Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 9 September 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-1102 [2016] NZHC 1839
UNDER
|
the Companies Act 1993
|
IN THE MATTER OF
|
an application for orders setting aside a statutory demand
|
BETWEEN
|
CONCAST WEST LIMITED Applicant
|
AND
|
OCEAN KING ENTERPRISE LIMITED Respondent
|
Hearing:
|
8 August 2016
|
Appearances:
|
H Lim and M Moon for Applicant
N Tabb for Respondent
|
Judgment:
|
8 August 2016
|
ORAL JUDGMENT OF ASSOCIATE JUDGE R M
BELL
Solicitors:
Forest Harrison (H M Lim/M Moon) Auckland, for Applicant
Natalie Tabb, North Harbour, Auckland, for Respondent
CONCAST WEST LIMITED v OCEAN KING ENTERPRISE LIMITED [2016] NZHC 1839 [8
August 2016]
[1] Concast West Ltd applies to set aside a statutory demand by Ocean
King Enterprise Ltd dated 12 May 2016. The demand requires
payment of
$102,673.17, “being money due and owing unpaid invoices from April
2015-February 2016 plus collection costs and
cost of this demand”.
Concast West Ltd says that there is a genuine and substantial dispute whether or
not the debt demanded
is due and owing, and that it has a counterclaim or
set-off that exceeds the value of the alleged debt. These are recognised grounds
for setting aside a statutory demand under s 290(4)(a) and (b) of the Companies
Act 1993.
[2] Concast West Ltd is a property developer. It owns land at 178
McLeod Road, Te Atatu, Auckland, on which it is carrying
out a
development. Ocean King Enterprise Ltd is an earthworks contractor. It
carried out work on the site between April and
December 2015. That work
appears to have included excavation and disposing of fill from the site, the
purchase and supply of metal
and also some labour on site, including some work
on drilling.
[3] Ocean King Enterprise Ltd’s invoices total $230,261.97.
Concast West Ltd
made payments to Ocean King Enterprise Ltd between 8 June
2015 and
20 November 2015 totalling $150,960.32. On my arithmetic, the difference
between the total invoices and the amount paid is $79,301.65.
That is less than
the amount stated in the statutory demand.
[4] On applications to set aside statutory demands, the basic
principles are not in dispute. The Court of Appeal conveniently
repeated them
in AAI Ltd v 92 Lichfield Street Ltd (in rec and in liq). It quoted with
approval these principles stated by the Associate Judge at the first
instance:1
As to s 290(4)(a)
(a) The applicant must show that there is arguably a genuine and
substantial dispute as to the existence of the debt.
1 AAI Ltd v 92 Lichfield Street Ltd (in rec and in liq) [2015] NZCA 559, (2015) 23 PRNZ 52 at
[19].
(b) The mere assertion that the dispute exists is not sufficient.
Material short of proof is required to support the claim
that the debt is
disputed.
(c) If such material is available the dispute should normally be
resolved other than by means of proceedings in the Court’s
Companies Act
jurisdiction.
As to s 290(4)(b)
(d) Alternatively, an applicant must establish that any
counterclaim, cross demand or set-off is reasonably arguable
in all the
circumstances.
As to both ss 290(4)(a) and (b)
(e) It is not usually possible to resolve disputed questions of fact
on affidavit evidence alone, particularly when issues
of credibility
arise.
[5] In addition, the court repeated its statement in Industrial
Group Ltd v
Bakker:2
[21] We are not persuaded that is the threshold an applicant must meet
under s 290(4). Such a threshold would be inconsistent
with a statutory scheme
which provides for a process summary in nature, with potentially draconian
consequences for the unsuccessful
applicant and tighter time frames than
those applying in the summary judgment jurisdiction. In Industrial Group Ltd
v Bakker this Court said:
... the statutory scheme ... for applications to set aside statutory demands
[is] a summary proceeding ... The section calls for a
prompt judgement as to
whether or not there is a substantial dispute ... The test may be compared with
the principles in cognate
fields such as applications to remove caveats, [and]
leave to appeal an arbitrator’s award ... The tight time constraints
distinguish
the s 290 discretion from that to be exercised on say, a summary
judgment application, where the presence of complex legal issues
is not
necessarily a bar to a remedy. As with leave to appeal an arbitrator’s
award, the hearing should, in the normal course,
be short and to the point. And
the judgment likewise.
[6] As to counterclaims under s 290(4)(b), in Covington Railways Ltd v Uni- Accommodation Ltd the Court of Appeal stated that a company must show “clear and
persuasive
grounds”.3
2 Industrial Group Ltd v Bakker [2011] NZCA 142, (2011) 20 PRNZ 413 at [24]- [25].
3 Covington Railways Ltd v Uni-Accommodation Ltd [2000] NZCA 230; [2001] 1 NZLR 272 (CA) at [11].
Preliminary matters
Late tender of affidavits
[7] At the hearing, Ocean King Enterprise Ltd tendered two
affidavits by machine operators who had worked on the job
at McLeod Road. By
this time, the applicant had already long filed and served its evidence in
reply. When the case was called on
10 June 2016 Associate Judge Doogue recorded
that all of the affidavits relied on were in, except for any reply affidavits by
the
applicant. He did not reserve leave to the respondent to file further
affidavits and, as I have noted, reply evidence has now come
in. The
respondent’s explanation for tendering the affidavits late is that the
matters covered in the affidavits were relatively
narrow and that they go only
to corroborate evidence that has been given on its behalf already.
[8] I refused leave for those affidavits. In short, the affidavits
were filed well out of time. It is important to adhere
to appropriate procedure
which is to ensure that when respondents file their evidence the applicant is
given an adequate opportunity
to reply. It is undesirable to give other parties
the opportunity to file evidence late. It is likely to create embarrassment,
lead
to unfairness, or otherwise lead to further delays. I regard further delay
as undesirable for this case. Applications to set aside
statutory demands
should be determined promptly.
Hearsay evidence
[9] The evidence for the applicant includes an affidavit of Mr Yang,
sworn on
26 May 2016 where, at paragraph 13, he refers to a plan by a surveyor said to show the location of piles on the site. The surveyor himself has not given evidence. I consider that there has been adequate opportunity for the surveyor to give evidence. The applicant has not suggested that the surveyor was unavailable in terms of s 16 of the Evidence Act. The plan does not satisfy the requirements for admitting hearsay evidence under s 18 of the Evidence Act. There is nothing about that document to give me any assurance that the plan is reliable. There is no evidence to show that the surveyor is unavailable and I do not consider that there would be undue difficulty or expense in requiring the surveyor to give an affidavit. I accept that there may be
difficulty in obtaining an affidavit from the surveyor within the 10 days
after service of the application. Admittedly priority
has to be given to
filing and serving a primary affidavit in support of the setting aside
application. But in this case there was
adequate time after the initial
affidavit in which to obtain an affidavit by the surveyor.
[10] The same objection goes to Exhibits D and E in Mr Yang’s
affidavit of
24 June 2016. That is another plan by the surveyor, and also a letter from
an engineer. The same objections apply to their admissibility.
[11] Mr Yang has also put in evidence estimates as to the costs of
remedial work. I accept that it is standard practice when claims
are made for
remedial work to exhibit quotes from other contractors as to the costs for
remedial work. I allow that in.
[12] Another unacceptable and inadmissible part of Mr Yang’s reply
affidavit is paragraph 19. He deposes that Concast
staff raised objections
with Ocean King Enterprise Ltd as to the invoices at earlier dates. There is no
reason why those people could
not have deposed to that. I do not see that there
is any reason why they could not have given affidavits themselves as to it. I
exclude paragraph 19 of Mr Yang’s reply affidavit as inadmissible
hearsay.
[13] There is also an aspect relating to paragraph 7 of the affidavit of
Mr Turvey but I will deal with that when I come to the
question of the
counterclaim.
Allegations as to solvency and insolvency
[14] Mr Turvey’s affidavit contains allegations suggesting
insolvency on the part of Ocean King Enterprise Ltd. The solvency
or otherwise
of Ocean King Enterprise Ltd is not relevant to the merits of this application.
Paragraph 13 of his affidavit is irrelevant.
[15] Concast West Ltd also alleges solvency on its part. In its first affidavit in support of the setting aside application, it says that it is the owner of the land at
178 McLeod Road and that the land has a rating value of $2.5 million. That, by itself, is not evidence of solvency. To establish its solvency, Concast West Ltd also needs to give evidence as to its liabilities. It has given absolutely no evidence as to its liabilities. Balance sheet solvency is not by itself relevant on a liquidation application. Rather, cash-flow solvency is what counts. There is no evidence from Concast West Ltd as to its cash-flow solvency. In any event, solvency is not ordinarily by itself a ground for a setting aside application. It is at best no more than
bolstering evidence to show that its application is otherwise
well-grounded.4
Contract terms
[16] It is necessary to give some background as to the operation of the
contract. It is common ground that Ocean King Enterprise
Ltd did carry out work
for Concast West Ltd between April and December 2015, that it charged
$230,261.97 for that work, and to
date has been paid $150,960.32. The
parties, however, have not troubled themselves with giving evidence as to
when any
contract between the parties was made, whether the contract was in
writing or oral, and what the terms of the contract were. I
was advised by
counsel that the contract was oral, although I was not told when the contract
was entered into.
[17] I am left to draw some inferences:
(a) In the absence of any evidence as to express terms, there
is no provision in the contract under which Concast
West Ltd was entitled to
hold retentions.
(b) In the absence of any evidence that there was an agreed price for
the work, it appears that Ocean King Enterprise Ltd was
entitled to charge a
reasonable price for the work it carried out.
(c) In the absence of any evidence, there is no provision that in
default of payment Concast West Ltd was to pay any interest
on unpaid
sums.
4 AMC Construction Ltd v Frews Contracting Ltd [2008] NZCA 389, (2008) 19 PRNZ 13 at [8].
(d) In the absence of any evidence, there is no provision in the
contract under which Concast West Ltd was to pay any debt collection
costs
incurred by Ocean King Enterprise Ltd. Of course, if Ocean King Enterprise Ltd
had sued for the unpaid debt, a court would
have a discretion to award interest
under the District Courts Act or the Judicature Act. The point I am making is
that there is
no evidence of contractual terms allowing interest to be charged
or debt collection costs to be recovered.
[18] Ocean King Enterprise Ltd inserted this wording into its
invoices:
Terms and conditions of sale:
Payment of our service is due within seven days of this invoice unless
otherwise agreed. Interest may be charged on overdue accounts
from the date
payment falls due at 2 per cent interest per Months. The client shall be liable
for all cost statement of facts collection
and legal fees incurred by Ocean King
Enterprise Ltd in recovering amounts payable.
[19] Given the absence of any contractual terms to that effect, the
provisions on the invoices have been added after the parties
contracted. There
is no evidence of any course of dealing between the parties under which it could
be considered that this wording
had become part of the parties’
contractual terms. It is arguable for Concast West Ltd that under the contract
it is not
liable to pay contractual interest or to pay debt collection
costs.
[20] I have mentioned that because the debt claimed by Ocean King Enterprise Ltd in part includes claims for interest and debt collection costs. It claims $5,575.00 interest and $18,041.52 for debt collecting costs. I find that Concast West Ltd has genuine grounds for disputing its liability for these sums, given that they do not appear to be supported by contract terms on the evidence available at present. I add that even if debt collecting costs were recoverable, I would require to be satisfied as to the reasonableness of the amount claimed - $18,041.52.
Is there a genuine and substantial dispute as to the charges for work
carried out?
[21] The real matters in dispute are whether Concast West Ltd has shown
either an arguable case for disputing its liability for
the balance sum of
$79,301.65 and also whether it has shown clear and persuasive grounds for a
counterclaim.
[22] In the first affidavit in support of its application, Concast West Ltd exhibited invoices from Ocean King Enterprise Ltd, from September onwards. These invoices have handwritten notes on them which generally say: “Payment on hold. There are not enough supporting documents” with the date of the notation added. The invoices show charges for tasks carried out by Ocean King Enterprise Ltd for the job at
178 McLeod Road. They show the date the work was carried out, the
particular machinery used, the hours of work, the rate per hour,
and then each
invoice shows a charge for the particular day covered. In the affidavit by
Ocean King Enterprise Ltd, its director
shows all the invoices. In addition,
he has attached to each invoice documents which Ocean King Enterprise Ltd
contends support
the charges made in the associated invoice.
[23] The contest here is as to the position taken by Concast West Ltd, as recorded on its invoices, that there are not enough supporting documents. In short, it is taking the point that Ocean King Enterprise Ltd cannot prove that it carried out all the work for which it has claimed payment. In its affidavit Ocean King Enterprise Ltd exhibited all the invoices with supporting documentation. In its written submission for the hearing, Concast West Ltd presented an analysis of the invoices and the associated documents. This analysis went to show that there was overcharging of
$5,380.00 on invoices and that there was no documentation to support the
claims, showing a deficiency of $182,809.30. That was said
to show that there
was a genuine dispute as to the liability of Concast West Ltd.
[24] In submissions counsel for Concast West Ltd went through the carefully prepared schedule and also a chronology of invoices. As she progressed, it became apparent that there was little substance in the complaints of overcharging and insufficient supporting documentation. For the first invoice, the point was taken that
time records showed that the time spent on the job was 8½ hours for the first 2 days and 9 hours for the third day, whereas the correct time was said to be 8 hours each day resulting in an over-claim of 2 hours. Notwithstanding that apparent over- charging of 2 hours’ work for a total sum of $130.00, it became clear that later Ocean King Enterprise Ltd had, if anything, under-charged the hours it had worked. The
$130.00 was, by itself, trifling.
[25] There were also said to be insufficient supporting documents. When
this was examined it was found that there was adequate
verification of the
charges made. For example, in many cases Ocean King Enterprise Ltd attached
dockets for materials from suppliers,
showing that quantities of metal had been
despatched and taken by Ocean King Enterprise Ltd with the docket identifying
the job as
“Te Atatu” or “McLeod Road”. The reference
to “Te Atatu” was said to be insufficient identification.
That is
when it became apparent to me that Concast West Ltd was very much into quibbling
over matters. There was no evidence that
Ocean King Enterprise Ltd was
carrying out any work in Te Atatu other than at the site of Concast West Ltd at
178 McLeod Road. Similarly,
for an invoice for work carried out in May 2015 (on
p 15 of the bundle), objection was taken to claims for delivery of metal
although
there was adequate supporting documentation.
[26] As counsel progressed, I challenged her to show me any charge by Ocean King Enterprise Ltd which was not in fact supported by documentation. She was unable to do so. Again, the matter was no more than quibbling. As an example, issue was taken with an invoice for work carried out during June 2015. There was a challenge to a charge for 3 hours’ work on 9 June 2015 by reference to a diary – clearly a driver’s diary recording his work on that day. That work showed the driver starting at 7:00am and finishing at 11:30am. That was sufficient to show at least
3 hours’ work. As it happens, at the bottom of the diary note there was a record that a further three loads were taken away from the McLeod Road site by another driver named “Eric”. The diary had been completed by a driver called “Sam”. Ocean King Enterprise Ltd may not have charged for all the work it carried out in the month of June. If anything, Concast West Ltd may have done fairly well by being under- charged for the work that day.
[27] Similarly, there was a challenge to the work recorded in the diary
notes on
10 June 2015. The driver concerned had recorded having started work at Dairy
Flat. I take “Dairy Flat” to be a reference
to the refuse facility
at Dairy Flat. It makes sense that material excavated from the site at 178
McLeod Road would be taken to
the facility at Dairy Flat. Again, Concast West
Ltd quibbled, saying that I could not take such judicial notice for the hours
charged
for 10 June 2015. There was also a supporting invoice from Ocean King
Enterprise Ltd’s sub-contractor, Legand Management Ltd,
for work carried
out on the same date. Ultimately, counsel did not persist with trying to show
that there was no supporting documentation
for the invoices by Ocean King
Enterprise Ltd.
[28] In submissions in response, counsel for Ocean King Enterprise Ltd
referred to some of the supporting documents, showing that
that had been signed
for on behalf of Concast West Ltd. But not all of the supporting
documents carry a signature from
someone acting on behalf of Concast West Ltd.
The point remains that to the extent that anyone acting on behalf of Concast
West
Ltd has signed off work sheets, that shows approval for the work recorded
and puts that beyond dispute. Equally, I am satisfied that
the supporting
documents relied on by Ocean King Enterprise Ltd can be used to show that the
work claimed for has been carried out.
[29] I cannot see any basis upon which Concast West Ltd could reasonably
argue that there is ground for dispute for the work charged
for in the invoices
of Ocean King Enterprise Ltd. There are some bolstering signs to support that
conclusion. Concast West Ltd
has not adduced any admissible evidence that during
the contract it raised any questions as to the correctness of the amounts for
which it had been invoiced. If it intended to be business-like about matters,
I would ordinarily have expected that it would have
checked the invoices when
they came in and raised any queries. Instead, it seems to have made some
payments to Ocean King Enterprise
Ltd during the contract, although never paying
all invoices in full, notwithstanding that there was no provision for
retentions.
At the end of the contract, when the work has been done, it chose to
take the point that documentation may be inadequate.
[30] It has also raised doubts as to its bona fides in disputing the debts by taking a point - before proceedings were issued – that it was not the party that contracted with
Ocean King Enterprise Ltd. It contended that the correct debtor was another
company, Concast Construction Ltd. That was not pursued
at the hearing, but
its resort to deflecting the claim by suggesting that other associated companies
may be liable, is consistent
with it using delaying tactics.
[31] It is apparent that Concast West Ltd is tight-fisted and reluctant
to pay its bills as they fall due, but it has not satisfied
me under s 290(4)(a)
that there is any reasonable ground on which it can dispute that the work
charged for in the invoices of Ocean
King Enterprise Ltd was carried
out.
Counterclaim
[32] Concast West Ltd alleges that the work that Ocean King Enterprise Ltd carried out was defective: the piles on site were installed in the wrong places. I have excluded as hearsay plans intended to show that the piles were installed in places other than what was required in the building plans. At this stage, the matter is little more than assertion. Concast West Ltd did identify from the work sheets of Ocean King Enterprise Ltd that operators of Ocean King Enterprise Ltd did carry out drilling work. I refer in particular to work sheet records for the period 12 October
2015 to 15 October 2015. The evidence, at the highest, does no more than
show that Ocean King Enterprise Ltd did drilling work.
It does not show that
Ocean King Enterprise Ltd was responsible for choosing the sites for the piles.
That is normally a design
decision. Ocean King Enterprise Ltd has charged its
staff out at $35.00 per hour. That is an understandable charge-out rate for
a
machine operator, but it is not the kind of charge one would expect to see for
structural design work. It is general practice
that surveyors are engaged to
identify the sites for foundation works. It does not appear that Ocean King
Enterprise Ltd was required,
as part of its contract, to identify the sites for
piles. I would have expected evidence from those who were on site at the time
that the piles were drilled to explain how piles were drilled in places now
contended to be wrong.
[33] I bear in mind that in terms of the Court of Appeal’s decision
in Covington
Railways5 that there must be clear,
persuasive grounds. At this stage the
5 Covington Railways Ltd v Uni-Accommodation Ltd, above n 3.
counterclaim allegations are little more than assertions. I accept the point made by Ocean King Enterprise Ltd, relying on Clemence Drilling Contractors Ltd v Anglo Pacific International (1998) Ltd6 that mere association with something that has gone wrong is not by itself enough to create grounds for a counterclaim. I would expect the evidence to be more persuasive than that presented here for Concast West Ltd to show that it has anything by way of a set off or grounds for abating the price to be paid. I am satisfied that there is not any proper ground for disputing the liability of
$79,301.65.
Adequacy of statutory demand
[34] At the outset of the hearing I raised with counsel for the
respondent the adequacy of the statutory demand. I was
concerned that
that demand did not adequately set out for Concast West Ltd how the alleged
debt was made up. It is apparent
from the first affidavit in support of the
application that Concast West Ltd appreciated that the claim made against it was
for work
carried out at 178 McLeod Road, Te Atatu. After all, it exhibited
invoices totalling $101,875.77 for work carried out from
September 2015
onwards. Nevertheless, I consider that there has been some embarrassment to
Concast West Ltd in the debt not being
adequately identified. To a certain
extent, that has been remedied during the proceeding by Ocean King Enterprise
Ltd putting in
evidence all its invoices with its supporting documentation.
Only then did it become clear that there was an adequate basis for
the charges
made.
[35] I accept also that the statements in the invoices attached to the applicant’s first affidavit that there were not enough supporting documents indicates that it did receive some supporting documents. It therefore had some foreknowledge of the debt claimed against it. Where Concast West Ltd has not been adequately informed is that it did not appreciate that a claim was being made against it for interest and it did not know the amount of the debt collecting costs. Any prejudice to it from that
has been addressed by my disallowing those
claims.
[36] As to
any prejudice from not having the debt fully set out in the statutory demand,
that matter can be addressed by an adjustment
as to the normal award of costs
that would be made. In taking that approach I am applying s 290(5) of the
Companies Act:
A demand must not be set aside by reason only of a defect or irregularity
unless the court considers that substantial injustice would
be caused if it were
not set aside.
Outcome
[37] The irregularities in the statutory demand can be addressed by
reducing the amount claimed under the statutory demand to
the sum of $79,301.65.
With that adjustment, I set aside the statutory demand except for the sum of
$79,301.65.
[38] I make an order under s 291 of the Companies Act that Concast West
Ltd is to pay to Ocean King Enterprise Ltd the sum of
$79,301.65. If payment is
not made by the end of 22 August 2016, Ocean King Enterprise Ltd may begin an
application for the liquidation
of Concast West Ltd.
Costs
[39] Ms Tabb suggested costs on a 1A basis. That is a reduction from
normal 2B costs. That reduction is made on account of the
clumsiness in the
statutory demand. Ms Lim accepted that that would be appropriate. I order costs
accordingly. If there is any
dispute as to quantum that can be referred to
me.
[40] I record that the hearing took one day.
.......................................
Associate Judge R M Bell
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/1839.html