Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 17 December 2016
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV-2016-476-000032 [2016] NZHC 3015
BETWEEN
|
SAMUEL JOSEPH DESMOND MILLAR
AND CAROL MILLAR Applicants
|
AND
|
ASHBURTON DISTRICT COUNCIL First Respondent
|
AND
|
GREG DONALDSON CONTRACTING LIMITED
Second Respondent
|
Hearing:
|
17 November 2016
|
Appearances:
|
P A C Maw and K H Woods for Applicants
A J Schulte for First Respondent
M J Wallace and J R King for Second Respondents
|
Judgment:
|
13 December 2016
|
JUDGMENT OF DUNNINGHAM J
Introduction
[1] Mr and Mrs Millar have lived on their 13.6 hectare rural property
on the outskirts of Tinwald, just south of Ashburton township,
for nearly 30
years. Diagonally across the road from them, and adjoining the urban boundary of
Tinwald, is a similar size rural block
owned by Greg Donaldson Contracting
Limited (GDCL).
[2] In November 2015, GDCL applied to the Ashburton District Council
(the Council) for resource consent to use part of its property
as a
contractor’s yard for its rural based contracting business.
[3] A few months before this, Mr and Mrs Millar had advised the Council
that they wished to be heard on a different proposal
to develop GDCL’s
site, as they
MILLAR v ASHBURTON DISTRICT COUNCIL [2016] NZHC 3015 [13 December 2016]
opposed development of the site for non-rural use. Although that proposal
did not proceed, they expected to be advised of any further
proposals by GDCL to
develop its site. They are aggrieved, therefore, that the application for the
current consent was not notified
to them and was subsequently
granted.
[4] In these proceedings they have applied to judicially
review:
(a) the decision (if any was made) that there would not be
limited notification of the application for resource consent
to them as affected
persons; and
(b) the decision to subsequently grant the consent.
They seek a declaration that both the purported decision on notification, and
the substantive decision to grant consent, are invalid,
as well as orders
quashing the decisions.
Issues
[5] While the parties expressed the issues differently, in summary they
are as follows:
(a) Did the Council make a decision as to notification when
the independent hearings Commissioner only signed
the substantive report
on the grant of the resource consent prepared by the consultant planner, and not
the separate report prepared
by the consultant planner on the issue of
notification?
(b) If the Council did make a decision on notification, did it take
into account all relevant considerations, including, in
particular, the effects
of the storage of soil in the area described as a storage area?
(c) If the Council did make a decision on notification, did it apply the correct legal test when assessing the permitted baseline under s 95E(2)(a) of the Resource Management Act 1991 (RMA)?
(d) If the Council did make a decision on notification, was its
decision that the adverse effects on the Millars and other neighbours
were less
than minor an unreasonable decision?
(e) Did the Council wrongly conflate the separate statutory tests
relating to the notification of the application and the decision
to grant
consent?
(f) If the Council did make a decision on notification, did it take
into account all relevant considerations when making its
decision to grant
consent?
(g) If the Council did err in the decision-making process on notification and/or the substantive decision, is this nevertheless a case where I should decline to exercise my discretion to set aside the Council’s decision, particularly taking into account GDCL’s decision to relinquish that part of the resource consent which would allow it to
store soil in excess of the District Plan limits?1
Background
The first application
[6] The application for resource consent which is the
subject of these proceedings was not the first application
lodged by GDCL.
In July 2015, GDCL made an application to establish and operate a contracting
base for the storage and maintenance
of contracting machinery, and also to
establish and operate a bulk-fertiliser and lime storage and transport
facility on
the property.
[7] The Millars became aware of this application through a neighbour and were concerned about it. From their perspective, they would be adversely affected by the proposed activity as the south eastern corner of the application site is approximately
80 metres from the Millars’ house. The Millars instructed their
lawyers to write to
1 Although noting GDCL’s primary position was that the consent did not permit soil storage in
excess of the District Plan limits.
the Council informing the Council that they were opposed to GDCL’s
application
and wanted it to be publicly notified.
[8] As it transpired, Mr David Mountfort, the independent consultant
planner who had been engaged by the Council to assess the
application under s
42A of the RMA, rejected it in its entirety under s 88(3) of the RMA for failing
to provide sufficient information
and assessment. GDCL was advised to obtain
expert assessments of transport, noise, dust and visual effects before the
application
would be accepted.
[9] GDCL did not proceed with that application but instead lodged a
modified application. It retained the proposal to establish
a
contractor’s yard and associated storage, but omitted the proposed
fertiliser storage and transport facility. The application
was accompanied by
four expert reports which included an engineering assessment, a visual and
landscape assessment, a transport assessment,
and a noise and dust assessment.
That application was subject to a request for further information under
s 92 of the RMA.
In response, GDCL lodged a third complete version of the
application which, as Mr Mountfort explains, is the one that was
processed.
The current application
[10] The application sought land use consent to establish and
operate a contractor’s yard on the 13.3 hectare
L-shaped block owned by
GDCL and located in the rural A zone under the Ashburton District
Plan.
[11] To the north of the application site are the Tinwald sale
yards, and
5.4 hectares of GDCL’s land on the boundary to the sale yards would continue to be used as holding paddocks for stock being sold in the sale yards. The middle section of the property, comprising approximately 3.5 hectares, would encompass the contractor’s yard base area and buildings. It would include an 800 square metre workshop building plus an associated 60 square metre staff area. It was also to include a 350 square metre office building to accommodate up to five fulltime equivalent staff.
[12] Finally, the balance of 4.31 hectares on the southern-most
part of the property, which is closest to the Millars’
property, would
be used for “storage of aggregates and soil and part of the storm water
detention area for the site”.
That part of the site was also to be bunded
with a minimum 1.5 metre high earth bund which was to be extensively planted in
accordance
with a landscape plan provided. I refer to it as the “storage
area”.
[13] The hours of operation were proposed to be 06.30 to 18.00 Monday to
Friday and 07.30 to 13.00 Saturdays, although it was
explained that at times
there might be vehicle movements outside these hours, for example, for emergency
works, or for mechanics
requiring equipment for offsite
repair/maintenance.
[14] The proposed activity was classed as a “service
activity”, which is a non-complying activity within
the rural A zone
of the District Plan. The other non-compliances identified in the assessment
of environmental effects (AEE) were:
(a) the proposal failed to comply with the site standards for site
coverage and earthworks, (although site standards are applicable
only to
permitted or controlled activities within the District Plan);
(b) the proposal would potentially breach the night time noise
standards between the hours of 06.30 and 07.00;
(c) the size of the freestanding sign and the sign on the facade of the
building exceeded the permitted size of signs within
rural zones;
and
(d) the proposed above ground diesel storage tank of 10,000
litres exceeded the permitted 3,000 litres for an above
ground storage tank in a
rural zone.
[15] As a consequence, the application sought consent for a non-complying activity.
The assessment of environment effects
[16] The AEE and accompanying expert reports were, in the
applicant’s view, deficient in their assessment of the effects
of storage
of aggregates and soil within the storage area and of the activities which would
be associated with the storage of such
material, including the transportation of
the aggregate and soil in and out of the area.
[17] In particular, the applicant considers there were the following
deficiencies:
(a) the expert noise and dust assessment included a site plan
which labelled the storage area as “rural land”;
(b) the noise and dust assessment did not consider noise and
dust emissions from within the storage area, only from
the contractor ’s
yard;
(c) the transport assessment did not assess the transport of aggregate
and soil to and from, and from unloading it within, the
storage
area;
(d) because the transport assessment listed the anticipated daily
traffic generated by staff equipment deliveries and staff
arrival/departures for
half day projects as being “car/ute trips”, whereas in the
application itself they were described
as “Heavy Goods Vehicle
(HGV)” trips, it is not clear what type of vehicles were used to reach the
conclusion that the
activity would not adversely impact the overall ambient
noise environment;
(e) in any event, the noise assessment relied on ambient
monitoring carried out during off-peak traffic periods and
so underestimated the
contribution of the existing noise environment to the overall noise which would
be generated by the additional
noise of the activity;
(f) the AEE concluded that the effects of the activity would be minor but no more than minor. As a result, the notification section of the
application incorrectly stated that there was no requirement to notify
affected persons pursuant to s 95F of the RMA.
Council processing of the application
[18] For various reasons, the Council did not process this application
internally. Instead, Mr Ian Hyde, the Council’s
district planning
manager, commissioned Mr David Mountfort to assess the application and provide
a report under s 42A of the
RMA. Mr Mountfort was chosen both because he was a
highly experienced planner, having been in practice at the time for some 47
years,
and because he was familiar with the application site from his work
reviewing the earlier application.
[19] In early January 2016, Mr Mountfort prepared a draft s 42A report
for the
Council. That included two recommendations:
(a) that GDCL’s application be processed on a non-notified
basis in accordance with ss 95A – 95F of the RMA;
and
(b) that GDCL’s application be granted pursuant to ss 104, 104A,
104B,
104C and 108 of the RMA subject to a set of conditions.
[20] When he received the draft report, Mr Hyde suggested that it would
be preferable to separate the combined report into two
reports: one dealing
with the recommendation as to notification (the notification report), and the
other dealing with the recommendation
on the substantive decision (the
decision report). Mr Mountfort duly did this. However, the content of the
reports as it
related to assessment of effects and notification did not alter.
The only real difference between the text of the two reports was
that the
decision report included two further pages which assessed the proposal against
the relevant planning framework, and set
out conditions on which it was
recommended that consent be granted.
[21] On 20 January 2016 an independent hearings commissioner, Ms Patricia Harte, was given delegated authority by the Council to “make a decision on notification, to hear submissions (if required) and to make a decision on the application for resource consent described above”.
[22] Ms Harte was sent both the notification report and the
decision report prepared by Mr Mountfort on the application.
She received and
reviewed those reports and made some enquiries of Mr Mountfort by email on 26
January. After receiving what she
describes as satisfactory responses in
relation to the matters she raised with Mr Mountfort, she signed the decision
report which
recommended the grant of consent on conditions, and that became the
decision. She did not sign the separate report containing the
recommendation on
notification.
[23] The applicants’ case is that, as there was no prior decision
on notification, the resource consent could not lawfully
be granted, but even if
there was a notification decision, there were flaws in both that decision and
the substantive decision which
invalidate the grant of consent.
The relevant statutory framework
Provisions relating to notification
[24] The decision as to whether to notify a consent, and to whom, is
dealt with in ss 95 and 95A - 95G of the RMA.
[25] By s 95A(1) a consent authority may, in its discretion, decide whether to publicly notify an application for a resource consent for an activity. There is no statutory presumption in favour of notification,2 but s 95A(2) requires a consent authority to publicly notify the application if –
(a) it decides (under s 95D) that the activity will have or is likely to have
adverse effects on the environment that are more than
minor; or
(b) the applicant requests public notification of the applicant; or
(c) a rule or national environmental standard requires public notification of
the application.
[26] However, even if (pursuant to s 95B) a consent authority decides not to publicly notify an application for a resource consent for an activity, it must decide
(under ss 95E to 95G) whether there is any affected person, protected
customary
rights group or customary marine title group
in relation to the activity. Section 95E provides that a person is an affected
person
for the purposes of the RMA, “if the activities adverse effects on
the person are minor or more than minor (but are not less
than
minor)”.
[27] Where there is an affected person, the consent authority must give
limited notification of the application to any affected
person, unless a rule or
national environmental standard precludes limited notification of the
application.
[28] The RMA also provides that, in certain circumstances, the consent
authority is permitted to, or is required to, disregard
adverse effects on an
affected person. Relevantly, in the present case, the consent
authority:3
(a) may disregard an adverse effect of the activity on the person if a rule
or national environment standard permits an activity with
that effect.
...
Provisions relating to the substantive decision
[29] The application by GDCL was for resource consent for an activity
which was categorised as non-complying under the
Ashburton District
Plan. As a non-complying activity, the proposal had to meet one of the
thresholds set out in s 104D
of the Act.4 If s 104D is satisfied,
the consent authority then has a discretion as to whether to grant the
application or not having regard to
the criteria set out in s 104 which include,
relevantly:
(a) any actual and potential effects on the environment of allowing
the activity; and
(b) any relevant provisions of –
(i) a national environmental standard: (ii) other regulations:
(iii) a national policy statement:
(iv) a New Zealand coastal policy statement:
3 RMA s 95E(2)(a).
(v) a regional policy statement or
proposed regional policy statement;
(vi) a plan or proposed plan; and
...
(3) A consent authority must not, –
(d) grant a resource consent if the application should have been notified and
was not.
...
(6) a consent authority may decline an application for a resource
consent on the grounds that it has inadequate information
to determine the
application.
The notification decision
Did the Council make a decision on notification?
[30] The applicants argue that because Council’s delegated
decision-maker, Ms Harte, only signed the decision report,
and not the separate
report on notification, there was no decision on notification. Even if the text
of the decision is looked at
in substance, they say it can only be read as
addressing the grant of consent. The section at the end of the decision report
entitled
“Decision”, and which was signed by Ms Harte, simply
stated:
That the above recommendations be adopted for the reasons outlined in the
report.
In the recommendation section above, there is no recommendation as
to the
notification of GDCL’s application. Instead, the recommendation
section records:
That, for the above reasons:
The application be granted pursuant to ss 104, 104A/104B/104C and 108
of the Resource Management Act 1991, subject to the following
conditions:
...
[31] The applicants also say that I cannot rely on Ms Harte’s affidavit evidence to support a finding that a decision was made. She provided affidavit evidence which explains that she saw no point in signing a separate report confirming the acceptance of the planner’s recommendation on notification when “the substantive decision also
included a discussion and finding on notification, and that the subsequent
grant of consent proceeded on the basis that no notification
was
required”. She also added that, in her experience, making such a
“combined decision” on both notification
and the grant or refusal of
consent, is reasonably standard practice at other councils.
[32] In the applicant’s submission, such an explanation fell into the same category as that in Hanna v Whanganui District Council, where Williams J found it inappropriate to give any real weight to the evidence of Council officers that expanded on and explained the reasons underlying the notification and consent decisions.5 As said in Hanna, “the decision must stand or fall on its own terms as
written at the time”.6 Similarly, Wylie J in Tasti
Products Limited v Auckland
Council said, “[the decision] stands to be considered in its
terms and no amount of
ex-post facto criticism or justification can change
it”.7
[33] However, the respondents say that this is not a case where I have to
rely on explanations subsequently given. Here, it is
clear on the face of the
decision that it comprises a decision on notification. They say it is
artificial to suggest that the substantive
report signed by the Commissioner,
which includes all the content of the notification report and reaches a
conclusion on notification,
does not amount to a written record of the
decision made on notification. Furthermore, reading the content of the
substantive
decision report, it is obvious that the notification decision was
addressed in advance of the decision to grant consent, and the
decision to grant
consent relied on the conclusion that notification was not required in this
case.
[34] I agree that I do not need to resort to explanation from Ms Harte to
be satisfied that the decision report, which was adopted
by Ms Harte as her
reasons for granting consent, included a fully reasoned decision as to why
notification (whether full or limited
notification) was not required. The
relevant paragraph of the report on notification read as follows:
For the reasons given in the above discussion of effects, I consider that any
adverse effects from this proposal on the environment
would be less than minor,
and therefore, pursuant to s 95A of the Resource Management Act
5 Hanna v Whanganui District Council [2013] NZHC 1360, 17 ELRNZ 314.
6 At [14].
7 Tasti Products Limited v Auckland Council [2016] NZHC 1673 at [75].
1991 there is no need for the application to be publically notified. I also
consider there are no parties who would be affected
to an extent that would be
minor or greater for the purposes of s 95E of the Act, and therefore no reason
for limited notification
of the application to any parties... I have considered
possible effects on rural residential properties in Fords Road and along State
Highway 1 ... Therefore I consider that this application can be processed on a
non-notified basis.
[35] Furthermore, the report, also expressly acknowledged the
prohibition in s 104(3)(d) of the RMA on the grant of consent
for an
application that should have been notified and was not. Again, the report
reiterated that notification either in full or
on a limited basis was not
considered necessary because the effects would be less than minor and there
would be no adversely affected
parties. The recommendation to grant consent
which was adopted by the Commissioner is premised on the reasons given in the
document,
and includes the conclusion that notification is not
required.
[36] Given the report includes a reasoned decision which
concludes that notification is not required and averts to the
fact that consent
cannot be granted if notification should have occurred and did not, I am
satisfied that the report signed by the
Commissioner includes a decision on
notification, as well as a decision as to the grant of consent.
Did the Council take into account all relevant
considerations?
[37] If the Court finds that the Council’s decision did include a
decision on notification, the next ground of review is
that the Council did not
take into account all relevant considerations in its decision on notification.
In this regard, Mr Maw
submitted that the Council did not consider several
crucial elements of GDCL’s proposal that may have significant adverse
effects
on the Millars. In particular, the applicants consider that the
effects of activities within the storage area (which
include the storage
of aggregates and soil) were not assessed by the Council.
[38] While they say there is no doubt that GDCL’s application referred to soil being stored on site, the application was silent on the amount and the size of any stockpiles. The applicants’ expert, Mr McCallum Clark, says that, in the absence of any defined limits, GDCL could stockpile large quantities of soil and would only be limited by the size of the application site.
[39] In addition, the applicants say that the Council’s decision
did not expressly refer to the storage of soil as part
of the description of
GDCL’s activities. The Council’s decision described the activity
as follows:
This application seeks consent for the establishment and operation of a
contracting base for the storage and maintenance of general
and rural based
machinery, including office administration and workshop, fuel storage, aggregate
storage, truck wash and weighbridge
facility for Greg Donaldson Contracting
Limited.
[40] The omission of soil storage from this summary of the proposal is
taken as an indication that the effects of soil storage
were not
considered by the Council. Indeed, the applicants say the Council’s
internal planner, Mr Hyde, raised concerns
about this very issue in an email to
Mr Mountfort, where he asked whether the noise/dust assessment took into account
the storage
of material and associated uses in the storage area. Mr
Mountfort’s reply refers only to the assessment of noise from the
yard and
does not confirm that the noise and dust assessment takes into account the
effects from the storage area, whereas Mr McCallum
Clark’s evidence is
that if the storage area had a high turnover of a material then that could lead
to relatively significant
increases in noise and transportation
effects.
[41] The Council responds by saying it did have adequate information on
the soil and aggregate storage in order to determine that
the effects would be
less than minor. The key effect of soil storage that has been raised is the dust
potential, and the impact of
dust production from the activity was the subject
of expert assessment in the AEE. It was only during the construction
phase of the activity that the application stated there would be any
non-compliance with the earthworks provisions
of the District Plan.
Other than that, there is no identified non-compliance with the
plan.
[42] The respondents say, therefore, that the reporting planner and the decision- maker were clearly aware of what was to occur in the storage area and took that into account, along with the advice that aspects of these activities would be complying with the relevant plan rules. There was no error in that assessment process which would justify invalidating the decision.
[43] In my view, reading the application as a whole, it cannot be said to
permit soil storage beyond the District Plan limits.
This is because the
application expressly identified all components of the activity which were
non-complying with the plan and did
not include earthworks (including deposition
of soil) which would exceed permitted limits after the construction of the
bunds.
Mr Mountfort is therefore correct in concluding that the consent cannot
be said to allow unlimited storage constrained only by the
size of the site.
In terms of the quantity of the aggregate storage, express limits were given on
that by the applicants, so the
effects of that activity could be assessed by
reference to those limits.
[44] Having understood what was proposed, the effects of the activities
were then considered. For example, dust effects on site
during construction
were considered, and were to be mitigated by a condition. Dust effects
post-construction were also assessed.
The application identified that they
would not trigger any non-compliance with the air discharge rules in the
regional plan which
do not permit objectionable dust effects from the bulk
handling and storage of goods (including soil) beyond the boundary of a site.
The Council also accepted the expert report from Nova which recorded
that:
No other activities proposed would give rise to significant dust generation
beyond what is experienced from the current use of the
access road for trucks
and farm machinery serving the sale yards and paddocks.
The decision report concluded “due to the relatively small amount of
material in the stockpiles and prevailing winds, dust emissions
would be (sic)
have less than minor effects”. In this regard, the application differed
from the situation in Hanna, where no such reports existed to support the
position presented on adverse effects.
[45] The same adequate level of assessment occurred in relation to the assessment of noise generated by the activity, including from vehicles used for the transport of aggregate and soil stored in the storage area. The application provided quite a detailed description of traffic movements, both to and from the site, and within the site. In summary, it explained that a typical generation of up to 36 vehicle movements per day would be created for the contractor’s yard but, because most of the work would be undertaken off-site, the proposal would not “involve significant vehicle movements or staff on-site for extended periods of time”. The logical
corollary was that the proposed activity did not involve significant
movements of vehicles to the storage area for the purpose of
loading and
unloading aggregates and soil. This was reflected in the transport assessment
which discuss movement to this area as
follows:
The contractor’s yard access will also serve the rural land that forms
the southern proportion of the site. Vehicle movements
to and from that area are
considered negligible.
[46] The noise assessment reflects the transport assessment and focuses
on the noise from the contractor’s yard. Using
reference levels for heavy
machinery depots and workshops, it concludes that the main sources of noise that
would be associated with
the proposed development would be vehicle start-up and
engine revving. The noise assessment was cognisant of the need to assess
effects on adjacent neighbours, including the Millars, and concludes that even
predicting a “worst case scenario” where
noise in the yard areas
would involve large vehicles and would be sustained and continuous for an hour,
the proposal would comply
with the applicable noise standards in the District
Plan at all adjacent properties.
[47] The reporting planner, Mr Mountfort, who was fully versed
with the proposal, was prepared to accept the expert
conclusions noting, in
particular, the limited number of vehicle movements which would occur as a
consequence of the activity.
[48] Thus, while there is limited discussion of the activity to occur in
the storage area in the application and accompanying
reports, what can
occur there is constrained by the description in the consent and the proposed
number of vehicle movements.
I consider the reporting planner, and the
Commission did have regard to all relevant considerations before reaching the
conclusion
that the dust and noise effects of the activity, including from the
transport generated by it, would be less than minor.
Did the Council misapply the permitted baseline test?
[49] The next criticism of the decision on notification is that it failed to correctly apply the permitted baseline test. The “permitted baseline” test, as developed in case
law,8 allows a decision-maker to exclude from consideration,
effects which would in any event be authorised on that site, whether through
rules in a plan or a resource consent. However, the permitted baseline test has
also been qualified by excluding the use of “fanciful”
activities
for comparison, that is, activities which are technically permitted, but which
would be unlikely to occur in reality.
[50] The permitted baseline test is now expressly incorporated into the
RMA, and decision-makers considering notification have
a discretion to:
... disregard an adverse effect of the [proposed] activity on the person if a
rule or national environmental standard permits an activity
with that
effect.
[51] In the present case, the Millars are critical of the purported
application of the permitted baseline test to disregard the
effects of
GDCL’s proposal for the purposes of notification and for the grant of
consent.
[52] The relevant paragraph in the decision report discusses the
permitted baseline test as follows:
The most relevant comparable activity which could be established on the site
would be a farming activity, either grazing or cropping.
This could be
expected to include large utilitarian sheds, use a range of farm machinery on
site, generate heavy traffic movements
and create a certain amount of noise and
dust. None of this activity would be on a scale as large as that proposed, but
could take
place at any hours of the day or night. Such activities would not be
obliged to provide landscaping or screening and none of the
activities would
take place off-site. The point of this is that this area is not necessarily
always going to be a quiet peaceful
rural retreat and residents can expect a
certain amount of activity, traffic, noise, dust etc. on the site even with
fully-complying
rural activities. The effects of this proposal should be
compared with the effects of a complying rural activity, not with a zero
baseline.
[53] The Millars’ criticism of this passage is that it picks out “a smorgasbord of high impact permitted issues and amalgamate[s] them together to produce a series of unrelated effects that must be excluded from the notification decision”. Reflecting the language used by the Court when criticising the assessment in the notification decision in Hanna, they say that by doing this, the decision “decontextualises effects
producing both unrealistic comparators and results that undermine rather than
uphold
Part II of the Act”.9
[54] However, on a plain reading of the statement, the only conclusion
drawn by the planner, and thus the decision-maker, is that
effects which are
similar in nature, if not in scale, could occur as of right. More importantly,
this is not a case, as in Hanna when the comparison farming activity
is fanciful. In that case, the comparison was to a permitted large scale
dairy or
dry stock farming operation and it was considered fanciful because the
relevant area was subdivided into one and two hectare blocks
which could not
accommodate such activities. That is not the case here.
[55] In any event, when the decision is looked at as a whole, there is no
evidence that the reporting officer or the Commissioner
has completely excluded
such effects from the assessment of effects for notification. The report writer
and, ultimately, the Commissioner
making the decision, assessed each of the
relevant effects (being visual effects, transport effects, noise and dust
effects, hazardous
substances, loss of rural land and surface water management)
having regard to the moderate scale of activity, and the mitigation
proposed
(for example, landscaping and screening). The effects were all assessed to be
less than minor and there is no suggestion
that the effects were considered to
be completely negated by the application of the permitted baseline
test.
[56] I do not consider that there has been an error in the
application of the permitted baseline test. The application
for review fails
on this ground.
Was the Council’s decision on notification manifestly
unreasonable?
[57] The next ground of review is that, even if the Council made a decision on notification and took into account all relevant considerations, the decision that the adverse effects on the Millars and other neighbours were less than minor was not a decision a reasonable decision-maker would have reached on the basis of the material in front of it.
[58] The basis on which the Millars assert the
Council’s decision was
unreasonable include:
(a) the sheer scale and scope of GDCL’s proposed activity,
unconstrained by conditions of consent and the proximity of
those activities to
neighbours;
(b) the fact the activity is a non-complying activity in a rural zone;
and
(c) GDCL’s application concluded the adverse of the activity were
likely
to be minor.
[59] I do not consider the second ground has any bearing on the issue.
The test for notification makes no distinction
between discretionary
and non-complying activities. It is a test with a low threshold that applies
to both categories of activity.
[60] The first and third grounds are connected and relate to
whether it was reasonable to assess the activity as having
effects which are
less than minor. I will therefore consider them together.
[61] The Millars place particular weight on the High Court’s
decision in Hanna, where the Court found that the Council’s
decision not to notify the neighbours of a non-complying resource consent
application
to develop a small scale heavy machinery depot in a rural zone was
unlawful and unreasonable. In that case, Williams J
held:10
After all, the standard for limited notification is not that high. A minor
impact is enough. It does not take much of a leap of
imagination to conclude
that sighting 7-8 pieces of heavy equipment on land adjacent to a residence with
a view to regularly transporting
such equipment to and from the site, could at
least have a minor impact on the adjacent residence.
[62] In this case, I accept that the application itself was inconsistent in its explanation of the test for notification and therefore of whether that threshold had been met. At one point it stated that “no persons [would] experience adverse effects that are minor or more than minor as a result of this activity”, but a paragraph further
on, referred to the effects on any person being “minor or no more than
minor”. If the latter was correct then, of course,
limited notification
would have been required on such persons.
[63] In addition, the Millars’ expert witness for this
hearing records his professional opinion that the effects
on the neighbours
would have been at least minor, saying:
In my opinion, there is considerable potential for minor or more than minor
effects on the adjoining or nearby properties from noise,
traffic movements,
visual effects, and dust.
However, equally, the two experienced planners involved in the
application, Mr Mountfort and Ms Harte, both reach the view
that the effects
will be less than minor
[64] In my view, the fact the application itself described the effects as
minor at some points, is not determinative. The Council
must make its own
assessment independently of the applicant and it can not be criticised for
that.
[65] Furthermore, it is unclear why the person preparing the GDCL
application concluded that the effects would be minor for the
purposes of
notification when the expert reports relied on did not share that view and
consistently concluded that the effects would
be less than minor. For
instance, the noise assessment, assuming a “worst case scenario of vehicle
engines running for the
whole hour rather than just the period when they are
entering or exiting the site or warming up or warming down”, concluded
that any potential noise effects of the operation of the facility on other
properties would be less than minor. Equally, any effects
associated with dust
from the proposed development were concluded to be less than minor and would
comply with the District Plan “at
all locations beyond the property
boundary”. The traffic report also considered that “the proposed
development can be
supported from a traffic and transport perspective as having
less than minor effects”.
[66] Thus, although the application itself wrongly refers to the test for avoiding notification having been met because the adverse effects will be minor or no more than minor, it is clear that the more detailed assessment of those effects included in
the application reached the more stringent conclusion required to avoid
notification, which is that the effects on any other person
would be less than
minor.
[67] To the extent that the applicants’ expert witness, Mr McCallum
Clark, draws the conclusion that the effects would be
minor or more than minor I
consider those were based on erroneous assumptions. Mr McCallum
Clark’s concerns appear
focussed not on the application as described,
but on the potential for expansion of the activity given the generous size of
the site,
and it is that which gives rise to his conclusion that there is the
“potential” for minor or more than minor effects
on the adjoining
properties.
[68] It is clear that Mr McCallum Clark largely concurs with the
assessment of Mr Mountfort and Ms Harte if the activity was limited
to what was
proposed to occur in the application. He says:
In my opinion, if the application site was smaller in scale, such that the
described activities were commensurate with the site area
and the buildings to
be constructed, or there were appropriate conditions limiting the activities to
those described in a general
way, then it may have been appropriate to process
this application on a non-notified basis and possibly without the need for the
written approval of the neighbours, given the separation distance of the
core activities.
[69] Thus, Mr McCallum Clark’s conclusion that GDCL’s
neighbours may experience minor or more than minor effects is
based on GDCL
being able to increase the scale of the activity occurring on the site without
further recourse to the Council or
the neighbours. He assumes that, as long as
the activity falls within the general description of what is proposed (that is,
use
of the site for a contractor’s yard and storage of materials), the
only constraint on GDCL’s expansion is the physical
size of the
site.
[70] I am satisfied that that reasoning is fallacious. It does not take into account that the activity is limited by the scope of the application, and by the condition imposed which requires the activity to proceed “in accordance with the information and plans submitted with the application”, all of which are specifically referenced in that condition.
[71] It is a well established legal principle that the scope of the activity is confined by the terms of the application and a consent can not grant more than was applied for.11 Here the application had a comprehensive description of the proposed activity, including number of staff, size of building, average vehicle movements per day and maximum amount of aggregate to be stored. The report, which was adopted by the Commissioner as the reason for her decision, made it clear that the scope of the activity outlined in the application was crucial to her understanding of the application and its effects. By imposing the condition which required the
development to proceed in accordance with the information and plans submitted
with the application the Commission made that limitation
explicit, and provided
a clearer mechanism for enforcement of it.
[72] There may well be room for debate about the desirability of
reflecting limitations contained in an application in more specific
conditions,
for example, by imposing conditions as to the number of staff to be employed or
specifying the maximum number of vehicle
movements, as clearly that
makes enforcement a simpler task than by relying on a generic condition such
as the one imposed.
However, it is not appropriate on an application for review
to explore the merits of the conditions imposed, as long as the decision
maker
has not omitted to consider the need for conditions, or erred in law when
imposing them.
[73] Thus, I do not accept the Millars’ expert evidence that the
effects would be minor or more than minor when that assumes
the resource consent
permits unconstrained expansion of the activity on the site. The fact that
even he acknowledges that the proposal,
on its present terms, would likely have
effects that are less than minor, reinforces the reasonableness of the decision
made.
[74] Given my conclusions that the report writer and the independent Commissioner did not err on the other issues raised, I do not consider that their conclusion that the effects would be less than minor on the neighbouring properties
can be considered unreasonable.
11 Sutton v Moule (1992) 2 NZRMA 41, Clevedon Protection Society Inc. v Warren Fowler Ltd
[1997] NZEnvC 152; (1997) 3 ELRNZ 169.
Did the Council wrongly conflate the statutory test required for the
notification decision and for the substantive decision?
[75] The next ground of review alleges that the Council erred
in law by “conflating the separate statutory tests
relating to the
notification and the grant of consent” and by “considering its
notification decision and the substantive
decision as one
decision”.
[76] I have already concluded that it is clear from the face of the
document, which was endorsed as Council’s decision,
that a decision was
made as to notification in advance of the decision on the grant of consent.
Furthermore, it was clear that the
decision-maker was aware she could not go on
to grant consent if the decision should have been notified but was
not.
[77] That leaves the issue of whether the Council erred, in the section
of the report labelled “effects on the environment”,
by combining
the assessment of effects in relation to both notification and the substantive
grant of consent. The gist of this
argument is that consideration of adverse
effects on the environment for the purpose of the grant of consent is not the
same as the
more fine-grained test of whether there are any persons who would be
affected to an extent that would be minor or greater for the
purposes of s
95E.
[78] I accept those are different tests. For example, it may be possible
to conclude that a development would have an effect
on the environment which is
less than minor when viewed as a whole, but one neighbour’s outlook may be
adversely affected in
a minor way, thus requiring limited notification on that
neighbour.
[79] However, again, it is important to look at the detail of the decision. The effects of the proposal are assessed both in a general sense and also having regard to the properties in closest proximity. Indeed, it is a striking feature of the decision that the reporting planner and the decision-maker were aware of the Millars’ concerns and took particular care to assess the application in light of the effects on them. It is clear that the Council assessed the effects in light of the test which triggers the need for notification, in addition to undertaking a wider assessment of the effects on the environment which was relied on for the grant of consent.
[80] For this reason, I consider the Council did not conflate the
notification and substantive decision and there was no error
on this
account.
Challenge to the substantive decision granting consent
Was the grant of consent invalid because there had been no notification
decision?
[81] Given my findings above, which include that there was a
notification decision which was reached applying the appropriate
legal test and
having regard to the relevant considerations, I do not need to consider whether
the grant of consent was invalid because
there was no notification
decision.
Did the Council take into account all relevant
considerations?
[82] If a decision was made on notification, the Millars then say that
the decision granting consent failed to take into account
all relevant
considerations, because it did not consider:
(a) the effects of the storage of soil as part of GDCL’s operations;
and
(b) the effects of storage of aggregates and soil and associated
activities within the storage area; and
(c) did not consider the scheduled activity standards for the Ryal Bush
Transport site when GDCL had suggested that some
of those standards
could form appropriate conditions of consent.
[83] I have already considered the first two of these criticisms and have
rejected them. Properly read, I have held the application
did not seek the
right to store soil in excess of the District Plan limits and so the effects of
that permitted activity could have
been discounted by applying the statutory
permitted baseline test. In any event, in relation to the notification
decision, the effects
of aggregate and soil storage (being visual, dust and
noise effects) were all taken into account as discussed above.
[84] The third consideration raised under this head is that the application included a reference to the provisions in the District Plan for scheduled activities at the nearby
Ryal Bush Transport Limited site in Tinwald, which was a transport activity occurring on a rural A zoned site. The application noted that, while there were a number of standards applying to Ryal Bush that would not be relevant to the GDCL proposal,12 other aspects of the standards that applied to Ryal Bush could be considered and imposed as conditions of consent for this proposal. The Millars are critical of the fact that the Council did not make direct reference to the Ryal Bush
Transport standards in its decision, nor did it incorporate them into
conditions.
[85] In my view, this cannot be an error of law. The decision-maker must
consider the effects of the activity on the environment
and decide what
conditions, if any, should be imposed on the consent if granted, to mitigate
those effects. That is a question
of judgment. It is not for the Court, on
judicial review, to second guess the decision-maker’s judgment on that
issue. The
mere failure to adopt a suggested source of material for the
drafting of conditions cannot be considered a failure to avert to a
relevant
consideration. The relevant consideration in this case is whether conditions
should be imposed to control the effects
of the activity on the
environment. The decision-maker averted to that consideration and imposed a
range of conditions. To
go further than that is to embark on a merit-based
review of the decision which is not appropriate on an application for
review.
[86] For these reasons, I reject this ground of review.
Relief
[87] As I have found in favour of the respondents on all grounds of the
application for review, I do not need to go on to consider
the exercise of the
discretion as to whether to grant relief.
[88] However, I accept that where a claimant demonstrates that a public decision-maker has erred in the exercise of power, there must be “extremely strong reasons” for declining relief.13 However, had I found in the Millars’ favour solely on
the basis of accepting their expert evidence that unlimited soil storage
could occur on
12 This is because Ryal Bush was predominantly a stock truck transport firm which required very early morning truck movements and significant heavy vehicle washing, which was not the case with GDCL’s application.
13 Independent Fisheries Ltd v Minister of Earthquake Recovery [2012] NZHC 1810 at [186].
site and that it was not constrained by the fact the application did not seek
to store a non-complying amount of soil on the property,
then the fact that GDCL
has subsequently (for the avoidance of doubt) relinquished any entitlement to
store soil in excess of the
District Plan limits would have been relevant to the
exercise of my discretion.
[89] However, nothing else raised by the parties would have displaced the
usual position that the decision should be set aside
if it was made in error and
the process commenced from scratch.
Result
[90] The application for review of the Council’s decision on
notification and grant of the GDCL consent for a resource consent
for a
contractor ’s yard is rejected and I decline to make any of the orders
sought.
[91] If costs cannot be agreed as between the parties, they may file
memoranda as follows:
(a) within 20 working days of receipt of the decision by the
respondents;
and
(b) within 10 working days of receipt of the respondents’ memoranda,
by
the applicants.
Solicitors:
Wynn Williams, Christchurch
Cavell Leitch, Christchurch
Malcolm Wallace, Barrister, Christchurch
Tavendale and Partners, Christchurch
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/3015.html