Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 19 August 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2015-404-2192 [2016] NZHC 1527
BETWEEN
|
BARRY PARK INVESTMENTS
LIMITED Applicant
|
AND
|
BODY CORPORATE NUMBER 95388
Respondent
|
Hearing:
|
On the papers
|
Counsel:
|
T J Herbert for Applicant
I J Stephenson for Respondent
|
Judgment:
|
6 July 2016
|
COSTS JUDGMENT OF PAUL DAVISON J
This judgment was delivered by me on 6 July 2016 at 4pm pursuant to r 11.5
of the High Court Rules.
Registrar/Deputy Registrar
Solicitors:
Castle Brown, Newmarket, Auckland
Minter Ellison Rudd Watts, Auckland
BARRY PARK INVESTMENTS LTD v BODY CORPORATE 95388 COSTS JUDGMENT [2016] NZHC 1527 [6 July 2016]
Introduction
[1] These proceedings were discontinued by consent. The only issue
outstanding is that of costs.
[2] In a Minute dated 18 February 2016, I issued timetabling orders for
the filing of memoranda by both parties regarding costs
which provided for each
party to contemporaneously file their memoranda and, by a later date, respond to
each other’s memorandum.
However the parties proceeded to file and
exchange a series of further and additional memoranda and thereby introduced
contentions
against each other regarding the merits of the substantive
proceeding.
[3] In response to a memorandum by the respondent seeking costs, the
applicant filed a further memorandum and challenged the
respondent’s
entitlement to seek costs, saying that the respondent had assumed an unwarranted
right of reply to the applicant’s
reply memorandum. The respondent in
reply, disputed the applicant’s contention and requested that a hearing be
set down if
the applicant were to maintain its complaints. In the end, the
applicant withdrew the complaints.
[4] Putting these issues aside, I briefly summarise the parties’
position on the
issue of costs. First, I set out the factual context.
Background
[5] The respondent is the Body Corporate of a building comprising 15
units. The applicant owns one of those units.
[6] The respondent sought to carry out remedial works which would
affect the
applicant’s unit and part of the common property.
[7] Two ordinary resolutions by the body corporate were passed.1
The first
resolution approved the design work and authorised the respondent “to
raise such
special levies” for that work. The respondent voted against this
by proxy. The
second (unanimous) resolution gave the respondent approval to
take steps to secure a remedial works contract, and authorised the raising
of
levies on a basis other than in accordance with each owner’s utility
interest apportionment. The applicant did not attend
the annual general meeting
at which this resolution was passed; nor did it provide a proxy to indicate its
voting preference.
[8] On 24 June 2015, the respondent’s committee raised a
special levy of
$102,925.12 against the applicant’s unit and sought payment of that
levy from the
applicant. The applicant refused to pay the levy.
[9] In August 2015, contractors engaged by the respondent began
remedial works on the building. The applicant refused access
to its
unit.
[10] In September 2015, the applicant commenced proceedings against the
respondent, seeking declaratory and ancillary relief on
the basis that the first
and second resolutions were ultra vires because they were contrary to ss 120 and
121 of the Unit Titles
Act 2010.
[11] In October 2015, the respondent defended the allegations and made a
counterclaim, seeking (inter alia) a declaration that the
applicant was in
breach of its statutory obligations when refusing the respondent and its agent
access to its unit to undertake the
planned work.
[12] On 14 December 2015, the respondent passed two further resolutions. The third resolution effectively rectified the respondent’s position, which achieved compliance with the provisions of the Unit Titles Act.2 The fourth resolution gave the respondent the discretion to exclude the applicant’s unit from the remedial works. It has since exercised that discretion, with the result that the declarations sought by
the applicant would no longer be of any affect and rendered
nugatory.
2 It resolved to levy the remedial works on a utility interest basis as between all owners. On 21
December 2015, the respondent issued a demand for payment of the levy raised pursuant to the resolution of 14 December 2015. The levy remains unpaid and the respondent has filed proceedings in the District Court for payment of levies in the amount of $111,86.84.
[13] The parties’ respective claim and counterclaim were discontinued
by consent
on 18 February 2016. It is in this context that the issue of costs is
addressed.
Submissions
[14] In chronological order, the parties made the following submissions in
their costs memoranda:
(a) 26 February 2016: the applicant said the presumption contained in
r
15.23 of the High Court Rules (the Rules), that the party who discontinues a
proceeding must pay costs, is displaced here because
the respondent’s
passing of the third and fourth resolutions amounts to a change of circumstances
rendering the proceedings
unnecessary; hence its discontinuance. Further, the
third and fourth resolutions represent an implied admission on the part of
the
respondents that the first and second resolutions were ultra vires, as was
alleged by the applicant.
(b) 1 March 2016: the respondent said the presumption does apply
in this case, requiring the applicant to pay costs to the respondent for the
following
reasons:
(i) The applicant did not engage in or contribute to
the respondent’s decision making process. It
did not attend the AGMs to
voice its concerns, and only voted (via proxy) on the first
resolution.
(ii) The proceedings were brought prematurely in a context where the
respondent had proposed a further two weeks to continue
negotiations.
(iii) It was unnecessary to put the respondent to the cost of a proceeding. The respondent did not dispute the applicant’s position that the levy was invalidly raised and “was happy to put a new motion to owners to resolve that concern.”
The respondent also seeks costs on costs.
(c) 8 March 2016: the applicant in reply, disputed the
respondent’s
contentions and said:
(i) It did in fact participate in the decision making process but this
was to no avail. That it did not attend the AGMs does
not assist the
respondent’s position as it cannot show that the resolutions would not
have been passed (so as to render the
proceeding unnecessary) had the applicant
attended the AGM.
(ii) Although there was an undertaking on the part of the
respondent that it and/or its agent would not carry out works
to the
applicant’s unit while negotiations were ongoing, it was a condition of
the undertaking that the applicant “bring[s]
the proceedings on an
expedited basis and the proceedings are indeed dealt with on an expedited
basis”. Therefore, said
the applicant, the proceeding was effectively
brought at the behest of the respondent.
(iii) At all relevant times (prior to and after the proceeding had been commenced) the respondent’s position was that the levy was validly raised. The applicant only learned that the respondent had rectified its position on or around 14
December 2015, which was after the proceeding had been
commenced.
The applicant agreed that there should be costs on costs, but said it is the
applicant who is entitled to them.
(d) 9 March 2016: the applicant identified an error in its earlier memorandum.
(e) 10 March 2016: the respondent submitted that the
applicant’s claim that the proceedings had been brought at the behest of
the respondent was
incorrect. Furthermore, the respondent repeated the
submission that the applicant had not voted against the second resolution, and
complained that the applicant had “sat on its rights”. If it had
voted, and had the vote been rejected, the respondent
could have sought minority
relief under s 210. The respondent made a further submission on the
issue of costs on costs,
saying that daily allocations for costs memoranda
should be made as though they were submissions on an interlocutory
application.
(f) 11 March 2016: applicant’s memorandum
filed, subsequently withdrawn by consent.
(g) 11 March 2016: respondent’s memorandum filed, advising
that it does not consent to any of its own memoranda being
withdrawn.
Analysis
[15] The principal issue of dispute is whether the presumption that a
plaintiff who discontinues a proceeding against a defendant
should pay costs to
the defendant, applies in this case.
[16] The focus is not on whether the applicant has acted unreasonably in
commencing and then discontinuing the proceeding, but whether
there are
circumstances which make it just and equitable that the presumption should not
apply.3 The reasonableness of the parties’ conduct up to the
point of discontinuance may be taken into account.4
[17] The Court will not usually consider the merits of the respective
claims unless, as in this case, they are so obvious that
they should influence
the costs outcome.5
3 The rationale is to obviate any requirement for the defendant to demonstrate that the plaintiff acted unreasonably in commencing and then discontinuing the proceeding. The defendant has the advantage of the presumption even where there has not been such unreasonableness.
4 Kroma Colour Prints Ltd v Tridonicatco NZ Ltd [2008] NZCA 150 at [29].
5 See generally, FM Custodians Ltd v Pati [2012] NZHC 1902 at [11].
[18] The respondent’s submission that the applicant should have
taken alternative steps before commencing its proceeding
– for
example, by continuing its negotiations with the respondent or
participating more in the decision
making process before seeking relief
– is an insufficient answer to the applicant’s submission as to why
the circumstances
after the proceedings were commenced make it just and
equitable that the presumption should not apply.
[19] For present purposes, the relevant circumstances are simply that the
applicant brought a proceeding against the respondent
setting out its
complaints, following which, the respondent took remedial steps to resolve them.
It was only after the respondent
took such actions that the applicant
discontinued the proceeding. For that reason, I agree with the
applicant’s submission
that the circumstances leading to discontinuance
were brought about by the actions of the respondent, making it just and
equitable
that the applicant should not pay costs on the
discontinuance.
[20] The respondent says it was always willing to accept that the levy was invalidly raised. Therefore, says the respondent, the applicant should not have brought the proceeding or it was unreasonable for it to have done so. I do not agree. The reality is that up until 14 December 2015, the respondent had not taken any steps to demonstrate a concession on its part that the levy had been invalidly raised. To the contrary, by its statement of defence dated 7 October 2015, the respondent defended the claims made against it, and maintained the position that the levy had been validly raised. The respondent’s change of position between October and December 2015, well after the applicant’s proceeding was commenced on 18
September 2015, supports the applicant’s contention that the
respondent’s remedial steps had overtaken the proceeding
and it was
because of that development that the applicant then discontinued its
proceeding.
[21] I agree with the applicant’s submission that the resolutions
of 14 December
2015 had the effect of rendering the applicant’s proceeding nugatory. I add further, that it would have been unreasonable for the applicant to continue its proceeding in circumstances where the granting of the relief sought would have been futile.
[22] Accordingly, I find that the presumption contained in r 15.23 is
displaced, and the applicant is not liable to pay the respondent
costs.
[23] The next issue is whether the respondent is liable to pay the
applicant costs. If not, costs should lie where they fall.
[24] In my view, and in light of the circumstances of this case, I
consider the general principle that the “losing”
party should
pay costs to the party who “succeeds” applies by analogy here.
The applicant could have done no
better even if it had succeeded. For this
reason, I order that the respondent is to pay costs to the
applicant.
[25] I decline to award costs on costs. In the chain of exchanged
memoranda, both parties fell into the tempting error of raising
and repeating
issues of dispute which led to an extended sequence of memoranda and an
expansion of the dispute as to responsibility
and, consequently, as to
costs. Despite the Court’s general reluctance to award costs on
costs applications, it
would be rare for this Court to award costs on costs
where doing so would conflict with the general principle and objective that
the
determination of costs should be expeditious.
Conclusion
[26] The respondent is to pay costs to the applicant in the sum of
$11,596, plus disbursements in the sum of $1,350.
[27] Costs on costs shall lie where they
fall.
Paul Davison J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/1527.html