Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 24 November 2016
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV-2015-409-000163 [2016] NZHC 2686
BETWEEN
|
MICHAEL COLLIS and KEITH
CHARLES LANGTON Plaintiffs
|
AND
|
HYPOWER ELECTRICAL LIMITED First Defendant
|
AND
|
WAYNE MARK HYDES Second Defendant
|
Hearing:
|
7 November 2016
|
Appearances:
|
G M Brodie and A G M Whalan for the Plaintiffs
P J L Hunt and T W Clark for the Defendants
|
Judgment:
|
10 November 2016
|
JUDGMENT AS TO REASONS OF NATION
J
[1] In these proceedings, the plaintiffs seek damages from the
defendants following the loss of a reasonably substantial
hut located in an
area, largely of bush, near Kaikoura. The hut was destroyed in a fire that
occurred on 25 October 2014.
[2] The plaintiffs filed proceedings on 30 March 2015. On 30 November
2015, Associate Judge Matthews made timetabling directions.1 These
included a direction that the close of pleadings date was to be 8 July 2016.
On 11 February 2016 the proceedings were set
down for hearing for ten days
beginning 7 November 2016.
[3] On 4 November 2016, counsel for the plaintiffs, Mr Brodie, by memorandum, effectively sought leave from the Court to amend the statement of
claim. Counsel for the defendants filed a memorandum indicating the
application
1 Collis v Hypower Electrical Ltd HC Christchurch CIV-2015-409-000163, 30 November 2015.
would be opposed. Because of my unavailability, the issue was discussed in
telephone conferences with Davidson J on 4 November 2016.
[4] Further memoranda, including the draft amended statement of claim,
were then filed by counsel. The parties’ positions
with regard to the
amendment remained the same. I heard argument when the proceedings were
called. After hearing argument,
I ruled that I would allow the amendment; I
also refused the defendants’ request for an adjournment of the
trial.2 I now give reasons for both decisions.
[5] The defendants are a company and its director who carried out
substantial work on the hut between January 2014 and May 2014.
That work
related to the installation of a solar powered electricity supply to the hut,
integrated with electricity supplied from
a generator (the integrated power
system).
[6] No person was at the hut when the fire occurred on 25
October 2014. Because of the location of the hut, no
one was able to fight the
fire after it started. This led to the almost complete destruction of the
building and difficulties in
identifying what had caused the fire.
[7] In their first statement of claim, the plaintiffs alleged the
defendants had failed to carry out the electrical work required
of them with the
required skill and care. In making that general allegation, they
included six particulars. It was
apparent from those particulars that they
identified the fire as originating from a cupboard in which were installed
various
components relating to the integrated power system. One of the
particulars alleged a particular fault in that the system had
been installed and
left operational by the defendants with only one power inverter in place and
working when two were required.
[8] The statement of claim identified that the causes of action were based on a breach of the Consumer Guarantees Act 1993, breach of contract and in tort for
negligence.
2 Collis v Hypower Electrical Ltd [2016] NZHC 2652.
[9] In referring to breach of the Consumer Guarantees Act as a cause of
action, the plaintiffs alleged that the defendants owed
a statutory guarantee to
the plaintiffs to carry out electrical services with reasonable care and skill,
and that he failed to exercise
the due care and skill in installing the
integrated power system. The plaintiffs relied on the same particulars as had
already
been pleaded in relation to all causes of action.
[10] In their statements of defence, the defendants denied both
the general allegation that the defendants had failed
to exercise the required
skill and care in carrying out their work and relevant aspects of the various
particulars.
[11] On 29 July 2015, the plaintiffs filed an amended statement of claim.
This included the same particulars of negligence as
originally filed but added
further particulars. It was alleged that the fire had been caused by a screw,
used to secure a solar
panel, going through the roofing iron into a cable so as
to compromise the safety of the whole wiring system.
[12] A second amended statement of claim was filed on 28 June 2016. The
only change related to quantum of damages claimed.
[13] Both parties briefed evidence on the basis of those allegations.
The evidence included detailed, and no doubt expensive,
evidence from
experts.
[14] Mr Brodie was instructed as counsel only some two weeks before the
trial. He explained to me that, after reviewing the evidence,
he considered the
pleadings as they stood did not fairly put before the Court what was really at
issue between the parties. He submitted
that, if the proceedings remained as
they were, the plaintiffs could effectively be denied the benefit of the
guarantees which he
contends they were entitled to by legislation: the Consumer
Guarantees Act.
[15] He argued that, with the proceedings as they stood, before amendment, it was clear the issue at trial would be and should be whether the fire resulted from some failure in the electrical work and installation carried out by the defendants. He said the plaintiffs would be establishing this by ruling out any other reasonable
explanation for the fire. He said that, if the plaintiffs could establish
the fire had its origins in the electrical work carried
out by the defendants,
they would be entitled to the remedy they were seeking through the guarantee in
relation to both goods and
services provided by the defendant electricians under
the Consumer Guarantees Act.
[16] In the proposed amended statement of claim, the plaintiffs added a
further and alternative cause of action against both defendants.
With that
pleading, they in summary alleged that, in installing the integrated power
system, the defendants had supplied goods and
services covered by the Consumer
Guarantees Act, subject to the guarantees provided for by that Act. It was
alleged that those
guarantees required that the installation would be carried
out with reasonable care and skill, and the supply of the integrated power
system and the system itself would be reasonably fit for purpose and of such a
nature and quality that it could be expected to achieve
a domestic electricity
supply. It was alleged that, if the precise fault or defect which caused the
fire could not be identified,
the fire was nevertheless caused by the integrated
power supply and thus could not have been:
(a) of acceptable quality;
(b) installed with reasonable care and skill; and
(c) fit for the intended purpose of a domestic electricity
supply.
[17] After the conference which took place with Davidson J on 4 November
2016, Mr Brodie for the plaintiffs confirmed that the
amendment to the pleadings
would not require the plaintiffs to file any further or different evidence.
Independent of that, he
did give notice that he would be seeking leave to lead
evidence from a further witness, essentially backing up the evidence to be
given
by a fire service investigator who had initially investigated the
fire.
[18] Counsel for the defendants filed a memorandum setting out the grounds on which they opposed the amendment and the basis on which they said an amendment would require an adjournment of the proceedings. In that memorandum, counsel referred to dicta from Brownlie v Shotover Mining Limited and from Barker J in
Securitibank Limited (in rec and in liq) v Rutherford.3
Mr Brodie referred me to Heath J’s detailed discussion of applicable
principles in EBR Holdings Ltd (in liquidation) v van
Duyn.4
[19] These authorities emphasise the importance of pleadings. It is also important that the Court’s directions as to how and when proceedings are progressed to trial are observed. Failure to do so can result in avoidable delays which deny the parties justice. These delays also make it more difficult for the Court to manage its resources and time so that other parties can utilise the courts to resolve their litigation.5 Counsel and any experts assisting them do not serve well the parties involved, the public generally or the administration of justice if they do not abide by timetabling directions and only get to grips with the details of the evidence, the
difficult issues in the proceedings and the need for any change in the
pleadings just prior to trial.
[20] Having said that, the Court of Appeal has acknowledged
that:6
It will, of course, happen from time to time that there will be inadequacies
in the original pleading, and these may not emerge until
trial. In such cases,
the proper course is for an appropriate amendment to be sought, and it will be
allowed where this can be done
without injustice.
[21] In assessing whether a proposed amendment will result in an
injustice and whether it will require an adjournment of the trial,
it is
important that a party should not be prejudiced through being taken by
surprise.
[22] It is also important that litigation between the parties and the trial should be conducted fairly, openly and incidentally to reduce cost. In the administration of justice generally, it is also important that time allocated for the hearing of proceedings should be utilised effectively if that can be achieved without causing an
injustice.7
4 EBR Holdings Ltd (in liquidation) v van Duyn [2016] NZHC 1169.
5 SM v LFDB [2014] NZCA 326, [2014] 3 NZLR 494 at [27]; Aon Risk Services Australia Ltd v
Australian National University [2009] HCA 27, (2009) 239 CLR 175 at [5].
6 Brownlie v Shotover Mining Limited, above n 3, at 19.
7 Securitibank Limited (in rec and in liq) v Rutherford, above n 3, at 10.
[23] Mr Hunt for the defendants argued that the proposed amendment
involved the inclusion of a new cause of action and was a new
way of presenting
the case. He also argued the amendments meant the pleadings had gone from
pleading specific causes of the fire
to a more general cause. He argued that
the defendants would be prejudiced because, in preparing for the trial, the
defendants had
focused on the specific causes that had earlier been pleaded
rather than the general. He argued that allowing the plaintiffs to
plead a
deficiency in the installation of the integrated power system did not give the
defendants fair notice of the case against
them or meet the plaintiffs’
requirements in terms of proof. He argued that, if the plaintiffs were allowed
to amend the
pleadings in this way, they would need to examine the whole of the
integrated power system to assess potential defects and potential
causes of the
fire.
[24] Counsel for the plaintiffs who, as I said, has only been
instructed very recently, acknowledged the lateness
of the application for
leave to amend and the need to consider prejudice arising out of this. He
confirmed that the specific failures
in installation are still being relied upon
although he suggested that, with the benefit of the statutory guarantees, if the
plaintiffs
could establish that the fire resulted from a failure in the
integrated power system, that might well be sufficient for
the
plaintiffs to prove the defendants were liable for the damage caused by the
fire.
[25] He submitted that, with the amendment, the essential issues in this case will not change. The plaintiffs have always had to establish that the fire resulted from some failure with the integrated power system and not from some other cause. He argued that had been the issue on which the defendants’ main experts had been engaged from very soon after the fire occurred. Without being contradicted, he said the defendants’ main fire investigator and an electrical engineering expert had visited the scene of the fire to assess potential causes of the fire in the days immediately after it occurred. He submitted that it was unlikely they would need to make any further investigations which they could not have already carried out. Such investigations would always have been necessary given the defendants’ denial that the fire had resulted from any failure connected with the integrated power system.
[26] In the week before the trial was due to commence, the parties filed
with the
Court copies of the expert evidence they were intending to provide to the
Court.
[27] Mr House is an electrical inspector to give evidence for the
plaintiffs. He said he was instructed to provide an opinion
as to the conduct
of the electrician in installing the solar power unit in the hut and whether
negligent installation of the unit
was the cause of the fire. His evidence
relates solely to the nature of the system and the way a neutral wire associated
with the
system appears to have been compromised by a screw going through
corrugated iron into a cable.
[28] Mr Shelton is an electrical engineer. His brief of evidence
explained why he came to the same conclusion but he also explained
why he
considered the fire was not in the log-fire area but was electrical in
origin.
[29] The plaintiffs were going to call evidence from Mr Irvine, a fire risk
management officer with the New Zealand Fire Service.
In his evidence, he
referred to the investigations he had made in the days immediately after the
fire, how he concluded the area
of origin of the fire was within the electrical
system and why he concluded the fire could not have been caused by any natural
event
or through being deliberately set alight. He produced a report for the
fire service dated 9 March 2015 in which he expressed the
conclusion:
It is determined that the fire is not suspicious in cause and that the origin
was within the Area 2 of the building and not from the
fire place, kitchen,
stove or fridge within this area ... It is believed that the point of origin
is somewhere near the Electrical
switchboard area, including the solar power and
generator control units. Exact cause could not be determined from the remaining
evidence at the scene that we observed.
[30] The defendants have thus been on notice since soon after the fire
that, from the fire investigator’s report and the
plaintiffs’
subsequent briefs of evidence, it was claimed that this fire originated from a
fault in the electrical system and
that other potential causes could be
excluded.
[31] I was also satisfied from reading the briefs of evidence that, although there is a considerable amount of expert evidence relating to the particular defect in the system which has been identified by the plaintiffs, the defendants’ expert had always
addressed the issue of whether the fire could have resulted from a cause
other than the integrated power system.
[32] In a brief of evidence filed for the defendants, Mr Joseph said that
on 31
October 2014 he was asked to:
1. investigate the origin and cause of the fire;
[33] He said in his brief that he has reviewed relevant information,
reports and records. He said he inspected the scene on 1
November 2014 and
revisited the scene on 5 August 2016 and examined additional items Mr Collis had
taken from the fire scene. In
his evidence, he says that, as a result of his
investigation, he considered the most probable cause of the fire originated in
the
immediate vicinity of the wood- burner flue system at the eastern end of the
open plan lounge/kitchen area of the hut. It is apparent
that this was away from
the area which Mr Irvine had identified as the origin of the fire.
[34] Mr Joseph confirmed he was giving his evidence as an expert witness
and was complying with the code of conduct for expert
witnesses. I thus
proceeded on the basis that he would have carefully and fully investigated
potential alternative causes of the
fire, and the basis on which Mr Irvine and
Mr Skelton considered the fire originated in the area of the integrated power
system.
It was also apparent from his brief that the fundamental dispute
between the plaintiffs and the defendants has always been whether
the fire
originated from a fault in the integrated power system or from some other
cause.
[35] Against that background, I did not consider the proposed amended pleading would take the defendants by surprise. Were I to refuse the amendment, potentially a defect in the pleadings could have denied the plaintiffs the benefit of guarantees to which they were entitled by legislation. The amendment was thus required to
determine, on the merits and on the basis of relevant evidence, the real
controversy between the parties. For all those reasons,
I considered it
appropriate to give leave to the plaintiffs to file the amended statement of
claim as provided to the Court.
[36] Counsel for the defendants had also suggested that, if the amendment
was allowed, the proceedings should be adjourned so
the defendants could
consider the further basis on which the plaintiffs’ case was being
pursued, and make other
enquiries that might be relevant. It was suggested
that such enquiries could include obtaining information as to the
appropriateness
and adequacy of the components used in the integrated power
system which was installed and also the state of any appliances, such
as a
fridge, that remained at the property and which it was suggested could
have been the cause of the fire.
[37] Given the expert evidence being led from Mr Joseph, I considered that these matters would or should have been investigated when he was asked to carry out his initial investigation. Given the extent of the destruction caused by the fire, it seemed unlikely that any further investigations of this sort would result in different and relevant evidence becoming available. The mere possibility that such evidence might be available did not, in my view, justify the prejudice that would be done to the administration of justice and to the plaintiffs if there was a further significant delay in bringing these proceedings on for hearing and having to abandon a hearing
which had been scheduled to take nine days.8
[38] For those reasons, an adjournment of the proceedings was denied. I
did indicate in my ruling that I would consider allowing
further evidence to be
called at a later date if, in the interests of justice, this was
required.9
Solicitors:
Geoffrey Brodie, Barrister, Christchurch
Rhodes & Co., Christchurch
McElroys, Auckland.
8 The fifth scheduled day falling on the Canterbury Anniversary. As to the “irreparable element of unfair prejudice in unnecessarily delaying proceedings”, the need to maintain public confidence in the judicial system and the allied need to use the court’s time efficiently, see Aon Risk Services Australia Ltd v Australian National University, above n 5, at [5].
9 The hearing thus began but the proceedings were settled on the second day.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/2686.html