Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 8 March 2016
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV-2015-485-457 [2016] NZHC 211
UNDER
|
the Judicature Amendment Act 1972 and
the Construction Contracts Act 2002
|
IN THE MATTER OF
|
an adjudication held pursuant to Part 3
Construction Contracts Act 2002
|
BETWEEN
|
MANCHESTER INDUSTRIAL HOLDINGS LIMITED Applicant
|
AND
|
ANDREW G HAZELTON First Respondent
BUSSELL CONSTRUCTION LIMITED Second Respondent
|
Hearing:
|
26 January 2016
|
Counsel:
|
J R Grace for applicant
No appearance for first respondent (abiding the decision) F B Collins for
second respondent
|
Judgment:
|
18 February 2016
|
RESERVED JUDGMENT OF DOBSON J
[1] This proceeding comprises an application for judicial review alleging errors of law by an adjudicator in a determination under the Construction Contracts Act
2002 (CCA). The applicant (MIH) owns a block of residential flats in Eva Street, central Wellington, including a penthouse on the top floor of the building. MIH concluded an oral contract with the respondent (Bussell) to do building work on the property. The work could be characterised as either part of earthquake strengthening work being undertaken by engineers at the property, or otherwise renovations being
undertaken contemporaneously with earthquake strengthening
work.
MANCHESTER INDUSTRIAL HOLDINGS LTD v ANDREW G HAZELTON [2016] NZHC 211 [18 February
2016]
[2] The contract was not for a fixed price, but rather Bussell was to
charge for the time its workers spent working at the premises,
plus charges for
the materials used. Invoices were to be presented on a monthly
basis.
[3] Bussell undertook physical works between late 2012 and early 2013
and MIH paid the first five claims up to February
2013 for a total
of some $103,000. Questions were raised on behalf of MIH and by its architect
about the content of Bussell’s
invoices after the first five payments.
Those questions were not resolved and on 1 April 2013 Bussell issued a further
payment claim
for $27,499.05. MIH questioned the payment claim and its concerns
remained unresolved.
[4] On 6 April 2013, MIH terminated its contract with Bussell and
engaged an alternative builder to complete the works contemplated
by the
original contract with Bussell.
[5] On 13 April 2013, Bussell issued another payment claim for
a further
$16,942.64. The following day, 14 April 2013, MIH emailed Bussell, disputing both of the April payment claims. That email stated that Bussell’s work had been defective and asked for particulars of the charges. Further information was sought including details of the areas of work to which the various components of the charges related. There was no timely response. However, some 15 months later on
31 July 2014, Bussell issued a payment claim for $40,648.15 plus GST. It described the claim as relating to work on the Eva Street project for the period from
26 November 2012 to 5 April 2013.
[6] The following day, MIH emailed back to Bussell in the following
terms:
Dear Geoff
Your claim for payment is not accepted
As previously discussed this account is disputed
The matters raised in our correspondence to you last year have not been
addressed
The claim under the contracts act is not accepted
The payment schedule is zero
|
We believe your claim to be faulty as it was last year and that nothing
has
changed with you submitting this new “bill”
|
|
The onus is still on you to address the issues raised-you have not done
this
|
|
|
There are a number of outstanding matters we would raise with you if you
want to pursue this
|
|
|
Firstly we have a clearly documented repair schedule of work your company
completed that was not to standard or to the plans for the
work at Eva St, that
had to be rebuilt
|
|
|
The list goes on
|
|
|
Do we want to explore your own performance and the problems we had with
your absence from site, the consumption of alcohol during
work hours etc
etc
|
|
|
We have these clearly documented
|
|
|
Geoff we have not heard from you for over a year
|
|
|
We had thought this matter settled ...
|
|
|
[7]
|
Three months later, on 30 October 2014, Bussell served a
notice
|
of
|
adjudication of claim under the CCA on MIH. It sought determination of
liability on the basis of MIH’s failure to pay the payment
claim. The
matter proceeded to a determination on the papers and on 19 December 2014 the
adjudicator, Andrew Hazelton, determined
that Bussell had presented valid
payment claims but that the response for MIH did not constitute a payment
schedule so as to relieve
it of the statutory obligation under the CCA to pay
the amount of the payment claim. I will return to the reasons for the
determination
in analysing the criticisms of it advanced in this
proceeding.
[8] Each party had very different perceptions of the merits of their
position, which coloured the arguments they advanced.
For MIH, Mr Grace
emphasised that:
• the standards of work were deficient;
• there had been workers standing around under-utilised;
and
• there had been the drinking of alcohol on the site.
[9] When those complaints were raised, MIH requested further detail
of the hours worked and the materials charged for,
that had not been addressed
in any timely fashion. From MIH’s perspective, there had been a
significant lapse between the
challenges raised in April 2013 and the present
payment claims being made in July and August 2014, without Bussell making any
attempt
to deny the criticisms that MIH had advanced. The perceived lack of
merit in Bussell’s position was compounded by MIH’s
concern that it
would be pointless to pursue a counterclaim for overcharging and defective
workmanship because, MIH contends, Bussell
is now insolvent.
[10] The on-going solvency of Bussell has been addressed provisionally in related proceedings. Once the adjudicator’s determination was issued, Bussell sought to enforce payment by commencing liquidation proceedings against MIH. In April
2015, Associate Judge Smith issued a judgment restraining advertising of
those proceedings and staying them pending resolution
of the present
proceeding.1 The Associate Judge found that it was unlikely
Bussell would be able to refund the figure of some $49,000 payable under the
adjudicator’s
determination if it had to do so.2
[11] From Bussell’s perspective, it has legitimately invoked procedures under the CCA designed to protect contractors, has complied with the requirements to enforce a payment claim and it is not prevented from doing so because MIH failed to serve it with a payment schedule that would have relieved MIH of the obligation to make prompt payment. Its case is squarely within the “pay now, argue later” policy of the
CCA, and neither the lapse in time between the end of its work on the
contract and
1 Bussell Construction Ltd v Manchester Industrial Holdings Ltd [2015] NZHC 858.
2 At [62].
the presentation of its payment claims, nor the prospect of its current
insolvency
(which was not accepted) can operate to qualify its right to
payment.
[12] MIH has lodged the amount of the adjudicator’s determination
in favour of
Bussell with an independent stakeholder, pending resolution of this
proceeding.
[13] In response to MIH’s frustration at not being able to pursue
its own claims against Bussell, Mr Collins for Bussell
submitted that there were
other avenues for MIH to pursue its claim that could have enabled consideration
of the substantive claims
on both sides at the same time. This could either
have occurred by MIH commencing its own adjudication under the CCA
and moving for their consolidation, or promptly pursuing an independent
claim against Bussell and applying for stay of the
effect of an adjudication
pending its determination. On Mr Collins’ view of the dispute, MIH had
done none of these things
and instead had simply resisted payment,
inconsistently with the “pay now, argue later” policy of the
CCA.
[14] That characterisation of the relevant parts of the CCA is now well settled. It reflects the vital importance for contractors of maintaining cash flow if construction businesses are to survive. The CCA has created a procedure that is intended to protect contractors’ cash flow, and limits an employer’s opportunities for lawfully resisting payment, which depends on adherence to the response required of an employer by the CCA. As Asher J put it in Marsden Villas Ltd v Wooding
Construction Ltd:3
[17] The Act therefore has a focus on a payment procedure, the results
that arise from the observance or non-observance of those
procedures, and the
quick resolution of disputes. The processes that it sets up are designed to
side-step immediate engagement on
the substantive issues such as set-off for
poor workmanship which were in the past so often used as tools for unscrupulous
principals
and head contractors to delay payments. As far as the principal is
concerned, the regime set up is “sudden death”.
Should the
principal not follow the correct procedure, it can be obliged to pay in the
interim what is claimed, whatever the merits.
In that way if a principal does
not act in accordance with the quick procedures of the Act, that
principal,
3 Marsden Villas Ltd v Wooding Construction Ltd [2006] NZHC 569; [2007] 1 NZLR 807 (HC); endorsed by the Court of Appeal in SOL Trustees Ltd v Giles Civil Ltd [2014] NZCA 539, [2015] 2 NZLR 482 at [25].
rather than the contractor and sub-contractors, will have to bear
the consequences of delay in terms of cashflow.
[15] Accordingly, the part of the dispute that was before the adjudicator
was not about the merits of the parties’ competing
positions. Rather, the
issue was whether the steps taken by either or both parties were sufficient to
bring themselves within the
process in the CCA, which entitles a contractor to
demand to be paid forthwith despite the prospect of the payer having a separate
claim that would then need to be pursued later. The adjudicator was confined
to determining whether the payment claim submitted
for Bussell in July 2014
qualified as such under s 20 of the CCA and, if so, whether the response for MIH
qualified as a payment
schedule for the purposes of s 21 of the CCA so as to
relieve it of the obligation to pay the amount demanded in the payment
claim.
Did Bussell submit a payment claim?
[16] The requirements for a valid payment claim are set out in s 20 of
the CCA in the following terms:
20 Payment claims
(2) A payment claim must—
(a) be in writing; and
(b) contain sufficient details to identify the construction contract to which
the payment relates; and
(c) identify the construction work and the relevant period to which the
payment relates; and
(d) state a claimed amount and the due date for payment; and
(e) indicate the manner in which the payee calculated the claimed
amount; and
(f) state that it is made under this Act.
...
[17] There was no issue that Bussell’s payment claim was in writing. It purported to identify the construction contract as “... 3 Eva Street earthquake strengthening for Manchester Holdings Ltd”. That was held by the adjudicator to satisfy the requirement in s 20(2)(b) for sufficient details to identify the construction contract to
which the payments related. This was one of the respects in which Mr Grace
argued that the adjudicator erred. He argued that more
is required if one
correctly assessed the context of the requirements in s 20(2) and applied them
to the circumstances of the contract
in issue.
[18] Mr Grace repeated arguments that had been made by MIH’s
architect in the papers before the adjudicator, to the effect
that
Bussell’s work did not constitute earthquake strengthening, which rather
was undertaken by engineering companies, so that
arguably the work was
misdescribed in the payment claim.
[19] I agree with the adjudicator that any misdescription (Bussell
disputing that there was one) was immaterial in conveying the
identity of the
construction contract to which the payment claim related. There was only one
contract for Bussell’s work at
3 Eva Street, and no prospect of confusion
on MIH’s part as to which contract the claim related. Mr Grace
criticised a finding
by the adjudicator that MIH “... was fairly put on
notice as to what project the payment claim was seeking payment for”.
Mr
Grace argued that this either related to, or influenced, the adjudicator’s
analysis of the content of a payment claim as
required by s 20(2)(c), namely to
identify the construction work (arguably distinguishable from “the
project”) and the
relevant period to which the progress payment related.
The finding just quoted was followed immediately by:
The construction work is clearly identified by reference to the covering
letter and supporting information filed, as is the period
to which the claim
relates which is stated to be from 26 November 2012 to 5 April 2013.
This therefore satisfies [subs]
2(c).
[20] The adjudicator treated the payment claim as comprising a covering
letter specifying that it was a payment claim, which identified
the periods to
which the claim related, and the amount of the claim. It also described the
attachments, which were:
• a summary of the invoices previously presented and the payments
received
(leaving a net amount payable as the subject of the claim); and
• copies of the seven invoices for different periods detailing
hours by each of the
Bussell employees plus the materials used on the job.
Some of the invoices were headed “Level 1 earthquake
strengthening” and some
“Eva Street renovation”.
[21] The details conveyed in all of these documents do identify the
construction work involved, relative to the oral contract
for Bussell to do
building work at the Eva Street property. I can see no error in the
adjudicator’s analysis that the requirement
in s 20(2)(c) of the CCA was
satisfied.
[22] Mr Grace added a refinement to this criticism of the
adjudicator’s analysis. He argued that in the context of MIH’s
April
2013 challenge to the invoices as presented at that time, both parties would
know that greater detail of the construction work
was required to give MIH fair
notice, sufficiently to enable it to consider the components of the payment
claim that it would dispute
in any payment schedule.
[23] In particular, Bussell’s work at the property had been on level one and in the penthouse, and to efficiently analyse and challenge work on the penthouse required the payment claim to distinguish charges for labour and materials in relation to the first floor. Mr Grace relied on Asher J’s characterisation of the s 20 requirements in
Marsden Villas:4
... do not relate to the substantive content of claims, ... but rather on clarity
of form, so the principal knows what the claim is and can respond to
it.
[24] Mr Collins’ response to this argument was that the breakdown
as between components of the job was more than was required
by s 20. In any
event, he argued that a fair measure of distinction between works on the two
floors could be achieved from a detailed
analysis of the information provided.
Mr Collins conceded that a more detailed breakdown may have been desirable, but
was not required
under s 20.
[25] Mr Grace’s argument is supported by the good sense in applying
the CCA in a way that enables disputes arising out of
construction contracts to
be defined and
4 Marsden Villas Ltd v Wooding Construction Ltd, above n 3, at [70].
determined as efficiently as possible. On the facts in this case, if MIH
wished to retain a quantity surveyor to review the reasonableness
of the hours
charged, when its concern related only to the work on the penthouse, the
quantity surveyor would have to undertake a
materially larger assessment
involving the reasonableness of hours worked for the whole job, if its
two components were
not separately identifiable from the details presented
on behalf of Bussell in its payment claim. The concerns MIH raised in 2013
arguably gave fair warning of its concerns and the additional information
required.
[26] However, such individual concerns are not reflected in the
requirements stipulated in s 20(2). It is not appropriate to
add to the
statutory requirements by imposing another layer of detail going
beyond what the section requires.
Accordingly, I can find no error in
the adjudicator upholding the status of Bussell’s payment
claim.
Did MIH submit a payment schedule?
[27] MIH relied on the 1 August 2014 email communication quoted at [6]
above as constituting a payment schedule that relieved
it of the obligation
under the CCA to make timely payment of Bussell’s payment
claim.
[28] The requirements for a payment schedule are set out in s 21(2) and
(3) of the
CCA in the following terms:
21 Payment schedules
...
(2) A payment schedule must—
(a) be in writing; and
(b) identify the payment claim to which it relates; and
(c) state a scheduled amount.
(3) If the scheduled amount is less than the claimed amount, the
payment schedule must indicate—
(a) the manner in which the payer calculated the scheduled amount; and
(b) the payer’s reason or reasons for the difference between the
scheduled amount and the claimed amount; and
(c) in a case where the difference is because the payer is withholding
payment on any basis, the payer’s reason or reasons
for withholding
payment.
[29] Decisions on the adequacy of documents in these contexts have often
acknowledged that “technical quibbles” should
not be allowed to
disqualify documents that otherwise substantially conform with the requirements
of s 20(2) and s 21(2) and (3).5 The substantive purpose is to
adequately inform the claimant of the nature and extent to which its payment
claim is disputed, to enable
a decision on whether to dispute the payment
schedule and, if so, on what grounds.
[30] The adjudicator determined that MIH’s 1 August 2014
email did not sufficiently indicate the manner in which
MIH had calculated the
scheduled amount (which was simply stipulated as zero), and that MIH’s
response therefore did not qualify
as a payment schedule. The adjudicator
excluded a 14 April 2013 email that set out the basis for MIH’s challenge
to the payment
claim made at that time.6
[31] The adjudicator appears to have excluded the content of MIH’s
14 April 2013 email in part by ruling that a payment
schedule should be
comprised in a single document. He cited a decision of Associate Judge
Christiansen in support of that requirement.7 In that decision, the
Associate Judge observed:
[60] Section 21 contemplates that a payment schedule should be
comprised in “a” (ie a single document).
Even if that is not the
case and a payment schedule could comprise more than one document then there
must be a sufficiently identified
relationship and cross-referencing of those
composite parts to leave a contractor in no doubt about what is being addressed
and the
fact that those matters are appropriately being addressed in response to
the payment claim.
[32] The requirement for a payment schedule to be comprised in a single document was one of the errors of law Mr Grace raised in criticising the determination that MIH had not presented a valid payment schedule. I am not
persuaded that Associate Judge Christiansen’s judgment did
clearly require a
5 See SOL Trustees Ltd v Giles Civil Ltd, above n 3, at [39].
6 The content of the 14 April 2013 email is described in [5] above.
7 Canam Construction Ltd v George Developments Ltd HC Auckland CIV-2004-404-3565,
10 November 2004.
payment schedule to be comprised in a single document. His reasoning expressed a qualification to the proposition, and to the extent that his judgment is to be taken as requiring a single document, then with respect it is wrong. It would be patently unfair if (as is demonstrated on the facts here) a claimant could present a valid payment claim that comprised numerous documents, but the payer’s response in a payment schedule had to be assembled in a single document. Numerous decisions consider the adequacy of a payment schedule when comprised in a number of documents, and there would be no justification for imposing such a restriction as to
form.8
[33] However, the prospect of including other information in multiple
documents does not necessarily mean the additional content
qualified it as a
payment schedule.
[34] Decisions have consistently acknowledged that the requirement is to “indicate” reasons for withholding payment rather than to state, specify or set out reasons. That suggests a degree of flexibility or that some lack of precision or particularity is permissible.9 I agree with the adjudicator that the 1 August 2014 email does not have sufficient detail to indicate the reasons for MIH’s refusal to pay the amount of the payment claim. It provides no indication of any calculations relied on for MIH to quantify the counterclaims, or how those counterclaims related to the extent specified in the payment claim. The information conveyed could not allow Bussell to decide which components of the dispute raised by MIH it would accept,
and which it would contest.
[35] Mr Grace argued that once interpreted in light of the matters raised by MIH in its 14 April 2013 email, then the combined effect was sufficient to indicate the manner in which MIH calculated the scheduled amount at zero, and the reasons for the difference between zero and the amount claimed by Bussell. Mr Grace argued that Bussell could not be confused as to the correspondence from the previous year
referred to in the 1 August 2014 email. MIH’s challenges in April
2013 had gone
9 See Foggo v R J Merrifield Ltd HC Christchurch CIV-2009-409-000605, 21 September 2009 at
[37] and Westnorth Labour Hire Ltd v S B Properties Ltd HC Auckland CIV-2006-404-001858,
19 December 2006 at [29] (adopting Australian authority).
unanswered, and the matter had thereafter not been addressed again until the
July
2014 payment claim was presented.
[36] Mr Collins argued that there was no sufficient cross-reference in
the 1 August
2014 email to the matters that had been raised in April 2013, so that the
matters raised in 2013 could not be taken into account in
assessing whether MIH
had sufficiently indicated the matters required in a payment schedule
by s 21(3). Mr Collins conceded
that his argument would have less force if MIH
had annexed a copy of the 2013 email to the 1 August 2014 email and
made
specific cross- reference. However, even in those circumstances, he
argued that insufficient information was conveyed to indicate
the requisite
matters.
[37] In Westnorth Labour Hire Ltd v S B Properties Ltd, Rodney
Hansen J upheld the adequacy of an employer’s response to a payment claim
that did not specify the scheduled amount
or the reasons for the difference
between the scheduled amount and the claimed amount.10 In that
case, Rodney Hansen J reasoned:
[28] ... Although the letter does not adopt the terminology of the Act,
is not stated to be a payment schedule and does not specify
that the scheduled
amount is nil, the essential message is clear and unequivocal. Mr Mullane
explains why he now doubts the accuracy
of Westnorth timesheets and hence the
sums he has been charged. He identifies a charge for materials that have been
returned and
instances of faulty workmanship which would entitle S B
Properties to counterclaim. He says he will not pay the two invoices
until
Westnorth provides him with full particulars of what the contracted labour has
done.
The employer’s letter in that case ran to some two and a half pages,
indicating considerable detail of concerns on numerous
matters and requesting
further information to enable a counterclaim to be prepared in more precise
terms.
[38] As the Court of Appeal did in SOL Trustees Ltd, I consider that Rodney Hansen J’s analysis is distinguishable because of the thoroughness of the response in that case that was relied on as a payment schedule. Without provision of a copy of the April 2013 email when MIH purported to send its payment schedule on
1 August 2014, it is difficult to treat the content of those
unspecified earlier
communications as part of a payment schedule. Further, even if their
content is
10 Westnorth Labour Hire Ltd v S B Properties Ltd, above n 9.
included, there is no information as to the extent of overcharging MIH would
claim, or the cost of remedial work it had to pay for
with a subsequent
contractor to correct work inadequately or incorrectly done by Bussell.
Presumably, either or both of those matters
would have to be outlined for MIH to
indicate the matters required by s 21(3).
Conclusion
[39] To the extent that the adjudicator ruled that a payment schedule had
to be contained in a single document, then that constituted
an error of
law.11 However, when communications from MIH are considered on a
broader basis, there is still inadequate to constitute a payment
schedule.
[40] Accordingly, the application for judicial review is dismissed.
Bussell is entitled to costs on a 2B basis, together
with disbursements, if
any, to be settled by the Registrar.
Dobson J
Solicitors:
Surridge & Co, Porirua for applicant
Gibson Sheat, Wellington for second
respondent
11 The adjudicator’s reliance on the point was somewhat unclear, and was not determinative in the
finding that MIH had failed to present a payment schedule.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/211.html