earlier a board is required to “have regard to” the Minister’s reasons.34 In the case of a notice of requirement for a designation or for a heritage order a board is required to “have regard to” the matters set out in s 171(1)35 and s 191(1)36 respectively. However both ss 171(1) and 191(1) direct that such matters are to be the subject of “particular regard”. I raised with counsel the possibility that, given the terms of s 149P, the obligation on a board might be only to “have regard” to the matters in s 171(1). That would have the consequence of equality of treatment between the s 171(1) matters
and the Minister’s reasons. However neither side was attracted to
that
interpretation.
32 At [51] above.
33 Resource Management Act 1991, ss 131(1), 138A and 142.
34 At [4] above.
35 Section 149P(4)(a).
36 Section 149B(5)(a).
“have regard to”
[59] Taking the phrase “have regard to” as the starting
point, in New Zealand Co-operative Dairy Co Ltd v Commerce
Commission Wylie J (sitting with Mr R G Blunt)
said:37
We do not think there is any magic in the words “have regard to”.
They mean no more than they say. The tribunal may not
ignore the statement. It
must be given genuine attention and thought, and such weight as the tribunal
considers appropriate. But
having done that the tribunal is entitled to
conclude it is not of sufficient significance either alone or together with
other matters
to outweigh other contrary considerations which it must take into
account in accordance with its statutory function[.]
[60] It follows that the phrase “have regard to” does not
mean “to give effect to”. In New Zealand Fishing Industry
Association Inc v Minister of Agriculture and Fisheries Cooke P agreed
with and adopted the following analysis of McGechan J at first
instance:38
... He is directed by s 107G(7) to ‘have regard’ to any
submissions made. Such submissions are to be given genuine attention
and
thought. That does not mean that industry submissions after attention and
thought necessarily must be accepted. The phrase
is ‘have regard
to’ not ‘give effect to’. They may in the end be rejected, or
accepted only in part. They
are not, however, to be rebuffed at outset by a
closed mind so as to make the statutory process some idle exercise.
Section 107G(7) in its direction that the Minister ‘have regard’
to five stated criteria does not direct that any one
or more be given greater
weight than others. In particular it does not direct that (a) value of ITQ is
to have greater or lesser
regard paid than (b) net returns and likely net
returns. Weight, in the end and provided he observes recognised principles of
administrative
law, is for the Minister.
[61] Specifically in an RMA context John Hansen J took a similar approach
in
Foodstuffs (South Island) Ltd v Christchurch City
Council:39
I do not consider the term “shall have regard to” in s 104 RMA
should be given any different meaning from the cases referred
to above. In my
view, the appellant is seeking to elevate the term from “shall have regard
to” to
37 New Zealand Co-operative Dairy Co Ltd v Commerce Commission [1992] 1 NZLR 601 (HC) at
612.
38 New Zealand Fishing Industry Association v Minister of Agriculture and Fisheries [1988]
1 NZLR 544 (CA) at 551. Similarly see R v Police Complaints Board, ex parte Madden [1983]
2 All ER 353 (QBD) at 369–370 where a number of English decisions are discussed.
“shall give effect to”.
The requirement for the decision-maker is to give genuine attention and thought
to the matters
set out in s 104, but they must not necessarily be
accepted.
[62] One of the authorities cited by John Hansen J was R v
CD,40 a judgment of Somers J who expressed the view in the
context of the Costs in Criminal Cases Act 1967 that the expression “shall
have regard to” is not synonymous with “shall take into
account”. However I
note that in a number of subsequent decisions in
Australia the two phrases have been treated as
equivalent.41
[63] In my view the expression “to take into account” is susceptible of different shades of meaning. I consider that the two phrases can be viewed as synonymous if the phrase “to take into account” is used in the sense referred to by Lord Hewart CJ in Metropolitan Water Board v Assessment Committee of the Metropolitan Borough of St Maryleborne “of paying attention to a matter in the course of an intellectual
process”.42 The key point is that the decision-maker is
free to attribute such weight
as it thinks fit to the specified matter but can ultimately choose to reject
the matter.
“having particular regard to”
[64] Plainly the phrase “shall have particular regard
to” conveys a stronger direction than merely “to
have regard
to”. Section 7 (which includes the phrase) is one of the four
sections in Part 2 which McGuire described as being “strong
directions”.43
[65] The issue is most recently informed by the discussion of Part 2 in King Salmon.44 Having observed that s 5 is a carefully formulated statement of principle intended to guide those who make decisions under the RMA, which is given further elaboration by the remaining sections in Part 2 (ss 6, 7 and 8), Arnold J
writing for the majority of the Supreme Court said:
40 R v CD [1976] 1 NZLR 436 (SC) at 437.
41 R v Hunt; Ex parte Sean Investments Pty Ltd [1979] HCA 32; (1979) 25 ALR 497 (HCA); Queensland Medical
Laboratory Ltd v Blewett [1988] FCA 423; (1988) 84 ALR 615 (FCA) at 623; Minister for Immigration and Ethnic Affairs v Baker (1997) 45 ALD 136 (FCA) at 142; Friends of Hinchinbrook Society Inc v Minister for the Environment (1997) 147 ALR 608 (FCA) at 627.
42 Metropolitan Water Board v Assessment Committee of the Metropolitan Borough of
St Maryleborne [1923] 1 KB 86 (CA) at 99.
43 At [39] above.
44 King Salmon, above n 26.
[26] Section 5 sets out the core purpose of the RMA – the promotion of sustainable management of natural and physical resources. Sections 6, 7 and
8 supplement that by stating the particular obligations of those administering the RMA in relation to the various matters identified. As between ss 6 and
7, the stronger direction is given by s 6 – decision-makers
“shall recognise and provide for” what are described as
“matters of national importance”,
whereas s 7 requires
decision-makers to “have particular regard to” the specified
matters. The matters set out in s 6 fall naturally within the concept of
sustainable management in a New Zealand context. The requirement to
“recognise and provide
for” the specified matters as “matters
of national importance” identifies the nature of the obligation that
decision-makers
have in relation to those matters when implementing the
principle of sustainable management. The matters referred to in s 7 tend to
be more abstract and more evaluative than the matters set out in s 6. This may
explain why the requirement in s 7 is to “have particular regard to”
them (rather than being in similar terms to s 6).
[27] Under s 8 decision-makers are required to “take into
account” the principles of the Treaty of Waitangi.
Section 8 is
a different type of provision again, in the sense that the principles of the
Treaty may have an additional relevance
to decision-makers.
(emphasis added)
[66] While NZTA submitted that the (a) to (d) matters in s 171(1) were to
be carefully weighed in coming to a conclusion, no submission
was advanced in
the course of argument on the interpretation issue to the effect that the
matters to which particular regard was
to be had were required to be the subject
of extra weight.45 On that issue I share the view of Sir Andrew
Morritt V-C in Ashdown v Telegraph Group Ltd:46
It was submitted that the phrase ‘must have particular regard to’
indicates that the court should place extra weight
on the matters to
which the subsection refers. I do not so read it. Rather it points to the
need for the court to consider
the matters to which the subsection refers
specifically and separately from other relevant considerations.
[67] In the event NZTA and the respondents appeared to be on the same
page on the interpretation of the phrase. Both sides
cited the
decision of the Planning
45 However NZTA’s submissions argued that the Project’s enabling effect for future projects was a highly relevant effect that ought to have been considered and “given sufficient weight” by reason of the requirement to have particular regard in s 171(1).
46 Ashdown v Telegraph Group Ltd [2001] 2 All ER 370 (Ch) at [34] where the phrase “must have particular regard to” in s 12 of the Copyright Act 1988 with reference to the European Convention for the Protection of Human Rights and Fundamental Freedoms was considered.
Tribunal in Marlborough District Council v Southern Ocean Seafoods Ltd
where the following view was expressed:47
The duty to have particular regard to these matters has been described in one
case as “a duty to be on inquiry” Gill v Rotorua District Council (1993) 2
NZRMA 604, 2 NZPTD Part 5. With respect in our view it goes further than the
need to merely be on inquiry. To have particular regard
to something in our
view is an injunction to take the matter into account, recognising it as
something important to the particular
decision and therefore to be considered
and carefully weighed in coming to a conclusion.
[68] I agree that that is an appropriate interpretation provided that the
reference to
“take the matter into account” is understood in the sense
explained at [63] above.
Did the Board adopt the correct approach?
[69] NZTA’s real complaint was that the Board failed to adhere to
the identified standard. It placed particular reliance
on the Board’s
comments at [175]:48
[175] What is required (subject to consideration of the King
Salmon decision, which we address next) is a consideration of the effects on
the environment of allowing the requirement having particular
regard to the
matters set out in sub-sections (a)–(d). This means that the matters in
(a)– (d) need to be considered
to the extent that our finding on these
matters are to be heeded (or borne in mind) when considering our findings on the
effects
on the environment.
[70] I would agree with NZTA that merely to heed or bear in mind matters
would fall below the requisite level of attention which
the phrase “have
particular regard to” imports. However I do not consider that the
comments at [175], which were introductory
in character, accurately reflect the
Board’s approach which is more evident at [181]–[182]:
[181] By contrast, in considering the NoR we are required to have
particular regard to the relevant instruments.
[182] The phrase have particular regard to has been
interpreted as requiring that we specifically turn our mind to each of the
listed matters, and give them some greater
weight than those to which we are
only required to have regard. This is a different and lesser test than
the requirement to give effect to, as was being considered in King
Salmon. The Supreme Court interpreted give effect to as simply
meaning implement, and considered that this requirement was intended
to constrain decision makers.
47 Marlborough District Council v Southern Ocean Seafoods Ltd [1995] NZRMA 220 at 228.
48 Attention was also drawn to the use of the verb “informed” in [196].
[71] That such turning of their minds was required separately in respect
of each of the listed matters was acknowledged in the
Board’s subsequent
endorsement at [194] of a passage from the Report and Decision of the Board of
Inquiry into the Upper North
Island Grid Upgrade Project
(NIGUP).49
[72] It is convenient at this point to address Q 28A which
states:
Does the difference in wording between s 104 and s 171 require a
substantively different approach to considering effects
on the environment
arising from notices of requirement as that for determining consent
applications?
[73] This ground of appeal was directed to the Board’s statements
at [193]–[194]:
[193] ... We acknowledge (as [NZTA] noted) that the obligation to assess
effects with respect to NoRs under Section 171(1) is expressed
in subtly
different language from the equivalent obligation arising with respect to
resource consents under Section 104(1).
Specifically, Section
171(1) requires consideration of the effects on the environment having
particular regard to the matters
in sub-sections (a)–(d). Whereas under
Section 104(1), the activity’s actual and potential effects are instead
listed
as one of the matters to which a decision maker must have regard,
alongside those in Section 104(1)(b) and (c). Both Sections 104(1) and 171(1)
though, are subject to Part 2.
[194] However, we do not consider that difference in wording requires a substantively different approach to considering effects on the environment arising from NoRs as that for determining consent applications, as counsel for [NZTA] claimed. Indeed in our experience, it does not. To the contrary, we adopt the findings of the Report and Decision of the Board of Inquiry into the Upper North Island Grid Upgrade Project, that Section 171(1) is to be applied as follows:
[a] The language ... consider the effects ... having particular
regard to ... expresses a duty to do both together, without necessarily
giving one primacy over, or making one subordinate to, the other;
[b] The language having particular regard expresses a duty for
us to turn our mind separately to each of the matters listed, to consider and
carefully weigh each one. The
words do not carry a meaning that the matters
listed in (a)–(d) are necessarily more or less important than the effects
on
the environment of allowing the requirement;
and
49 At [73] below.
[c] We must make our own judgment, based on the evidence and in the
circumstances of the case, about the effects on the environment,
about the
matters listed in (a)–(d), and about the relative importance of each in
all the circumstances.
[74] NZTA’s objection to that analysis was directed both to the
equivalence of treatment of the two sections and to the
issue of “subject
to Part 2”. That latter issue is addressed below in the context of my
consideration of Part 2.
[75] NZTA’s argument was that the Board misapplied s 171(1)
by in effect inserting the word “and”
into the subsection
(presumably before the phrase “having particular regard to”) so that
it read to the same effect as
s 104(1). As its written submissions
stated:
28.7 ... By inserting ‘and’ into s 171(1), the Majority
has given it a different meaning. On the Majority’s
interpretation of
s 171(1) a decision-maker is required to:
a Make its own judgment, through Part 2, concerning the
effects on the environment of allowing the requirement;
and
b Make a separate judgment concerning the matters listed in
paragraphs (a)–(d); and
c Make its own overall judgment, subject to Part 2, regarding the
relative importance of each in all the circumstances.
28.8 This is not what s 171(1) requires. The correct approach to s
171(1) is to consider the effects of the proposed requirement
‘having
particular regard to’ (in the sense of ‘through the lens’ of)
the (a) to (d) matters and then come
to a decision on the basis of that
assessment of effects. Where there is a conflict in the (a) to (d) matters,
the decision-maker
will have recourse to Part 2 (we return to the meaning of
‘subject to Part 2’ in the section below).
[76] I accept the respondents’ submission that, while there is a difference in wording between ss 104 and 171, in its analysis of those sections at [193]–[194] the Board has not misinterpreted s 171 in the manner suggested by NZTA. As noted above, in discharging the obligation to have “particular” regard to the specified matters the Board has recognised that each specified matter is to be the subject of separate attention.
[77] The Board transparently stated its intended decision-making process
at [199]:
[199] We therefore propose to structure this part of our decision
(appropriately applying the guidance from King Salmon, as just
identified) as follows:
[a] To identify and set out the relevant provisions of the main RMA statutory instruments that we must have particular regard to under Section 171(1)(a), and the relevant provisions of the main non-RMA statutory instruments and non-statutory documents that we must have particular regard to under Section 171(1)(d);
[b] To consider and evaluate the adverse and beneficial effects on the
environment informed by the relevant provisions of Part
2; the relevant
statutory instruments; and other relevant matters being the relevant
conditions and the relevant non-statutory
documents;
[c] To consider and evaluate the directions given in
Section 171(1)(b) as to whether adequate consideration has been given to
alternative sites, routes or methods of undertaking the work;
[d] To consider and evaluate the directions given in
Section 171(1)(c) as to whether the work and designation are reasonably
necessary for achieving the objectives for which the designation is sought;
and
[e] In making our overall judgment subject to Part 2, to consider and
evaluate our findings in (a) to (d) above, and
to determine whether the
requirement achieves the RMA’s purpose of sustainability.
[78] I do not consider that that formulation is susceptible to challenge
so far as the appropriate consideration of the 171(1)(a)
to (d) matters is
concerned.
[79] It is convenient at this point to address the contention at ground
of appeal
29(b) that the matters listed in s 171(1)(a) to (d) ought to have been
determined prior to the Board’s substantive consideration
of the
Proposal’s effects. This complaint is directed to the observation in the
Decision at [197]:
[197] In applying Section 171(1) of the RMA, there is also no explicit obligation that our determination regarding the matters in Section 171(1)(b) must be made in advance of our substantive consideration of effects.
[80] The Board proceeded to note that the Wiri Prison Board50
had undertaken a substantive effects assessment, and determined that that
project would result in some significant effects, before
moving on to consider
the s 171(1)(b) matters. The Board favoured that approach:
[198] We adopt the same approach, as we consider it:
[a] Allows us to fully consider all mitigation being offered by
[NZTA], and whether there actually will be significant adverse
effects remaining
once that mitigation is taken into account;
[b] Would be consistent with the High Court’s comments in
Queenstown Airport Corporation Limited v Queenstown Lakes District Council
that the greater the impact on private land (or similarly, the more
significant the project’s adverse effects), the more careful
the
assessment of alternative sites, routes and methods will need to be. We will
have a better understanding of the significance
of the Project’s adverse
effects (and therefore the robustness of the alternatives assessment required),
if we undertake our
substantive effects assessment before considering the
adequacy of the [NZTA’s] alternatives assessment; and
[c] Would appropriately reflect the fact that as Section 171(1) is
subject to Part 2, some consideration of the relevant matters
from that Part is
required in terms of forming a view on potential effects. As such, we consider
we need to have some understanding
of the evidence/effects assessments to reach
a view on whether effects are in fact likely to be
significant.
[81] Having made the argument at [75] above, on this issue NZTA’s
submission
was:
28.21 The Majority was required to assess the effects having particular
regard to the (a) to (d) matters as something important
to be considered and
carefully weighed in coming to a conclusion, rather than simply as matters that
needed to be borne in mind.
It was therefore necessary (inter alia) to
have addressed the (a) to (d) matters before then considering the effects
‘having particular regard to’ those
matters.
50 Final Report and Decision of the Board of Inquiry into the Proposed Men’s Correctional Facility
at Wiri, September 2011.
[82] I do not accept that the sequence of consideration is required to be
as NZTA maintains. The Board’s reasoning in [198]
appears to me to be
sound. As Burchett J remarked in Friends of Hinchinbrook Society Inc v
Minister for the Environment:51
... What is the effect of a requirement that “[i]n determining whether
or not to give a consent ... the Minister shall have
regard only to the
protection, conservation and presentation ... of the property”? An
instant’s reflection shows that
these words just cannot be applied
mechanically. The minister must consider the application made to him and
ascertain what it involves
before he can have regard to the protection,
conversation and presentation of the property in relation to it.
The effect of the phrase “subject to Part 2” in s
171
[83] The only question of law in the amended notice of appeal which
specifically raised Part 2 was Q 13 [subissue 1D] which states:
Does s 171(1)(b) require the requiring authority’s
consideration of alternatives to incorporate Part 2 considerations;
including
(in particular) the weight given to particular evaluation criteria.
[84] However the fundamental nature of NZTA’s Part 2 argument
emerged more clearly in the further refinement of the
Issue 3 questions,
in particular restated Q 28D:
When considering a requirement under s 171(1) RMA, how are the words
‘subject to Part 2’ to be applied (in particular, following the recent Supreme
Court decision in King Salmon)?
The issue of the capacity for the Board to “resort to Part 2” was
also implicit in
restated Q 45E:
What is the correct approach to the application of the test of
‘inappropriateness’ in s 6(f) [should the Court consider resort to Part 2 of the
RMA was available to the Board in the circumstances of this
case]?
[85] As noted in the brief discussion of legislative history,52 two primary arguments were advanced by NZTA concerning the role played by Part 2 in the
s 171(1) consideration:
51 Friends of Hinchinbrook Society Inc v Minister for the Environment, above n 41, at 627.
52 At [43] and [49] above.
(a) did the relocation of the phrase within s 171(1) have the
consequence contended by NZTA that the phrase related to the consideration
of
effects rather than to the (a) to (d) matters?
(b) did King Salmon change the approach to the application of
this phrase in s 171(1)?
The relocation of the phrase within s 171(1)
[86] It was not apparent either from NZTA’s submissions to the
Board or in the Board’s Decision whether this line
of argument had
prominence. However the argument as developed before me is conveniently
summarised in NZTA’s written reply
as follows:
11.22 The 2003 amendment separates the (a)–(d) matters from
the overriding ‘subject to Part 2’ direction
that was clear in the
previous drafting. It is well established that differences in wording between
repealed provisions and those
enacted is an aid to statutory interpretation and
may throw light on the intended meaning. It is submitted that if Parliament
intended the whole of the s 171(1) assessment still to be ‘subject to
Part 2’, it would have retained more of the
previous wording, such as
follows:
(1) Subject to Part 2, when considering a requirement and any
submissions received, a territorial authority must consider the effects
on the
environment of allowing the requirement and shall also have particular regard
to–
11.23 Parliament did not do this. Instead, it moved the position of the
‘subject to Part 2’ direction to relate to the assessment of
effects and used the words ‘having particular regard
to’ to qualify
the consideration of effects such that the (a)–(d) matters are not
directly made subject to Part 2.
[87] There appears to have been no judicial consideration of the implications of the relocation. Nor do the travaux preparatoires throw any express light on the question. If the implications of the movement of the phrase were as significant as NZTA’s argument suggests, then one would have expected that there would have been some sign on the legislative trail. One would also expect that the same change as made to ss 104(1), 168A(3) and 171(1) would also have appeared in s 191(1).
[88] The first manifestation of the relocation was in the Resource Management Amendment Bill53 which was the culmination of a review of the RMA which started in August 1997. The bill had its first reading on 13 July 1999 and was referred to the Local Government and Environment Committee. The bill made changes to ss 104,
168A and 171 but not to s 191 which may account for the fact of the current
point of difference.
[89] Because the form of s 171 proposed in 1999 was different from the
section in its ultimate form in 2003, I set out its original
terms:
171(1) When considering a requirement and any submissions received, a
territorial authority must, subject to Part II, consider the
effects on the
environment of allowing the requirement, having regard to–
(a) Any relevant provisions of the plan or proposed plan; and
(b) If the requiring authority does not own the land or it is likely
that the designation will have a significant adverse effect
on the environment,
whether adequate consideration has been given to alternative sites, routes, or
methods of undertaking the work;
and
(c) Whether the designation is reasonably necessary for
achieving the objectives of the requiring authority; and
(d) Any other matter the territorial authority considers
reasonably necessary in order to make a recommendation
on the
requirement.
(2) A requirement must not conflict with any relevant provisions of a
national policy statement or a New Zealand coastal policy
statement.
An equivalent amendment was proposed as s 168A(3) and (4).
[90] However the structure of s 104 was substantially different,
particularly inasmuch that a distinction was made in
relation to the
consideration of resource consents for controlled activities, restricted
discretionary activities and discretionary
activities. Only in relation to
discretionary activities was there a reference to “Part II”:
that reference
appeared in the first subparagraph:
104(3) When considering an application for a resource consent for a
discretionary activity and any submissions received, a consent
authority–
53 Resource Management Amendment Bill 1999 (313–2) (Select Committee Report).
(a) Must, subject to Part II, consider the effects on the environment of allowing the application, having regard to–
(i) Any relevant provision in a plan or proposed plan: (ii) Any other matter the consent authority considers
reasonably necessary to decide the application; and
(b) May grant or refuse the application; and
(c) If it grants the application, may impose conditions.
[91] The fact and the implications of the different activities were
usefully explored in the judgment of Randerson J in Auckland City Council v
John Woolley Trust.54
[92] The Committee’s report to the House on 8 May 200155
did not support the proposal that Part 2 of the Act would not be required
to be considered in respect of controlled and restricted
discretionary
activities. While agreeing that s 104 should be simplified, the Committee
said:
... However, we are not prepared to remove explicit reference to Part II and
significant planning documents such as national and regional
policy statements
and relevant or proposed plans. We recommend that a new, overarching
subsection be added to new section
104, requiring consent authorities to
consider all applications subject to Part II and to have regard to matters that
include the
above planning documents.
The amendment proposed as s 104(1A) was identical to s 104(1) in
the 2003
Amendment.
[93] With reference to ss 168A and 171 the Committee’s report
said:
Section 168A specifies the matters a territorial authority must consider on a
notice of requirement for a designation in its own district
for a work for which
that territorial authority itself has financial responsibility. Section 171
specifies the matters a territorial
authority is required to consider when
assessing a notice of requirement for designation by another requiring
authority. Proposed
amendments to these two sections are set out in
clauses 56 and 58 respectively. As introduced, the new provisions place
greater emphasis on environmental effects when considering a requirement, and
the need to consider alternatives is reduced. These clauses also make
sections 168A and 171 more consistent with the proposed new wording for the
consideration of resource consents. Finally, the emphasis is
shifted
54 Auckland City Council v John Woolley Trust [2008] NZHC 28; (2008) 14 ELRNZ 106, [2008] NZRMA 260 (HC)
at [24]–[29].
55 Above n 52.
from considering whether a designation is necessary, to whether or not the
work is necessary in achieving the objectives of the requiring
authority.
(emphasis added)
[94] No further progress was made on the 1999 bill in the House after the Committee had reported and the report was not debated by the House. The order of the day for consideration of the report was discharged on 24 March 2003. The Resource Management Amendment Bill (No 2) was introduced on 17 March 2003 and referred to the Committee on 20 March 2003. An instruction from the House stated that the Bill was referred to the Committee for the purpose only of the Committee receiving a briefing from officials and the Committee was required to
report to the House by 28 April 2003.56
[95] With reference to s 171 the report stated:
[it] requires a territorial authority to consider environmental effects when
considering a requirement and to have particular regard
to various other
matters. Alternative sites, routes, or methods will now only need to be
considered if the requiring authority
does not have a legal interest in the land
or it is likely that the designation will have a significant adverse effect on
the environment.
The application of the “reasonable necessity” test
is clarified. This amendment complements the amendment to section
168A.
[96] A consideration of that history leads me to infer that:
(a) the catalyst for the relocation of the phrase was the
proposed s 104(3),57 the structure of which precluded the phrase
being located at the commencement of the subsection;
(b) sections 168A(1) and 171(1) were amended for consistency
with s 104;
(c) section 191(1) was left unchanged because it was not addressed in
the
2003 Amendment.
56 Resource Management Amendment Bill 1999 (No 2) (39–2) (Select Committee Report).
57 At [90] above.
[97] However there is nothing to suggest that the relocation of the
phrase within s 171(1) (and similarly within s 168A) was for
the significant
purpose contended for by NZTA, namely to change the focus of application of Part
2 within s 171. I also note that
such an argument could not logically be
mounted in relation to s 104(1) given its structure (with effects on the
environment being
only one of the matters to which regard is to be had). Yet the
phrase was also relocated within that subsection.
[98] For these reasons I do not accept that the relocation within s
171(1) of the phrase “subject to Part 2” had the
purpose or effect
of making any material change to the application of that section. I reject
NZTA’s contention at [86] above
that the consequence of that amendment was
that the phrase “subject to Part 2” related only to the assessment
of effects
and that the (a) to (d) matters were no longer directly subject to
Part 2.
The implications of King Salmon
[99] It is fair to say that NZTA’s approach to the role of Part 2
with reference to the NoR evolved not only throughout
the course of the hearing
before the Board but also on the appeal in this Court.
[100] Its opening position was recorded in the Decision in this
way:
[190] In opening, [NZTA] submitted that when considering its NoR, we must
(among other things):
[a] Consider the effects on the environment of allowing the
NoR; and
[b] Have particular regard to the matters in Sections (sic) 171(1)
as if we were a territorial authority, namely:
[i] The relevant provisions of planning instruments;
[ii] Whether adequate consideration has been given to alternative
sites, routes and methods of undertaking the work;
[iii] Whether the work and designation are reasonably necessary for
achieving [NZTA’s] project objectives, as set out in
the NoR;
[iv] Any other matters we consider reasonably necessary to determine the NoR; and
[v] Above all, consider Part 2 matters.
[101] In closing before the Board NZTA submitted that,
notwithstanding King Salmon, an “overall judgment” approach
remained relevant in the consenting and designation context. It submitted that
Part
2 was relevant to the Board primarily because of the presence in s 171 of
the phrase “subject to Part 2”, drawing attention
to that part of
McGuire highlighted in [39] above. It said:
16.12 It is submitted that the position as expressed in McGuire
above, has not been upset by King Salmon. The Supreme Court
did not consider sections 104 and 171 of the RMA, or the way in which Part 2
matters are approached in a
consenting context.
16.13 Nonetheless, the Supreme Court’s conclusions may in
certain respects be taken as impacting on the approach taken
to RMA
decision-making more broadly. For instance, paragraph 151 of the Court’s
decision quoted above is noticeably broad
in its language (it refers to
“planning decisions” generally).
...
16.16 It is submitted that, in the context of ... the applications for this
Project, and adopting the reasoning of the Supreme Court:
a Sections 104 and 171 are expressly subject to Part 2, and the
provisions in Part 2 remain relevant;
b Section 6 elaborates on the guiding principle in section 5. It
does not ‘trump’ it in the way suggested for TAC and NRA;
c Section 5 supports the approval of this Project, but [NZTA]
is not relying on this section alone;
d The following discussion of effects will allow the Board to
conclude as to each of the elements of Part 2, before
undertaking an
overall judgment.
[102] In the section of its Decision headed “Overview of the
statutory and legal context” the Board recorded its understanding
of the
established framework for considering s 171(1) before addressing whether that
framework had been modified by King Salmon. Its analysis commenced in
this way:
[169] We are required to consider the matters set out in Section 171(1) subject to Part 2. This has been interpreted as meaning that the directions in Part 2 are therefore paramount, and are overriding in the event of conflict. The relevant Part 2 directions therefore apply to:
[a] Our evaluation of specific effects on the environment; and
[b] Our evaluation in the final analysis.
[170] The focal point of the assessment is, subject to Part 2,
consideration of the effects of allowing the requirement having
particular
regard to the stated matters. The import of this is that the purpose, policy
and directions in Part 2 set the frame for
the consideration of the effects on
the environment of allowing the requirement. Paramount in this regard is
Section 5 dealing with
the purpose of the Act, namely to promote sustainable
management of natural and physical resources.
[103] Having set out key passages from McGuire, the Decision
stated:
[174] The reference being subject to Part 2 does not entitle us to
ask whether some other project alignment or design better meets
the requirements of Part 2,
as the Act does not direct a particular use or
require the best use of resources. All that is required is a careful assessment
of
the Project in and of itself to determine whether it achieves the RMA’s
purpose. A matter that we will consider in detail at
the time of our overall
judgment.
There then followed [175] previously quoted.58
[104] Having recorded its view that, where an evaluation under Part 2 (and
in particular s 5) was required or permitted, that should
continue to involve an
overall broad judgment as held in NZ Rail Ltd v Marlborough District
Council,59 the Board stated its understanding of the King
Salmon decision:
[177] While the Supreme Court reviewed the previous overall broad
judgment and environmental bottom line jurisprudence around the
correct application of Section 5 (where required), it did not go on to
substantively consider or evaluate
that issue. We accordingly understand that
where an evaluation under Part 2 (and in particular Section 5) is
required
(or permitted), this should continue to involve an overall broad
judgment as held in NZ Rail and outlined above.
[178] The majority of the Supreme Court in King Salmon found that
the plan change at issue ... did not comply with [Section] 67(3)(b) ... in
that it did not give effect to the NZCPS. In doing so, it found that in
considering whether the New Zealand Coastal Policy Statement had been given
effect to, and finally determining the plan change before it, that Board was
not entitled by reference to the principles in Part 2,
to carry out a
balancing of all relevant interests in order to reach a decision. Rather,
the plan change should have been
dealt with in terms of the New Zealand Coastal
Policy Statement, without reference back to Part 2. This was primarily because
of
what the Court considered to be strongly worded directives in two of
the New Zealand Coastal Policy Statement policies that were
particularly
58 At [69] above.
59 NZ Rail Ltd v Marlborough District Council [1994] NZRMA 70 (HC).
relevant in that case, which the Board found would not be given effect to
if the plan change was granted.
[105] The Board then said:
[179] Again, we consider that properly construed, this aspect of
King Salmon does not directly affect our determination of [NZTA’s]
NoR, for the following reasons. King Salmon involved consideration of a
plan change, and therefore different statutory tests from those applying to
[NZTA’s] NoR. Importantly,
the Supreme Court observed that Section
67(3)(b) provides a strong directive, creating a firm obligation on the part
of those subject to it, to give effect to the New Zealand Coastal Policy
Statement.
[180] Reading the majority decision as a whole, we consider that this
specific statutory context was clearly central to
the Supreme
Court’s decision. ...
[181] By contrast, in considering the NoR we are required to have
particular regard to the relevant instruments.
There then followed [182] previously quoted.60
[106] NZTA disagreed with the Board’s analysis of King
Salmon and with its reliance on McGuire. Its principal written
submissions on appeal stated:
29.7 King Salmon has significantly modified the
approach to decision-making under the RMA and in particular, what
‘subject to
Part 2’ means. In other words, when is recourse to be
had to Part 2?
...
29.11 While the decision was in the context of a plan change, the Supreme
Court’s findings in relation to the planning framework,
and the
application of Part 2 to decision-making generally, have wider
application.
...
29.13 We submit that the Supreme Court has given a clear direction that it
is the planning documents that generally form
the basis for
decision-making under the RMA. Parliament has provided for a hierarchy of
planning documents, relevant to
planning decisions under the RMA. These
documents are drafted ‘in accordance with Part 2’ and ‘flesh
out’
the provisions of Part 2 in a manner that is increasingly detailed
both as to content and location.
[107] Then, under a heading “Application of King Salmon to s
171(1)”, NZTA
contended:
60 At [70] above.
29.16 For the reasons summarised in para 29.13, the planning documents give
effect to Part 2. Decisions made in reliance on those
documents therefore
achieve the sustainable management purpose of the Act, as provided for in Part
2.
29.17 The Supreme Court held that s 5 (the purpose of the Act) is not an
operative provision. Nor therefore is Part 2 as a whole
given that ss 6, 7
and 8 are a further elaboration of that purpose. Part 2 provisions
are particularised (both as to
substantive content and locality) by the planning
documents, from national policy statements down to district plans.
...
29.22 Section 171(1) directs that when considering a
notice of requirement, a decision-maker’s assessment
of effects on the
environment is ‘subject to Part 2’. However, on the basis of the
principles established by the Supreme
Court in King Salmon, and
consistent with McGuire, Part 2 will be relevant if one of the three
caveats is established or there is a conflict in the exercise of the statutory
duty
under s 171(1)(a) to (d). In this case the planning framework did
contemplate the Project and therefore there was no conflict so
as to bring Part
2 into play.
[108] In response TAC maintained the primacy of Part 2 and criticised
NZTA’s submission for failing to address how the “subject
to Part
2” direction is to be complied with. NZTA’s reply submissions were
interesting on both those points:
11.15 ... We agree with the submissions of TAC to the effect that Part 2
retains primacy.
11.16 The approach by the Appellant to the application of Part 2, assumes
primacy, but the question remains as to how that primacy
is to be provided for.
How it is provided for is cogently summarised at [30] of King Salmon.
The crucial point is that the Supreme Court has determined that it is the
planning documents which give effect to s 5 and Part
2 more generally unless one
of the three caveats apply or there is a conflict. Following King
Salmon, the primacy of Part 2 is maintained and applied through the planning
documents; both as to substantive content and the locality
to which those
documents apply.
11.17 It follows that the phrase ‘subject to Part 2’ in s 171(1) (or in s 104 for that matter) does not imply the re-litigation of previously settled planning provisions where no caveats or conflict arise. This is why at [151] the Supreme Court determined that s 5 is not intended to be an operative provision in the sense that it is not a section under which particular planning decisions are made. It is the hierarchy (cascade) of planning documents which flesh out the principles in s 5 and the remainder of Part 2, and it is those documents which form the basis of decision-making; in this case being the framework in which effects are to be considered.
[109] It is only proper that I record that, when in the course of his oral
reply I explored with Mr Casey QC the issue of the scope
of NZTA’s
argument before the Board on the implications of King Salmon, Mr
Casey acknowledged that the submission relating to caveats and conflicts had
not been developed before the Board to the extent
that it had on appeal. In
particular para 16.16(a)61 did not indicate how primacy was to be
given whereas NZTA’s current stance is that such primacy is via the plan
in the absence
of any conflict.
[110] While the provisions in Part 2 are not operative provisions (in the
sense of being sections under which particular planning
decisions are
made),62 they nevertheless comprise a guide for the performance of
the specific legislative functions. As King Salmon said with reference to
s 5:
(a) [it] states a guiding principle which is intended to be applied by
those performing functions under the RMA rather
than a specifically
worded purpose intended more as an aid to
interpretation;63
(b) [it] is a carefully formulated statement of principle intended to
guide those who make decisions under the RMA.64
The other three sections supplement the core purpose in s 5 by stating the particular obligations of those administering the RMA in relation to the various matters
identified.65
61 At [101] above.
62 King Salmon, above n 26, at [151]; see also [129].
63 At [24(a)].
64 At [25].
65 At [26].
[111] Consistent with that view, in John Woolley Trust Randerson J
observed:66
[47] ... Given the primacy of Part 2 in setting out the
purpose and principles of the RMA, I do not accept the general
proposition
mentioned at para [94] of the decision in Auckland City Council v Auckland
Regional Council, that the words “subject to Part 2” in s 104
mean that Part 2 matters only become engaged when there is a conflict between
any of the matters in Part 2 and the matters in s 104. Part 2 is the engine
room of the RMA and is intended to infuse the approach to its interpretation and
implementation throughout, except
where Part 2 is clearly excluded or limited in
application by other specific provisions of the RMA.
(emphasis added)
[112] The role of Part 2 is reinforced and reiterated in certain sections
(specifically s 104(1), 168A(3), 171(1) and 191(1)) by
the presence of the
phrase “subject to Part 2”. As the Privy Council stated in
McGuire:67
[22] ... Note that s 171 is expressly made subject to Part II,
which includes ss 6, 7 and 8. This means that the directions
in the latter
sections have to be considered as well as those in s 171 and indeed override
them in the event of conflict.
The meaning of the “subject to” drafting method had been
previously explained by
Cooke P in Mangonui County Council.68
[113] However the provisions with which King Salmon was concerned
did not contain that phrase. Furthermore the role of Part 2 in s 66(1) had to
be viewed in the light of the direction
in s 67(3) which the Supreme Court
described as follows:
[85] First, while we acknowledge that a regional council is directed by
s 66(1) to prepare and change any regional plan
“in accordance
with” (among other things) Part 2, it is also directed by s 67(3) to
“give effect to” the
NZCPS. As we have said, the purpose of the
NZCPS is to state policies in order to achieve the RMA’s purpose in
relation to
New Zealand’s coastal environment. That is, the NZCPS gives
substance to Part 2’s provisions in relation to the coastal
environment.
In principle, by giving effect to the NZCPS, a regional council is necessarily
acting “in accordance with”
Part 2 and there is no need to refer
back to the part when determining a plan change. There are several caveats to
this, however,
which we will mention shortly.
66 Auckland City Council v John Woolley Trust, above n 53, at [47]; the highlighted words were referred to in Ayrburn Farms Estate Ltd v Queenstown Lakes District Council, above n 6, at [99] and in Man O’War Station Ltd v Auckland Regional Council [2011] NZHC 469; (2011) 16 ELRNZ 475, [2011] NZRMA 235 (HC) at [20].
67 McGuire, above n 19.
68 At [38] above.
[114] In a sense King Salmon might be viewed as a case where, to
adopt the phrase of Randerson J in John Woolley Trust, Part 2 was limited
in application by other specific provisions of the RMA although I consider that
it would be more accurate to
say that its application was provided for in a
particular way.
[115] The Board’s error in King Salmon lay in considering that
it was entitled, by reference to the principles in Part 2, to carry out a
balancing exercise of all relevant
interests in order to reach a decision
whereas it was obliged to deal with the plan change application in terms of the
NZCPS and
failed to do so.69 The Supreme Court summarised the
Board’s approach in this way:
[83] On the Board’s approach, whether the NZCPS has been given
effect to in determining a regional plan change application
depends on an
“overall judgment” reached after consideration of all relevant
circumstances. The direction to “give
effect to” the NZCPS is,
then, essentially a requirement that the decision-maker consider the factors
that are relevant in
the particular case (given the objectives and policies
stated in the NZCPS) before making a decision. While the weight given to
particular factors may vary, no one factor has the capacity to create a veto
– there is no bottom line, environmental or otherwise.
The effect of the
Board’s view is that the NZCPS is essentially a listing of potentially
relevant considerations, which will
have varying weight in different fact
situations ...
[116] I consider that the Decision in the present case demonstrates that
the Board correctly analysed and well understood the ratio
of the King Salmon
decision.70
[117] However the Board’s task in the present matter was different,
as reflected in
Mr Palmer QC’s submission:
8.10 Rather, the Board is required by s 171, “subject to Part 2, to
consider the effects on the environment of allowing
the requirement”,
“having particular regard” to various factors including the adequacy
of alternatives and the
relevant provisions of the planning documents. So
consideration of the effects, subject to Part 2, having particular regard to the
stated matters is (as the Board said, at [170]) the “focal point of the
assessment”. Planning documents do not determine
the outcome of a s 171
decision, unlike the NZCPS which can determine a plan change decision under s
67.
[118] It is apparent that the Board understood not only the different nature of its task in considering an application under s 17171 but also the implications of the
“subject to Part 2” component:
69 King Salmon, above n 26, at [153]–[154].
70 [179]–[180] of the Final Decision at [105] above.
[183] Further and perhaps more importantly, as we have already noted,
Section 171(1) and the considerations it prescribes are expressed
as being
subject to Part 2. We accordingly have a specific statutory
direction to appropriately consider and apply that part of the Act in making
our determination. The closest corresponding requirement with
respect to
statutory planning documents is that those must be prepared and changed in
accordance with ... the provisions of Part 2.
[184] For the above reasons, the statutory framework and expectation of
Section 171(1) relevant to our current decision can be
contrasted with the
situation in King Salmon. The plan change being considered in that case
was required to give effect to a higher order planning document which the
Supreme Court considered should already give substance to pt 2’s
provisions in relation to ... [the] coastal environment. By
contrast, here we are required to consider the environmental effects of the
NoR, subject to Part 2 and having particular regard to the
relevant statutory planning documents.
Consideration of alternative options – an overview
[119] The Decision recorded that NZTA acknowledged that both prerequisites
in s 171(1)(b) applied with respect to the Project.
In any event the Board
concluded that the Project would have significant adverse effects, including
heritage, amenity and landscape
matters.72
[120] Consequently the Board was required in considering the effects on the
environment under s 171(1) to have particular
regard to whether
adequate consideration had been given by NZTA to alternative sites, routes or
methods of undertaking the
work.
[121] As the Board noted in its introduction to the s 171(1)(b)
issue,73 a feature of the hearing process was the strong assertions
by some of the parties that there had not been adequate consideration of
alternative options. The Board recorded that an enormous amount of information
had been put before it about the methodology of the
option selection process and
how that process took into account the significant effects of the
Project.
[122] Opponents of the application presented alternative options to the
Board in order to establish that such options were not suppositious
and should
have been
71 [181]–[182] at [70] above.
72 At [1084(c)].
73 At [1082]–[1083].
explored as part of the option evaluation process. The Board’s
conclusion that there had been a failure to adequately assess
non-suppositious
options is the focus of Issue 1B.
Chronology
[123] In what the Board described as a “somewhat complex
chronology”74 the Decision provides a thorough review of
the historical background and the chronology of the option process spanning
[1097]
to [1164] under the following headings:
(a) March 2001: Scheme assessment report by Meritec;
(b) 2006 to 2008: Ngauranga to Wellington Airport strategic study and
the
Corridor Plan;
(c) 2008 to 2009: Basin Reserve Inquiry-By-Design workshop; (d) January 2011: Feasible Options Report;
(e) July and August 2011: Public engagement and refinement of the
preferred option;
(f) Tunnel options; (g) BRREO option.
[124] At the Inquiry-By-Design workshop five options were selected for further consideration comprising one at-grade option (with a variation) and four grade-separated bridge options. In order that the discussion below of the several Issue 1 questions may be comprehensible to those who may not read the Decision, I
set out certain key passages from the Board’s
chronology:
74 At [1165].
[1118] Between 2009 and 2010, the five options were subjected to further
detailed analysis, which resulted in one of the at-grade
variants being
discarded. During this process, one more option was uncovered and added. During
2010, as a result of the government
signalling a possibility of contributing
financially to a tunnel under the proposed NWM Park, a tunnel option (Option F)
was added,
making six options in all.
...
[1122] The Feasible Options Report on page 67 sets out the conclusions and
recommendations:
Our team recommended options A and B as preferred options if more weight is
given to urban design, social impacts, and long term strategic
fit. Of those
two options, option A is the better of the two when giving more weight to these
criteria. Option A requires the
relocation of the [former Home of Compassion]
Crèche. We acknowledge that while relocating heritage buildings is not
favoured,
this may be mitigated to some extent by being able to relocate the
Crèche building to provide improved connections to Buckle
Street or to
relocated the Crèche to a larger historic precinct closer to the War
Memorial.
[1123] Following development of the options and before the evaluation of the
options, the tunnel option (Option F) was removed and
the explanation given
was:
Following development of the options the specialists received a
data-pack containing a description of Options A to E together
with sufficient
information to enable them to undertake peer assessment. It is important to note
that the specialists are only comparing
the options which permit SH1 to be
at-grade in front of the War Memorial: Options A to E. Once the
government makes a decision on whether to fund the War Memorial Tunnel, Option
F will be assessed with other options
which permit SH1 to be located in a tunnel
in front of the War Memorial.
[our emphasis]
...
[1125] This suite of five options was assessed against evaluation criteria
as reported in Section 5.3 of Technical Report 19.
Using a pair-wise
comparison and a weighting process, the workshop participants recommended
Option A and Option B –
both grade-separated bridge options. Option A
eventually evolved into the Project.
...
[1138] In mid-2012, the government was exploring whether it would construct the NWM Park in time for the 100th Gallipoli Remembrance in
2015, including the idea of locating Buckle Street under the park. [NZTA]
asked the Project team to reappraise the cost of Option F. This review was carried out with respect to both Options F and X. By letter dated
3 July 2012, Opus set out what it termed an alternate review. The
letter concluded:
Conclusions
1. NZTA has previously determined that Option F was
unaffordable. A decision by the government to underground
Buckle Street will
not change this decision.
2. Option X is likely to be more expensive than Option A while having
no more (possibly less) transportation benefits. It
is unlikely that Option X
would prove to be preferable to Option A.
3. A decision by the government to underground Buckle Street will
not change the outcomes of the option evaluation
process used to compare
alternatives at the Basin Reserve.
4. Option A remains the preferred option even if the
government decides to underground Buckle Street.
[1139] On 7 August 2012, the government announced that the NWM Park would be
completed by April 2015 and that empowering legislation
would be enacted and
that it would be contributing $50m towards the costs of undergrounding Buckle
Street.
...
[1132] On 17 August 2012, [NZTA] confirmed and announced Option A as the
preferred option. They also confirmed that a pedestrian
and cycling facility
would be added to the Basin Bridge to provide a link between Mt Victoria Tunnel
and Buckle Street.
...
[1151] In January 2013, Richard Reid and Associates supplied to the City
Council conceptual drawings for improving the lane configuration
around the
Basin Reserve roundabout. Before us, Mr Reid produced an enhanced proposal he
called the Basin Reserve Roundabout Enhancement
Option (the BRREO
Option). ...
[1152] Essentially, but somewhat simplistically, the BRREO Option proposes an upgrading of the existing roundabout by widening Paterson Street westbound up to the Dufferin Street stop line and widening Dufferin Street to between Paterson Street and Rugby Street, in each case to three lanes. This would provide three continuous lanes westbound around the roundabout from the exit from the Mt Victoria Tunnel to Buckle Street. It also proposes to add a third lane on Paterson Street for westbound traffic in the event of the duplication of the Mt Victoria Tunnel.
The Board’s general approach
[125] In a section of the Decision spanning [1085] to [1096] the Board
directed itself on the proper approach to and the application
of s 171(1)(b).
After a discussion of aspects of Queenstown Airport75 (which
is the focus of the questions in Issues 1A and 1B) and after considering the
meaning of adequate consideration, the Board described
its task as
follows:
[1090] Subsection 1(b) requires a judgement on whether an adequate
process has been followed, including an assessment of what
consideration has
been adopted. The enquiry is not into whether the best alternative has been
chosen. It is not incumbent on a
requiring authority to demonstrate that it has
considered all possible alternatives or that it has selected the best of all
available
alternatives. Rather, it is for the requiring authority to establish
an appropriate range of alternatives and properly consider
them.
[126] The Board’s findings on the consideration of alternatives
stated:
[1215] Clearly, the purpose of the statutory direction in Section 171(1)(b)
of the RMA is to ensure that the decision to proceed
with the preferred option
is soundly based and other options (particularly those with reduced adverse
environmental effects) have
been dismissed for good reason. Adequate
consideration becomes even more relevant when the Project, as here,
involves significant
adverse environmental effects.
[1216] We find the consideration of alternatives has, in the circumstances
of this case, been inadequate for the reasons set out
above, which
include:
[a] A lack of transparency and replicability of the option
evaluation; and
[b] A failure to adequately assess non-suppositious options,
particularly those with potentially reduced environmental effects.
[127] In Issues 1A to 1G addressed below NZTA challenges various aspects of
the Board’s approach in coming to the conclusion
that NZTA had not given
adequate consideration to alternatives to the proposed flyover. The questions
of law which NZTA invites
the Court to consider include several in the
Edwards v Bairstow category.
[128] The respondents contend that most of NZTA’s points of
contention are dressed up in the legal language
of “tests”
and “thresholds” but are, in effect,
75 Queenstown Airport, above n 22.
challenges to the Board’s view of the facts and hence beyond the proper
ambit of this
appeal.
Subissue 1A: Relating the measure of adequacy to the adversity of
effects
[129] The general requirement in the original s 17176 to have
particular regard to whether adequate consideration had been given to
alternative sites, routes or methods of achieving
the work was confined in
2003 to two scenarios,77 namely if:
(a) the requiring authority does not have an interest in the land sufficient
for undertaking the work; or
(b) it is likely that the work will have a significant adverse effect on the
environment.
[130] The former scenario was the subject of consideration in Queenstown Airport.78 Queenstown Airport Corporation wished to provide for the expansion of Queenstown Airport and to achieve that objective it issued a notice of requirement seeking in effect to acquire approximately 19 hectares of land owned by Remarkables Park Ltd. The Environment Court rejected that part of the NoR seeking to provide for a precision instrument approach runway and a parallel taxiway and as a consequence the area of land subject to the NoR was reduced to
8.07 hectares.
[131] In the course of considering s 171(1)(b) on appeal Whata J
said:
[121] The section presupposes that where private land will be affected by
a designation, adequate consideration of alternative
sites not involving private
land must be undertaken by the requiring authority. Furthermore, the
measure of adequacy will
depend on the extent of the land affected by the
designation. The greater the impact on private land, the more careful the
assessment
of alternative sites not affecting private land will need to
be.
[132] In its closing statement to the Board NZTA contended that
Queenstown
Airport was relevant for three purposes, the first of which
was:
76 At [32] above.
77 At [95] above.
78 Queenstown Airport, above n 22.
... it establishes that the concept of adequacy in section 171(1)(b) is a sliding scale, with the measure of adequacy depending on the extent of private land affected by the designation. The extent of land required for the Basin Bridge Project is shown on the preliminary land requirement plans and schedule (sheets 2A.01–03). These show that, of the 46 titles affected by the NOR footprint, only 8 are privately owned. Expressed in land area, 0.3 ha of the
2 ha to which the NOR relates is privately owned. Applying the reasoning in the Queenstown Airport Corporation Limited decision, this would suggest
that a less careful assessment of alternative sites is required. However,
[NZTA] has not sought to undertake a less careful assessment of alternatives.
Instead, it considers that the assessment it has undertaken
is thorough and
robust.
[133] After setting out para [121] of Queenstown Airport, the Board
said:
[1087] In this case, the extent of private land subject to the proposed
designation is not significant. However, as we have said,
[NZTA] acknowledged
(and our assessment confirms) that the work would be likely to have a
significant adverse effect
on the environment. While Justice
Whata’s comments applied to the impact on private land, the same logic
must apply
to the extent of the Project’s adverse effects. The measure of
adequacy of the consideration of alternatives will depend on
the impact on the
environment of adverse effects.
[1088] Accordingly, we must be satisfied that the assessment of alternative
sites was adequate, in light of our findings as to the
Project’s effects
on the environment. The more significant the adverse effects (as we have found
them to be), the more careful
the assessment of alternatives that is
required.
[134] On appeal NZTA seeks to resile from its stance before the Board,
proposing to argue that the Board erred in law by adopting
the logic of
Queenstown Airport and extending it to s 171(1)(b)(ii). It seeks to
argue first that different considerations apply according to whether the
designation
will impose restrictions on private land and secondly that there is
no “sliding scale” according to the degree of adverse
effect. NZTA
accordingly invites the Court to consider the following question of law:
Does s 171(1)(b) of the Act require a more careful consideration of
alternatives where there are more significant adverse
effects of allowing the
requirement?
[135] NZTA’s change in stance was resisted by Mr Palmer who cited an
impressive list of authorities deprecating reversals
of position in lower
courts.79 While mindful
79 Ihaka Te Rou v Love (1891) 10 NZLR 529 (CA); Grobbelaar v News Group Newspaper [2002] 1
WLR 3024 (HL); TV3 Network Services Ltd v ECPAT New Zealand Inc [2003] NZAR 501 (HC);
Wymondley against the Motorway Action Group Inc v Transit New Zealand [2004] NZRMA 162
of the reasons that have been advanced over time, I consider in the
circumstances of this case where the issue involved is a question
of law that it
is in the broader interest to consider the argument which NZTA wishes to
advance. In doing so I am particularly
influenced by the approach of
the Privy Council in Foodstuffs (Auckland) Ltd v Commerce
Commission:80
Their Lordships gave leave to do so on the basis of this lack of material
prejudice and also because they considered it important,
albeit the issue is now
essentially spent, to determine the case on the correct legal footing. Not only
does that accord with justice
between the parties, but it also seemed
appropriate from the point of view of ascertaining the true intention of
Parliament
when the amending legislation was enacted.
Q 4(a): Does s 171(1)(b) of the Act require a more careful
consideration of alternatives where there are more significant
adverse effects
of allowing the requirement?
[136] NZTA’s argument was structured as follows:
(a) the two scenarios in s 171(1)(b)(i) and (ii) are thresholds
for any consideration of alternatives and do not
give rise to a need
for “closer” scrutiny;
(b) the RMA does not mandate any “hard-look” or
“anxious scrutiny” concept such as have been considered
in the
context of judicial review and applied where fundamental human rights are at
stake;
(c) Whata J erred in introducing the concept of a different measure of
adequacy according to the level of impact of
the designation on
private land;
(d) the Board was equally, if not more, wrong to extend that logic to
the degree of adverse effects;
(e) if Queenstown Airport was correct in importing a sliding
scale of adequacy, then such should only apply to the first limb of s
171(1)(b).
(HC); New Zealand Meat Board v Paramount Export Ltd (in liq) [2004] UKPC 45; [2005] 2 NZLR 447 (PC);
Patcroft Properties Ltd v Ingram [2010] NZCA 275, [2010] 3 NZLR 681.
80 Foodstuffs (Auckland) Ltd v Commerce Commission [2004] 1 NZLR 145 (PC) at [9].
[137] The section requires that where either scenario exists not only must
there be consideration of alternative sites but that
such consideration should
be “adequate”. It appeared to be common ground that the meaning of
“adequate”
was as stated by the Environment Court in Te Runanga O
Ati Awa Ki Whakarongotai Inc v Kapiti District Council:81
... The word ‘adequate’ is a perfectly simple word and we have no
doubt has been deliberately used in this context.
It does not mean
‘meticulous’. It does not mean ‘exhaustive’. It
means ‘sufficient’ or ‘satisfactory’.
No challenge was made to the Board’s analysis of the meaning of
adequate at [1089].
[138] It was the respondents’ contention that the adequacy (or
sufficiency) of consideration in any given case must
be circumstances dependent
and that that must be so for both scenarios, given that the phrase
“adequate consideration”
appears in the chapeau to subparagraphs (i)
and (ii).
[139] Mr Palmer drew attention to the decision of the Supreme Court in
King
Salmon,82 in particular to the highlighted part of the
following passage:
[170] This brings us back to the question when consideration of
alternative sites may be necessary. This will be determined by
the nature and
circumstances of the particular site-specific plan change application. For
example, an applicant may claim that
that (sic) a particular activity needs to
occur in part of the coast environment. If that activity would adversely
affect the preservation
of natural character in the coast environment, the
decision-maker ought to consider whether the activity does in fact need to occur
in the coastal environment. Almost inevitably, this will involve the
consideration of alternative localities. Similarly, even where
it is clear that
an activity must occur in the coastal environment, if the applicant claims that
a particular site has features that
make it uniquely, or even especially
suitable for the activity, the decision-maker will be obliged to test that
claim; that may well
involve consideration of alternative sites, particularly
where the decision-maker considers that the activity will have significant
adverse effects on the natural attributes
of the proposed site. In short,
the need to consider alternatives will be determined by the nature and
circumstances of the particular application relating
to the coastal environment,
and the justifications advanced in support of it, as Mr Nolan went some way to
accepting in oral argument.
82 King Salmon, above n 26.
[140] In my view the analysis in Queenstown Airport is correct. I
consider that it must logically apply to both the scenarios described in s
171(1)(b). It is simply common sense that
what will amount to sufficient
consideration of alternative sites will be influenced to some degree by the
extent of the consequences
of the scenarios in s 171(1)(b)(i) and (ii). That
said, I doubt the utility of the expression “sliding scale” as a
description of the extent of the consequences because it conveys an unduly
mechanical approach to the extent of consideration required.
[141] Accordingly I consider that the Board’s approach at [1087] to
[1088] is not
vulnerable to criticism.
[142] So far as Q 4 is concerned, the word “require” is
problematic. A more careful consideration of alternatives may
or may not be
required: it will be very much circumstances dependent. I would answer in the
affirmative either of the following
rephrased questions of
law:83
(a) May s 171(1)(b) of the Act require a more careful
consideration of alternatives where there are more significant adverse effects
of allowing
the requirement?
(b) Does s 171(1)(b) of the Act permit a more careful
consideration of alternatives when there are more significant adverse
effects of allowing the requirement?
[143] In the context of Subissue 1A NZTA poses a second and alternative
question of law:
Q 4(b) In the alternative, was the finding that [NZTA] had not
given sufficient careful consideration to alternatives a
finding to what the
Board could reasonably have come on the evidence?
[144] Mr Casey addressed this question in conjunction with the similarly
expressed
Q 22 in Subissue 1G. I adopt the same approach.
83 Although I have retained the word “careful”, because that word is employed in Queenstown Airport and hence in the question posed, I suggest that it may be preferable to avoid the notion of degrees of “care”. My preference would be a phrase such as “greater scrutiny”.
Subissue 1B: The requirement to consider all non-suppositious options with
potentially less adverse effects
[145] Following paragraph [121] addressed in Subissue 1A above, Whata J
further said:
[122] It is beyond doubt that the extent of private land subject to the
proposed designation is significant. As notified 19 ha
would be affected. The
modified version still encompasses 8 ha. The Court had to be satisfied that the
assessment of alternative
sites was adequate having regard to this impact.
There is authority however that a suppositious or hypothetical alternative need
not be considered. But given the statutory requirement to have particular
regard to the adequacy of the consideration given to alternatives,
it is not
sufficient to rely on the absence of a merits assessment of an alternative or on
the assertion of the requiring authority.
Provided there is some evidence that
the alternative is not merely suppositious or hypothetical, then the Court must
have particular
regard to whether it was adequately considered.
[146] The third respect in which NZTA contended before the Board
that
Queenstown Airport was relevant concerned this issue:
11.2(c) Third, should the Board find that any alternative suggested by a
submitter (such as BRREO) is not hypothetical or suppositious,
then the Board
must have particular regard to whether it was adequately considered.
[147] Specifically in the context of the assessment of alternatives NZTA
recorded that the parties were in agreement that:
Speculative, suppositious or hypothetical alternatives need not
be considered. However, provided there is some evidence
that an alternative is
not merely suppositious or hypothetical, then the Board must have particular
regard to whether it was adequately
considered.
NZTA’s case was that all relevant alternatives had been adequately
considered.
[148] Under the heading “Non-Suppositious Options, with
Potentially Reduced
Environmental Effects” the Board said:
[1182] Because of the Project’s significant adverse environmental effects (as we have found them to be) it was necessary for [NZTA] to give adequate consideration to alternatives, particularly those options with reduced environmental effects. As we have said, the measure of that adequacy would depend on how significant the adverse effects would be. In this case, we have found that there would be significant adverse effects.
[1183] A number of options were referred to in the evidence. The option
evaluation team considered some of them at various stages
of the process. The
Architectural Centre and Richard Reid and Associates, on behalf of the Mt
Victoria Residents Association, put
options before us. This was not for the
purpose of persuading us that their options were better, but to establish that
these options
were not suppositious, would potentially have reduced
environmental effects than the Project before us, and should have been explored
as part of the option evaluation process.
[1184] The evaluation teams considered both tunnel and at-grade options. The
tunnel options were synthesised down to a tunnel option
known as Option F. The
Architectural Centre’s Option X, proffered during 2011, was another
variant of a tunnel option.
...
[1186] The BRREO Option consisted of improving the lane configuration around
the Basin Reserve. When introducing his concept, Mr
Reid told us:
19. The existing network has sustained NZTA’s many attempts to
engineer a motorway ‘solution’ over the past
50 years. These
‘solutions’ have almost always diverted highway traffic
northwards from its current route around
the Basin Reserve roundabout and
involve a flyover or tunnel structure which invariably destroys the amenity of
the Basin Reserve
and the urban structure of the city.
20. I believe the existing network will continue to have
sufficient flexibility, tolerance and resilience to serve the
city well into the
future. The objectives to the project can be met without the need for the Basin
Bridge proposal.
[1187] We heard a considerable amount of evidence on these options. The
evidence reached the threshold of requiring our careful
consideration. We
propose to consider first the tunnel options and secondly the at-grade
options.
[149] In concluding its discussion of certain options the Board then
said:
[1213] As we have said, it is not for us to determine which is the best
option. The statutory requirement directs us to have particular
regard to the
adequacy of consideration of alternatives. Mr Justice Whata said in
the Queenstown case that, where there is evidence that the alternative is
not merely suppositious or hypothetical, then the Court (or in this case
this
Board) must have particular regard to whether it was adequately
considered.
The Board concluded that NZTA’s consideration of alternatives had been inadequate
for reasons which included a failure to adequately assess non-suppositious
options, particularly those with potentially reduced environment
effects.84
84 At [126] above.
[150] NZTA acknowledged that before the Board it had accepted the
proposition which is reflected in [1213]. However it submitted
that on
reflection the proposition at [122] of Queenstown Airport goes too far or
should be limited to the first limb of s 171(1)(b). NZTA again sought on appeal
to reverse its stance before the
Board and it proposed for consideration the
following question of law:
Q 7(a) Does s 171(1)(b) require the requiring authority to fully evaluate
every non-suppositious alternative with potentially reduced
environmental
effects?
[151] On this issue also I am prepared to consider the question of law,
thereby permitting NZTA to reverse its stance below, for
the same reasons as
stated in the context of Subissue 1A at [135] above.
Q 7(a): Does s 171(1)(b) require the requiring authority to fully evaluate
every non-suppositious alternative with potentially reduced
environmental
effects?
[152] As is apparent from ground of appeal 8(b), NZTA’s contention is
that the Board had required NZTA to demonstrate
that it had
considered every non-suppositious option with potentially less adverse
effects. NZTA’s argument was
that in so doing the Board had elevated the
standard of consideration beyond “adequacy”.
[153] Referring to what it described as the classic approach, namely that a
requiring authority is not required to eliminate speculative
alternatives or
suppositious outcomes, NZTA submitted:
16.7 In Queenstown Airport and the Majority’s decision, this
test has been inverted to require every non-suppositious option to have
been considered. Indeed, the Majority’s decision takes the test a step
further and requires
other options with potentially less adverse effects
to have been dismissed only for good reason.
16.8 This takes the test of adequacy too far. In any significant project there are likely to be any number of options and variations of options that could be considered. It is unreasonable to expect a requiring authority to give detailed consideration to every permutation of the non-suppositious. That is, there may be any number of permutations of the (for example) at-grade option; [NZTA] does not have to show that it specifically addressed each and every one.
[154] I do not accept that the Board approached its task in the manner
suggested by
NZTA. On the contrary (as NZTA acknowledged) the Board said:
[1090] Subsection 1(b) requires a judgement on whether an adequate
process has been followed, including an assessment of what
consideration has
been adopted. The enquiry is not into whether the best alternative has been
chosen. It is not incumbent on a
requiring authority to demonstrate that it has
considered all possible alternatives or that it has selected the best of all
available
alternatives. Rather, it is for the requiring authority to establish
an appropriate range of alternatives and properly consider
them.
[155] Mr Palmer neatly captured the point here when he
submitted:
NZTA appears to wish to elide the point that witnesses
identified non-suppositious options with reduced environmental
effects with the
point that NZTA’s consideration of alternatives was not adequate, to
create a straw man that the Board required
NZTA to examine every possible
alternative. It certainly did not.
[156] The answer to Q 7(a) is, therefore, in the negative.
[157] While not accepting that s 171(1)(b) creates a duty to
consider all non-suppositious options, in section 17
of its primary
submissions NZTA mounted a reasonably extensive argument that it had in fact
considered the options identified by
the Board as non-suppositious and that its
consideration had been adequate.
[158] The respondents attacked this argument as being blatantly a
disagreement with the Board’s assessment of the facts and
not a question
of law as required by s 149V(1).
[159] As noted in the discussion of “a question of law”85 the Board’s conclusions on fact can only be challenged on an Edwards v Bairstow basis. NZTA recognises that reality by the formulation of the questions comprising Q 7(b)(i), (ii) and (iii). I proceed to address them, albeit reframed to align precisely with Lord Radcliffe’s
third description for the reasons explained at [16] to [23]
above.
85 At [12]–[15] above.
Q 7(b)(i): Is the case one in which the true and only
reasonable conclusion contradicts the determination that BRREO
was a
non-suppositious option?
[160] With reference to at-grade options (including BRREO) NZTA first
submitted that the Board’s finding, that such options
had not been
adequately considered, “was not a finding that it could reasonably have
come to on the evidence”. That,
of course, was not the nature of the
Edwards v Bairstow question framed in relation to BRREO.
[161] The argument was then developed in this way:
(a) the Majority failed to evaluate the evidence of the independent
peer reviewers and to determine whether an at-grade solution,
such as BRREO,
could meet the Project objectives;
(b) in the absence of a finding from the Majority to the contrary, the
Minority’s finding that an at-grade option could
not meet the Project
objectives must stand;
(c) an option that does not meet the Project objectives should
be considered to be a suppositious option.
[162] However the issue which I am required to determine is not whether BRREO was or was not a suppositious option but whether the true and only reasonable conclusion contradicts the Board’s conclusion. In addressing the reframed question I remind myself of the Supreme Court’s direction in Bryson that appellate judges must keep firmly in mind that on a challenge of this nature an appellant faces a very high
hurdle.86
[163] The nature of the Board’s consideration of and conclusion on
the BRREO
option is apparent from the following
paragraphs:87
86 At [14] above.
87 The issue is also touched on at [1210] and [1214].
[1162] We do not propose to resolve the apparent conflicts in the evidence
relating to BRREO. It is not for us to determine the
best option. The
question is whether this less-harmful option is hypothetical or suppositious. We
bear in mind that BRREO is still
at an indicative stage and could be subject to
more detailed analysis, such as to geometry and intersection control
phasing,
by an option evaluation process.
[1163] At its worst, Mr Dunlop acknowledged that general traffic and
freight would receive some benefit from the BRREO Option,
now and following
duplication of the Mt Victoria Tunnel, but he quantifies that the transport
benefits (over 40 years) would be approximately
40% less than the benefits the
Project can achieve. However, following a detailed assessment, he noted that
both the Project and
BRREO displayed significant journey time savings over the
do-minimum scenario, which includes improvements to the Vivian Street/Pirie
Street and Taranaki Street/Buckle Street intersections.
[1164] We are satisfied the BRREO Option, particularly having regard to the
adverse effects we have identified with regard to the
Project, is not so
suppositional that it is not worthy of consideration as an option to be
evaluated.
[164] Given the preliminary nature of the Board’s appraisal and the
material to which it referred I do not consider that it
could fairly be said
that the Board’s finding on the BRREO option was insupportable. The answer
to Q 7(b)(i) is No.
Q 7(b)(ii): Is the case one in which the true and only
reasonable conclusion contradicts the determination that Option
X was an
option with potentially less adverse effects?
[165] NZTA’s submissions on Option X echoed its BRREO
submission in combining different points of complaint:
(a) in the absence of an explicit finding by the Majority, the
Minority’s
finding that Option X had been adequately considered must stand;
(b) a finding that Option X had not been adequately considered was not a
finding that could reasonably be reached on the evidence;
(c) there was no evidence to support a finding that Option X was an option
with potentially less adverse effects.
Only the third of those points of criticism engages with Q 7(b)(ii).
[166] The genesis of Option X was described at
[1135]:88
[1135] During the period from 2007–2009, the Architectural Centre
developed a concept that later became known as Option X.
It provided for
westbound State Highway 1 traffic to travel at grade in front of the Basin
Reserve northern entrance. All vehicles
travelling between Adelaide Road and
Kent and Cambridge Terraces would be diverted around the western sides of the
Basin Reserve
along Sussex Street. Local traffic would pass over a War
Memorial Tunnel providing grade separation. The removal of circulatory
traffic
on the eastern side of the Basin Reserve would enable the Dufferin/Rugby Street
corner to be developed into a park area.
[167] In the course of its conclusions the Board at [1319]89
stated that it was satisfied on the evidence that similar transportation
benefits as those from the Project could be achieved by
a tunnel option or
variant similar to Option X and that such should have been included in a robust
option evaluation process.
[168] Mr Palmer contended that the Board did not make a finding that Option
X was an option with potentially less adverse effects.
Neither the amended
notice of appeal nor NZTA’s submissions indicated where in the Decision
such a finding was made.
[169] While I was unable to identify a specific finding to that effect, I
inferred that the basis for the allegation was the second
of the two overarching
themes which the Board at [1171] described as being worthy of careful
consideration, namely “the consideration
given to non-suppositious
options, with potentially reduced environmental effects”.90
As Option X was discussed in the section which followed, then it could
fairly be assumed that it met that description.
[170] It was Mr Milne’s submission by reference to several items in the transcript that there was evidence from which it could have been found that Option X or a variant of it, if it had been properly considered within the context of the National War Memorial Tunnel, might have less adverse effects. He also made the point that NZTA had found Option X to have sufficient merit to warrant preliminary and later
more detailed consideration, as had WCC. He submitted that that of
itself was
89 At [234] below.
90 At [178] below. Essentially the same statement was made at [1183].
indicative that both entities accepted that an Option X variant could
potentially have lesser environmental effects.
[171] On the basis of that material I consider that there was
evidence which warranted the Board including Option X
within the category of
options which had “potentially” reduced environmental effects.
NZTA has not demonstrated that
a different view was the true and only reasonable
conclusion.
Q 7(b)(iii): Is the case one in which the true and only
reasonable conclusion contradicts the determination that a
long tunnel
option was a non-suppositious option?
[172] Ground of appeal 8(a)(iii) asserted that the evidence showed
that NZTA considered the long tunnel option to be unaffordable,
that the Board
acknowledged at [1206] that affordability is properly a matter for the requiring
authority and that consequently the
Board could not reasonably conclude that the
long tunnel option was non-suppositious.
[173] While cost can be exclusionary, it was apparent the Board had reservations about the consistency in the assessment of cost among the options and the omission to undertake a reassessment subsequent to the government’s decision to underground Buckle Street. Under the heading “Affordability” the Board observed with reference
to Option F:91
[1204] As we have said, notwithstanding that Option F provided
better overall outcomes than Option A in respect of
the simplified
evaluation criteria, Option F was dismissed on the basis of being
unaffordable. Mr Durdin pointed out
in the Abey Peer Review Report that the
additional weighting given to economic efficiency, when comparing Option
A to Option
F, was inconsistent with the approach used to identify Options A
and B as being preferred to Options C and D, in the evaluation of
the initial
options. In that instance, the assessment concluded that a difference in
Benefit-Cost Ratio of approximately 0.5 was
insignificant for a project of this
scale, yet the difference in BCR between Option A and Option F is of a similar
magnitude given
the additional costs of Option F and the similar level of
benefits generated by each option. He concluded:
The apparent inconsistency and
lack of transparency in the underlying process by which options
have been compared
in different stages of the project is a significant
concern of the reviewers.
[1205] In his concise summary of evidence, Mr Durdin again said:
My concern is that Technical Report 19 provides its recommendation on
preferring Option A over Option F on the basis of affordability.
The lack of
transparency around this process has led me to question the extent to which this
can be considered a substantive assessment
of alternatives.
[1206] We agree with Mr Cameron that the question of affordability is a
matter for [NZTA]. As pointed out by Mr Cameron, the cost
of an option could
make the option unrealistic. However, affordability is a relative term. In the
context of this case, where we
have found that there would be significant
adverse effects, there is a greater need to test the cost against the adverse
effects
in a transparent and comparative evaluation against other options. This
should have been done at the Feasible Options Report stage.
It was not.
[1207] Option F was removed from that process on the grounds of
affordability. At the time it was removed there was a
clear statement of
intent in the Feasible Options Report to assess Option F once the
Government made a decision whether
to fund the NWM Park and Buckle Street
Underpass. This was not done once that decision was made by the Government.
Rather, an
ex post facto comparison of Options A, F and X was appended as
Appendix B to Technical Report 19. At this stage [NZTA] had indicated
a
preference for the Basin Bridge (Option A) and were preparing to lodge
the application documents.
[174] Although a number of items of evidence were cited by the respondents
in their opposition on this issue, in my view those observations
of the Board
suffice to repel the argument that a different determination on the
non-suppositious nature of Option F was the true
and only reasonable
conclusion.
Subissue 1C: Interpreting adequacy as requiring transparency and
replicability
Context
[175] To comprehend the nature of NZTA’s complaint it will assist to
refer in a little
more detail to aspects of the chronology of events and the Board’s discussion.
[176] With reference to the suite of five options referred to in
[1125]92 the Board said:
[1125] This suite of five options was assessed against evaluation criteria
as reported in Section 5.3 of Technical Report 19.
Using a pair-wise
comparison and a weighting process, the workshop participants recommended
Option A and Option B –
both grade-separated bridge options. Option A
eventually evolved into the Project.
[1126] The option evaluation did not identify whether certain evaluation
criteria were given more weight than others until the end
of the process. This
made following the process to arrive at the preferred option difficult to
follow.
[1127] Mr Milne’s cross-examination of Dr Stewart focused on
this apparent lack of transparency at some length.
While it became apparent
that weighting was applied at different stages of the process, just how those
weightings were applied
was not explained. A clear expression of the
weighting factors would have made it much easier to follow and would have
enabled
a replication of the selection process.
[1128] Abley Transportation Consultants, instructed by the Board to peer
review aspects of the transportation issues including alternatives,
attempted to
replicate the selection process used to arrive at the preferred options. Several
scoring systems were applied to the
negative and positive effects ratings
presented in Technical Report 19. By assuming equal weighting for each
criteria, their analysis
concluded that the at-grade Option D should receive
the highest ranking. This highlights the sensitivity of the outcome to the
relative weightings of the criteria.
[1129] Of note also are the following comments from page 65 of the
Feasible Options Report:
[177] After discussing the March 2013 option evaluation recorded in
Technical Report 19, the Board referred to the Traffic and
Transportation
Effects Peer Review of 25 November 2013 by Abley Transport Consultants which
concluded with the observation:
The apparent inconsistency and a lack of transparency in the underlying
process by which options have been compared at different stages
of the project
is a significant concern of the reviewers.
92 At [124] above.
[178] In turning to address the many criticisms levelled at the process and
its underlying methodology, the Board reminded itself
of the limitation on its
function:
[1167] At this stage, it is important to remind ourselves that Parliament
has stopped short of giving this Board the jurisdiction
to direct that any other
alternative must be selected. It would thus become an exercise in futility if
we were required to examine,
in detail, and adjudicate upon, in detail, the
merits of the various alternatives.
[1168] While there were numerous criticisms made, we propose to identify
those that we consider cogent to an overall appraisal of
the process ...
[1171] From these criticisms, we distil two overarching themes that we
consider worthy of our careful consideration:
[a] The transparency and replicability of the option evaluation;
and
[b] The consideration given to non-suppositious options, with potentially
reduced environmental effects.
The transparency and replicability of the option
evaluation
[179] While [1172] is the primary focus of NZTA’s complaint,
NZTA’s submissions analysed the Board’s observations
in several
subsequent paragraphs. It is useful to record them:
[1172] It was accepted that any evaluation process needed to be transparent.
Dr Stewart acknowledged the need for this during his
cross-examination by Mr
Milne. Mr Durdin was also of the same view. This is necessary in order that
what occurred during the option
evaluation process can be fully understood,
particularly if weightings are given to evaluation criteria. Mr Durdin
also considered
it is important that any process be replicable so that its
robustness can be tested. Thus, transparency and replicability go hand
in
hand.
[1173] It was clear from the questioning of Mr Stewart and other witnesses
that each specialist applied weighting at various stages
of the process.
However, this was not explicit and was not documented. We have already
expressed our concern about how the option
evaluation, particularly as
summarised in Technical Report 19, did not identify whether certain evaluation
criteria were given
more weight than others. This made it difficult
to follow.
[1174] The problem manifested itself by the fact that Mr Durdin was unable to replicate the selection process used to arrive at the preferred options in the Feasible Options Report. The November 2013 Peer Review (Report 1) included a test of the decision-making process using a non-weighted multi-criteria analysis approach. As Mr Durdin pointed out in his evidence-in-chief, the test was completed to check the robustness of identifying Option A as the preferred option. That process showed that
Option A could have been selected, but equally Options B, C or D could have
been selected using that approach.
[1175] Dr Stewart has accepted, both in the Joint Witness Statement –
Transportation, February 2014 and in cross-examination that:
Put simply, if a different process was used, a different recommendation may
have resulted.
[1176] All of the experts at that conference agreed.
[1177] As Mr Durdin pointed out, this demonstrated the selection is highly
reliant on the assessment technique used. He said:
Ideally, the preferred option would be identified independent of the
assessment technique thereby providing greater confidence in
the robustness of
selecting one option over another. That is not the case in this instance, as
Option A was selected using
the pair-wise analysis method, Option D would
be selected using the NZTA incremental BCR method and Option A, B, C or D could
have been selected using multi-criteria analysis.
[1178] This emphasises, or highlights, the need for transparency in
explicitly setting out the weightings that are used,
and the reason why they
have been used, in any multi-criteria analysis. This would enable a
decision-maker, in this case
this Board, to adequately carry out its statutory
functions under Section 171(1)(b). Parliament has directed decision makers to
have particular regard to whether adequate consideration has been given to
alternative sites, routes or methods of undertaking the
work. We take that
explicit direction seriously.
The issue
[180] NZTA contended that the Board erred in law in finding that, in order
to be adequate under s 171(1)(b), the consideration
of alternatives
must also be “transparent and replicable”. It framed the
following question of law:
Q 10 Does the inquiry into adequacy under s 171(1)(b) require that the
consideration of alternatives be transparent and replicable;
or is it sufficient
that the consideration is apparent?
[181] NZTA contended that the paragraphs quoted above demonstrated that the Board descended into a level of enquiry that is neither permitted nor appropriate under s 171(1)(b). It argued that, by requiring “replicability”, the Board sought to audit NZTA’s consideration of alternatives and in doing so engaged with the outcome as opposed to the process, which is not its role. In its primary submissions NZTA said:
18.7 While the consideration of alternatives must be apparent in order
for the adequacy of the consideration to be assessed, the
Majority erred in law
by requiring that the consideration be ‘transparent and replicable’.
The Majority heard detailed
and lengthy evidence regarding the consideration of
alternatives, such that the consideration given was readily apparent.
18.8 The Act does not require that the consideration given to
alternatives be replicable, or mandate the Board to conduct an audit
of the
requiring authority’s selection process. It clearly contemplates that the
requiring authority will have exercised judgement
in selecting the preferred
option.
...
18.11 ... the correct approach under s 171(1)(b) ... recognises that it is
for the requiring authority to exercise judgement and
make a policy decision as
to which option to pursue. The decision-maker should not seek to ensure that
the ‘best’ option
has been selected by auditing the consideration of
alternatives, in particular, by seeking to replicate the selection
process.
[182] As with some of NZTA’s other specified questions of law, I
consider that the inclusion of the verb “require”
misdirects the
inquiry. Certainly the Board did not suggest that in all cases a conclusion on
the adequacy of consideration of alternatives
will necessitate demonstrating
replicability. If the question is viewed as importing such a general
requirement the answer would
be No.
[183] The issue of replicability has arisen in this case because of the
fact that weightings were applied to various evaluation
criteria at various
stages of the process.93 The Board’s complaint was that the
selection process is in effect opaque in the absence of information about the
different weightings
applied. Given the Board’s perception that
NZTA’s preference for Option A had become entrenched,94 the
Board was not satisfied that the consideration of other non-suppositious options
had been adequate. It felt the need to state
that it viewed its obligation
“seriously”.
[184] NZTA’s complaint is that the Board took its role too seriously. Both the form of the question and its submissions emphasised that the inquiry is whether the requiring authority’s consideration of alternatives is “apparent”. Mr Milne’s
submissions for TAC construed that approach as
being:
93 At [176] above.
94 At [1200].
trust us ... measure adequacy by the volume of paper we produce not the
quality of the process.
[185] I do not accept NZTA’s submission95 that the Board was seeking to ensure that the “best” option had been selected by auditing the consideration of alternatives. I consider that the Board had a clear understanding of the confined nature of its role: see [1090]96 and [1167].97 While I can understand how NZTA might perceive the Board’s concern about weightings as approximating to an audit, it is clear in my view that that was not the Board’s objective. The Board’s concern as expressed at [1181] was that, absent an understanding of the weightings applied, it was not possible to determine that adequate consideration had been given to relevant
alternative options.
[186] In my view in some, but by no means in all, cases it may be necessary
for the decision-maker to gain access to the weightings
in a multi-criteria
analysis in order to be satisfied that adequate consideration has been given to
alternatives. The cases will
inevitably be circumstances dependent. I do not
consider that that is an unreasonable approach given the context of s 171(1)(b)
where:
(a) as I have held with reference to Issue 1A above, the
measure of adequacy of the consideration of alternatives
will depend on
the impact on the environment of adverse effects; and
(b) the subject of s 171(1)(b) is one of the matters to which
particular regard is to be had.
[187] I am unable to discern an error of law in the Board’s approach to this question. Indeed I perceive that this is another instance where NZTA is in effect inviting the Court, under the guise of a question of law, to second-guess the Board’s conclusions. There is force in Mr Palmer’s submission that NZTA’s argument at para 18.9 of its primary submissions, that the Board placed “too much weight on the opinion evidence of Mr Durdin”, serves to illustrate that NZTA’s real complaint
amounts to a disagreement about a matter of factual inference and
assessment.
95 At para 18.11 in [181] above.
96 At [125] above.
97 At [178] above.
Subissue 1D: Requiring the assessment methodology to incorporate
Part 2 weightings
[188] NZTA’s challenge on this issue is directed at the Board’s
concluding observations following those considered
in Issue 1C above, in
particular the emphasised words:
[1180] A failure to explain the reasons for any weighting (if any) can
create difficulty for us in exercising our statutory function
by making it
difficult for us to assess any such weightings against Part 2 and the objectives
of the Project. While we accept that each alternative does not need
to be assessed against Part 2, nevertheless, Part 2 considerations should
be
reflected in any weight given to a particular evaluation criteria (sic) over
another, as is clear from the North Island Grid Upgrade
Project Board of Inquiry
decision, quoted earlier. Furthermore, as was pointed out in the Feasible
Options Report, a key focus of the evaluation process was that the preferred
option
can be considered as that option that best meets the Project objectives
with the least overall social, community and environmental
impacts.
[1181] The failure for either the evidence or the reports to explicitly
explain what weightings were given at each of the option
evaluation stages makes
it difficult, if not impossible, to determine if adequate consideration was
given to alternative options.
(emphasis added)
[189] The amended notice of appeal at paragraph 12 contended that the Board
erred in law by finding at [1180] that considerations
under Part 2 of the Act
should be reflected in the weight given to particular evaluation criteria, and
consequently in finding at
[1181] that the failure explicitly to explain the
weightings given to criteria made it difficult, if not impossible, to determine
if adequate consideration was given to alternative options.
[190] NZTA posed the following question of law:
Q 13 Does s 171(1)(b) require the requiring authority’s
consideration of alternatives to incorporate Part 2 considerations;
including (in particular) the weight given to particular evaluation
criteria?
[191] NZTA criticised the highlighted passage on two counts. First it contended that the second sentence contained inconsistent findings. Secondly it said that the NIGUP decision was not authority for the proposition that Part 2 considerations must
be reflected in any weight given to a particular evaluation criterion over
another during the consideration of alternatives.
[192] NZTA submitted that each alternative does not have to be tested
against Part 2, citing Volcanic Cones Society98 and
Queenstown Airport.99 The Board acknowledged that that
is so. Indeed the Board had emphasised that point in the quotation from the
NIGUP decision at
[1094].
[193] NZTA developed the argument in this way:
19.3 The only purpose of requiring Part 2 to be reflected in weightings could be to ensure that the alternative met the requirements of Part 2
– in other words, to test the alternative against Part 2. Thus, by
finding that Part 2 considerations should be reflected in any weight given to
a particular evaluation criteria over another, the Majority
effectively required
alternatives to be tested against Part 2 (which the Majority was obliged to
acknowledge is not the legal test).
These findings are
inconsistent.
[194] NZTA’s argument was that, by recognising a requirement
for evaluation criteria weightings to reflect Part 2
considerations, the Board
was in effect requiring each individual alternative to be assessed against
Part 2 despite the
Board disclaiming such an intention.
[195] The issue is a subtle one. The Board’s statement needs to be
read in context, namely its consideration of the
transparency and
replicability of the option evaluation. The passage at [1180] follows the
discussion at [1173] to [1177]100 of the significance for the outcome
of the weighting of the evaluation criteria and the fact that it was not known
whether certain
evaluation criteria had been given more weight than
others.
[196] That discussion had prompted the Board’s observation at [1178]
about the need for transparency in explicitly setting
out the weightings
used in any multi-criteria analysis. All of that had been preceded by the
chronology which had
98 Volcanic Cones Society, above n 20, at [61].
99 Queenstown Airport, above n 22, at [50].
100 At [179] above.
included the significant paragraphs [1128] and [1129]101 where the
sensitivity of the outcome to the relative weightings of the criteria had been
noted.
[197] I do not consider that the Board’s intention was to subvert the
established position, which it clearly recognised, that
each alternative does
not have to be tested against Part 2. My impression is that the Board was
saying that, if a range of alternatives
are to be the subject of evaluation by
criteria which are to be variably weighted, then the selection of the
different weightings
should “reflect” Part 2
considerations.
[198] In view of the discussion of the role of Part 2 in both McGuire
and King Salmon I do not view that suggestion as controversial.
While each alternative does not need to be measured against Part 2, it is not
unreasonable
that a mechanism which provides the basis for the comparison of
alternatives inter se should not be subject to the infusion of Part 2.
Consequently I do not consider that the second (“nevertheless”) part
of the highlighted sentence of paragraph [1180] is erroneous in law.
[199] NZTA’s second point was that the Board misapplied the NIGUP
decision. The answer to this criticism is simpler. As Mr
Palmer acknowledged,
the sentence structure is a little puzzling. I agree that the NIGUP decision is
not authority for the “nevertheless”
proposition. However, as the
Board had already recognised at [1094], it is clear authority for the first
statement that each alternative
does not need to be assessed against Part 2. In
my view the Board was intending to say no more than that. Although located
at
the end of the sentence, its reference to the NIGUP decision was not
intended as support for the observation about weightings
reflecting Part 2
considerations.
[200] Reverting to Q 13, I do not consider that the question as framed is sufficiently precise to permit an answer reflecting my reasons above. An affirmative answer could be construed as departing from the established position that individual alternatives do not have to be separately tested against Part 2. I consider that a more
accurate way of encapsulating my view of this aspect of the
Board’s decision is to
101 At [176] above.
say that, in circumstances where the requiring authority’s
consideration of alternatives involves the application
of evaluation criteria
which are variably weighted, the decision to allocate the variable weightings
should be subject to Part 2.
Subissue 1E: Conflation of s 171(1)(b) and (c)
considerations
[201] The question of law posed under this heading is:
Q16 Does the test of adequacy under s 171(1)(b) require a
requiring authority to select the option that best meets the
transportation
objectives while minimising environment effects?
[202] In relation to that question the amended notice of appeal at
paragraph 15 states that the Board erred:
(a) By inferring at [1180] that the assessment of alternatives must
result in selecting the alternative (“the preferred
option”) that
best meets the project objectives with the least overall social, community and
environmental impacts.
(b) By inferring at [961] that the project objectives ought to have
included an environmental objective so that the Proposal
could be
tested against transportation effects and adverse environmental
effects.
[203] Paragraph [961] appears in a discussion of the marked conflict of
evidence between NZTA’s expert witnesses and the witnesses
called by the
opposing parties. It states:
[961] Both at the Feasible Options Report stage and at the hearing before
us, there appeared to have been an overemphasis on transport
and related
benefits (which reflects the Project’s objectives) rather than an
assessment of the relevant amenity and environmental
effects of the Project
(which are absent from the objectives), assessed by reference to what is sought
to be protected, maintained
or enhanced in the statutory
instruments.
[204] With reference to that paragraph NZTA submitted:
20.2 This comment is provided against the context of the Majority’s assessment that the urban design and landscape evidence called by [NZTA] was influenced by the transportation objectives of the Project and the acceptance that grade separation by way of a bridge
is the only way of achieving those objectives. However, it is submitted
that this criticism has also permeated the Majority’s
assessment of the
Appellant’s consideration of alternatives.
[205] Then, after referring to [1180]102 and [1198], NZTA
submitted that, while NZTA’s aim throughout the process of considering
alternatives was to select the option
that best met the project objectives with
the least environmental effects, NZTA did not accept that s 171(1)(b) required
that test
to be applied or met. NZTA argued that the Board’s approach
unnecessarily conflated ss 171(1)(b) and (c).
[206] I do not consider that the Board made any error of law as suggested.
I agree with Mr Palmer that [961], read in the context
of the relevant
discussion, is simply designed to explain why there might have been a conflict
of evidence between the witnesses
on the opposing sides. I also accept his
submission that the final sentence of [1180] on what NZTA relies is an
attribution to NZTA’s
own Feasible Options Report. I am unable to discern
a conflation error of the nature advanced.
[207] While in those circumstances I consider that Q 16 is inapt, the
answer is in the negative.
Subissue 1F: Finding that adequate consideration was not given to alternatives
following the Government’s decision to underground Buckle
Street
Context
[208] The short chronology in the overview of the consideration of
alternative options referred to the letter from Opus to NZTA
dated 3 July
2012.103 The Decision continued in this way:
[1196] The five-page document was essentially a brief summary or
overview of Option F and Option X. It briefly referred
to the decision being
made that Option A was preferred over Option B. It touched on other
options. It was not a careful
evaluation of options in light of the decision by
the government to underground Buckle Street. It could not be compared to the
rigour
of the Feasible Options Report stage. At most it could be called nothing
but a cursory review of the situation.
102 At [188] above.
103 In [1138] at [124] above.
[1197] Following its public announcement on 17 August 2012 that Option A was
the preferred option, [NZTA] then proceeded
to prepare its
documentation for lodging its application with the EPA. The application was
lodged on 17 June 2013.
[1198] Our concern is that the playing field changed with the likelihood of
the Buckle Street Underpass and the bringing forward
of Mt Victoria Tunnel
duplication options. These should have resulted in re-evaluation of the
options, including Option F,
against the Project objectives. The Feasible
Options Report, as we have said, itself specifically states the need to
reconsider
the ability of options to work in with a possible underpass. This
was not done. There was no proper reconsideration of options
once the
underpass became a certainty.
[1199] Nothing further was done until the City Council decided on
19 December 2012 to order an assessment of Option RR (the precursor of the BRREO Option), Option X and Option A. An Option X transportation
assessment was prepared by Opus for the City Council and was published on
20 February 2013. The overall assessment was completed on
28 March 2013. It concluded:
Overall Conclusions
From an urban design perspective, the preference would be for an at-grade
solution – that is, a solution that does not require
any elevated
structures. However, it may not be possible to achieve the required transport
benefits with an at-grade option.
In that case, the preference is for the simplest structure – one does
not make this part of the city harder for people to find
their way around, or
compromise access to neighbouring facilities.
[1200] It was not until late March that [NZTA] acted. In late March 2013, the Project team carried out an option evaluation of Options A, F and X. According to the introduction of the Comparison of Options, the evaluation was undertaken to confirm the decision previously made by [NZTA] that Option A was the preferred option. The document is dated June 2013, and by this time, the application documents for Option A would have been well advanced, as they would have been in late March when the evaluation commenced. Furthermore, it would appear from the letter dated
19 December from Mr Dangerfield, the CEO of [NZTA], to the CEO of the City
Council that [NZTA] had become entrenched with Option A
well before November
2012. It had, as we have said, made its decision, making Option A
its preferred option on 17 August
2012.
[1201] We were not provided with any documentation or evidence as to why the Project team was asked to do its assessment in March 2013. Nor was any reason given for the failure to carry out a feasible option type assessment soon after the Government’s decision to underground Buckle Street, as was foreshadowed in the Feasible Options Report.
[1202] The chronology of events and the failure to carry out the clear
statement of intent to reassess options in the event of the
undergrounding of
Buckle Street raises doubts as to the adequacy of consideration
of alternatives. This is particularly
so having regard to Mr Durdin’s
comments on the March 2013 comparison of options:
37. The simplified decision matrix for the comparison between Options A
and F consolidates down to four evaluation criteria,
mainly Built
Heritage, CPTED, Transportation and Visual. That process shows Option A as
considered positive against two criteria
(CPTED and Transportation)
and negative against the other two. In comparison, Option F is considered
positive against all
four criteria.
38. Given that the decision-making process is premised around selecting
the option “... with the least social, community
and environmental
impacts” it would follow that Option F should have been
selected.
Issues
[209] NZTA asserted that in those paragraphs the Board made three errors of
law:
(a) By finding at [1196] that the review of alternatives carried out
in
July 2012 was “cursory”.
(b) By inferring at [1200] that NZTA’s consideration of
alternatives in March 2013 was too late because the application
documentation would have been well advanced, and NZTA appeared to have been
entrenched with its preferred option by that time.
(c) By finding at [1201] that NZTA was required to carry out a
“feasible option type assessment” following the Government’s
decision.
[210] Those errors translated into four different questions of
law:
19(a) Was the Board’s finding that the review of alternatives
carried out in July 2012 was ‘cursory’ a finding
to which it could
reasonably have come on the evidence, including in relation to suppositious
options (refer Subissue 1B)?
19(b) In order for the consideration of alternatives to be relevant must the consideration be completed before the application documentation is well advanced?
19(c) Is a requiring authority required to prepare a ‘feasible
option type assessment’ when the environment changes?
Or is it entitled
to rely on earlier work?
19(d) Was the Board’s finding that adequate consideration was not
given to alternatives following the Government’s
decision a finding to
which it could reasonably have come on the evidence?
Q 19(a) [recast]: Is this a case in which the true and only reasonable
conclusion contradicts the determination that the review of
alternatives carried
out in July 2012 was cursory?
[211] Referring to the Opus letter and an undated cost estimate for Option
F of
19 July 2012, NZTA’s short submission was that, while those documents
were not a “feasible options type assessment”,
they
reflected a level of consideration appropriate to the circumstances.
In particular it was said that the two documents
provided expert advice
that:
(a) Option F remained significantly more expensive than the Project;
and
(b) Option X remained a less desirable option due to cost and other
concerns.
[212] The question whether the 3 July 2012 review of alternatives was
cursory is to be viewed, as NZTA says, in the context of the
circumstances.
Those circumstances included the stance earlier taken that Option F was to be
assessed with other options which permitted
SH1 to be located in a tunnel in
front of the War Memorial once the government had made a decision on whether to
fund the War Memorial
Tunnel.104
[213] The Opus letter set out what it termed an alternate review.105 The Board did not view it as a careful evaluation of options in light of the government’s decision to underground Buckle Street, observing that it could not be compared with the vigour of the Feasible Options Report stage. It is apparent that the Board regarded the letter
as superficial.
104 [1123] at [124] above.
105 [1138] at [124] above.
[214] It may be that an alternative view was available. However, on the
facts as recited in the Decision such an alternative view
could not be said to
be compelling. There was ample basis for the Board’s assessment of the
situation. Consequently it cannot
be concluded that the true and only
reasonable conclusion contradicted the Board’s view.
Q 19(b): In order for the consideration of alternatives to be
relevant must the consideration be completed before the
application
documentation is well advanced?
[215] NZTA submitted that s 171(1)(b) does not set a deadline by
which alternatives must have been considered in order
for that consideration to
have been adequate. I agree. However, whether the consideration of
alternatives, which occurs comparatively
late in the process, will be adequate
or not is a matter of fact.
[216] That point is illustrated by the authority cited by NZTA, Nelson
Intermediate School v Transit New Zealand.106 As NZTA notes,
the Environment Court there did not find that alternatives needed to have been
considered prior to a particular date.
However it found that Transit’s
development and consideration of alternatives during an appeal hearing was not
adequate.
[217] That was not a finding of law. Nor was the view reached by the Board
in the present case, that NZTA had become entrenched
with Option A well
before November 2012, a finding which contains an error of law. For that reason
I do not answer the question
which, in any event, is inappropriately
vague.
[218] Any attack on the Board’s view would need to resort to an Edwards v
Bairstow type challenge. That is the nature of NZTA’s fourth
question in Issue 1F to which I now
turn.
106 Nelson Intermediate School v Transit New Zealand [2004] NZEnvC 96; (2010) 10 ELRNZ 369 (EnvC).
Q19(d) [recast]: Is this a case in which the true and only reasonable
conclusion contradicts the determination that adequate consideration
was not
given to alternatives following the Government’s decision?
[219] NZTA’s primary submissions stated:
22.1 ... on 20 February 2013, Opus briefed [NZTA’s] specialists to
assess Options A, F and X for the purposes of
Technical Report 19:
Alternative Options Omnibus. The results of that exercise are summarised in
Technical Report 19: Alternative
Options Omnibus at Appendix B.
22.2 The Majority gave this exercise little or no weight in its
assessment of [NZTA’s] consideration of alternatives. No
explicit reason
for this is given. However, at [1200] the Majority stated that it would appear
that [NZTA] was “entrenched
with Option A well before
November 2012”.
22.3 Absent an explicit finding of bias or predetermination, there was no
reasonable basis on the evidence for the Majority to
find or infer that
[NZTA’s] consideration of alternatives in March 2013 was too
late.
[220] In my view NZTA falls well short of the high hurdle of establishing
that the Board’s view was insupportable. Indeed,
with reference to
NZTA’s submission at para 22.3, I consider that there were ample grounds
for the Board’s view on the
basis of the 19 December 2012 letter
alone.
[221] Accordingly the answer to Q 19(d) is No.
Q 19(c): Is a requiring authority required to prepare a
“feasible option type assessment” when the environment
changes?
Or is it entitled to rely on earlier work?
[222] In the heading to this issue in its primary submissions NZTA posed
the question: was NZTA required to “start again”
following the
Government’s decision? It acknowledged that the Opus letter and the
updated cost estimate107 were not a feasible option type assessment
but submitted:
21.6 It is appropriate (and economically responsible) for a
requiring authority to rely on its earlier consideration of
alternatives when
the environment for a project changes. It is not required to carry out a new
‘feasible option type assessment’
whenever the environment for
receiving the project changes.
107 At [211] above.
[223] The response (it is obviously not an “answer”) to this
question is: it depends. It is dependent on the nature
and extent of the change
to the environment and the extent of the reconsideration that such change
necessitates. A comparatively
minor change would be unlikely to require a
requiring authority to “start again”. The earlier work could no
doubt be
relied upon in large part. However a significant change to the
environment might require a substantial revisiting of the prior
work.
[224] The relevant event here was the government’s decision
concerning funding of the War Memorial Tunnel. Whether that event
was of such
significance as to require a more thorough-going reconsideration than was
reflected in the 3 July 2012 letter is essentially
a question of fact. There is
no question of law to be answered.
Subissue 1G: Adequacy of the consideration
[225] In support of an alleged error of law in finding that adequate
consideration was not given to alternatives, NZTA advances
the following grounds
of appeal:
(a) The evidence was of a lengthy, detailed and thorough consideration
of a range of alternatives.
(b) For the reasons set out under Issues 1A to 1F, the Board applied
the wrong legal tests to what was required of NZTA in its
consideration of
alternatives. Had the Board applied the correct test it should have found on
the evidence before it that the consideration
was adequate.
(c) Further, the Board allowed itself to be distracted by the merits of alternatives preferred by submitters (including BRREO, Option X and the long tunnel option) and failed to properly consider the evidence of the consideration given by NZTA to alternatives. Section 171(1)(b) requires decision-makers to inquire as to the process, rather than the outcome of the consideration given to alternatives.
[226] From that footing NZTA proposed the following question of
law:
Q 22 Is the Board’s finding that adequate consideration was not
given to alternatives a finding that it could reasonably
have come to on the
evidence?
[227] For the reasons explained at [16] to [23] that question is reframed
in this way:
Is the case one in which the true and only reasonable conclusion contradicts
the determination that adequate consideration was not
given to
alternatives?
As earlier noted108 that question effectively subsumes the
alternative question in
Issue 1A which reframed is:
Is the case one in which the true and only reasonable conclusion contradicts
the determination that NZTA had not given sufficiently
careful consideration to
alternatives?
[228] NZTA’s argument relied on Annexure A to its primary submissions
which traversed the history of events from the Meritec
Scheme Assessment
Report in March 2001 to the lodgement of the NoR in June 2013.
[229] Clearly there was a large volume of evidence before the Board which it appears to have diligently considered. Further, given that Mr McMahon, in his alternate view at Part 2 of the Report, accepted that adequate consideration had been given to alternative sites, routes and methods of undertaking the work, it may well be that this is a case where different decision-makers, each acting rationally, might
reach differing conclusions.109
[230] However the issue for me is whether the Board’s decision is
within the category of rare cases where its conclusion
is so clearly untenable
as to amount to an error of law because the proper application of the law
requires a different answer.110
[231] If the law is as I have found in the course of my consideration of
the earlier parts of Issue 1, then I consider that, on
the basis of the
Board’s consideration of the
108 At [144] above.
109 Vodafone, above n 2, at [56].
110 At [52].
dual issues of transparency/replicability and assessment of non-suppositious
options, the answer to the questions in their reframed
form can only be in the
negative.
Issue 2: Inquiring as to the outcome rather than the process of
considering alternatives
[232] In the course of considering Issue 1C reference was made to
NZTA’s contention that the Board had engaged inappropriately
with the
outcome rather than the process.111 That theme is developed in
Issue 2 where two errors of law are alleged:
(a) When exercising its overall judgement in accordance with s
5, applying McGuire v Hastings District Council [2001] UKPC 43; [2001] NZRMA 557 to hold
that if an alternative is available that is reasonably acceptable,
though not ideal, it would
accord with the spirit of the legislation to prefer
that (at [1324]. See also [1319] and [1182]– [1187]).
(b) By assessing the effects of the Proposal by reference to
alternatives that the Board considered would have less adverse
effects on the
environment (in particular, BRREO, Option X and tunnel options). (See [403],
[510], [643], [1241], [1319]).
[233] Those dual errors give rise to a single question of law, Q
25, which incorporates two alternatives:
Q 25 Is a decision-maker (in this case the Board) permitted to compare an
option against other alternatives that it considers
would have less adverse
effects on the environment, either in assessing the effects of the Proposal
under s 171(1), or in exercising
its overall judgment in accordance with s
5?
[234] In Issue 1B reference was made to the circumstances in which and the
reason why various options were put before the Board.112 Those
paragraphs, together with the following two paragraphs from that part of the
Decision headed “Exercise of judgment in
accordance with Section 5”,
are referred to in the first of the alleged errors of law:
[1319] Having said that, we are satisfied on the evidence that similar
transportation benefits that would give effect to such integrated
management
could be achieved by a tunnel option or variant similar to Option X. We are
also satisfied on the evidence that an at-grade
option, along the lines of
the
111 At [181] above.
112 [1182]–[1187] at [148] above.
BRREO Option, could facilitate some benefits, albeit not as well as the
Project, at least until the Mt Victoria Tunnel duplication
and possibly well
beyond. We consider such options should have been included as part of a robust
option evaluation process.
...
[1324] In the final outcome, we are required to evaluate the significant
adverse effects taken together with the significance of
the national and
regional need for and benefit of the Project. In carrying out this evaluation,
we are conscious of the dicta of
the Privy Council in McGuire that
relevantly Sections 6 and 7 are strong directions to be borne in mind,
and if an alternative is available that is
reasonably acceptable, though not
ideal, it would accord with the spirit of the legislation to prefer
that.
[235] NZTA noted that McGuire was focused on Māori
land rights and jurisprudence around the Treaty of Waitangi, including the
processes in ss 6(e),
7(a) and 8 of the RMA. It said that the Privy
Council’s reference to “the spirit of the legislation” can
only
be read as referring to the particular discussion of Treaty
jurisprudence and its place in the RMA. It argued that the Board
was wrong in
[1324] to extend those observations more generally.
[236] NZTA also relied on Quay Property Management Ltd v Transit
NZ113 in support of the proposition that a decision-maker should
not cross the line into adjudication of the merits of the options and by
that
measure determine whether the chosen route was reasonable.114 Hence
it submitted:
23.6 The Majority therefore erred by comparing the Project to
alternatives when assessing the Proposal’s effects under s
171(1) or
exercising its overall judgement in accordance with s 5. (See [403], [510],
[643], [1241], [1319] and [1324].
[237] I do not consider that the Board was purporting or attempting to “cross the line” as described in Quay Property. The Board’s understanding of the nature of its task is readily apparent from paragraphs to which reference has already been made. I consider that the respondents are correct when they say that a comparison of the relative effects of various aspects of the Project with those of alternatives was a natural corollary of the Board’s considering whether NZTA had given adequate
consideration to those alternatives.
113 Quay Property Management Ltd v Transit NZ EnvC Wellington W28/00, 29 May 2000 at [152]
applied in Queenstown Airport, above n 22, at [50].
114 [1090] at [125] above and [1167] at [178] above.
[238] I consider that the analysis of Mr Milne for TAC fairly responds to
NZTA’s
complaint:
156. The Board did not assess the overall merits or effects of
the alternatives. The Board did not draw a conclusion
as to whether the
alternatives referred to would have been better options overall.
Rather, it considered whether Option X-type options, tunnel options and
BRREO-type options were non-suppositious
and whether it was likely that they
might have less impact on heritage and amenity values. It reached the
inevitable conclusion
that such options would potentially have fewer adverse
effects on amenity values and heritage values. It was necessary
for the Board to understand the extent to which the various alternatives which
submitters claimed had not been properly considered,
had the potential
to address project objectives with lesser environmental effects; so that it
could reach a conclusion as to
whether those alternatives should have been
adequately considered.
[239] Consequently for these reasons I answer Q 25 in the
affirmative.
Issue 3: Misapplication of s 171(1) of the Act
[240] The refined Issue 3 questions of law are recorded at [53] above.
Three of those questions have been addressed in the course
of the analysis of
the statutory interpretation issues, namely:
– Q 28A at [72] to [76];
– Q 28C at [64] to [68];
– Q 28D at [99] to [118].
[241] It remains to address Q 28B which states:
Was the Board in error by considering the effects of the environment of
allowing the requirement without having particular regard
to the matters listed
in s 171(1)(a) to (d)?
[242] No light is shone on that very general question by reference to the error of law pleaded at paragraph 27(c) of the amended notice of appeal which simply alleges a failure by the Board to assess the effects of the environment of allowing the requirement having particular regard to the matters in s 171(1)(a) to (d).
[243] However some clarification is derived from the following grounds of
appeal at paragraph 29:
(c) In terms of the matters in s 171(1)(a) and (d), the Board failed
to have particular regard to the following relevant matters
when assessing the
Proposal’s effects:
(i) the Proposal’s consistency with regional/city transportation
strategies, as discussed by the Board at [520]–[526],
in particular, when
considering what weight to give to the Proposal’s ‘enabling
benefits’ for future transportation
developments (see below under Issue
3); and
(ii) relevant matters in the District Plan when assessing the
Proposal’s effects on historic heritage and amenity values (see
below
under Issue 6).
(d) In terms of s 171(1)(b), for the reasons set out above under Issue
1, the Board ought to have found that adequate consideration
had been given to
alternatives and assessed the Proposal’s effects having particular regard
to this finding.
(e) In terms of s 171(1)(c), when assessing the Proposal’s
effects, the Board failed to have particular regard to its
finding at [1230]
that the work is reasonably necessary to achieve the objectives of the requiring
authority.
[244] With reference to the s 171(1)(a), (b) and (d) matters, it will be observed that the grounds of appeal incorporate cross-references to other issues, namely Issues 1,
4115 and 6. I did not receive discrete argument on these
matters in the context of
Issue 3 and consequently, like counsel, I treat these matters as addressed in
the context of those other Issues. The point concerning
s 171(1)(c) is
addressed in the context of Q 45B at [356] below.
Issue 4: Incorrect approach to assessment of enabling
benefits
A stand-alone project
[245] The Decision notes that a consistent issue during the
hearing was the
implications of NZTA’s having sought approvals for the project
separately from
those for related parts of the network, particularly the Mt
Victoria Tunnel
duplication, and in advance of details
of the Public Transport Spine Study and its outcomes being
finalised.116
[246] NZTA’s closing statement to the Board of 3 June 2014 explained
its reasons for the Project being pursued on a stand-alone
basis:117
12.9 It is for [NZTA], together with WCC and GWRC, to decide when applications for its various projects are lodged, and the make-up of each project. It would be ridiculous to suggest that, in Auckland for example, applications for all Auckland State highway and local roading improvements should be lodged at the same time, so that their inter-relationships can be explored. For Wellington, the Ngauranga to Wellington Airport Corridor Plan signalled in 2008 that the Basin Bridge Project is to be implemented before 2018, whereas the Mt Victoria and Terrace Tunnel duplication projects are described as “measures that may be implemented (beyond
10 years)”. [NZTA] has structured the Project (and sought approvals
for that Project) in a manner which is entirely consistent with that
description.
12.10 Mr Blackmore’s evidence is that one of the reasons for
separating the Basin Bridge and Mt Victoria Tunnel Duplication
Projects was
[NZTA’s] wish to improve the Basin Reserve road network and thereby
facilitate public transport improvements (and
increased use) prior to the
duplication of the Mt Victoria and Terrace Tunnels. This is supported by the
GWRC. In addition, [NZTA’s]
view was that the environmental and social
aspects of both Projects were sufficiently different in nature that there
was no
need to combine the two Projects for consenting purposes. Mr
Blackmore’s evidence was that the Basin Bridge Project is
a standalone
project which is not dependent on the Mt Victoria Tunnel Project proceeding, and
will have benefits for north-south
traffic regardless of what happens at Mt
Victoria. By comparison, the Mt Victoria and Terrace Tunnel Duplication
Projects, and
the Bus Rapid Transport Project, are reliant on the Basin
Bridge Project being in place.
[247] The Board said:
[232] We accept [NZTA’s] submission that this is not a case where
the Project itself requires further consents or authorisations
under the
RMA which are not currently before us. Rather, the issue is the extent to which
the Project and its effects, can
be properly understood and assessed
having regard to the current status of the Public Transport Spine Study, and in
isolation
from the Mt Victoria Tunnel duplication project in
particular.
116 At [225].
117 Noted at [230].
[233] The power to defer a matter lodged with the EPA under Part 6AA while
other related applications are made lies with the Minister,
not the Board.
Further, this power is to be exercised before notification of the original
applications. The matter now having
been referred in accordance with Section
147(1)(a), we are required to make a determination on the Project before
us, having
regard to the effects of the Project (both positive and negative),
and that Project alone. We address the scope of the relevant
future state of
the environment and effects (including additive and cumulative
effects) we can consider (particularly
with respect to the Mt Victoria
Tunnel duplication) elsewhere in our decision.
[248] The Board accepted TAC’s submission that it must take the
position “as it is”.
It said:
[234] ... we must determine whether the project before us meets the
Act’s sustainable management purpose as a stand-alone
Project (i.e. in the
absence of the Mt Victoria Tunnel duplication), and on the basis of the
information regarding the outcomes of
the Public Transport Spine Study available
to us. That is the key consequence of [NZTA’s] decision to seek approval
for the
Project as a stand-alone project separate from that of the Mt Victoria
Tunnel duplication, and in advance of the Public Transport
Spine Study and its
outcomes being finalised.
Effects and benefits – terminology and meaning
[249] The fact of the stand-alone nature of the Project was the catalyst for
a significant debate about the benefits which could
fairly be attributed to the
Project, including contingent benefits and enabling effects. As Mr Cameron
observed in the course of
closing arguments before the Board, these are elusive
concepts.118
[250] “Effects” are defined in s 3 of the RMA:
In this Act, unless the context otherwise requires, the term effect
includes–
(a) any positive or adverse effect; and
(b) any temporary or permanent effect; and
(c) any past, present, or future effect; and
(d) any cumulative effect which arises over time or in combination with other
effects–
118 Transcript page 8146 line 27, 4 June 2014.
regardless of the scale, intensity, duration, or frequency of the effect, and
also includes–
(e) any potential effect of high probability; and
(f) any potential effect of low probability which has a high potential
impact.
[251] In its written closing statement to the Board NZTA stated that future
effects, cumulative effects arising over time or in
combination with other
effects, and uncertain effects, are all relevant effects. Challenging the
opposing contention that contingent
benefits (being those benefits reliant on
another consenting process or event in order to materialise) should not be taken
into account
by the Board, NZTA contended that the cumulative and in-combination
effects to be considered by the Board included the Project’s
effects
in combination with contingent benefits of works which are yet to receive
RMA or another type of approval, citing
as examples the Mt Victoria and Terrace
Tunnel duplications.
[252] TAC’s submissions on appeal argued that NZTA had shifted its emphasis on appeal from “strategic fit” with objectives to “enabling benefits”. Although NZTA’s closing statement used the phrase “facilitate/enable”, as the Decision recognises, in oral submissions NZTA had submitted that “enabling effects” were a separate and
identifiable benefit of the Project and that the Board should treat them as
such.119
[253] In its written reply submissions NZTA maintained that there is a
difference between the strategic fit of a project and its
enabling benefits. It
explained:
22.12 To be clear, in response to the submissions of TAC, [NZTA]
considers that there is a difference between ‘strategic
fit’ of a
project and ‘enabling benefits’. An ‘enabling
benefit’ is an effect of a proposal
that facilitates or creates
an opportunity for the achievement of an outcome. Such an effect
is an identifiable
positive benefit of a project. Of course, what that might
be is dependent on context.
22.13 In the context of this Project, the positive enabling effect is how
the Project facilitates (will not frustrate) the development
and potential
implementation of related projects, particularly the Mt Victoria Tunnel
duplication and the Public Transport Spine
Study (‘PTTS’). [NZTA]
is not referring to the benefits from the actual implementation
of the wider
Roads of National Significance
119 At [507] in [256] below.
(‘RoNS’) programme or the PTSS. Rather, it is the fact that
this Project enables/facilitates/provides the opportunity
for those other
projects to be implemented.
The Board’s Decision
[254] The Board accepted as correct NZTA’s final analysis of the
existing or future state of the environment.120 In addition it
stated that the approved sections of the Wellington Northern Corridor RoNS
should appropriately be considered as part
of the environment for assessment of
the Project, being the Transmission Gully and the Mackays to Peka Peka and Peka
Peka to Otaki
(Kapiti Expressway) sections of the Wellington Northern
Corridor.
[255] At [343] to [346] the Board considered the issue whether contingent
benefits, (benefits flowing from related projects which
are intended but not
consented) should be attributed as flowing from the Project. It recorded that
at the end of the hearing it
was agreed that the benefits from a second Mt
Victoria Tunnel and a third lane as part of the Buckle Street Underpass should
not
be attributed to the Project because the tunnel duplication had yet to be
consented to and the Buckle Street Underpass was part of
the existing
environment.
[256] At [506] to [519] the Board proceeded to address the issue of
“enabling effects”, namely the consequence that
the Project
facilitates (or at least does not frustrate) the development of related
projects, particularly the Mt Victoria Tunnel
duplication and the Public
Transport Spine Study. The following paragraphs provide the context for and are
referred to in the discussion
of the several questions of law posed in Issue
4:
[506] One of the issues raised before us was whether (and if so, how) we
are able to take into account the enabling effect of the Project. That
is, how should we deal with [NZTA’s] argument that the Project facilitates
(or at least does not frustrate)
the development of related projects,
particularly the Mt Victoria tunnel duplication and Public Transport Spine
Study.
[507] In closing, Mr Cameron submitted that such effects are a separate
and identifiable benefit of the Project, and we should
treat them as such. We
were not provided with any case law authority to support this submission. Nor
are we aware of any.
120 At [336].
[508] We acknowledge that the Project enabling element may arguably
be viewed as a potential positive future effect which arises from the NoR before
us, and thus is within the scope
of what we are tasked to consider under
Sections 149P(4) and 171(1). The RMA’s definition of effects in Section 3
may also
be wide enough to encapsulate or incorporate such effects. In
particular, it includes any positive effects – although notably,
unless
the context otherwise requires. As the High Court held in Elderslie
in the context of a resource consent application:
... To ignore real benefits that an activity for which consent
is sought would bring necessarily produces an artificial and unbalanced picture
of
the real effect of the activity.
[our emphasis]
[509] However, even if we accept (without finally determining the matter)
that we can treat the project’s enabling element
as a separate and
identifiable positive benefit, we consider this is largely a moot point. That
is because in our view, any such
benefit can be given little (if any)
weight, primarily for the reasons set out below.
[510] Even if we assume that some modifications to the Basin Reserve
gyratory are required in order for the Mt Victoria Tunnel
duplication and Public
Transport Study to proceed, the Basin Bridge Project is only one of potentially
several solutions that might
be put in place for that purpose. Such solutions
could equally (or to a greater or lesser degree) facilitate (or not frustrate)
the
progression of those projects.
[511] We do not consider the evidence before us sufficiently establishes
that the enabling element of the Project is something unique to, or which
can only be achieved by, [NZTA’s] current NoR.
[512] Perhaps more importantly, we have no guarantee that either (or both) of those projects would in fact go ahead. Indeed, as outlined elsewhere in our decision, we are required to make our determination on the basis that the Mt Victoria Tunnel duplication does not form part of the future state of the environment, and on the basis of the limited information currently available to us regarding the Public Transport Spine Study outcomes.
[513] That is the key result of [NZTA’s] election to seek approval
for the Project separately from that for the Mt Victoria
Tunnel duplication, and
in advance of the Public Transport Spine Study and its outcomes being
finalised. In having made
that strategic decision, [NZTA] must now accept the
consequences of doing so. Put simply, and using the wording from
Elderslie, we cannot place any significant weight on a supposed (but not
quantified) Project benefit which is not real – in that we have
no
certainty or assurance it would actually materialise.
...
[516] As we have already found, the Mt Victoria Tunnel duplication should not be assumed to occur for the purposes of evaluating the Project. Further, we do not see our approach in this regard as inconsistent (nor do we in any way disagree) with the Environment Court’s observations in Cammack (cited to us by [NZTA] in opening) that the RMA’s:
... concept of sustainable management does not require the status quo to
simply continue. Provided the imperatives contained
in s 5(a)–(c)
can be justified, RMA contemplates management of use, development and
protection, not just retention of the
status quo.
[517] Rather, it is a reflection of our view that it would not be
sustainable, or provide for sustainable management, to approve
projects such as
this, primarily because they were necessary to facilitate future developments,
which may (or may not) proceed.
[518] Accordingly, we consider the most appropriate way to take
into account the Project’s facilitating or enabling
element is not as an
identifiable benefit in and of itself, but in the context of Section 171(1), and
particular sub-sections (a)
and (d). That is, the extent to which the Project
is consistent with the strategies identified and in the context of the other
RoNS
related projects.
[257] In that part of the Decision headed “Exercise of Judgment in
accordance with
Section 5” the Board said:
[1318] The Project would have an enabling element to the extent that it
would fit well with the proposed works planned to implement
the City
Council’s Growth Spine form Ngauranga to the Airport. To this extent, it
would be consistent with the transportation
theme identified by the planning
caucus and the integration of land use and transport planning.
There followed [1319]121 which has been discussed already in the
context of Issue 2.
[258] On this aspect of the appeal it is appropriate to also note
the distinctly different view of Mr McMahon:
[1510] In my consideration, the Project’s enabling effect is of
considerable importance and should be acknowledged as an important and
determinative transportation benefit of the Project.
[1511] For the record, I should clarify that I am not referring to the other
benefits that may result from the actual implementation
of the wider RoNS
programme or Public Transport Spine Study that are not part of this Project.
Those are contingent benefits and
I wholly accept that these should not form
part of the Board’s substantive consideration of this Project. Rather,
what I am
referring to is how the Project facilitates (or at least does not
frustrate) the development and potential implementation
of related
Projects, particularly the Mt Victoria Tunnel duplication and the Public
Transport Spine Study.
121 At [234] above.
The parties’ positions
[259] NZTA mounted a comprehensive attack on this aspect of the Decision
which is encapsulated in the following extract from its
primary written
submissions:
31.7 There are significant errors of law in this aspect of the Majority’s
decision, including:
a It has failed to treat enabling benefits as separate and identifiable positive effects of the Project that properly fall within the scope of ‘effect’ as defined by s 3 RMA.
b It has failed to assess the effects of the Project
‘having particular regard to’ the fact that the
Project is part of a
programme of works set out in the relevant statutory and non-statutory documents
under s 171(1)(a) and (d).
c It has failed to access the effects of the Project
‘having particular regard to’ the requiring authority’s
objectives, which explicitly include ‘not constraining opportunities for
future transport developments’.
d By requiring that a project’s enable effects be
‘unique’ to the project (and to the particular option),
it has
failed to assess the effects of allowing the requirement and has instead engaged
in a comparative exercise with other alternatives.
e It has required the Appellant to demonstrate the certainty of
benefits, when the RMA does not require this standard.
f It has conflated the concepts of ‘environment’ and
‘effects’.
g Although it claims to have taken into account the enabling
elements of the Project as a relevant factor under
s 7(b) when
exercising its overall judgment, the rest of the Majority’s decision shows
that this effect has been given little,
if any, weight.
31.8 As a result of these errors of law, the Board wrongly attributed little,
if any, weight to this highly relevant positive effect
of the
Project.
Seven questions of law were posed with reference to the Board’s
consideration of
enabling benefits.
[260] While the burden of the opposition on this topic was carried by Mr Milne, Mr Palmer took the fundamental point that the seven different instances of alleged error all suffered from the same difficulty that the Board did treat enabling effects as relevant. He maintained that NZTA’s real objection was that the Board did not give those enabling effects sufficient weight, a point which he reinforced by listing the
repeated references to weight in the relevant part of NZTA’s
primary written
submissions.
Q 31(a): Is a project’s enabling benefit an effect in terms of s 3
that can and should be taken into account under s 171(1)
and/or s
5?
[261] There is no doubt that the Board took into account and gave at least
some weight to the enabling element of the Project.
NZTA’s complaint
concerns the manner in which the Board did so, as explained in ground of appeal
30(a):
(a) At [506]–[519], by failing to treat and/or give weight to
the enabling benefits of the Proposal as a positive effect
in terms of s 3
and/or s 171(1) of the Act; and instead finding:
(i) at [518] that the most appropriate way to take into account the
Proposal’s enabling element is by considering the
extent to which the
Proposal is consistent with the strategies identified in relevant documents
identified under s 171(1)(a) and
(d);
(ii) at [519] that the enabling component is a matter which could be
taken into account under s 7(b) (noting that this did not
appear in the
Board’s reasoning in its draft Decision).
[262] It is apparent that the approach which the Board should adopt was
traversed in oral closing submissions before the Board.
NZTA’s written
reply submissions on appeal explained:
22.3 TAC submits that [NZTA] has shifted its emphasis from
‘strategic fit’ with objectives and transport plans, to
‘enabling benefits’. This is incorrect. [NZTA’s] closing
submissions before the Board asked the Board to count
the contingent benefits of
the Project as relevant effects. This was the subject of some discussion
between counsel and the Board.
Counsel accepted that the Board may choose to
consider the enabling aspect of the project as a relevant matter under s
171(1)(a)
and (d), however, in doing so, it was anticipated that this aspect of
the Project would be given appropriate weight. However, the
effect of the
Board’s approach is to relegate the enabling benefit to an almost
irrelevant ‘other matter’.
22.4 It is of considerable importance that this issue is corrected as a
matter of law. As discussed in [NZTA’s] Primary
Submissions, the Majority
has made findings in relation to the ‘enabling element’ of the
Project that [NZTA] says are
wrong in law. The Minority has not. This appeal
seeks to address those errors.122
122 The reference to the Minority was to [1511] at [258] above.
[263] Both ground of appeal 30(a) and that extract from NZTA’s reply
submission provide traction for Mr Palmer’s criticism
that NZTA’s
real objection concerns the weight which the Board accorded to enabling
benefits, a view with which I agree.
[264] However Q 31(a) as framed does appear to raise a question of law, at
least with reference to the “can” rather
than the
“should” component. That said, I do not consider that the Board
made an error of law of the nature implied.
It did not reject the contention
that an enabling benefit could be a potential positive future effect in terms of
s 3.123 In fact, it did not actually determine the point as it
expressly acknowledges at [509]. Instead, it proceeded to take the enabling
element into account at [518] in the manner which counsel had agreed was
acceptable.124
[265] The enabling effect or benefits of a project will inevitably be
circumstances specific. As the Board recognised in relation
to this particular
Project, in some cases the enabling element may properly be viewed as a
potential positive future effect. In
that sense I consider that an affirmative
answer can be given to the question whether a project’s enabling element
“can”
constitute an effect to be taken into account under s 171(1)
and/or s 5.
[266] However, whether it will be appropriate to do so or instead to
proceed as the Board did in this case at [518] will turn
on the
particular circumstances. The “should” component of Q 31(a)
does not raise a question of law and
is not susceptible of answer in
abstract terms.
Q 31(b): Where a project’s enabling benefits are consistent with a
programme of infrastructure development that is recognised
in
relevant documents under s 171(1)(a) and (d), should those enabling benefits
be given considerable weight as an effect
of the project under s 171(1) and/or s
5?
[267] This question, which is directed to the weight to be given to a
project’s
enabling benefits, does not involve a question of law. In any event a
question framed
in terms of “considerable” weight is too imprecise to sound
in a useful answer.
123 At [508].
124 In paragraph 22.3 at [262] above.
Q 31(c): In order to be taken into account, must a project’s enabling benefits be
unique to that project, guaranteed to go ahead, and able to be
quantified?
[268] In my view the answer to this question is No. Nor do I consider
that the Board made the erroneous finding alleged, namely
that in order to be
given weight, enabling benefits must be unique to a project, guaranteed to go
ahead and able to be quantified.
[269] The Board certainly observed at [511]–[512] that the
Project did not incorporate those characteristics. However
I do not construe
the Board’s decision as stipulating that such characteristics were
prerequisites to enabling elements being
taken into account. If it had viewed
such features as necessary pre-conditions, then the Board would not have taken
the enabling
element into account at all. Yet the Board did so. In my view
the Board referred to those matters as bearing on the weight to
be attributed to
the enabling effects. Because those features were not present, the weight
which the Board allocated to enabling
elements was correspondingly
less.
Q 31(d): Does the definition of the future environment constrain the
ability of a decision-maker to consider the enabling benefits
of a
project?
[270] The concern which prompted this question is revealed in the relevant
ground of appeal:
30(c) At [512] by wrongly conflating the environment with effects, and
thereby finding that because the Mt Victoria Tunnel duplication
and Public
Transport Spine Study outcomes do not form part of the future state of
the environment, the Board is prevented
from giving weight to the enabling
benefits of the Proposal for those future projects.
[271] Noting that s 171(1) directs a decision-maker to “consider the effects on the environment of allowing the requirement”, NZTA drew attention to the direction of the Court of Appeal in Royal Forest and Bird Protection Society of New Zealand v Buller District Council125 that decision-makers are required to distinguish the
environment from the effects of a proposal:
[W]e cannot see
how s 3(f) comes into play at all in determining what is the
“environment” against which the actual and
potential effects of
allowing the activity for which consent is sought are to be considered. In
determining what the “environment”
is, the attention of the consent
authority or a court on appeal is directed toward the physical environment as it
exists at the relevant
time, modified by those considerations required to be
taken into account by the Act and applying Hawthorn, treating any
permitted activity or any activity for which resource consent has been granted
and which is likely to be implemented
as included in the
“environment”. None of this has anything to do with the definition
of “effect” in s
3. The definition of “environment” is
a prior question to consideration of the effects of the proposed activity on
the
environment.
[272] Submitting that the two exercises must be kept separate, NZTA
contended:
31.32 The Majority has wrongly conflated the concept of
‘environment’ with the meaning of ‘effect’ by
determining
that the enabling benefit of the Project should not be considered to
be/or attributed any weight as an ‘effect’ because
the Mt
Victoria Tunnel duplication is not considered to be part of the future state
of the environment. In doing so, the Board
unduly limited the meaning of
‘effect’ to the Board’s assessment of what constitutes the
environment, rather than
ensuring that effects of the Project are properly
identified and considered. This is a fundamental error of law.
31.33 With respect, what is considered to be part of the future state of
the environment (whether that includes the Mt
Victoria Tunnel
Duplication or the Public Transport Spine outcomes) has nothing to do with the
identification of the effects of
the Project. What is important is that the
evidence shows that the enabling benefit of the Project (being what this
infrastructure
project facilitates) is an effect attributable to the Project.
As we have submitted, the evidence established that the Project
will
facilitate planned developments (whatever their final form may take) and that
without this Project, future development will
be frustrated/not
enabled.
[273] Mr Milne observed that NZTA did not take issue with the Board’s
conclusion that the tunnel duplication process did
not form part of the
future state of the environment while at the same time it suggested that the
Board should have treated
the facilitation of such a project as a positive
effect on the environment. In his submission the fatal flaw in NZTA’s
argument
was that s 171 is concerned with effects on the environment, and an
effect which does not affect the environment is not a relevant
effect.
[274] I agree with Mr Milne that the Board decided as a first step what the environment was by resolving the contest about the existing, permitted and reasonably foreseeable future environment and concluding that the Mt Victoria
Tunnel duplication was not part of that environment. I do not consider that
it is fair to say, as NZTA contends, that the Board conflated
the environment
with effects.
[275] The Board recognised the Project’s enabling
element.126 However it considered that the most appropriate
way to take that enabling benefit into account was in the manner explained at
[518].
[276] Reverting to the content of Q 31(d), if “constrain” is
given the same meaning as “prevent” (in ground
of appeal 30(c)),
then, as the Board’s Decision demonstrates, a decision-maker is not
precluded by the definition of the future
environment from considering the
enabling effect of a project. However, again as the Board’s Decision
demonstrates, the decision-maker’s
conclusion on the state of the future
environment may influence the manner in which the decision-maker chooses to take
an enabling
benefit into account.
[277] Consequently I do not consider that Q 31(d) is susceptible of a
simple Yes or No answer. As the explanation above indicates,
the finding as to
the state of the future environment is likely to be material to, and even
influential on, the way in which a decision-maker
considers and weighs a
project’s enabling elements.
Q 31(e): In order for the positive effects of a future development to be
taken into account must the approvals for that development
be sought at the same
time as (or in advance of) the project?
[278] The answer to that question (which refers to the positive effects
“of” a future development) must be in the affirmative.
On that
point I apprehend the Board was unanimous.127
[279] The error of law alleged in the amended notice of appeal
read:
30(d) By finding at [513] that in order for the positive effects of a
future development to be taken into account the approvals
for that development
must be sought at the same time or in advance of a
project.
126 [1318] at [257] above.
127 The majority at [233] at [247] above; Mr McMahon at [1511] at [258] above.
[280] However in the course of presentation of NZTA’s submissions Mr
Casey indicated that the preposition “of”
should in fact have read
“on”. The consequence of that amendment was to significantly change
the meaning of the question.
Indeed, to make sense I consider that the question
needs to be redrafted to introduce a reference to the project into the subject
of the sentence.
[281] In my view a negative answer applies to the following reframed
question:
In order for a prior project’s enabling effects on a future development
to be taken into account on the prior project, must
the approvals for the future
development be sought at the same time or in advance of the project?
[282] In any event I do not discern any error in the Board’s
approach. It clearly did take into account the Project’s
facilitating or
enabling element.128
Q 31(f): Is it consistent with sustainable management (in terms of s 5) to
approve an infrastructure project because it is necessary
to facilitate future
developments; and does it make a difference if the project is primarily
necessary to facilitate those future
infrastructure
developments?
[283] This question reflected what was said to be the Board’s error
in allegedly finding at [517] that it was not sustainable
management to
approve a project primarily because the project is necessary to facilitate
future developments.
[284] Neither this question, nor Q 31(g) below, received attention
in NZTA’s presentation of its case. It was not
a matter included in the
list of significant errors of law listed in paragraph 31.7 at [259]
above.
[285] The Board’s statement at [517] was by way of explanation for its previously expressed view that the Mt Victoria Tunnel duplication should not be assumed to occur for the purposes of evaluating the Project,129 which also appeared to be the view of Mr McMahon.130 In [517] the Board stated that that approach was “a
reflection” of the view criticised in the current
question.
128 At [518].
129 [234] at [248] above.
130 [1511] at [258] above.
[286] I do not consider that at [517] the Board was purporting to formulate
any statement of general principle. It was an expression
of view about a
particular category of projects, namely those necessary to facilitate future
developments which may or may not proceed.
I do not discern an error of law in
the Board’s observation.
[287] In any event I do not consider that Q 31(f) aligns with,
and hence is responsive to, the Board’s statement
at [517]. The
question does not incorporate the component that the future development may or
may not proceed.
Q 31(g): In the alternative, given its conclusion that the Proposal was
necessary primarily to enable future roading projects, did
the Board err in law
by failing to consider conditions to address this concern?
[288] Although an error of law was alleged at para 30(f) in essentially the
same terms as Q 31(g), there was no suggestion in NZTA’s
submission either
that relevant conditions had been proposed to the Board or that the Board had
failed to consider conditions which
had been proposed. Indeed it is
not apparent to me how a condition could be crafted which would address the
issues
the subject of Issue 4. In those circumstances I do not consider that Q
31(g) requires a response.
Issue 5: Assessment of transportation benefits – an
overview
[289] It will be recalled that improvements in transportation featured
prominently in the Project Objectives recorded at [30] above.
[290] The subject of transportation is addressed at length in the Decision
from [260] to [505]. The breadth and structure of that
consideration is
conveyed in the opening paragraph:
[260] The Project is a transport infrastructure project and the transportation effects are central to our consideration. In this part of our decision we set out the central transportation issues, briefly identify the key provisions of relevant statutory and other documents which provide guidance for our consideration of transport effects, then discuss the existing situation and appropriate baseline against which to assess the transport effects. We then discuss those transport effects, and assess them in terms of the stated objectives of the Project and the intended outcomes of the relevant statutory instruments and non-statutory documents, and the purpose of the RMA set out in Part 2 of the Act.
[291] The Board noted that regard had also been had to the fourth matter in
the
Minister’s reasons for referring the Project to the
Board:131
The proposal is intended to reduce journey time and variability for people
and freight, thereby facilitating economic development.
The proposal is also
likely to provide for public transport, walking and cycling opportunities;
reduce congestion and accident rates
in the area; and improve emergency access
to the Wellington Regional Hospital. If realised, these benefits will assist
the Crown
in fulfilling its public health, welfare, security, and safety
functions.
[292] NZTA’s challenge to this part of the Decision was
presented as three
subissues:
(a) standard of proof required to demonstrate transportation
benefits:
subissue 5A;
(b) assessment of immediate transportation benefits: subissue
5B;
(c) requiring the proposal to demonstrate benefits that go beyond
NZTA’s
objectives: subissue 5C.
Subissue 5A: Standard of proof required to demonstrate
transportation benefits
[293] The focus of this aspect of the appeal was on two paragraphs in that
part of the Decision which addressed underlying assumptions
about traffic
growth:
[484] We have no doubt that the assumptions fed into the traffic models are
the best estimates of competent and experienced people.
The point rightly made
by critics however is that these assumptions largely determine the outcomes of
the complex modelling exercise.
Any errors in the assumptions compound when
they are used to project traffic flows beyond the immediate future.
[485] The issue would not be important if we were
considering infrastructure improvements with minimal adverse
environmental
effects. In that situation it would not be important from an RMA perspective if
the works proved to be premature or
not needed at all. The situation here is
that, as discussed later in this decision, the Basin Bridge would have
significant adverse
effects, so the level of confidence we can have in the
modelled need and benefits, which depend on the underlying assumptions, is
important.
131 At [3] above.
[294] NZTA asserted that the Board had erred in law in two
respects:
– By inferring at [485] that a higher standard of proof (in
relation to transportation modelling) is required if the
adverse effects of a
project are more than minimal.
– By requiring a higher standard of proof to
demonstrate the transportation benefits of the Proposal.
[295] It was apparent from the grounds of appeal that NZTA maintained that
the Board had effectively required it to demonstrate
the transportation benefits
of the Proposal beyond reasonable doubt.
[296] Two questions of law were proposed:
Q 36(a) Is a higher standard of proof required to demonstrate
the transportation benefits of a project where it
will have adverse
effects that are more than minimal?
Q 36(b) If the Board applied the wrong standard of proof, were the
Board’s findings regarding the transportation benefits of
the Proposal
ones that the Board could reasonably have come to on the evidence?
Q 36(a): Is a higher standard of proof required to demonstrate the
transportation benefits of a project where it will have adverse
effects that are
more than minimal?
[297] In support of its contention that the Board erred in law
by effectively requiring NZTA to demonstrate the transportation
benefits of the
Project beyond reasonable doubt, NZTA first referred to the following
decisions:
– Genesis Power Ltd v Manawatu-Wanganui Regional
Council;132
– Shirley Primary School v Telecom Mobile Communications
Ltd;133
– McIntyre v Christchurch City
Council.134
133 Shirley Primary School v Telecom Mobile Communications Ltd [1998] NZEnvC 394; [1999] NZRMA 66 (EnvC).
134 McIntyre v Christchurch City Council (1996) 2 ELRNZ 84, [1996] NZRMA 289 (Planning
Tribunal).
[298] It will suffice to refer to the decision of the Court of Appeal in
Ngati Rangi Trust v Genesis Power Ltd135 which was an appeal
from Genesis Power above. Although dissenting in the result, the
following statement of Ellen France J reflected the view of the Court:
[23] On [the question of the onus of proof], it need only be noted I see
no difficulty with the statement in Shirley Primary School v Telecom Mobile
Communications Ltd [1998] NZEnvC 394; [1999] NZRMA 66 at para [121] that “[i]n a basic
way there is always a persuasive burden” on an applicant for a resource
consent. As the Environment
Court said in Shirley, that approach reflects
the requirement that a person who wants the Court to take action must prove his
or her case. In addition,
as the Court observed, there are also statutory
reasons for speaking of a legal burden on an applicant:
[122] Since the ultimate issue in each case is always whether granting the
consent will meet the single purpose of sustainable
management, even if the
Court hears no evidence from anyone other than the applicant it would still be
entitled to decline consent.
[299] It is clear, and I did not understand the respondents to suggest
otherwise, that the criminal standard of proof does not apply
in RMA matters.
The answer to Q 36(a) is plainly No.
[300] I do not accept NZTA’s submission that an inference can be
drawn that at [485] the Board was applying a standard
of proof higher
than the recognised standard. I find myself in agreement with Mr
Palmer’s submission on this point:
7.17 The Board simply said the level of confidence it could have in the
assumptions of the model is important. So it focussed
on them. Witnesses cast
doubt on the assumptions (e.g. at [497]) and NZTA kept revising them (e.g.
[386]) and the Board commissioned
its own review by Abley. The Board simply
made its own fair assessment of the assumptions and modelling outcomes. This
was an
important element of discharging its obligation to consider the effects
of the proposed flyover requirement.
[301] In the course of its submission NZTA drew attention to a number of places in the Board’s reasons which it said showed that the Board had required NZTA to demonstrate certain matters to a higher standard or to a level of “certainty”. However none of those matters suggested to me that the Board was applying
anything other than a conventional civil standard of
proof.
135 Ngati Rangi Trust v Genesis Power Ltd [2009] NZCA 222, (2009) 15 ELRNZ 164.
Q 36(b): If the Board applied the wrong standard of proof, were the
Board’s findings regarding the transportation benefits of
the Proposal
ones that the Board could reasonably have come to on the
evidence?
[302] Given my view that the Board did not apply the wrong standard of
proof, this question is otiose.
Subissue 5B: Assessment of immediate transportation
benefits
[303] Under this heading the amended notice of appeal asserted a single
error of law:
The Board erred in law by finding at [517] that the Proposal is primarily
necessary to facilitate future developments, and thereby failing to
have regard to the immediate transportation benefits
of the Proposal as
a stand-alone project. (See also [466]).
[304] Paragraph [466], which was located in the Board’s summary of
transportation
effects,136 stated:
[466] The Project has been put forward on the basis that it is
a multi-modal, long term, integrated solution and is
part of a sequence of road
improvements along the Wellington Northern Corridor, most of which are consented
and some of which are
under construction. The evidence was that much or even
most of the transport benefits from the Basin Bridge Project depend on
completion
of that sequence of road improvements and can be regarded as
contingent benefits.
[305] Although paragraph [517] has already been noted in the consideration
of enabling benefits it will be convenient to set it
out again:
[517] Rather, it is a reflection of our view that it would not be
sustainable, or provide for sustainable management, to approve
projects such as
this, primarily because they were necessary to facilitate future
developments, which may (or may not) proceed.
[306] The question of law framed under this heading contained two
limbs:
Q39 Did the Board fail to have regard to immediate transportation
benefits of the Proposal, such that:
136 [464]–[476].
(a) it failed to take into account relevant matters; and/or
(b) its decision regarding the immediate transportation benefits of
the Proposal is not a decision that it could reasonably
have come to on the
evidence?
Q 39(a): Did the Board fail to take into account a relevant matter in
failing to have regard to the immediate transportation benefits
of the
Proposal?
[307] NZTA submitted that the passages at [466] and [517] showed that the
Board decided that the Project did not offer “any
significant or
worthwhile immediate benefit”. It argued that that finding stemmed from
the Board’s “reductive
approach” to the transportation
benefits of the Project, which failed to have regard to the following matters
said to be relevant
under s 171(1)(a) to (d):
– a planning framework that recognises the importance of
the Basin
Reserve transportation node;
– a planning framework that provides for the immediate
implementation of bus priority; and
– NZTA’s objectives for the Project.
[308] NZTA advanced this aspect of its case by reference to three matters
to which it contended the Board had failed to have regard
or given any
weight:
– the failure to resolve the critical issue of
congestion;
– bus priority; and
– economic criteria.
[309] Each of these matters was addressed succinctly but
comprehensively by Mr Palmer. Rather than attempting to paraphrase
his
responses I believe it is useful to recite them in full:
7.8 First, NZTA says (at 32.7) the Board gave no weight to the relief of congestion from Paterson St to Tory St but “analysed the time travel savings only”. But the Board was explicit (at [329]) that is
considered congestion in terms of indicators that the consensus of experts
agreed on, including “difficulties getting through
controlled
intersections in a single phase and major variability in travel times”. It
considered these benefits extensively,
in particular at [305]–[316] and
[359]–[381] and in its overall summary at [1242], [1244]–[1247]
(noting the time
savings were substantially less than originally put forward
when the third lane at Buckle Street and the effect of the Mt Victoria
tunnel
duplication are accounted for). It noted that the proposed flyover requirement
would provide a time saving for the west-bound
journey of 90 seconds in 2021 (at
[330], [365], [1244]).
7.9 Second, NZTA says (at 32.15) the Board failed to have regard to the
immediate benefit of providing for bus priority. But
one of the paragraphs
NZTA cites (at 32.12) in the Board’s report ([405]) demonstrates
the opposite:
We are satisfied the improved journey times discussed earlier would
improve journey times for buses passing through the Basin
Reserve area.
[NZTA’s] modelling shows that the partial bus lanes proposed as part of
the Project would not prevent other
vehicular traffic also gaining similar time
savings. We can accept that the increased priority for public transport
provided by
the Project could be viewed as a precursor to BRT promoted by the
Regional Council, but we have no evidence about the effect of what
is proposed
here on mode share, which is an objective of the planning documents.
...
7.11 Finally NZTA says (at 32.16, 32.19) that the Board failed
to reference the quantification of economic benefits.
The Board did (at [536],
[539], [543], [545]–[550] and [552]), noting (at [543]) that “[a]
number of Benefit-Cost Ratio
figures were presented to us in the application
documents and in the evidence”. If the Board hadn’t referenced
specific
evidence that would not justify NZTA’s complaint.
But it did even that, citing (at [542] the evidence of NZTA’s
expert, Mr
Copeland, whose economic assessment of the project relied upon the BCRs
developed by Mr Dunlop upon which NZTA now seeks
to rely. The Board’s
conclusion (at [550]) is reached after seeing how contested were the BCR
assumptions. Again
the objection is to weight.
[310] I accept the respondents’ argument on these three points. Mr Palmer made the further point that much of NZTA’s complaint concerned the weight accorded to the relevant factors, drawing attention for example to NZTA’s submission in the context of bus priority that it was a matter to which the Board should have given “considerable weight”. I agree that the Board did not err in the manner asserted. The answer to Q 39(a) is in the negative.
The meaning of Q 39(b)?
[311] Question 39(b) attempts to combine an error in failing to have regard
to a matter (immediate transportation benefits) with
an Edwards v Bairstow
type question directed to the conclusion on that same matter. As such, it
does not make sense. That can be demonstrated by my attempt
to reframe the
Edwards v Bairstow question by reference to Lord Radcliffe’s third
formulation:
Is this case one in which the true and only reasonable conclusion contradicts
the determination that there were no immediate transportation
benefits of the
Proposal?
[312] Once it is accepted, as I have found in relation to Q 39(a), that the
Board did not fail to have regard to the immediate transportation
benefits of
the Proposal, I have difficulty seeing how an Edwards v Bairstow
type question can be appropriately framed.
Subissue 5C: Requiring the Proposal to demonstrate benefits that go beyond
the requiring authority’s objections
[313] The question of law posed under this heading is:
42 Did the Board err in requiring [NZTA] to demonstrate that
the Proposal would achieve specific benefits that were
not part of the project
objectives (namely, mode shift and providing a long-term solution for eastbound
State Highway traffic)?
Mode shift
[314] It will be recalled that Project Objective 3 stated:
To support mobility and modal choices within Wellington City:
(i) by providing opportunities for improved public transport,
cycling and walking; ...
[315] With reference to that objective, NZTA’s grounds of appeal
stated that the project objectives did not include an objective
“actually
to achieve mode shift” and that the Board erred in requiring NZTA to
demonstrate that the Proposal would achieve
mode shift/mode share. Two errors of
law were alleged:
|
(a) By finding at [405] that [NZTA] was required to establish
(and quantify) the extent and benefits of mode share (or
mode shift) that would
be achieved by the Proposal when the project objectives were to support modal
choices, inter alia, by providing
opportunities for improved public
transport.
|
|
(b) By finding at [441] that the Proposal is not a truly
multi-modal, integrated long-term solution for cycling and walking
in the
project area, when the project objectives were to support modal choices, inter
alia, by providing opportunities for improved cycling and walking.
|
|
|
[316]
|
The two paragraphs to which reference was made stated:
|
|
|
[405] We are satisfied the improved journey times discussed earlier
would improve journey times for buses passing through the Basin
Reserve area.
[NZTA’s] modelling shows that the partial bus lanes proposed as part of
the Project would not prevent other vehicular
traffic also gaining similar time
savings. We can accept that the increased priority for public transport
provided by the Project
could be viewed as a precursor to BRT promoted by the
Regional Council, but we have no evidence about the effect of what is proposed
here on mode share, which is an objective of the planning documents.
|
|
|
...
|
|
|
[441] In summary, the Project would make some improvements for circulation
of cyclists and pedestrians in the Basin Reserve area,
but as these are mostly
in the form of shared paths they would introduce potential conflicts
between these modes,
especially if these modes continue to increase in
popularity. We do not see this package of proposals as a truly multi-modal,
integrated, long term solution for cycling and walking in the project area.
...
|
|
[317]
|
Specifically with reference to the provision of “opportunities”
|
in
|
Objective 3(i) NZTA argued:
33.7 It is submitted that framing its objectives in this way is appropriate.
In this context, [NZTA] has requiring authority status under s 167
RMA for the construction and operation of any State highway or motorway. While [NZTA] has a significant role under the LTMA
investing in outcomes for public transport, cycling and walking; in
its capacity as requiring authority its role is to provide infrastructure
which assists or facilitates such outcomes rather than providing
them
directly.
[318] To my mind the distinction which NZTA seeks to draw is excessively fine. I consider that the sense of the word “opportunities” (which is the plural) in Objective 3(i) means a state of affairs favourable for a particular action or aim. It was in that sense that I consider that the Board considered the implications for
improved cycling and walking. It noted that, like the shared pathway on the
bridge itself, all of the proposed facilities for pedestrians
and cyclists were
shared paths137 in relation to which the Board had a general concern
about safety.138
[319] I do not consider that the Board can be criticised for its
consideration (and rejection) at [441] of the package of proposals
as amounting
to a truly multi-modal, integrated long term solution for cycling and walking in
the area when, as recorded in [418],
it was NZTA’s own case that the
proposed pedestrian and cycling facilities would have significant benefits, with
the phrase
“multi-modal solution” featuring often in submissions and
cross-examination.
[320] Finally there is the point made by Mr Milne that the Board was
obliged to consider certain RMA and non-RMA documents under
s 171(1)(a) and (d).
By way of example he pointed to the Wellington RLTS’s key outcomes which
include increased mode share
for pedestrians and cyclists. Mr Milne submitted,
and I accept, that consideration of the extent to which the Project would
contribute
to mode shift was therefore necessary in order for the Board to
consider the Project against those documents.
[321] For these reasons I do not consider that the Board erred in law in its
consideration of mode shift.
The issue of a long-term solution
[322] The Board’s lengthy discussion of transportation issues139
concluded with the following comments:
A Long Term Solution?
[498] Counsel for [NZTA] made frequent reference to the Project being a
long term and enduring solution. The first objective for the
Project is: To improve the resilience, efficiency and
reliability of the State Highway network. [our emphasis], although the
methods then listed for achieving this refer only to the section of the
westbound part of State Highway
1 from Paterson Street to Tory Street. We have
a concern about the longer term
137 At [433].
138 At [1252].
139 At [290] above.
resilience (ability to cope with change) of the eastbound part of State
Highway 1 through the central city.
...
[502] The City Council’s report: Basin Reserve –
Assessment of Alternative Options for Transport Improvements notes that if
the Project proceeds, in addition to the mitigation measures proposed by [NZTA]
there should be:
Commitment to consolidating state highway traffic away from
Vivian Street and into a single east-west corridor.
and:
Consideration of how consolidating state highway traffic away from
Vivian Street can be accommodated.
[503] This raises the question of whether the Basin Bridge would
facilitate or impede that long term option. Only Mr Reid commented
on this and
his view was that a bridge in the position proposed would make it more difficult
to bring the State Highway one-way pair
together into a single corridor.
[504] There is of course no obligation for [NZTA] to convince us
otherwise. The evidence is that Vivian Street would
have to be revisited in
about five years time (to allow time for planning another upgrade), and that the
creation of additional eastbound
capacity, especially at intersections, can be
expected to have significant environmental implications.
[505] Thus we do not consider the Project can be credited with being a
long term solution.
[323] With reference to those observations NZTA’s ground of appeal
stated:
c The project objectives included ‘to improve the resilience,
efficiency and reliability of the State Highway
network’ inter
alia, ‘by providing relief from congestion on State Highway 1 between
Paterson Street and Tory Street’.
d The project objectives clearly related to the westbound section of the
State Highway in this location.
e The project objectives did not include providing a long-term
solution for eastbound State Highway traffic in this location.
The Board erred
in requiring [NZTA] to demonstrate that the Proposal would address this
issue.
[324] Mr Milne suggested a different interpretation of the relevant objectives. Noting that the identified section of SH1 did not specify a direction of travel, he contended that the objectives identified two roads (Paterson Street and Tory Street) between which two sections of SH1 lie, one eastbound and the other westbound. I
do not accept that interpretation. I note that at [498] the Board
construed the objective as referring to the section of
the westbound part of
SH1 “from Paterson Street to Tory Street”.
[325] Consequently I accept NZTA’s submission that the project
objectives clearly related to the westbound section of SH1
in this location.
That view is reinforced by the reference to westbound traffic in the
Minister’s direction.
[326] However, if the Board had considered the eastbound part of SH1
through the central city to be part of its brief, then I am
sure that the topic
would have received much greater attention than in the closing paragraphs
of the transportation discussion.
In my view that very limited discussion was
in the nature of a postscript which was responsive to what the Board referred to
at
[498] as NZTA’s frequent references to the project being a long term
and enduring solution. At [505] the Board rejected that
proposition for the
reasons given in that short discussion.
[327] While it may be thought to have been unnecessary for the Board to
engage at all with NZTA’s “solution” proposition,
the fact
that it did so does not suggest to me that the Board was requiring NZTA to
demonstrate such a “solution”
as a prerequisite for the
approval of the NoR. Consequently I do not consider that the Board made the
error alleged of wrongly
interpreting the objective as applying to the eastbound
part of SH1.
[328] For these reasons I answer Q 42 in the negative.
Issues 6, 7 and 8: Questions of law relevant to heritage and
amenity
The refinement of the questions of law
[329] Issue 6 in the amended notice of appeal contained a single
question:
Q 45 For all or some of the reasons outlined above under paragraph 44, did the Board fail to have particular regard to relevant matters under s 171(1)(a) and (d) in assessing the effects of the Proposal on historic heritage and amenity?
[330] Paragraph 44 recited a series of alleged errors of law and para 46
listed 16 quite detailed grounds of appeal, including the
contention at 46(e)
that:
The Board’s finding at [782]–[783] that the Proposal constitutes
an inappropriate development of historic heritage in
terms of s 6(f) of the Act
is based on the Board’s finding that the environment constitutes a
heritage area.
[331] Issue 7 posed questions Q 48(a) and Q 48(b) while Issue 8 specified a
single question, Q 51.
[332] Although the amended notice of appeal contained distinct Issues 6, 7 and 8, NZTA’s principal written submissions stated at para 35.2 that the questions of law relevant to heritage and amenity identified in those three issues had been refined to six questions which were set out and addressed in the submissions. Those refined
questions were revised still further in the memorandum of 23 July
2015140 as
follows:
In relation to Issue 6, we seek to refine the questions of law as outlined at
para 35.2 of [NZTA’s] Primary Submissions:
[45A] When assessing the heritage or amenity effects on the environment
under s 171(1), must the decision-maker do so ‘through
the lens’ of
the relevant plans under s 171(1)(a) and, if relevant, s 171(1)(d)
documents? That is, should the effects
be assessed ‘through the
lens’ of the recognition and protection provided by those plans and/or
documents?
[45B] Further, should the Board have assessed the effects having particular
regard to its finding at [1230] that the works were
reasonably necessary to
achieve the objectives under s 171(1)(c)?
[45C] When there is no ‘invalidity, incomplete coverage or
uncertainty of meaning’ in the relevant plans under s 171(1)(a),
is it
appropriate for a decision-maker to assess effects against s 6(f) (for
historic heritage) and s 7(c) (for amenity values)?
[45D] Did the Board correctly apply the definition of ‘historic heritage’
under s 2?
[45E] What is the correct approach to the application of the test of
‘inappropriateness’ in s 6(f) [should the Court consider resort to
Part 2 of the RMA was available to the Board in the circumstances of this
case]?
140 At [51] above.
Q 45A: When assessing the heritage or amenity effects on the environment
under s 171(1), must the decision-maker do so ‘through
the lens’ of
the relevant plans under s 171(1)(a) and, if relevant, s 171(1)(d) documents?
That is, should the effects be
assessed ‘through the lens’ of the
recognition and protection provided by those plans and/or
documents?
[333] This question invokes NZTA’s King Salmon argument. NZTA
contends that the effects on the Project of heritage and amenity must be
assessed having particular regard to the
recognition and protection
provided for in the Regional Policy Statement and the District Plan
because those documents
were prepared in accordance with and to give effect
to Part 2. Consequently it argues that the correct approach to the assessment
of heritage and amenity effects was:
not within the framework of Part 2, rather it is through the lens of s
171.
The nub of the respondents’ rejoinder is that planning documents do not
determine
the outcome of a s 171 decision.141
The planning framework
[334] The current Regional Policy Statement became operative in 2013 and
the District Plan has been the subject of two plan changes
in the last decade.
Within that process new heritage items were added and the District Plan’s
objectives, policies and rules
were amended in response to heritage
becoming a matter of national importance under the RMA.
[335] The heritage items within the vicinity of the Basin Reserve and the
wider bounds of the Project listed in the District Plan
are:
(a) The Museum Stand;
(b) The Memorial Fountain; (c) Government House;
141 At [117] above.
(d) Former Home of Compassion Crèche; and
(e) The Carillon.
As Mr McMahon noted,142 neither the Basin Reserve generally nor
its surrounds have been recognised in the planning documents as a listed
heritage item or
area.
[336] The District Plan recognises and provides for the protection of historic heritage in particular ways. Policy 20.2.1.4 is to ensure that the effects of subdivision and development on the same site as any listed building or object are avoided, remedied or mitigated. Other policies are to discourage demolition or relocation and to promote conservation and sustainable use (policies 20.2.1.1 and
20.2.1.3).
The Board’s decision
[337] The Board suggested that in terms of heritage issues the case was
somewhat unusual in that the Project did not result in the
actual loss of any
listed heritage fabric. However it considered that the geographical and
historical context for the Project contained
an unusual concentration of
buildings, structures and places of heritage interest.143
[338] It recognised that the primary means for giving effect to the
recognition of historic heritage is to include items of historic
heritage in the
District Plan under Schedule 1. However it stated that even if a place or area
is not so scheduled, the requirement
in s 6(f) would still
apply.144
[339] The Board proceeded to recognise a “wider heritage area”145 which it considered could be affected by the Project, which stretched from Taranaki Street in the west through the Basin Reserve and Council Reserve areas to Government House
and the Town Belt in the east.146
142 At [1603].
143 At [566].
144 At [556].
145 At [577].
146 At [588].
[340] In its summary of findings on heritage effects across the wider
heritage area of interest it said:
[757] Regarding adverse effects on historic heritage, we find that
two issues stand out:
(a) The risk to the status of the Basin Reserve as a venue for test cricket is confounded by the significance of the adverse effects on the heritage setting that arise from the mitigation required to address the risk to test-cricket status; and
(b) The cumulative adverse effects of dominance and severance caused
by the proposed transportation structure and associated
mitigation structure in
this sensitive heritage precinct, particularly on the northern and northeastern
sectors of the Basin Reserve
Historic Area setting.
[341] It is useful also to record Mr McMahon’s different view on
which NZTA
placed emphasis:
[1600] In respect of Section 6(f), I fully accept and support that
the protection of historic heritage from inappropriate
development
is inextricably linked with sustainable management practice. In making an
overall determination on any particular
proposal’s ability to fit with
this strategic aim, I also find that the significance of the heritage
resource(s) relevant in
this case must also be factored in. In this respect,
the settled provisions of the District Plan provide – for me –
a
critical filter through which significance is defined; and, in turn through
which accordance with Section 6(f) can ultimately be
determined.
[1601] In this respect, I reiterate that there was agreement that there is
no direct adverse effect arising from the Project on any
heritage items
currently identified (as significant and worthy of protection) in the operative
District Plan. The evidence strongly
suggests, therefore, that the Project is
most certainly consistent with Section 6(f) as it relates to those listed
items.
[342] After discussing the District Plan, the changes made to it
and the non-inclusion of the Basin Reserve and its surrounds
as a listed
heritage item or area, Mr McMahon said:
[1604] I am inclined, for this reason, not to afford the wider site the same significance that would otherwise be afforded to listed items. To do so would (in my view) undermine the integrity of the District Plan and the inherent effectiveness of the listing method as the primary tool to implement the District Plan’s objectives and policies relating to the protection of historic heritage. This implementation role is important as it enables a process to test development against those policies and objectives which have already been deemed to be the most effective provisions to give effect to Section 6(f) and the Act’s purpose.
He concluded that the Project did not represent inappropriate development in
terms of s 6(f).
The parties’ contentions
[343] NZTA submitted that, particularly in light of King Salmon, there was no mandate for a decision-maker on either a resource consent or designation to “re-write” the District Plan, citing the Supreme Court in Discount Brands Ltd v Westfield (New Zealand) Ltd:147
The district plan is key to the Act’s purpose of enabling “people
and communities to provide for their social, economic,
and cultural well
being”. It is arrived at through a participatory process, including
through appeal to the Environment Court.
The district plan has legislative
status. People and communities can order their lives under it with some
assurance. A local
authority is required by s 84 of the Act to
observe and enforce the observance of the policy statement or plan adopted
by
it. A district plan is a frame within which resource consent has to be
assessed.
[344] NZTA developed that theme in this way:
36.15 There is a comprehensive suite of rules and criteria in Chapters 20
and 21 by which the District Plan recognises and provides
for the protection of
historic heritage from inappropriate use and development. This must be assumed
to be a deliberate choice, tested
and confirmed by the public participatory
process. It is entirely appropriate in a built up, central city environment.
Not only
has the Majority failed to have particular regard to these provisions
when considering the effects of the Project, it has imposed
a wholly different
regime for the recognition and protection of unlisted historic heritage
well beyond what the Plan itself
does.
36.16 Just as it would not have been permissible for the Board to find that
any of the listed items was not a historic heritage
value, nor is it open to the
Board to substantially rewrite the Plan by adding items or, as in this case,
whole ‘precincts’,
which the Plan does not contemplate.
...
36.19 [NZTA] submits that the Majority was wrong to undertake a
sand-alone assessment of heritage within the Part 2 framework,
as discussed
above. Further, the Majority failed to have particular regard to the
relevant planning documents when assessing
the effects of the Project on
historic heritage by finding heritage features in this location requiring
protection under s 6(f);
these being features
147 Discount Brands Ltd v Westfield (New Zealand) Ltd [2005] NZSC 17, [2005] 2 NZLR 597 at
[10].
beyond what the District Plan protects. This also led to the Majority
finding that the Project was ‘inappropriate’ in
relation to historic
heritage without addressing that in the context of the District Plan and its
regime for protection against inappropriate
use and development.
[345] In his notes for oral reply Mr Casey emphasised that resort to Part 2
is only required in the case of conflict (or where a
caveat applies, to which Q
45C relates). The point was made that there is no conflict between the planning
documents and Part 2 and
no conflict between the Project and the planning
documents (including the derivative documents). It was submitted:
The Board is required (before resorting to Part 2) to first assess
effects having particular regard to the (a)–(d) matters
and then consider
whether a conflict exists that requires resolution. A ‘thoroughgoing
attempt’ to resolve any apparent
conflict must be made. If a conflict
cannot be resolved, resort to Part 2 will be required.
[346] NZTA’s position derived significant support from WCC on whose
behalf Ms Anderson presented a thoughtful submission confined
to the Issue 6
questions. Although aligned with NZTA’s position on the historic heritage
issue, WCC’s submissions were
not partisan in nature but reflected the
fact that, as creator and regulator of the District Plan, WCC has a particular
interest
in how the District Plan is applied and interpreted.
[347] Key points made by WCC were:
– The effects of allowing the requirement must be considered
“through the lens” or “in light of”
the s 171(1)(a) to
(d) matters. That means that the District Plan is a key “filter” of
whether the effects that arise
from a proposal are acceptable or
appropriate;
– That analysis is supported by the requirement in s 171(1) to have “particular regard” to the listed matters which include the District Plan. That is to be contrasted with the lesser obligation to “have regard to” in s 104(1), albeit that both are subject to Part 2;
– Because of the lack of recognition of the Basin Reserve in the
District Plan, the Board could not resort to Part 2 as justification
for its
elevated treatment of unlisted heritage items and views;
– The Board erred in recognising an extended important
heritage area which was inconsistent with the significance
the District Plan
gives to the heritage values in the area.
[348] Although, like NZTA, WCC accepted that simply because the Basin
Reserve or the view along Kent and Cambridge Terraces is not
listed or
specifically identified in the District Plan did not mean that they
were not of any heritage value or importance,
nevertheless the
decision-maker cannot resort to Part 2 as justification for the elevated
treatment of unlisted heritage items and
views.
[349] WCC’s position was that the District Plan is a key basis for
decision-making under the RMA and its provisions “must
be applied as
written”. In response to my question whether the District Plan is
exhaustive on the topic of historic heritage,
Ms Anderson replied in the
affirmative.
[350] The respondents’ submissions in response were no less
comprehensive. In
summary they submitted:
(a) NZTA’s argument was based on an erroneous application of
King
Salmon to the present circumstances;148
(b) the adverse effects which the Board identified at [757]149
were directly relevant to the inquiry not only because they were
environmental effects under s 171 but also under s 149P because
concerns about
them were an important part of the Minister’s decision to refer the
proposal to the Board;
(c) all that the Board was required to do was to have particular regard
to the various plans, and it duly did so;
148 See at [117] above.
149 At [340] above.
(d) the Board’s concern about the adverse effects was consistent with
the guidelines in Part 2 to which its s 171 consideration
was
subject.
Analysis
[351] The extensive argument which I heard convinced me that
phrasing the question by reference to “through the
lens” or by way
of a “filter”150 is more likely to confuse than to
clarify.151 The search for meaning inevitably invites elaboration
of the theme, an example of which appeared in TAC’s submissions:
... Contrary to the Appellant’s submissions, s 171 the (a–d)
matters do not form themselves into a combined lens which magnify the
benefit of a proposed designation and diminish or blur its adverse
effects.
I prefer to focus on the words of the statute.
[352] It is plain that the Board was required to have particular regard to inter alia the District Plan including the heritage items listed in Schedule 1. As NZTA says, it would not have been permissible for the Board to purport to find that any of the listed items was not of historic heritage value. Nor would it have been permissible for the Board to ignore them. The Board was required to consider the s 171(1)(a)
matters specifically and separately from other considerations.152
That said, the
obligation on the Board in a s 171(1) context is to have “particular
regard to”, not “to
give effect to”.
[353] How much weight the Board gives to an item to which it is required to have regard or particular regard is a matter solely for the Board in the context of an appeal that is confined to questions of law, subject of course to any Edwards v Bairstow challenge. The issue which I am required to decide is whether as a matter of law the Board was permitted to have regard to other areas or items of historic heritage beyond that specified by the District Plan. In other words: Is the Plan exhaustive on
the topic?
150 At [341] and [347] above.
151 Kim Lewison Metaphors and Legal Reasoning, The Chancery Bar Association Lecture 2015.
152 See [66] above.
[354] In my view the Board was not so confined. Its consideration of
Part 2 considerations was not restricted to instances
of unresolvable conflict.
Provided it discharged the obligation to have particular regard to the specified
matters, in pursuance
of its Part 2 obligation the Board was not precluded from
also taking into consideration as effects on the environment the adverse
effects
of the requirement on other items it identified as being of significant historic
heritage. In doing so it did not inevitably
fail to have particular regard to
the Plan as a s 171(1)(a) matter.
[355] NZTA’s submission was that the Board had imposed a
wholly different regime for the recognition and protection
of unlisted historic
heritage that went “well beyond what the Plan itself does”. However
it is not the function of the
Court on an appeal such as this to undertake a
qualitative assessment. The question to be answered must be confined to
whether
the Board made an error of law in reaching its conclusion. In my view
it did not do so.
Q 45B: Further, should the Board have assessed the effects having
particular regard to its finding at [1230] that the works were reasonably
necessary to achieve the objectives under s 171(1)(c)?
[356] This question was derived from ground of appeal 29(e) (in the context
of Issue 3) which asserted that the Board had failed
to have particular regard
to the finding at [1230] that the work was reasonably necessary to achieve
NZTA’s objectives. The
23 July 2015 memorandum described Q 45B as a
development of Q 28(b) in its application to the original Q 45.
[357] The answer to Q 45B is plainly in the affirmative. That
is simply the statutory obligation.
[358] However the reality is that NZTA’s contention is directed not to the nature of the obligation but to whether the obligation was in fact discharged. While such an inquiry could be pursued on a general right of appeal, I do not consider that it is properly the subject of an appeal limited to questions of law only. However, in the event that my analysis is incorrect, I make the following further observations.
[359] I apprehend that at least one of the reasons for the contention that
the Board did not have “particular” regard
to the finding at [1230]
is that in its description of its proposed decision structure at
[199]153 the Board did not include the word
“particular” in its reference to s 171(1)(c) in subpara (d).154
NZTA’s submissions stated that one of three noteworthy aspects of
[199] was:
28.5(b) The Majority explicitly separates the s 171(1)(b) and
(c) considerations from the consideration of effects.
That is, it says that it
will consider the effects of the requirement; then consider the (b) and (c)
matters separately. It does
not say that it will consider the effects of the
requirement, having particular regard to whether [NZTA] has adequately
considered
alternatives (s 171(1)(b)); or whether the designation and the
work is reasonably necessary for [NZTA] to achieve its objectives
(s
171(1)(c)).
[360] However it is quite apparent that the Board did have particular
regard to the s 171(1)(c) consideration. In addition to
the discussion
spanning [1217] to [1230] under the heading “Reasonably necessary for
achieving objectives (s 171(1)(c))”,
the Board touched again on the issue
of [1277] to [1278] and implicitly in the course of its ultimate conclusion at
[1317].
Q 45C: When there is no ‘invalidity, incomplete coverage
or uncertainty of meaning’ in the relevant
plans under s
171(1)(a), is it appropriate for a decision-maker to assess effects
against s 6(f) (for historic heritage)
and s 7(c) (for amenity
values)?
[361] This question also invokes NZTA’s King Salmon argument.
In essence it asks whether it is appropriate to address Part 2 considerations in
the absence of one of the three caveats
explained in King Salmon,155
namely:
(a) if the relevant plan is invalid;
(b) if the relevant plan does not “cover the field”;
(c) if there are uncertainties as to the meaning of the particular policies
in the plan.
153 At [77] above.
154 The same is true in relation to the reference to s 171(1)(b) in subpara (c).
155 King Salmon, above n 26, at [88].
[362] WCC supported NZTA’s case on this point, submitting that the key findings in King Salmon at [84]–[85] were as applicable to District Plans as to Regional Plans. It contended that King Salmon removed the ability for a decision-maker to have recourse to Part 2 when giving effect to or interpreting a plan unless one of the three specific caveats applied. This, it was said, was significantly different from the
previous treatment of Part 2 as the “engine room”156
of the RMA. Its submissions
also explained why the second and third caveats were not of application in
this case.
[363] I am unable to accept that submission. The role of the caveats
identified in King Salmon was to address the situation where there was,
what one might describe generically as, some inadequacy in the plan. The
caveats accordingly
qualified the obligation to give effect to such an
inadequate plan and preserved the avenue of reference back to Part 2 which the
“give effect to” formula had removed.
[364] As explained earlier, the manner of recourse to Part 2 in the context
of s 171 (and other sections stated to be “subject
to Part 2”) is
not limited in the manner described in King Salmon.157 Of
course the three caveats may still have application in relation to inadequate
plans so far as concerns the obligation to have particular
regard to
them.
[365] I have some reservation about the formulation of the question so far
as it incorporates the word “appropriate”.
As the Supreme Court
remarked in King Salmon,158 the scope of that word is heavily
affected by context. I tend to think that the words “permissible”
or “legitimate”
would have been preferable.
[366] However, assuming that the consideration of an application under s 171 does in fact engage historic heritage or amenity values, for the reasons above the answer
to Q 45C is in the
affirmative.
156 Auckland City Council v John Woolley Trust, above n 54; see also [111] above.
157 At [85] in [113] above.
158 King Salmon, above n 26, at [100].
Q 45D: Did the Board correctly apply the definition of ‘historic
heritage’ under s 2?
[367] One of the matters of national importance listed in s 6 as (f) is the
protection of historic heritage from inappropriate subdivision,
use and
development. “Historic heritage” is defined in s 2 of the RMA as
follows:
historic heritage–
(a) means those natural and physical resources that contribute to an understanding and appreciation of New Zealand’s history and cultures, deriving from any of the following qualities:
(i) archaeological: (ii) architectural:
(iii) cultural: (iv) historic:
(v) scientific:
(vi) technological; and
(b) includes–
(i) historic sites, structures, places, and areas; and
(ii) archaeological sites; and
(iii) sites of significance to Māori, including wāhi tapu; and
(iv) surroundings associated with the natural and physical
resources.
[368] The nature of the Board’s alleged error in its
interpretation of s 2 was described in ground of appeal 40(c)
as
follows:
The Board wrongly applied paragraph (b)(iv) of the definition of
‘historic heritage’ in s 2 of the Act and thereby extended
its
consideration beyond the surroundings associated with the natural and physical
resources constituting the historic heritage within
the project area (being the
Basin Reserve and listed heritage items) to conclude that the wider setting to
those resources was of
itself a heritage area.
The parties’ contentions
[369] NZTA’s primary written submissions developed the argument in
this way:
37.3 While the definition includes ‘historic’ places and
areas it does not specifically provide for heritage precincts
or landscapes.
The fact that there may be a collection of heritage items within the locality
does not make it an historic place
or area, unless that locality is a place or
area of historic significance in its own right. As a matter of law it was
not open
to the Majority to conclude that the wider Project area is a
heritage precinct/landscape.
37.4 By establishing a heritage precinct at this location, the Majority has developed a heritage landscape construct which it found stretches from Taranaki Street in the west through the Basin Reserve and Canal Reserve areas to Government House and the Town Belt in the
east and applied it to the wider Project site. It did so on the basis that
there is an unusual concentration of heritage buildings,
sites and places at
this location, such that the Project is contained within what it describes as an
important heritage area.
37.5 By establishing a heritage landscape of this scale in this location,
the Majority has purported to confer s 6(f) protection
over the entire landscape
rather than the particular heritage items within it. This level of protection
is not provided for in
the District Plan which, as noted, protects scheduled
sites and features while ensuring that the diversity of development
provided
for within the planning framework relevant to this location is
not constrained.
[370] NZTA acknowledged that the Environment Court in Waiareka Valley
Preservation Society Inc v Waitaki District Council159
had been satisfied that a purposive interpretation of s 6(f) enabled
that provision to describe a collection of historic sites,
places or areas as a
heritage landscape and had concluded that the nomenclature
‘landscape’ could easily be substituted
by ‘area’ or
‘surrounds’, depending on the particular context.
[371] However NZTA noted that the Court has since expressed
considerable caution regarding the extension of (b)(i) of the
definition to
include a collection of historic sites, places or areas as a “heritage
landscape”. In Maniototo Environment Society Inc v Central Otago
District Council,160 the Environment Court noted that such
usage:
... may be dangerous under the RMA where the word “landscape” is
used only in s 6(b). Further, the concept of a landscape
includes heritage
values, so there is a danger of double-counting as well as of confusion if the
word “landscape” is
used generally in respect of section 6(f) of the
Act.
Similarly in Gavin H Wallace Ltd v Auckland Council161 the
Court also expressed caution over the use of the term and its inclusion in the
lexicon of the RMA.
[372] Consequently NZTA submitted, having regard to the definition of “historic heritage”, the case law and the District Plan, that the RMA does not envisage
protection being extended under s 6(f) to a central city urban landscape
of the scale
159 Waiareka Valley Preservation Society Inc v Waitaki District Council EnvC Christchurch
C058/2009, 13 August 2009 at [230]–[231].
160 Maniototo Environment Society Inc v Central Otago District Council EnvC Christchurch
103/09, 28 October 2009 at [208].
161 Gavin H Wallace Ltd v Auckland Council [2012] NZEnvC 120 at [66]–[67].
determined by the Board. To do so would result in all activities within that
location being “effectively trapped” within
a special heritage
landscape thereby “locking up” future urban development contemplated
by the planning framework.
[373] In brief summary the respondents submitted that:
(a) the definition of “historic heritage” is broad and
explicitly “includes” historic sites, structures,
place and areas as
well as surroundings associated with physical resources;
(b) NZTA’s interpretation is unduly narrow and at odds with the
text and
purpose of the RMA;
(c) the Board examined whether there was an area of historic heritage,
as the definition permits, but NZTA wrongly suggests
that the Board concluded
that there was some formal heritage precinct or landscape.
Analysis
[374] The competing perspectives in the contest before the Board are
captured in the following paragraphs:
[614] Some heritage experts have chosen to focus their assessments on
individual heritage items, particularly listed or registered
items, while others
give attention to considerations of heritage setting as well. With reference to
terminology, this is partly
a distinction between built heritage and
historic heritage.
...
[616] The Assessment of Environmental Effects prepared by [NZTA]
refers explicitly to Built Heritage as the title for Section 26 of the
document, and Technical Report 12 is similarly entitled Assessments of
Effects on Built Heritage. [NZTA’s] closing submissions confirmed this
thematic focus.
...
[617] ... The City Council’s closing submissions made no reference
at all to section 6(f) of the RMA, nor to historic heritage, choosing
rather to focus on issues related specifically to listed or registered heritage
items.
...
[622] Mr Milne, in his closing submissions, made numerous references to
historic heritage and argued explicitly that the focus of [NZTA’s]
case on heritage matters was wrongly limited to built heritage. Mr
Bennion, in his closing submissions, having cited explicitly the relevant
RMA sections, similarly made numerous references
to historic heritage and
argued for the proper recognition of setting when assessing effects on
historic heritage.
[375] As earlier noted,162 while the Board recognised
the District Plan as the primary means of giving effect to the recognition
of historic heritage,
it proceeded on the basis that even if a place or area was
not scheduled s 6(f) still applied.
[376] There are a number of reasons why it is not easy to attribute to the
Board a particular interpretation of the definition of
“historic
heritage” in s 2. First, the Board’s discussion under the heading
“Heritage, Cultural and Archaeological”
is extensive, spanning [535]
to [783], and the evidence is exhaustively analysed. That said, within that
thorough review there are
certainly references to precincts and landscapes,
which are the focus of NZTA’s submission.
[377] Secondly, the protection of particular sites or areas is not confined
to the District Plan. Although the Basin Reserve is
not included in the schedule
to the Plan, it is registered as an historic area under the Heritage New Zealand
Pouhere Taonga Act
2014.163 Similarly the Board viewed the fact of
the creation of the National War Memorial Park under its own empowering
legislation164 as an indicator of its national
significance.
[378] Thirdly, the mosaic which the Board was required to consider was
augmented by the Minister’s reasons for direction
to which the
Board was directed by s 149P(1)(a) to have regard. Relevant to the issue of
historic heritage those reasons
stated:
• The proposal is adjacent to and partially within the
Basin Reserve Historic Area and international test cricket
ground; in the
vicinity of other historic places including the former Home of Compassion
Crèche, the former Mount Cook
Police Station, Government House and
the former National Art Gallery and Dominion Museum; and is adjacent
to
162 At [338] above.
163 At [562]. The definition of “historic area” in s 6 means an area of land that contains an inter-related group of historic places and forms part of the historical and cultural heritage of New Zealand.
164 National War Memorial Park (Pukeahu) Empowering Act 2012.
the National War Memorial Park (Pukeahu). The proposal is likely to affect
recreational, memorial, and heritage values associated
with this area of
national significance (including associated structures, features and places)
which contribute to New Zealand’s
national identity.
[379] There is force in the respondents’ submission that it is
difficult to see how the Board could have complied with its
obligation to have
regard to the reasons of the Minister in referring the proposal to it without
taking the approach it did to the
“area” of historic
heritage.
[380] Indeed one of the instances of the Board’s use of
“precinct” was with reference to three of
those places of
importance when, in relation to an anticipated Anzac Day centenary celebration,
it said:165
Such an event would clearly link the NWM Park, the Basin Reserve, and
Government House – covering the entire precinct we have
described.
[381] In seeking to identify from the Board’s broad review the
interpretation which the Board placed on s 2, there are three
paragraphs which I
consider are particularly instructive:
[557] The protection given by Section 6(f) extends to the curtilage of the
heritage item and the surrounding area that is significant
for retaining and
interpreting the heritage significance of the heritage item. This may include
the land on which a heritage
building is sited, its precincts and
the relationship of the heritage item with its built context
and
other surroundings.
...
[615] In defining historic heritage, the RMA makes a clear
distinction between historic sites and historic heritage. At their
conferencing, the experts drew
attention to the definition of historic
heritage in the RMA – which includes (b)(iv) surroundings associated with
the natural and physical
(historic heritage) resources.
...
[623] We agree that we are obliged to consider the effects on historic
heritage and that historic heritage includes not only built
heritage but the
surroundings and setting in which the built heritage exists. In our view, the
explicit focus of [NZTA], Wellington
City Council and Heritage NZ heritage
assessments on built heritage, as distinct from historic
heritage, unduly limited the scope of those assessments.
165 At [589].
The third of those paragraphs represented the Board’s conclusion on the
competing contentions in the extracts at [374] above.
[382] While for the reasons in [376] to [379] above Q 45D has proved to be
one of the more difficult issues in the case, my conclusion
is that there was no
error in the Board’s interpretation of the definition of
“historic heritage”. I
do not accept NZTA’s submission
that in its application of the definition the Board “went well beyond the
surrounds
and setting of historic heritage”.166
[383] NZTA’s submissions further argued that if s 6(f) protection as
found by the Board was unobjectionable, then the Board
had erred in law
“by applying this concept to the Project area without any methodology
being identified or followed on
which to base such a significant finding”.
I do not address that submission because I do not consider that it involves
either
a question of law or an issue sufficiently connected to Q
45D.
Q 45E: What is the correct approach to the application of the test of
‘inappropriateness’ in s 6(f) [should the Court consider resort to Part 2 of the RMA
was available to the Board in the circumstances of this
case]?
[384] The bracketed words in the question reflect the fact that this
question is conditional upon an affirmative answer to
Q 45C and a
rejection of NZTA’s argument that it was not appropriate for the Board
to assess historic heritage under
Part 2.
[385] NZTA’s argument in summary form was:
(a) prior to King Salmon, “inappropriate” in
the context of s 6 was understood as having a wider meaning than
“unnecessary”
and was to be considered on a case by case
basis;
(b) King Salmon held that the former approach did not accurately
reflect the proper relationship between ss 5 and 6;
166 See [757] in [340] above.
(c) King Salmon held that “inappropriateness”
is heavily affected by context and that the standard relates back to the
attributes
to be preserved or protected rather than the activity
proposed;
(d) King Salmon also gave a clear direction that it is the
relevant planning documents that provide the basis for decision-making under the
RMA. This
includes a decision-maker’s evaluation of
“inappropriateness” in the context of s 6.
[386] Consequently NZTA submitted:
38.6 ... Therefore, in the absence of any allegation of
invalidity, incomplete coverage or uncertainty of meaning; a
decision-maker is
required to assess s 6(f) matters as particularised by the relevant planning
documents before them, from National
Policy Statements down to district
plans.
38.7 Even if the Majority was right to go beyond the District Plan in
determining what constituted historic heritage, it should
still have assessed
what was appropriate by having particular regard to the scale and nature of the
protection conferred by the District
Plan. It did not do so.
[387] Mr Palmer raised the objection that this argument did not
appear in the amended notice of appeal. However in
my view the proposition
advanced is in essence a variation on the theme reflected in Q 45A and Q 45C, in
particular the “through
the lens” argument.
[388] I first note that the Board explicitly recognised the guidance of
King Salmon
on the meaning of “inappropriate” in s 6(f):
[558] Importantly, for this matter, we are guided by the Supreme Court in
King Salmon as to the application of the word inappropriate as it
is used in Section 6(f). Where the term inappropriate is used in the
context of protecting historic heritage, the
natural meaning is that
inappropriateness should be assessed by reference to what it is that is being
protected. That is, within
the context of the heritage elements that exist
within and around the Basin Reserve area, their value and the effects of the
project
on those values.
[389] In support of its conclusion at [783] that the Project was not
consistent with s 6(f) the Board said:
[780] Our overall evaluation is not simply a matter of considering effects on listed heritage items or confining our evaluation to a consideration only of the loss or restoration of heritage fabric, although such historic heritage
effects are part of the cumulative picture. We must consider the character
and significance of the whole wider heritage area and
the appropriateness of
such a structure within it.
[781] We noted in our introduction to this section that the common theme
in the relevant statutory documents – the RMA, Regional
Policy Statement
and District Plan – is to protect heritage from inappropriate use and
development. We concluded in our findings
from the sub-area analysis reported
earlier in this decision two important issues: the inherent conflict in
mitigating adverse effects,
and the cumulative adverse effects of severance
within the heritage setting. It appears to us that those conclusions align
clearly
with the final assessment of Mr Salmond on appropriateness and
the findings of Ms Poff from her Part 2 assessment.
[782] Consequently, we find that the evidence of historic heritage
supports the conclusion that the Project before us constitutes
an inappropriate
development within this significant heritage area of the city.
[390] It is apparent in my view from [781] and a number of other paragraphs
that the Board did have particular regard to
the District Plan and
other relevant documents. NZTA’s complaint is with the Board’s
ultimate conclusion, as reflected
in the submission:
38.8 ... the Majority should have concluded that, because there was no
direct adverse effect arising from the Project on any heritage
items identified
as significant and worthy of protection in the District Plan, the Project is
consistent with s 6(f) as it relates
to those listed items and therefore does
not represent inappropriate development in terms of s 6(f).
[391] In effect NZTA’s case is that the Board erred in not reaching a
conclusion in accordance with (ie by giving effect to)
the District Plan. As my
earlier findings reflect, I do not agree that the Board’s task under s
171(1) was so confined.
[392] I do not consider that there was any error of law in the Board’s consideration of inappropriateness in s 6(f). In this context it is desirable to reiterate that this is not a general appeal by way rehearing and I am not sitting in judgment on the merits of the Board’s conclusion.
Issue 8: Failure to consider options within the scope of the
application to address amenity and heritage related effects
to the Gateway
Building
[393] Although this item was omitted from the memorandum of 23 July
2015167 there was no issue that it remained live and the
parties’ written submissions addressed the following question:
Q 51 Did the Board fail to have regard to a relevant matter, being
options within the scope of the application that could balance
the effects of
the Proposal on the playing of cricket with other effects (heritage and
amenity)?
[394] NZTA’s grounds of appeal were:
52 The grounds of appeal in relation to this issue are:
(a) The Board found at [965] that the cricketing experts were of the
uncontested view that the 65m Northern Gateway Building
was necessary to
mitigate the effects on cricket when the evidence of Dr Sanderson was that
a Northern Gateway Building of
45m would be sufficient to mitigate the risk of
visual distraction to batters.
(b) As a consequence, the Board found at [758] to [761] that there is
an inherent conflict in mitigating the adverse effects
on heritage. In
particular, by finding that a Northern Gateway Building of 65m is required
to mitigate the effects on
cricket, but that mitigation has of itself other
adverse heritage-related effects, including effects on views and
amenity.
(c) Consequently, the Board failed to consider as a relevant
matter, options within the scope of the application to
balance the needs of
cricket with any other effects (historic heritage or amenity) of a longer
structure, in particular by:
(i) failing to consider a Northern Gateway Building of
45m or 55m;
(ii) failing to consider a Northern Gateway Building of
65m together with conditions to ensure that the
Building remain a sense of openness between 45 and
65 metres.
(d) In the alternative, by rejecting the evidence of Dr Sanderson, the
Board implicitly found that the evidence of the cricketers
was more persuasive
in assessing the Proposal’s effects on the Basin Reserve. The Board
therefore could only have reasonably
found in accordance with the
cricketers’ evidence on amenity effects that the Northern
Gateway
167 At [332] above.
Building would appropriately protect the ambience of the
Basin Reserve (contrary to the Board’s finding at [653]).
[395] It is quite apparent that the Board was cognisant of the options
involving a Northern Gateway Building (NGB) of reduced length.
At [36] the
Board notes that the key elements of the Project included:
(f) A new structure, known as the Northern Gateway Building,
approximately 65m long and 13m high at or about the northern end
of the Basin
Reserve, adjacent and to the east of the R.A. Vance Stand. Shorter alternatives
to the proposed structure within the
same approximate 65m long and 13m high
envelope/area are also proposed, together with landscaping;
[396] The primary function of the NGB was to screen the moving traffic on
the Basin Bridge from views within the Basin Reserve so
as to mitigate the
effects of the Basin Bridge on cricket and amenity within the Basin Reserve.
NZTA made it clear that it had no
interest in developing the building, except as
mitigation for the effects of the Basin Bridge.168
[397] Hence the longest option was naturally the focus of the Board’s
consideration because the cricketing experts were of
the universal view that
that option was necessary to mitigate the effects on cricket. So far as Dr
Sanderson’s evidence was
concerned, Mr McMahon
noted:169
[1383] ... The cricket evidence from the Basin Reserve Trust is preferred to
the evidence of Dr Sanderson for the Applicant,
who generously
acknowledged that, despite his technical evidence in respect to ophthalmology,
he should defer to cricket experts
on the extent of the length of screening
necessary to avoid distracting movement on the Basin Bridge for cricket
players.
[398] I agree with Mr Palmer’s submission that it is apparent from the Decision and from the Draft Decision (which included proposed conditions regarding design) that the Board did not fail to have regard to other options or conditions. I note the irony in his closing observation that NZTA appeared to be complaining that the Board did not consider options which would have had an even greater impact on historic
heritage than the option it did focus on.
168 [1424].
169 [1383].
Summary
[399] A decision on an appeal “only on a question of law” which
raises more than
35 questions of law is not well-suited to a succinct summary. That is
especially so when ten of the questions asked whether the Board’s
conclusions on various issues were findings to which it could reasonably have
come on the evidence, that is, whether those conclusions
were so insupportable
that they amounted to errors of law.
The judgment finds that the Board’s Decision does not contain any of
the errors of law alleged. Although it is not practicable
to recite each
finding, attention is drawn to the following points of general
application.
The meaning of s 171(1)
The provision in s 171(1) to have “particular regard to” the
matters specified in (a) to (d) required the Board to consider
these matters
specifically and separately from other relevant considerations but did not
indicate that extra weight should be placed
on those
matters.170
The relocation of “subject to Part 2” did not change the meaning
of s 171(1).171 The Board’s role under s 171(1) was
different from that in King Salmon where the obligation under s
67(3) was to give effect to the NZCPS. King Salmon did not change the
import of Part 2 for the consideration under s 171(1) of the effects on the
environment of a requirement.172
Adequate consideration of alternative options
Section 171(1)(b):
(a) permits a more careful consideration of alternatives when there are more
significant adverse effects of allowing a requirement;173
and
170 [64]–]68] above.
171 [86]–[98] above.
172 [99]–[118] above.
173 [140]–[142].
(b) does not require a requiring authority to fully evaluate
every non-suppositious alternative with potentially reduced
environment
effects.174
In some, but by no means in all, cases it may be necessary for the
decision-maker to gain access to the weightings in a multi-criteria
analysis in
order to be satisfied that adequate consideration has been given to
alternatives.
Enabling effects
A project’s enabling benefit can constitute an effect to be taken into
account under s 171(1) and/or s 5.175 In order to be given weight
the enabling benefit need not be unique to a project, guaranteed to go ahead or
able to be quantified.176
Transportation benefits
Where a project will have more than minimal adverse effects no higher
standard of
proof is required to demonstrate the project’s transportation
benefits.177
Heritage and amenity
On a s 171(1) application a District Plan is not exhaustive concerning items of historic heritage. The decision-maker’s consideration of Part 2 considerations is neither restricted to instances of unresolvable conflict178 nor confined to situations
where one of the three King Salmon caveats is
applicable.179
The Board did not err either in its interpretation of the definition of “historic heritage” in s 2180 or in its approach to the application of “inappropriateness” in
s 6(f).181
174 [156].
175 [265]–[266].
176 [268].
177 [299].
178 [354].
179 [363]–[364].
180 [382].
181 [392].
Disposition
[400] For the reasons above, NZTA has not established that in its Decision
the Board made any error of law of the nature reflected
in the several questions
of law in the amended notice of appeal, as revised by the 23 July 2015
memorandum. Consequently
NZTA’s appeal under s 149V(1) is
dismissed.
[401] The parties requested the opportunity to make submissions on costs.
In view of the outcome of the appeal:
(a) the respondents are to file any costs memoranda by
11 September 2015;
(b) NZTA is to file a costs memorandum by 2 October 2015; and
(c) the respondents may file any memoranda strictly in reply
by
16 October 2015.
Leave is reserved to apply to amend that timetable if necessary.
[402] Finally I record my appreciation to all counsel for the quality of their submissions and the assistance which they provided to the Court in navigating a
course through this complex
matter.
Brown J
Solicitors:
M Casey QC, Wellington
Andrew Cameron Law, Wellington
Kensington Swan, Wellington
DLA Phillips Fox, Wellington
Prestige Lawyers Ltd, Auckland
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/1991.html