Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 27 September 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-001649 [2016] NZHC 2245
IN THE MATTER
|
of an appeal against a decision of the
District Court
|
BETWEEN
|
AUCKLAND ELECTRICAL SOLUTIONS LIMITED Appellant
|
AND
|
THE WARRINGTON GROUP LIMITED Respondent
|
Hearing:
|
21 September 2016
|
Counsel:
|
N Tabb for Appellant
S Gazley for Respondent
|
Judgment:
|
22 September 2016
|
JUDGMENT OF DOWNS J
This judgment was delivered by me on Thursday, 22 September 2016 at 4 pm
pursuant to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Solicitors/Counsel: N Tabb, Auckland.
Steindle Williams Legal, Auckland.
AUCKLAND ELECTRICAL SOLUTIONS LTD v THE WARRINGTON GROUP LTD [2016] NZHC 2245 [22
September 2016]
Background
[1] The respondent engaged the appellant to provide electrical work on a single project from July 2014 until August 2015. The appellant sent the respondent invoices totalling $83,599.57. The respondent paid $62,214.39 but declined to pay five invoices issued within the period 30 April 2015 to 30 June 2015. Credit notes in the respondent’s favour and further payment by the respondent of $12,500 left
$8,659.83 outstanding.
[2] The appellant sought summary judgment of that sum on the basis the
invoices constituted payment claims pursuant to the Construction
Contracts Act
2002. It sought related debt collection costs of $4,428.86. The District
Court declined summary judgment. This
is an appeal against that
determination.
[3] In the Court below, Judge Lovell-Smith comprehensively set out the
facts, law, and arguments.1 But the Judge’s actual analysis
was brief:
[57] The plaintiff’s invoices annexed to the affidavits of John Campbell and Stephen Mettam all contain reference to the Act, whereas in those annexed to David O’Connell’s affidavit, there is no such reference.
[58] The invoices also lack detail in the areas outlined by the respondent. [59] These are significant credibility issues and in my view the respondent
has an arguable defence.
[60] Furthermore, the respondent has raised issues about the standard of
the work which should also be explored more fully.
[61] The application for summary judgment is therefore declined. Given
the amount involved, these proceedings are remitted back
to the Disputes
Tribunal.
[62] The respondent is entitled to costs on a Category 2 basis to be filed
by the Registrar.
[4] Such is the background to this
appeal.2
1 Auckland Electrical Solutions Ltd v Warrington Group Ltd [2016] NZDC 5565.
Something more about the
facts
[5] Mr Steven Mettam, the director of the appellant, has sworn an
affidavit attaching what he says are the invoices sent
to the respondent between
30 April 2015 and 30 June 2015. Materially, these invoices all contain the
notation: “This invoice
is tendered under the Construction Contracts Act
2002”.
[6] Mr David O’Connell, a director of the respondent, has sworn
an affidavit annexing what he says are the invoices received
from the appellant
in this period. Materially, these invoices do not contain the notation above.
This point has significance because
as observed above, the appellant’s
application for summary judgment was brought on the basis the invoices
constituted payment
claims under the Construction Contracts Act. And s 20(2)(f)
of that Act provides such a claim must state it is made under the
Act.
[7] The appellant instructed a debt collector, Law Debt Collection
Ltd. On
3 August 2015, it sent the respondent a statutory demand for
$21,159.83.
[8] On 11 August 2015, Mr John Campbell of Law Debt Collection Ltd sent
an email to the respondent attaching the five invoices.
It is common ground
this set of invoices did refer to the Construction Contracts Act. The
invoices did not provide a due date for payment other, on the appellant’s
argument,
by reference to the phrase: “Net 20”.
[9] Mr Campbell’s email informed the respondent:
(a) It had not filed a payment schedule as required by the Act,
and implying the period for doing so had passed.
(b) The outstanding monies “must be paid immediately” to the
offices of
Law Debt Collection or its bank account.
[10] On 14 August 2015 the respondent paid the appellant $12,500.00.
[11] On 20 August 2015 Mr Mettam met with Mr O’Connell and a second
director of the respondent at the offices of Law Debt
Collection Ltd, with a
view to resolving the dispute. Mr Campbell was also present. His
affidavit records that at that
meeting, the respondent’s directors
were “asked why they had not paid the outstanding invoices and apart from
a bare
assertion of a dispute they were not able to give any reasons for not
paying the invoices”. Mr Campbell gave the directors
another copy of the
five invoices identical to those sent by email nine days earlier.
[12] As will be apparent, the appellant’s position is that the
respondent had no reason not to pay and gave none.
[13] The respondent’s position is that it has paid most of the
invoices submitted by the appellant but not paid the balance
because the
underlying works were defective or of poor quality. Recognising s 79 of the
Construction Contracts Act precludes this
very type of argument, the
respondent’s position on appeal was that enactment had not been complied
with so that summary judgment
was unavailable.
[14] Events subsequent to the August meeting need not be recorded here.
It is sufficient to observe common sense did not prevail:
a modest dispute which
should have been resolved in the Disputes Tribunal—if not settled
outright—resulted in summary
judgment proceedings in the District Court
and this appeal when that application was dismissed.
Why the appeal must be dismissed
Service of the original invoices in April, May and June
[15] Summary judgment is available against a defendant only if the plaintiff satisfies the Court the defendant has no defence to the cause of action.3
Unsurprisingly, genuine credibility contests, meaning those which would or may go to the existence of a defence, are an impediment to summary judgment.4 This is
because on such applications, the evidence is in written form
only.
3 District Court Rules, r 12.2.
4 Andrew Beck (ed) McGechan on Procedure (online looseleaf edition, Westlaw) at [HR12.2.03].
[16] Against this background, Judge Lovell-Smith was unquestionably
correct to dismiss the summary judgment application insofar
as it relied upon
original service of the April, May and June invoices. If Mr Mettam is correct,
the invoices did contain reference
to the Construction Contracts Act as required
by that enactment. But if Mr O’Connell is correct, the original invoices
did
not. Moreover, there are two possibilities in relation to their evidence.
The first, and happy possibility, is that one of the
men is mistaken. The
second, unhappy possibility is that one of the men has been other than candid in
order to “win”.
These stark choices, which could only be resolved
through cross-examination at trial, serve to highlight the unsuitability of this
aspect of the claim to summary judgment.
[17] I record Ms Tabb’s submission summary judgment does not
preclude robust
factual assessment on the papers, a point emphasised by the Court of
Appeal:5
[26] The Court will not normally resolve material conflicts of evidence or
assess the credibility of deponents. But it need not
accept uncritically
evidence that is inherently lacking in credibility, as for example where the
evidence is inconsistent with undisputed
contemporary documents or other
statements by the same deponent, or is inherently improbable: Eng
Mee Yong
v Letchumanan [1980] AC 331 (PC) at 341. In the end the
Court’s assessment of the evidence is a matter of judgment. The Court may
take a robust and realistic approach where the facts warrant it: Bilbie
Dymock Corp
Ltd v Patel (1987) 1 PRNZ 84 (CA).
[18] But here, it is not possible to make the assessment without
cross-examination. And in any event, it would procedurally
unfair to do
otherwise in light of the implications of preferring one deponent’s
evidence over the other; see [16] above.
[19] Materially, the respondent sought a direction in advance of the hearing for the original invoices annexed to Mr O’Connell’s affidavit to be placed before me at the hearing—obviously for my inspection. Katz J made such an order on 12 September
2016. Unfortunately, the District Court was not able to comply with that direction. The point is that this is not a case in which the respondent was seeking to rely only upon copies of documents in circumstances in which those copies might have been
manipulated to advance its cause.
5 Krukziener v Hanover Finance Ltd [2008] NZCA 187, [2010] NZAR 307.
The August re-service of the invoices as a fresh payment claim under the
Act
[20] The remaining aspect of the claim must be dealt with wholly
afresh,6 because the Judge’s reasons in relation to this aspect
are open to a number of different interpretations, a difficulty compounded
by
their brevity. The appellant did not seek to persuade me from approaching the
case in this way, albeit it made no concession
the Judge had erred.
[21] The appellant contends that irrespective of whether the
original invoices satisfied the s 20(2)(f) requirement to
refer to the Act,
those emailed to the defendant on 11 August and provided again in person on 20
August, did so. So, the appellant
contends this sequence constituted service of
payment claims in terms of s 20 of the Act. It says that because the respondent
never
responded with a payment schedule, the outstanding portion became a debt
due to the appellant in terms of s 23 of the Act, and hence
one amenable to
enforcement by way of summary judgment.
[22] I disagree. While the law is clear a party may resubmit prior
claims by repeating them in subsequent payment claims,7 whether there
has been a subsequent payment claim turns on the facts. And here, the facts are
against the appellant. I am far from
satisfied there is no available defence.
Indeed, it is almost certain the August sequence did not give rise to a valid
payment
claim under the Act.
[23] The re-served invoices contained their original dates, being dates in April, May, and June 2015. Section 20(2)(d) of the Act requires a payment claim to identify “the due date for payment”. The only reference to a due date is a notation on each invoice of “Net 20”. There was no evidence before me as to what significance, if any, this phrase has in the building industry. But it is not an unreasonable assumption this means payment was due on the 20th of the month following the invoice, and there is support for that in the evidence: the appellant paid several invoices a month or so after they were tendered. It is here the appellant’s
problems arise:
6 As noted above, this is an appeal by way of rehearing, and hence there is a broad discretion to reconsider a lower Court’s decision. However, because of the difficulties identified at [20] above, by “wholly afresh”, I mean just that.
7 Sol Trustees Ltd v Giles Civil Ltd [2014] NZHC 1813.
(a) Notwithstanding the implication payment was due on the 20th
of the following month, these invoices were served with an associated
demand for immediate payment in the 11 August email. Nothing
was said or done
at the 20 August meeting to countermand that.
(b) More importantly, even though the Act provides time for
the respondent to file a payment schedule (within 20 working
days) after service
of a payment claim,8 Mr Campbell’s email of 11 August
implied that time had already passed. Again, nothing was said or done at the
20 August
meeting to correct that impression.
[24] Consequently, there is significant dissonance between
the appellant’s submission the invoices constituted
fresh payment
claims under the Act,9 and the available evidence, which implies the
appellant was relying upon the invoices as ones already tendered and liable for
immediate
payment.
[25] The case law to the effect an error in relation to the due
date will not necessarily vitiate a payment claim is
distinguishable,10
as here the invoices’ dates were inconsistent with the actions of
the appellant in seeking immediate payment. And importantly,
the appellant
implied the time for filing a payment schedule had passed when, if the payment
claims were freshly issued, it had not.
[26] In short, the evidence implies the invoices were provided as copies
of an antecedent payment claim rather than a fresh one,
which under the Act
would have given rise to a further 20 working day period for a payment
schedule.
[27] The appellant submitted the case should be approached in accordance
with
the Act’s purpose firmly in mind. As to that, the Court of Appeal has
observed:11
The purpose provision of the Act includes the fact that the Act was ‘to
facilitate regular and timely payments between the parties to a construction
8 Constructions Contracts Act 2002, s 22(b)(ii).
9 Given the acute factual dispute about whether the original invoices contained reference to the
Act, the appellant had to rely on the subsequent invoices being fresh claims to succeed.
10 CMP Construction Ltd v Aluminium Technology Ltd [2013] NZHC 2481 and Pedestal Ltd v City
Build Construction Ltd [2014] NZHC 1783, [2014] NZCCLR 32.
contract’. The importance of such regular and
timely payments is well recognised....
[28] To similar effect is Salem Ltd v Top End Homes Ltd, in which
the Court of
Appeal said:12
The whole thrust of the Act is to ensure that disputes are dealt with
promptly and payments made promptly, because of the disastrous
effects that
nonpayment has, not only on the head contractor, but also on its employees,
subcontractors, and suppliers....
[29] All of this is correct, and nothing in this judgment is intended to
suggest otherwise. But the difficulty for the appellant
remains: the evidence
does not support its thesis the August sequence was a fresh payment claim under
the Act. Square peg, round
hole.
[30] This aspect of the claim for summary judgment must also
fail.
Conclusion
[31] The appeal is dismissed.
[32] At the request of the parties, I reserve the issue of costs. I
will rule if necessary. However, I invite them to reach
agreement and remind
them of my observations at [14].
...................................
Downs J
12 Salem Ltd v Top End Homes Ltd [2005] NZCA 375; (2005) 18 PRNZ 122 (CA) at [11].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/2245.html