Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 9 September 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-000219 [2016] NZHC 2011
UNDER
|
the Arbitration Act 1996
|
BETWEEN
|
CUSTOM STREET HOTEL LIMITED Plaintiff
|
AND
|
PLUS CONSTRUCTION NZ LIMITED First Defendant
PLUS CONSTRUCTION CO LIMITED Second Defendant
|
Hearing:
|
3 August 2016
|
Appearances:
|
R B Stewart QC, I Rosic and S McMullan for Plaintiff
A Barker for Defendants
|
Judgment:
|
29 August 2016
|
JUDGMENT OF GILBERT J
This judgment is delivered by me on 29 August 2016 at 11.30 am pursuant to r 11.5 of the High Court Rules.
..................................................... Registrar / Deputy Registrar
Counsel/Solicitors:
R B Stewart QC, Auckland
Gilbert Walker, Auckland
Andrew Barker, Barrister, Auckland
CUSTOM STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD [2016] NZHC 2011 [29 August 2016]
Contents
Introduction
..........................................................................................................[1]
Background
...........................................................................................................[2]
Questions of
law..................................................................................................[19]
Question 1 – Did the arbitrator err in holding that Plus’s
breach must be repudiatory in nature before Plus would be
disentitled from terminating?
.......................................................................[20]
Question 2 – Did the arbitrator correctly construe clause 14.3.3 of the contract and err in holding that the defendants terminated
in accordance with clause 14.3.3?
................................................................[28]
Question 3 – Did the arbitrator correctly construe clause 14.2.4 of the contract and err in holding that the difference, between a certified cost to complete the contract works and the cost to Custom Street had the contract works been completed by Plus, could not be “properly due under the contract” until the contract
works have been
completed?........................................................................[40]
Question 4 – Did the arbitrator err in holding that the damages claimed by Custom Street for breach of contract cannot be “properly due under the contract” until Custom Street’s claim
is admitted or determined as to liability and quantum?
...............................[49]
Question 5 – Did the arbitrator err in holding that Custom Street cannot rely upon the amounts claimed under the indemnity clause
in the contract as amounts “properly due under the
contract”?....................[54]
Result
...................................................................................................................[61]
Introduction
[1] This is an appeal on questions of law arising out of an arbitral
award of
Hon. Rodney Hansen QC dated 17 November 2015.
Background
[2] The plaintiff, Custom Street Hotel Ltd (Custom Street), entered into
a construction contract dated 1 November 2013 with
the defendants, a
Korean company, Plus Construction Co. Ltd (Plus Korea) and Plus Construction NZ
Ltd (Plus NZ) (together, Plus)
for the re-development of the Reserve Bank
Building on Customs Street, Auckland into a 15 storey hotel. This contract
replaced an
earlier construction contract entered into in December 2012 between
Custom Street and Plus NZ.
[3] The contract price was $14.45 million plus GST subject to any variations or adjustments under the contract. The contract works were to be completed within
52 weeks.
[4] Plus as contractor and ANZ as surety provided a performance bond
for 25 per cent of the contract price, $3.6125 million,
in favour of Custom
Street as beneficiary. The expiry date of the bond was 31 March 2015. The bond
was payable:
Upon written demand by the beneficiary stating that the contractor has failed
to perform its obligations under the contract documents
and accompanied by a
certificate issued by the engineer in terms of clause 2, but otherwise
without proof or conditions.
[5] Clause 2 of the bond stipulates the requirements of the
engineer’s certificate:
2. The engineer’s certificate shall state, in the
engineer’s opinion:
(A) That the contractor has failed to perform its obligations under the
construction contract; and
(B) That the contractor has been given notice of the failure and has failed
to rectify that failure within the time set out in the
notice; and
(C) The amount claimed under the bond is properly due under the contract.
[6] Significant problems arose from the outset leading to
delays in the construction works. Plus ceased work on 23
July 2014 and has
not carried out any work on the site since. On 16 October 2014, Derek
Firth, a senior lawyer specialising
in construction disputes,
delivered an adjudication under the Construction Contracts Act 2002
finding that the original
contract programme had been disrupted, mainly because
of delays in obtaining the necessary consents. Nevertheless, Mr Firth found
that
there was a substantial amount of work that Plus could have completed but had
not. Mr Firth found that time for completion
of the contract works was at large
so that Plus was entitled to a reasonable time to complete them.
[7] The last of the consents required for the works was obtained in November 2014. The parties then engaged in discussions with a view to making a fresh start. A new programme of works was proposed and Plus engaged a new management team. Custom Street also sought a new bond because it was clear that the contract works would continue beyond the expiry of the existing bond on
31 March 2015. Prior to the conclusion of these discussions, Plus complained
about non-payment of invoices. At about this time,
Custom Street raised
concerns about health and safety issues posing significant risks to persons
working on or entering the site.
This led to the engineer suspending all works
on-site, except as necessary to address health and safety issues, on 5 February
2015.
[8] In the meantime, Plus served a default notice dated 27 January
2015 in respect of two unpaid amounts due under the contract
totalling
$258,507.62. This notice was given pursuant to cl 14.3 of the general
conditions of the contract (NZS 3910:2003).
Clause 14.3.3 provides:
If the Principal’s default is not remedied within 10 Working Days after
the giving of such notice ... the Contractor may require
the Engineer to suspend
the progress of the whole of the Contract Works under 6.7. Following such
suspension the Contractor shall
be entitled without prejudice to any other
rights and remedies to terminate the contract by giving notice in writing to the
Principal.
[9] Custom Street did not remedy the default within 10 working days of service of the notice. The 10 working day period expired at midnight on 11 February 2015. Prematurely, at 5.12 pm on 11 February 2015, Plus sent an email to the engineer
attaching a letter dated 12 February 2015 purporting to require him to
suspend the contract works in accordance with cl 14.3.3:
Please note that the period of 10 working days expired yesterday,
11 February 2015, and we have not received payment of either the balance of
Payment Schedule 10 or Payment Schedule 11. On that basis, we require you
to suspend the Contract Works in terms of clause 14.3.3
of the contract.
Can you please confirm as a matter of urgency.
[10] The engineer, who was in Shanghai at the time, was uncertain how to proceed because he had already suspended the works due to health and safety concerns. At
9.29 am on 12 February 2015, prior to receiving any formal response
from the engineer, Plus gave notice purporting
to terminate the
contract under cl 14.3.3. Custom Street paid the amounts outstanding under the
default notice later that day.
[11] On 20 February 2015, Custom Street issued a notice of default to
Plus under cl 14.2.1 of the contract claiming that it had
abandoned the contract
and persistently, flagrantly or wilfully neglected to carry out its obligations
under the contract. This
notice was based on a certificate issued by the
engineer the previous day under cl 14.2.1(c).
[12] Clause 14.2 of the contract deals with default by the contractor.
It relevantly provides:
14.2 Default by the Contractor
14.2.1 The Principal may at its option after giving notice to the
Contractor either terminate the contract or resume possession of the Site
in the
event of:
...
(c) The Engineer certifying in writing to the Principal that in his or
her opinion the Contractor has abandoned the contract
or is persistently,
flagrantly or wilfully neglecting to carry out its obligations under the
contract;
and the Contractor’s default has not been remedied within 10
Working Days of receiving the notice.
...
14.2.3 If the Principal elects to resume possession of the Site under the
provisions of 14.2.1... it may:
(a) Forthwith expel the Contractor without terminating the
contract or relieving the Contractor from any of its obligations
under the
contract; and
(b) Complete and remedy defects in any part of the Contract Works
remaining to be completed and for that purpose may let contracts
for such work
or employ any Persons other than the Contractor; and
(c) Take possession of, use and permit other Persons to use
Materials, Plant, Temporary Works and other things which
are on the Site owned
by the Contractor and are necessary for completing and remedying defects in
the Contract Works; and
(d) Require the Contractor to arrange within 10 Working Days the
assignment to the Principal or its nominee without payment
the benefit of any
agreement for the supply of Materials or execution of work under the
contract.
In any such case the Contractor shall not be entitled to any further payment
until the completion of the Contract Works.
14.2.4 On completion of the Contract Works, any Plant, Temporary
Works and surplus Materials of which the Principal has taken possession
shall be
handed back to the Contractor. The Engineer shall enquire into the cost to the
Principal of completing the Contract Works
and certify accordingly. Should the
amount certified exceed the Cost to the Principal had the Contract Works been
completed by the
Contractor, the difference between the two amounts shall be
certified by the Engineer and paid by the Contractor to the Principal.
Should
the amount certified be less than the cost to the Principal had the Contract
Works been completed by the Contractor, the
difference between the two amounts
shall be paid by the Principal to the Contractor.
14.2.5 If the Principal elects to terminate the contract under 14.2.1
it shall give written notice to the Contractor of its election. The
contract
shall thereupon be terminated. The Principal may thereupon expel the Contractor
from the Site and may take all or any of
the further steps in 14.2.3(b), (c) and
(d), and may claim damages for the Contractor’s breach of contract. If
the Principal
completes the Contract Works or arranges for them to be completed
then 14.2.4 shall apply, but any amount payable to the Contractor
thereunder
shall be subject to any damages to which the Principal shall be entitled as a
result of the Contractor’s breach...
[13] Plus took no steps under the contract following service of Custom Street’s notice on 20 February 2015, consistent with its position that it had already validly terminated it. Custom Street purported to terminate the contract on 11 March 2015, consistent with its position that Plus had not validly terminated the contract.
Custom Street then initiated the process required to enable it to
call on the performance bond.
[14] On 16 March 2015, Plus filed proceedings in this Court seeking an
interim injunction to restrain the engineer from issuing
the necessary
certificate and to restrain Custom Street from claiming under the bond. That
proceeding was settled on the basis
that the engineer would proceed to
consider whether to issue a certificate for the purposes of the bond. If
he did so,
Custom Street could make demand on the bond and the proceeds would be
paid into a solicitor’s trust account pending the arbitrator’s
determination of whether the engineer was entitled to issue the certificate and
whether Custom Street was entitled to make demand
on the bond.
[15] On 25 March 2015, the engineer certified that $24,948,392.35 was
properly due under both cl 14.2.5 and cl 7.1.1 of
the contract. This
was the projected additional cost of completing the contract works using
another contractor and was based
on an estimate that it would cost approximately
$42.6 million to complete the works.
[16] Clause 7.1.1 of the contract relevantly provides:
7.1 Indemnity
7.1.1 Except as otherwise provided in the Contract Documents the
Contractor shall indemnify the Principal against:
(a) Any loss suffered by the Principal which may arise out of, or in
consequence of the construction of, or remedying defects
in the Contract
Works.
[17] On 26 March 2015, the engineer issued a certificate under cl 2 of
the bond certifying as follows:
(A) That the contractor has failed to perform its obligations under
the construction contract, and
(B) That the contractor has been given notice of the failure and has failed to rectify that failure within the time set out in the notice, and
(C) The amount claimed under the bond is properly due under the contract. This amount claimed and certified under the bond is the full guarantee
amount being NZD 3,612,500.
[18] The arbitrator found that the engineer was not entitled to issue the
certificate for the purposes of the bond. In particular,
the arbitrator
found:
(a) The engineer was wrong to certify under cl 2(A) of the bond that
Plus had failed to perform its obligations under the contract.
This was
because Plus validly terminated the contract on 12 February 2015 and therefore
could not have been in default when the
engineer issued his certificate to this
effect one week later, on 19 February 2015.
(b) The engineer was also wrong to certify that the amount claimed as
damages of $24,948,392.35 was payable under either
cl 14.2.5 or cl 7.1.1
the contract. Any claim by Custom Street for additional costs of completing the
works is governed by cl
14.2.4 of the contract and can only be determined
after the works have been completed. Clause 7.1.1 does not apply. No
amount is currently properly due under the contract. Accordingly, the engineer
was wrong to certify under cl 2(C) that the full
amount of the bond was properly
due under the contract.
Questions of law
[19] Custom Street obtained leave to appeal against the award on the
following five questions of law:
(a) Did the arbitrator err in holding that the defendants’
breach must be repudiatory in nature before the defendants
would be
disentitled from terminating?
(b) Did the arbitrator correctly construe clause 14.3.3 of the
contract and err in holding that the defendants terminated in
accordance with
clause 14.3.3?
(c) Did the arbitrator correctly construe clause 14.2.4 of the
contract and err in holding that the difference, between
a certified
cost to complete the contract works and the cost to Custom Street had the
contract works been completed by Plus,
could not be “properly due under
the contract” until the contract works have been completed?
(d) Did the arbitrator err in holding that the damages claimed by Custom Street for breach of contract cannot be “properly due under the contract” until Custom Street’s claim is admitted or determined as to liability and quantum?
(e) Did the arbitrator err in holding that Custom Street cannot rely
upon the amounts claimed under the indemnity clause in
the contract as amounts
“properly due under the contract”.
Question 1 – Did the arbitrator err in holding that Plus’s breach must be
repudiatory in nature before Plus would be disentitled from
terminating?
[20] In its points of defence in the arbitration, Custom Street claimed
that Plus’s purported termination of the contract
on 12 February 2015 was
invalid because: Plus’s email attaching the 12 February 2015 request for
the engineer to suspend the
works was delivered prematurely, on 11 February
2015, and was therefore invalid; the engineer did not suspend the contract works
in response to the request; and a valid termination notice could only be given
following such a suspension.
[21] Custom Street did not plead that the termination notice was invalid
in any event on the basis that Plus was disentitled from
terminating because of
its own breaches of the contract. However, this was argued on its behalf in
closing submissions and dealt
with by the arbitrator in the following key
passages in his award:
40. [Custom Street] then argues that, leaving aside the issue
of compliance with clause 14.3.3, Plus was denied the
right to terminate by its
own breaches. Mr Stewart relied on the decision in Ingram v
Patcroft Properties Limited where the Supreme Court endorsed the principle
that a party seeking to cancel a contract must itself be willing and able to
perform
its obligations under the contract. The Court held that a lessor who
had unlawfully re-entered and excluded the lessee from premises
had repudiated
the lease and was thereby precluded from cancelling the lease for non-
payment of rent. The judgment makes it
clear however that the disentitling
conduct must be repudiatory in nature. The principle is concisely expressed by
Lord Finlay LC
in Morris v Baron and Co:
A party to a contract which imposes certain obligations and confers certain
rights upon him cannot claim to exercise these rights
while repudiating his
obligations in material particulars.
41. For [Custom Street] it is said that as at 12 February 2015 Plus was in serious dereliction of its obligations under the contract. Mr Stewart points to the fact that no work under the contract had been undertaken since July
2014; scaffolding had been removed in December 2014; and there had been persistent and serious breaches of health and safety requirements. He
submits that there was no justification for Plus ceasing work and failing to
resume.
...
43. In the circumstances, I consider it realistic to look afresh at the
conduct of the parties after the last of the adjudicator’s
decisions
issued in October 2014. It effectively required the parties to start again.
With time at large, the parties had to agree
a new programme and scope of works.
In November the last of the consents issued and the major impediment of which
Plus had complained
was finally cleared away. The parties then engaged in high
level discussions ... and talked about a fresh start. Plus employed
a new
management team. A new programme of works was proposed. While the dismantling
of the scaffolding was a matter of concern,
Plus was negotiating to employ a new
scaffolder and met with the Engineer for that purpose.
44. On my view of the evidence, the lack of action
on site notwithstanding, there was nothing to indicate
that Plus was not
committed to the Contract, albeit under a revised programme of works.
...
49. While [Custom Street’s] reservations about the ability of Plus to deliver were clearly justified and there were arguable grounds for the Engineer to certify that Plus was in default, I do not think that there is a sufficient basis for me to conclude that Plus had repudiated the contract or evinced an intention to do so. I consider the steps it had taken since October
2014 were sufficient to counter any suggestion that it was not prepared to meet its obligations. [Custom Street] certainly had reason to doubt whether
Plus had the resources, the expertise and the commitment to complete the works but objectively the facts do not establish that it had no serious
intention of doing so. In my view Plus is not prevented from relying on the
breach of [Custom Street] to terminate the contract.
50. I conclude that the Engineer was wrong to certify under clause 2(A)
of the Bond that Plus had failed to perform
its obligations under
the Contract. Plus validly terminated the Contract on 12 February 2015 and
could not have been in default.
(Footnotes omitted)
[22] Mr Stewart QC submits that the arbitrator erred in law in finding
that a party will only be disentitled from terminating
a contract if it is in
repudiatory breach of it at the time of the purported termination. He submits
that the correct position is
that a party must itself be ready and willing to
perform the substance of the contract at the time it purports to cancel. A
party
will not be considered to be ready and willing to perform its obligations
where its own breach of the contract is sufficiently serious
as to entitle the
other party to cancel the contract under s 7 of the Contractual Remedies Act
1979.
[23] In Ingram v Patcroft Properties the Supreme Court confirmed that the common law rule requiring that a cancelling party must be ready and willing to
perform the contract in all material respects was to ensure that it could not
benefit from its own wrong.1 The Court also endorsed the Court of
Appeal’s judgment in Noble Investments Ltd v Keenan that this
rule survived the passage of the Contractual Remedies Act but did not apply
where the cancelling party did not so
benefit.2 The Supreme Court
also agreed with the examples given by Glazebrook J, in giving the judgment of
the Court in Noble Investments, of circumstances in which a party would
be precluded from cancelling because this would enable it to benefit from its
own wrong:3
A party could be seen as benefiting from its own wrong if it seeks by
cancellation to deprive the other party of the benefit of the
contract in
circumstances where the other party’s breach is a direct result of breach
committed by the party seeking to cancel
the contract. ... A party could also
be seen as benefiting from its own wrong where it is unable or unwilling to
perform its obligations
under the contract and seeks to avoid liability for its
own breach by cancelling the contract on the basis of the other party’s
breach.
[24] More recently, in Kumar v Station Properties Ltd the Supreme
Court stated that a party who is in breach of an essential term of a contract is
not entitled to enforce its rights of
cancellation under the contract.4
Arnold J, who gave the reasons for judgment of the majority (Elias CJ,
McGrath, Glazebrook and Arnold JJ), said that “[T]his
is particularly so
where the obligations of the parties are mutually dependent and concurrent, as
in contracts for the sale of
land”.5
[25] It is clear that the circumstances in which a party may be
disentitled from cancelling a contract are not limited to those
where that party
has repudiated the contract; a breach of an essential term or other serious
breach entitling the other party to
cancel the contract under s 7 of the
Contractual Remedies Act could be sufficient. However, such breach will only
disentitle the
party from cancelling the contract where it would otherwise
benefit from its own wrong.
[26] Custom Street could only terminate under the terms of the contract
for the breaches it asserted if Plus failed to remedy
its default within 10
working days of
1 Ingram v Patcroft Properties [2011] NZSC 49; [2011] 3 NZLR 433 at [40].
2 Noble Investments Ltd v Keenan [2006] NZAR 594 (CA).
3 Noble Investments at [47].
4 Kumar v Station Properties Ltd [2015] NZSC 34; [2016] 1 NZLR 99 at [94].
5 Ibid.
receiving notice of the engineer’s certificate that Plus had abandoned
the contract or was persistently, flagrantly or wilfully
neglecting to carry out
its obligations under the contract. The engineer did not issue this certificate
until 19 February 2015,
after Plus’s notice purporting to terminate the
contract. Prior to the expiry of the notice based on the engineer’s
19
February 2015 certificate, time for performance by Plus was at large. It
follows that the alleged breaches by Plus could only
justify cancellation prior
to the expiry of the 10 working day notice period if they amounted to a
repudiation of the contract by
Plus. The arbitrator was therefore correct to
confine his attention in this case to whether or not Plus had repudiated the
contract
and was disentitled to terminate it in consequence. The arbitrator
found as a fact that Plus did not repudiate the contract and
remained ready and
willing to perform it.
[27] The answer to question 1 is “no” based on the facts
found by the arbitrator.
Question 2 – Did the arbitrator correctly construe clause 14.3.3 of
the contract and err in holding that the defendants
terminated in
accordance with clause 14.3.3?
[28] It is helpful to set out cl 14.3.3 again because this question turns
on its proper interpretation:
14.3.3 If the Principal’s default is not remedied within 10 Working
Days after the giving of such notice under 14.3.1 or 14.3.2
the Contractor may
require the Engineer to suspend the progress of the whole of the Contract Works
under 6.7. Following such suspension
the Contractor shall be entitled without
prejudice to any other rights and remedies to terminate the contract by giving
notice in
writing to the Principal.
[29] Mr Stewart submits that Plus’s right to terminate the contract under cl 14.3.3 can only be exercised after the engineer has suspended the progress of the whole of the contract works under cl 6.7 in accordance with a requirement made by Plus under the clause. He submits that the words “Following such suspension” in the second sentence of the clause would serve no purpose if the contractor was entitled to terminate immediately upon communicating to the engineer that it requires him to suspend the works. He relies on Brown & Doherty Ltd v Whangarei County Council in support of his contention that termination provisions in construction contracts
must be strictly interpreted because of the “drastic and far-reaching
consequences”
that may flow to the principal from a contractor’s decision to
cancel.6
[30] The arbitrator observed that if there is an unremedied default by
the principal following expiry of a notice requiring the
default to be remedied
within 10 working days, the contractor is entitled to “require” the
engineer to suspend the whole
of the contract works. The engineer is then
obliged to give effect to the requirement. The arbitrator found that a failure
by the
engineer to take this purely formal step could not prevent the contractor
from exercising its substantive rights to terminate under
cl 14.3.3:
37. The suspension of the Contract Works had become necessary as a
consequence of the Principal’s default and the Contractor’s
request.
The Engineer was then obliged to give effect to the request by giving
the necessary instruction to the Contractor.
Such an instruction can be seen as
little more than a formality. In my view it could not have been intended that
the refusal or
failure of the Engineer to take the purely formal step of issuing
an instruction to suspend would deny the Contractor its substantive
rights to
terminate under clause 14.3.3. Having required the Engineer to suspend, I
consider Plus was entitled to give notice of
termination notwithstanding the
Engineer’s failure to give the requisite notice of suspension.
[31] I agree with Mr Stewart that if the contract excluded the
contractor’s right of termination until the engineer suspended
the
contract works in accordance with a validly made request under cl 14.3.3, then
this requirement could not be ignored or dismissed
as a mere formality. In this
case, it is arguable that the contractor did not make a valid request for
suspension because it was
made prematurely. In any event, it is clear that the
engineer did not suspend the works in response to any such request. Therefore,
if suspension is a necessary precondition to termination, Plus did not validly
terminate the contract. However, for the reasons
that follow, I have come to
the conclusion that this is not the proper interpretation of cl 14.3.3. In my
view, this clause does
not exclude cancellation rights under s 7 of
the Contractual Remedies Act 1979.
[32] NZS 3910:2003 was first published on 11 August 2003. At that time, s 72 of the Construction Contracts Act 2002, which came into force on 1 April 2003,
provided that a party who carries out construction work under a
construction contract
6 Brown & Doherty Ltd v Whangarei County Council [1988] 1 NZLR 33 (HC) at 36.
has the right to suspend work under that contract in various circumstances,
including where a claimed amount is not paid in full by
the due date and no
payment schedule has been provided by the party claimed to be liable for the
payment. This provision was repealed
on 1 December 2015 and is now replaced by
s 24A of the same Act.
[33] Section 72 of the Act also provided that if the contractor exercised
its right of suspension, that would not prejudice its
right to exercise any
remedies otherwise available to it under the Contractual Remedies Act. This
meant that the contractor could
suspend without losing any right available under
that Act, including the right to cancel.
[34] Clause 14.3.3 modifies the contractor’s statutory right
of suspension following non-payment, deferring the
right until a 10 working day
notice has expired unremedied. The process to be followed in suspending the
works is also different
in that the contractor must require the engineer to
suspend the progress of the whole of the contract works under cl 6.7. However,
consistent with the position under the Act, if the contractor chooses to take
the step of suspending the works under the contract,
this will not amount to an
affirmation precluding cancellation in reliance on the same breach. This is
made clear by the words “Following
such suspension the contractor shall be
entitled ... to terminate the contract”.
[35] While cl 14.3.3 modifies rights that the contractor would otherwise have under the Construction Contracts Act, it does not purport to limit the contractor’s rights under the Contractual Remedies Act, including the right to cancel for breach of an essential term or for a repudiatory breach. Section 5 of the Contractual Remedies Act does not apply:
5. Remedy provided in contract
If a contract expressly provides for a remedy in respect of misrepresentation or repudiation or breach of contract or makes express provision for any of the other matters to which sections 6 to
10 relate, those sections shall have effect subject to that
provision.
[36] As Cooke P observed in MacIndoe v Mainzeal Group Ltd in the context of a standard form agreement for sale and purchase of real estate, the existence of
remedies in a clause such as this can stand alongside ordinary remedies under s 7 of the Contractual Remedies Act:7
Clause 8 gives various remedies, including the 12 working-day notice after
settlement date, which when available will avoid any question
as to whether
notice has been reasonable; but the existence of these remedies can stand
together with the availability also of the
ordinary remedies of a vendor (or a
purchaser) under s 7 of the Contractual Remedies Act. The cl 8 remedies are
additional. There
is nothing in the clause inconsistent with s 7, so s 5 does
not have the effect of making that clause exclude s 7.
[37] Under NZS 3910:2003, if the principal fails to remedy its breach
prior to the expiry of a 10 working day notice, this would
be a breach of an
essential term that would normally entitle the contractor to cancel the contract
under the Contractual Remedies
Act. Indeed, the contractor would normally be
put to an election as to whether to cancel the contract in reliance on that
breach.
If it did not do so, then, in the absence of any provision to the
contrary, it would be precluded from later cancelling the
contract for that
breach because of s 7(5) of the Contractual Remedies Act:
(5) A party shall not be entitled to cancel the contract if,
with full knowledge of the repudiation or misrepresentation
or breach, he has
affirmed the contract.
[38] If the contractor, faced with such a breach, does not wish to pursue the middle ground option of suspension provided under the contract, it would be odd if it could not instead elect to terminate the contract immediately. No useful purpose would be served by requiring the contractor to arrange for the engineer to suspend the works, even if only momentarily, before it could take the next step of cancelling the contract and, in my view, the contract does not require this. I do not consider that cl 14.3.3 excludes an innocent contractor’s right under s 7 of the Contractual Remedies Act to cancel the agreement in the event of the principal breaching an essential term. Clause 14.3.3 merely deals with the manner of exercise of the right of suspension and the consequences of exercising that right. In particular, it makes clear that the contractor retains its right of termination for the breach even if it affirms the contract by exercising its right under the contract to require the works to be suspended. There is nothing in cl 14.3.3 inconsistent with s 7 and those rights are
accordingly not excluded.
7 MacIndoe v Mainzeal Group Ltd [1991] 3 NZLR 273(CA) at 281.
[39] Although I arrive at the same result by a different route, I agree
with the arbitrator that Plus was entitled to
terminate the
contract as a result of Custom Street’s failure to make payment
within the 10 working day period.
The answer to question 2 is
“no”, the arbitrator did not err.
Question 3 – Did the arbitrator correctly construe clause 14.2.4 of
the contract and err in holding that the difference, between
a certified cost to
complete the contract works and the cost to Custom Street had the contract works
been completed by Plus, could
not be “properly due under the
contract” until the contract works have been completed?
[40] In its points of defence in the arbitration, Custom Street claimed
that it had a contractual right to damages under cl 14.2.5
and there was no
requirement in that clause for alternative performance of the contract to be
completed before pursuing such a claim.
[41] The arbitrator rejected that contention and held that any claim for
damages based on the additional cost of completing
the contract works
is governed by cl 14.2.4 and that the quantum of such a claim cannot be
determined until the contract
works have been completed.
[42] Ms Rosic, who presented this part of Custom Street’s argument, acknowledges that cl 14.2.4 applies where the principal terminates the contract and arranges for the contract works to be completed or completes the contract works. Clause 14.2.5 says so expressly. However, she argues that the principal is entitled to the additional cost of completion as soon as it arranges (organises or plans) for the contract works to be completed. She contends that there is nothing in the wording of cls 14.2.4 or 14.2.5 which confines the principal’s entitlement to the additional cost of completion until after the works have been completed. Ms Rosic submits that the opening words of cl 14.2.4 “On completion of the Contract Works” relate solely to the principal’s obligation to return plant, temporary works and surplus materials to the contractor. She argues that the remainder of the clause addresses the separate and unrelated issue of the additional cost of completion and that this is not subject to the same temporal restriction.
[43] Ms Rosic submits that the use of the word “enquire” in
cl 14.2.4 suggests that the engineer is required to make
an assessment of the
costs to complete. She argues that this supports her contention that the
exercise can be undertaken before
the actual costs of completion are known.
She contends that this interpretation is also supported by the use of the
words
“completing” (as opposed to “completed”) and
“cost” which is defined to include prospective costs,
not just those
that have actually been incurred. Ms Rosic submits that the principal has the
right to choose whether to claim under
cls 14.2.4 and 14.2.5 for damages
calculated on the basis of an assessment of the likely cost of completing the
works or wait until
the works have been completed and formulate its claim on the
basis of the actual costs. Ms Rosic contends that this interpretation
is
supported by commercial commonsense; the principal should not have to fund the
project through to completion and only then be
able to recover the additional
cost from the defaulting contractor.
[44] Clause 14.2.1 confers two broad options on the principal if the
contractor fails to remedy its default within 10 working
days of service of the
requisite notice, terminate the contract or resume possession of the site.
Clauses 14.2.3 and 14.2.4 apply
where the principal elects to resume possession
of the site. Clause 14.2.5 applies where the principal elects to terminate the
contract.
[45] Clause 14.2.3 provides that the contractor is not entitled
to any further payment until completion of the contract
works. It also
entitles the principal to expel the contractor from the site without
terminating the contract or relieving
the contractor from any of its
obligations under it (subclause (a)). The principal may complete the contract
works (subclause (b)),
take possession of and use materials, plant and temporary
works owned by the contractor for the purpose of completing the works (subclause
(c)) and require assignment of agreements for the supply of materials or
execution of work under the contract (subclause (d)).
[46] Clause 14.2.4 provides that upon completion of the contract works, any plant, temporary works and surplus materials are to be handed back to the contractor. The engineer is to enquire into the cost to the principal of completing the contract works and certify accordingly. If the amount is greater than the cost would have been had the contractor completed the works, this amount shall be paid by the contractor to the
principal. If the amount certified is less, the difference shall be paid by
the principal to the contractor. Because cl 14.2.3 suspends
the
contractor’s right to receive any further payment until the contract works
have been completed, it is clear that the engineer’s
enquiry and the
payment adjustment directed by cl 14.2.4 is to occur after the works have been
completed. In my view, the temporal
restriction “following completion of
the contract works” applies to all aspects of cl 14.2.4.
[47] As noted, cl 14.2.5 applies where the principal elects to terminate
the contract rather than resume possession of the site.
In that case, the
principal is also entitled to expel the contractor from the site and take all or
any of the steps referred to
in cl 14.2.3 (b) to (d). It may also claim
damages for the contractor’s breach of contract. However, if the
principal completes the contract works itself (under cl 14.2.3(b)) or
arranges for the works to be completed by someone
else, then cl 14.2.4
applies. The same exercise is undertaken but any payment that would otherwise
be due to the contractor on
completion of the contract works shall be subject
to any damages to which the principal is entitled as a result of
the contractor’s breach, including any liquidated damages for late
completion.
[48] I respectfully agree with the arbitrator’s interpretation of cl 14.2.4. Where the principal elects to complete the contract works or arrange for another to do so, a wash-up based on the engineer’s enquiry and certification is to occur once the contract works have been completed, taking into account the actual costs. Clause 14.2.4 does not allow for the contractor to claim damages based on an assessment of the projected costs to complete the contract works. It anticipates an enquiry into the actual costs of completing the contract works to determine whether payment is due by the principal to the contractor or vice versa. The contractor is not entitled to any further payment until after the contract works have been completed (cl 14.2.3) and it is therefore clear that this exercise can only be undertaken after that time. The answer to question 3 is “no”, the arbitrator did not err.
Question 4 – Did the arbitrator err in holding that the damages
claimed by Custom Street for breach of contract cannot be “properly
due
under the contract” until Custom Street’s claim is admitted or
determined as to liability and quantum?
[49] The arbitrator found that any claim for the additional cost of
alternative performance must be brought under cl 14.2.4 and
can only be assessed
after the contract works have been completed. Further, even if a
claim for damages is available
based on a forecast of the likely increased
costs of completing the works, such damages would not be “properly
due” until
either the contractor admits the claim or it is determined by
adjudication.
[50] Ms Rosic submits that the amount assessed by the engineer,
purportedly in terms of cl 14.2.4, as the projected additional
cost of
completing the contract works, is an amount “properly due under the
contract” for the purposes of cl 2(C) of
the bond. She argues that the
arbitrator’s finding to the contrary leads to an uncommercial result and
would substantially
defeat the purpose of the bond. This is because, by the
time any such claim could be determined by adjudication, the bond would
have
long since expired. She submits that the parties cannot have intended such a
result. Ms Rosic also notes that cl 14.2.4 creates
a payment obligation upon
certification.
[51] However, this submission begs the question as to when certification
can be made under the clause. For the reasons given
in answer to question 3,
the engineer’s enquiry and certification under cl 14.2.4 can only occur
after the contract works have
been completed.
[52] The question as to whether an amount is “properly due” under the contract is not informed by considering the terms of the bond. Other types of claim against the contractor under the contract could lead to amounts becoming properly due under the contract triggering a potential claim under the bond. The fact that a claim for the additional cost of completing the contract works under cl 14.2.4 may not be determined until after the expiry of the bond, thereby potentially limiting the value of the security it provides, cannot have any bearing on the proper interpretation of the construction contract.
[53] I respectfully agree with the arbitrator’s analysis and
conclusion on this issue. The answer to question 4 is “no”,
the
arbitrator did not err.
Question 5 – Did the arbitrator err in holding that Custom Street
cannot rely upon the amounts claimed under the indemnity
clause in the
contract as amounts “properly due under the
contract”?
[54] The arbitrator found that the indemnity in cl 7.1.1 could not be relied on by Custom Street to circumvent the process agreed under cl 14.2.4 and convert a damages claim for the forecast additional cost of completion into an amount properly due under the contract. The arbitrator contrasted the wording of cl 7.1.1 with the indemnity considered by the Victorian Court of Appeal in Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd upon which Custom Street placed considerable
reliance:8
[103] The wording of clause 7.1.1 is materially different from the indemnity clause in Sugar Australia. First, the introductory words of limitation “Except as otherwise provided...” appear to exclude rights of recovery that otherwise arise under the Contract. Second, the terms of the indemnity itself are directed to losses and liability of a consequential nature
– those “arising out of” or “the consequence of” construction works or of
remedial works and of injuries to person or damage to property sustained in the course of carrying out such works. The language is apt to cover claims by and liability to third parties as distinct from losses directly incurred for which the Contract provides a direct right of recovery. It is much more targeted in its terms than the indemnity in Sugar Australia. Third, clause
7.1.1 refers to “losses suffered”. That conforms to the essential character of an indemnity which is to make good losses that have actually occurred. Here, there is an expectation of loss, but none will be incurred until alternative performance takes place.
[104] Finally, as Mr Barker submitted, if clause 7.1.1 were to
be interpreted as conferring an all-embracing right to
recover in respect of
every loss or liability incurred there would be no need to resort to the
tailored remedies provided under the
Contract. It would render otiose much of
the Contract. In the event of breach the Principal could simply side-step the
dispute
resolution procedures and claim a right to indemnity. It seems much
more likely that clause 7.1.1 was intended to provide a distinct
right of
recovery for a category of loss or liability that is not sufficiently provided
for elsewhere in the Contract.
[105] In my view clause 7.1.1 cannot be invoked to establish a right to
recover the losses claimed by [Custom Street] but even
if it could, until such
time as the relevant losses have been sustained, it would not give rise to an
amount properly due under the
Contract in terms of clause 2(C) of the
Bond.
8 Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98.
[55] Mr Stewart submits that the arbitrator’s reasoning is
flawed and his conclusion is an error. He submits
that Custom Street’s
loss, being the additional cost of completion, became properly due under the
indemnity “as soon
as Plus defaulted in terms of cl 14.2.1(c), leading
Custom Street to assume liability for completion of the project and any costs
associated with it”.
[56] I cannot accept this submission. A default under cl 14.2.1(c),
where the engineer certifies that in his opinion the contractor
has abandoned
the contract or is persistently, flagrantly or wilfully neglecting to carry out
its obligations under the contract,
cannot immediately give rise to a liability
by the contractor for any additional costs of completion. At that point, the
contract
remains on foot and there cannot be any additional costs of completion
by alternative means. The liability for such additional
costs cannot arise,
“as soon as Plus defaulted in terms of cl 14.2.1(c)”. The
prospect of additional costs
of completion does not arise until expiry of a
10 working day notice without the default being remedied and Custom
Street
then electing to terminate the contract.
[57] The engineer did not issue his certificate under cl 14.2.1(c) until
19 February
2015. The arbitrator found that Plus had validly terminated the contract
for non- payment, on 12 February 2015. Plus was therefore
relieved of its
obligation to perform the contract at that time. However, even if Plus’s
termination was invalid and the contract
was instead terminated by Custom Street
on 11 March 2015, that did not give rise to Custom Street incurring a
“liability for
completion of the project and any costs associated with
it” as contended by Mr Stewart. Following termination, Custom Street
was
relieved of its obligations under the contract. It had no obligation to
complete the works and therefore had no “liability”
for any
associated costs. However, if it chose to complete the works, it had a right to
claim any additional costs under cl 14.2.4.
[58] Mr Stewart submits that cl 7.1.1 is a broad indemnity and applies except where the contract makes specific provision for some other form of indemnity. He referred to the other indemnity provisions in the contract: cl 5.12, which provides that the contractor shall indemnify the principal for any infringement of patents, registered designs, trademarks or copyright and royalties; cl 7.1.3, requiring the
principal to indemnify the contractor for various matters including
interference with the rights of third parties as the unavoidable
result of
carrying out the contract works; and cl 4.2.3, which requires subcontracts to
include provisions requiring the subcontractor
to indemnify the contractor for
various liabilities, including those for which the contractor has indemnified
the principal.
[59] While the indemnity can be read in this way, the critical issue is
what it covers. Custom Street relies on subclause (a)
which refers to
“Any loss suffered by the Principal which may arise out of, or in
consequence of the construction of, or remedying
of defects in the Contract
Works”. This refers to the contractor’s work in carrying out the
construction of the contract
works or remedying defects in them. Self-evidently,
the clause cannot cover losses arising out the construction of the contract
works
by a replacement contractor or remedying defects caused by such a
contractor. Further, any additional costs of completing
the works
using an alternative contractor do not come within this indemnity provision.
Such costs do not arise out of either
the construction of the contract works or
the remedying of defects in those works; rather, they arise out of the failure
to carry
out such works.
[60] The answer to question 5 is “no”, the arbitrator did not
err. I respectfully agree with him that the damages
Custom Street seeks to
claim for the additional costs of completion must be determined under cl 14.2.4
and are not covered by the
indemnity.
Result
[61] The appeal is dismissed.
[62] The defendants are entitled to costs on a 2B
basis.
M A Gilbert J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/2011.html