Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 1 August 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-000219 [2016] NZHC 1180
BETWEEN
|
CUSTOMS STREET HOTEL LIMITED
Applicant
|
AND
|
PLUS CONSTRUCTION NZ LIMITED First Respondent
PLUS CONSTRUCTION CO LIMITED Second Respondent
|
Hearing:
|
23 May 2016
|
Appearances:
|
R B Stewart QC and I Rosic for Applicant
A Barker for Respondents
|
Judgment:
|
2 June 2016
|
JUDGMENT OF PALMER J
This judgment is delivered by me on 2 June 2016 at 4.30 pm pursuant to r 11.5 of the High Court Rules.
..................................................... Registrar / Deputy Registrar
Counsel / Solicitors:
R B Stewart QC, Auckland
A Barker, Barrister, Auckland
Gilbert Walker, Auckland (I Rosic)
Alexander Dorrington, Auckland (D Marsden)
CUSTOMS STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD & ANOR [2016] NZHC 1180 [2 June 2016]
Summary
[1] Custom Street Hotel Ltd applies for leave to appeal an arbitral
award on five questions of law. I am satisfied there are
serious arguments
regarding the questions which could substantially affect the rights of the
parties and that leave to appeal should
be granted.
Questions for Appeal
[2] The applicants, Custom Street Hotel Ltd (CSH), contracted
with the respondents (to whom I refer collectively as
Plus) to develop a hotel
on Customs Street in Auckland. There were problems with the development. In
early 2015 CSH required the
engineer to suspend the contract works and both
parties purportedly terminated the contract. The parties agreed to arbitration
over
whether CSH could make demand on a performance bond for some $3.6 million.
In November 2015 the arbitrator, the Hon Rodney Hansen
QC, held Plus had validly
cancelled the contract and no sums were properly due by it under the contract.
So the engineer was wrong
to issue his certificate and CSH could not make demand
under the bond.
[3] CSH seeks leave to appeal on the following questions:
(a) In relation to Plus’ purported termination of the construction
contract:
(i) Did the arbitrator err in holding that the defendants’
breach must be repudiatory in nature before the defendants
would be disentitled
from terminating?
(ii) Did the arbitrator correctly construe clause 14.3.3 of the
contract and err in holding that the defendants terminated
in accordance with
clause 14.3.3?
(b) In relation to the proper construction of clause 2(c) of the performance bond issued by Plus in favour of CSH:
(i) Did the arbitrator correctly construe clause 14.2.4 of the
contract and err in holding that the difference, between
a certified cost to
complete the contract works and the cost to CSH had the contract works been
completed by Plus, could not be “properly
due under the contract”
until the contract works have been completed?
(ii) Did the arbitrator err in holding that the damages claimed by CSH
for breach of contract cannot be “properly due under
the contract”
until CSH’s claim is admitted or determined as to liability and
quantum?
(iii) Did the arbitrator err in holding that CSH cannot rely upon the
amounts claimed under the indemnity clause in the contract
as amounts
“properly due under the contract”.
Leave to Appeal
[4] Clause 5 of Schedule 2 of the Arbitration Act 1996 provides that the High Court must not grant leave to appeal on a question of law arising out of an arbitral award unless it considers “having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of 1 or more of
the parties”.1
[5] I am satisfied that the test for the grant of leave to appeal is
met here. I grant the leave as sought.
[6] Both parties’ positions were that, if leave were to be
granted, the substantive appeal should be heard separately
from the application
for leave. In accordance with Rule 7.14 the Registrar must make arrangements
for a case management conference
on the first available date 15 working days
after the date of this judgment.
Palmer J
1 See Gold and Resource Developments (NZ) Ltd v Doug Hood Ltd [2000] NZCA 131; [2000] 3 NZLR 318 (CA).
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/1180.html