Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 15 December 2015
IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
CIV-2014-419-348 [2015] NZHC 3147
IN THE MATTER
|
of an application for an order for
possession of land under s 244 of the
Property Law Act 2007
|
BETWEEN
|
WAIKATO DISTRICT COUNCIL Applicant
|
AND
|
CHUHAR SINGH AND AMRO SINGH Respondents
|
Hearing:
|
On the Papers
|
Appearances:
|
P Moodley for Applicant
D J Taylor for Respondents
|
Judgment:
|
10 December 2015
|
JUDGMENT (No.2) OF WHATA J
This judgment was delivered by Justice Whata on
10 December 2015 at 3.00 p.m., pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Date:
Solicitors:
Brookfields, Auckland
Kellaways, Hamilton
Counsel:
D J Taylor, Hamilton
WAIKATO DISTRICT COUNCIL v SINGH [2015] NZHC 3147 [10 December 2015]
Relief from cancellation orders
[1] In my judgment of 16 September 20151 I granted relief
from cancellation subject to the following conditions:
(a) The Singhs shall have completed all the requisite physical
works within 60 working days of obtaining any required
building
consent.
(b) The Singhs shall have approved by Mr Graham or other suitably qualified expert, a pool operational plan that conforms to the NZS
5826:2010 standard prior to the reopening of the facility to the
public.
(c) In the meantime, the Singhs must continue to pay rental and all
other outgoings under the lease and to comply with all obligations
as tenant
under the lease.
[2] I reserved leave to the parties to provide submissions on the
precise wording of the proposed conditions within five working
days.
[3] In response to my directions, I received detailed memoranda
including updating the Court as to the position reached
some months after my
judgment. I issued a minute reminding the parties of the limited scope for
which I granted leave to make submissions,
namely on the precise wording of the
orders as set out at paragraph [63].
[4] I have now received what I directed the parties to provide, namely
a draft form of the orders.
[5] There was one point of disagreement. The applicant
requested that a condition 3 be inserted as follows:
3. The pools are not to be reopened until: (a) the physical works are completed;
(b) both plans are duly approved;
1 Waikato District Council v Singh [2015] NZHC 2233.
(c) with such completion and approval to be confirmed by the experts who
signed the joint statement dated 21 August 2015; and
(d) the respondents apply for Pool Safe accreditation.
[6] I accept the objective of the proposed condition, but I am
concerned that the requirement for expert consensus runs the
risk of undue
delay. I therefore grant leave of the parties to seek the assistance of the
Court if expert approval cannot be obtained
within 30 days of the request to
provide that approval.
[7] Accordingly, I make a final order in terms of Annexure
A.
Costs
[8] Ordinarily in cases where relief against cancellation has been
granted, a costs award is made against the party obtaining
the indulgence.2
I do not propose to depart from this orthodoxy save in one respect; I
consider that the costs in favour of the lessor should be
discounted by 25
percent to take into account an unduly pedantic approach taken to the
remedial process. While steps taken
in advance of litigation are not normally
factored into a cost award, I consider that this course properly reflects the
extent to
which the lessors contributed to the need for the
litigation.
[9] I note Mr Taylor’s strong submission that in his view the
proceedings arose from the Council’s improper conduct
towards the lessees,
including the unhelpful approach taken by the Council towards consenting and the
blunderbuss approach taken
to the Property Law Act notice. He further submits
that, in short, the Council’s conduct has been oppressive and has had the
effect of keeping the respondents in breach and therefore creating the
jurisdiction for the Council to seek an order that it did
seek, but on which it
failed.
[10] While I have some sympathy for the respondents, in reality they failed to comply with the lease requirements over a lengthy period (and appear continue to do
369.
so). In those circumstances, relief from cancellation was still an
indulgence afforded to them. I accept, however, that the discount
of 25 percent
is required to reflect at least in part, the matters raised by Mr
Taylor.
Annexure A
CONDITIONS OF RELIEF FROM CANCELLATION
1. The respondents will complete the physical works required to the
Waingaro Hot Springs facility as set out in the joint
statement of experts dated
the 21st of August 2015 (“the Experts’ Statement”) within
sixty working days of obtaining
any required building consent. The physical
works are:
(a) At the number two unit motel block – flashings to prevent
water entering the building envelope where the chimney was
removed.
(b) At the hot water bore – secure the fencing to the block wall
structure and the pressure vessel inside the shed to
the floor. Mr Mark
Mitchell to prepare the bracing calculations to confirm the cantilevering piles
are adequate to brace the shed.
(c) At the reception kiosk – the pre cast concrete floor slabs
are to be securely connected to the block wall structure
using steel connection
angles and bolts.
(d) At the spa pools – the timber barrier walls do not all have
adequate support posts and those that do not will need
to be
upgraded.
(e) At the hydro slide pump room – to prevent surface water run
off flowing into the pump room on the north eastern side
of the building a drain
is to be provided to intercept the surface water runoff and direct it into the
storm water system.
(f) At the pool filter enclosure – nail fixing holes in the roof
of this facility are to be filled with a sealant to prevent
rainwater
ingress.
(g) Concrete steps to caravan park – overhead power cables pass to close
to the ground at a location in an area accessible to the public, the power
lines are to be raised to the required minimum height.
(h) Timber steps – the new timber steps are to have an anti slip
surface provided to the treads such as geogrid.
(i) The sand filters for the main pool and spa pools are to be
replaced.
(j) The pool plumbing and pipe routing is to be adjusted according to
a plan prepared by Mark Mitchell to provide for:
(i) pre-chlorination of geothermal water; and
(ii) discharge of geothermal spring water into the main pool
balance tank to provide some chlorine contact time and premixing
to reduce the
water temperature before the water is fed into all pools including the
toddlers’ pool.
2. The respondents are to prepare new risk management plans and water
quality plans both in conformity with NZS 5826:2010
the plans are to be approved
by a suitably qualified expert. The plans are to cover inter alia:
(a) The risk of stream water entering the pools at times of high
flood.
(b) The risk of stream water entering the wet well chamber at the
spring at times of high flood.
(c) The need to reinstate cyanuric acid dosing if the period of
exposure to sunlight prior to pool waters being discharged to
the local stream
is for a period longer than twelve hours.
(d) All sand filters to be opened and inspected on an annual basis and
the condition of the sand investigated by a suitably
qualified and experienced
professional.
(e) The water sampling programme and the calibration of any equipment used
for undertaking analysis.
(f) The pool manager must be trained and have undertaken a pool
operation training or refresher course within the past ten
years.
3. The pools are not to be reopened until:
(a) the physical works are completed; (b) both plans are duly approved;
(c) with such completion and approval to be confirmed by the experts who
signed the joint statement dated 21 August 2015; and
(d) the respondents apply for Pool Safe accreditation.
4. The parties have leave to seek the assistance of the Court in the
event that the experts are unable to provide approval
within 30 days of being
requested in writing to provide such approval.
5. The respondents are to pay all rental and other outgoings under the lease and to comply with all obligations as tenant under the lease whether the pools are open or not.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/3147.html