Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 22 April 2015
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-3206 [2015] NZHC 694
BETWEEN
|
MARQUIS PROPERTY
DEVELOPMENTS LIMITED Plaintiff
|
AND
|
RAYMOND WALTER LORENZEN First Defendant
RAY'S CONSTRUCTION LIMITED Second Defendant
ANTHONY MARQUISS KEMP Third Defendant
LEE KEMP Fourth Defendant
|
Hearing:
|
14 April 2015
|
Appearances:
|
P Rice for plaintiff
S Hamilton for defendants
|
Judgment:
|
14 April 2015
|
(ORAL) JUDGMENT OF LANG J [on applications for summary
judgment]
MARQUIS PROPERTY DEVELOPMENTS LTD v LORENZEN [2015] NZHC 694 [14 April 2015]
[1] This proceeding arises out of a dispute between Mr and Mrs Kemp and
their son-in-law, Mr Lorenzen.
Background
[2] The dispute arises for the most part as a result of a property
development project that Mr and Mrs Kemp entered into with
Mr Lorenzen. This
involved Mr and Mrs Kemp transferring a block of land that they owned to Marquis
Property Developments Limited
(Marquis), a company that they formed specifically
to undertake the development. They then engaged Mr Lorenzen’s company,
Ray’s Construction Limited (Ray’s Construction), to subdivide the
section into four lots and to build homes on them that
they intended to sell at
a profit.
[3] The project was not a success, and the present litigation follows
as a result. As currently framed, it contains three broad
aspects. First,
Marquis alleges that it had overpaid Ray’s Construction for the building
work that it had carried out. Secondly,
Marquis alleges that Mr Lorenzen
breached his fiduciary duties to it by allowing loan monies drawn down by
Marquis to be paid to
Ray’s Construction. Thirdly, Mr Lorenzen sought to
recover monies that he had earlier advanced to Mr and Mrs Kemp.
[4] In March 2014, the parties entered into a written agreement in
which they agreed to have all aspects of their dispute determined
by a building
expert, Mr Anthony Dean.1 Although the agreement specifically
provided that Mr Dean was not undertaking an arbitration, the process that he
followed was very
similar to a conventional arbitration. Mr Dean received
submissions from both parties in person because, in order to reduce costs,
they
agreed that they would not be represented by counsel.
[5] Mr Dean issued substantive determinations on 4 September and 15
October
2014. The first dealt with liability and the second dealt with interest and
costs.
[6] The principal features of the determinations
were:
1 This proceeding was stayed whilst that occurred.
i. Mr Dean held that Marquis had overpaid Ray’s Construction
in the sum of $76,062.92, and that Ray’s Construction
was required to
repay that amount together with interest totalling $4,605.45.
ii. He held that Mr and Mrs Kemp were required to repay Mr Lorenzen
the sum of $31,561.09, together with interest totalling
$1,785.58.
[7] Unfortunately, Mr Dean’s determinations did not finally
resolve the dispute. The amounts he awarded remain unpaid.
Both parties also
sought to have him review aspects of his decision. Mr Lorenzen asked him to
review his decision to the extent
that it allegedly contained a number of
factual errors. Mr and Mrs Kemp asked him to review his decision because it
did not deal
with the claim that Mr Lorenzen had breached his fiduciary duties
to Marquis. Mr Dean declined to alter or disturb his decision.
He took the
view that he was functus officio, and therefore unable to revisit any
aspect of his decision.
[8] Marquis then sought to revive the present proceeding in order to
have its claims against both Ray’s Construction
and Mr Lorenzen dealt
with by way of summary judgment. Mr Lorenzen opposed that
application.
[9] Ray’s Construction also now seeks summary judgment against Mr
and Mrs Kemp in respect of the amounts for which Mr
Dean found them to be liable
to it. They have never opposed judgment being entered against them in respect of
those amounts. Ray’s
Construction has similarly never opposed the
application by Marquis for summary judgment against it.
[10] The only issue to be determined today was therefore whether Marquis
ought to be permitted to use this proceeding in order
to pursue the outstanding
issue relating to alleged breaches by Mr Lorenzen of his fiduciary duties to
Marquis.
Decision
[11] I consider that the attempt by Marquis to revive this proceeding cannot succeed for the simple reason that the parties expressly agreed that Mr Dean was to determined all aspects of their dispute. In this context the written agreement said:
6. Authority of Expert The Expert [Mr Dean] has the
authority to impose a decision on the parties, and any decision made by the
Expert will be fully &
finally binding on the parties.
...
9. Stay of Other Proceedings The parties shall
refrain from commencing or continuing with any action to take the disputes
and differences to arbitration
or before the Courts of law prior to the
proper termination of the Agreement. *
* Upon the formal written decision of the Expert being issued, no further
legal action will be commenced or continued in respect of
the disputed matters
[e]xcept in relation to the enforcement of the Expert’s
decision.
[12] Marquis argues that a subsequent memorandum filed by its counsel in
this proceeding, in which counsel sought to reserve Marquis’s
right to
return to the courts should the need arise, permitted it to return to this forum
in the event that Mr Dean did not determine
all matters that had been referred
to him. I do not consider this argument to be sound. Memoranda filed by
counsel cannot override
the express provisions of a written agreement signed by
both parties.
[13] As I have indicated, I consider that the parties expressly agreed
that Mr Dean would determine all outstanding issues in
dispute. They also
agreed that they would not return to the Court in respect of any issue other
than the enforcement of any decision
that Mr Dean might make. For that reason I
consider that Marquis is now contractually precluded from returning to this
Court to
have any aspect of its claim resolved. The application for summary
judgment therefore cannot succeed.
[14] Although it is not strictly necessary for me to express a view on the matter, I disagree with Mr Dean’s assessment that he is now functus officio and therefore unable to deal with the issue of the alleged breach by Mr Lorenzen of his fiduciary duties to Marquis. That issue was expressly pleaded in the current version of the statement of claim. It was therefore before Mr Dean for decision. The fact that he has issued a determination that did not deal with the issue does not mean that he is functus officio in respect of it. He will not be functus officio until such time as he has determined all aspects of both parties’ claims. Moreover, it is not open to Mr Dean to determine that he is functus officio. Whether or not he has that status is a matter
of fact and law. A tribunal in Mr Deans’ position will not be
functus officio until such time as it has determined all of the matters
that are properly before it.
[15] Mr Deans makes it clear in a memorandum issued on 18 November 2014 that his failure to deal with the claim that Mr Lorenzen had breached his fiduciary duties to Marquis occurred by oversight. This Court has the power to recall its judgments where by oversight it fails to deal with an issue squarely raised by a party to the proceeding.2 It will do so where for a very special reason the interests of justice
require that to be done.3 By way of analogy, Mr Dean must also
have the power to
recall his original determinations so that he can deal with the issue that he
failed to determine by oversight. If he did not, this
aspect of Marquis’s
claim could never be determined.
[16] After I had discussed these issues with counsel, all parties agreed
that the appropriate course of action was for the matter
to be referred back to
Mr Dean so that he can reach a final determination regarding the outstanding
issue. I make no formal order
that this must occur, and indeed I do not
consider I have any power to do so. It will be for the parties jointly to ask
Mr Dean
to determine this final aspect of their dispute.
[17] The issue may raise some complex legal concepts.
Essentially Marquis contends that Mr Lorenzen failed to account
to them for
monies that belonged to them, and that this amounted to a breach of the
fiduciary duty that Mr Lorenzen owed to it.
Both parties would obviously
benefit from legal input into the submissions that they make to Mr Dean
regarding this issue because,
as I understand the position, he does not have
legal qualifications that would provide him with expertise in this
area.
Result
[18] I grant Mr Lorenzen’s application for summary judgment against
Mr and Mrs
Kemp in the amounts sought. I also grant Marquis’s
application for summary
2 See eg Brake v Boote (1991) 4 PRNZ 86 (HC).
3 Horowhenua County v Nash (No 2) [1968] NZLR 632 at 633.
judgment against Ray’s Construction in the amount sought. I dismiss
Marquis’s
application for summary judgment against Mr Lorenzen.
[19] Both successful parties are also entitled to interest on those
amounts, from
4 September 2014 at the rate of five per cent per annum to the date of this
judgment.
Costs
[20] Both parties seek orders for costs in their favour. Marquis points
out that it suggested at an early stage to Mr Lorenzen’s
counsel that the
issue relating to the alleged breach of fiduciary duties should be
referred back to Mr Dean. That
proposal was steadfastly rejected. Mr
Rice points out that Marquis therefore had no option but to apply for summary
judgment against
the defendants because that was the only remaining alternative
given the fact that Mr Dean had advised both parties that he was not
prepared to
revisit the issue.
[21] I understand this submission as far as it goes, but in this jurisdiction costs usually follow the event. An unsuccessful party is generally required to contribute to the costs of the successful party.4 For that reason, I am not prepared to make an award of costs in favour of Marquis. However, I have some sympathy with Marquis because it was placed in a difficult position once Mr Dean elected not to determine the issue that he acknowledged he had omitted to deal with. Probably the only
practical alternative open to Marquis at that point was to seek to have Mr
Dean revisit that decision. I am not sure that Marquis
could have had resort to
the Court to require him to do so, however, because he was not a party to the
agreement to refer the dispute
to him.
[22] I therefore consider that justice will be done if the defendants are
jointly ordered to pay the disbursements incurred by
Marquis in relation to the
present application for summary judgment.
[23] Costs should also, however, follow the event in relation to the
remaining applications before the Court. Mr Lorenzen is
therefore entitled to
costs against Mr
4 High Court Rules, r 14.2(a).
and Mrs Kemp on an undefended category 2B basis together with disbursements
as fixed by the Registrar. Marquis is entitled to costs
against Ray’s
Construction on an undefended category 2B basis together with disbursements as
fixed by the Registrar.
Stay of proceeding
[24] This proceeding, to the extent that it now remains undetermined, is now stayed again pending determination by Mr Dean of the outstanding claim by Marquis
against Mr Lorenzen.
Lang J
Solicitors:
Haigh Lyon, Auckland
Davenports West, Henderson
Counsel:
P Rice, Auckland
C T Patterson / S R J Hamilton
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/694.html