Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 21 December 2016
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV-2015-409-000530 [2016] NZHC 3105
BETWEEN
|
THE SOUTHERN RESPONSE
UNRESOLVED CLAIMS GROUP Plaintiff
|
AND
|
SOUTHERN RESPONSE EARTHQUAKE SERVICES LIMITED Defendant
|
Hearing:
|
19 October 2016
Joint Memorandum from Counsel for the Parties - Received 11 November
2016
|
Appearances:
|
F Cooke QC and M Smith for Plaintiffs
M OʼBrien QC, D J Friar and N F Moffatt for Defendant
|
Judgment:
|
16 December 2016
|
JUDGMENT OF GENDALL
J
SOUTHERN RESPONSE UNRESOLVED CLAIMS GROUP v SOUTHERN RESPONSE EARTHQUAKE SERVICES LIMITED [2016] NZHC 3105 [16 December 2016]
Table of Contents
Para No
Introduction
|
[1]
|
Background
|
[6]
|
Mander J decision on the plaintiffs’ first r 4.24
application
|
[8]
|
The test for leave to bring a representative action
|
[16]
|
The present application
|
[22]
|
A comparison of significant relevant differences between the first
amended
statement of claim and the original statement of claim
|
[32]
|
Discussion
|
[38]
|
Conclusion on the leave application
|
[62]
|
Litigation funding arrangement
|
[66]
|
Misleading communications
|
[78]
|
Unreasonable remuneration
|
[83]
|
CCFA issues – a credit contract?
|
[88]
|
Conclusion on litigation funding arrangement
|
[92]
|
Other orders sought
|
[93]
|
“Opt-in” direction
|
[94]
|
Discovery
|
[96]
|
Result
|
[101]
|
Costs
|
[109]
|
Introduction
[1] The plaintiffs are a group currently comprising 41 residential
homeowners all insured through the defendant company
(Southern Response)
whose insurance claims arising out of the sequence of Canterbury earthquakes
commencing in September 2010
have not as yet been resolved. The plaintiffs seek
leave to bring this proceeding as a representative action under r 4.24 of the
High Court Rules together with certain associated orders.
[2] This is the plaintiffs’ second application for leave to bring
this proceeding as a representative action.
[3] On 24 February 2016 Mander J in this Court declined the plaintiffs’ first application, (the first decision) essentially ruling that the plaintiffs had failed to meet the threshold requirements for a representative proceeding and that the “just, speedy and efficient determination” objectives of the High Court Rules would not be achieved by allowing the application before him.1 In doing so Mander J ruled that the plaintiffs’ pleadings failed to identify any substantial issue of significance that was common to the representatives. In giving his overall ruling, Mander J however specifically allowed the plaintiffs to bring a modified application to obtain representative action status by re-casting their claim to meet the concerns expressed
in his judgment. On 27 May 2016 the plaintiffs filed a first amended
statement of claim which they say does just that. It is that
first amended
statement of claim which is the subject of the present leave
application.
[4] It is the plaintiffs' contention that this first amended statement of claim meets the deficiencies identified by Mander J in the first decision in that it identifies the issues or claims common to all members of the group which provide a “spine” for this proceeding, and mean that it is appropriately the subject of a representative action. The defendant however disputes this. It contends that this renewed application is simply a re-run of the application which was the subject of the first decision, and it should be acknowledged as such and rejected. Southern Response
says that still no real common interest has been identified by the
plaintiffs here, the
1 Southern Response Unresolved Claims Group v Southern Response Earthquake Services Ltd
[2016] NZHC 245 at [92].
proposed representative action would not resolve the individual insurance
claims of each of the group claimants but will just add
further delay and, in
any event, no real worthwhile remedy for those claimants can arise in light of
their major insurance loss claims
being “parked”.
[5] In passing, at this point I note that the plaintiffs have also lodged an appeal against the first decision to the Court of Appeal and this has a fixture allocated for 7
March 2017. Notwithstanding this, the plaintiffs argue that in this first
amended statement of claim they have properly reformulated
their claims to meet
the requirements enunciated by Mander J in the first decision. It is noted
obviously that if the renewed application
which is before me is successful, then
that appeal to the Court of Appeal may become moot.
Background
[6] By way of initial background in this matter it is useful to set out
here the facts identified by Mander J in the first decision
at paras [3] –
[7] to “set the scene” that prevailed at the time the first leave
application was before this Court:
[3] Some five years have elapsed since the first of the Canterbury
earthquakes on 4 September 2010. The houses of the Group’s
members were
insured under the same or substantially similar policies of insurance with
Southern Response on a full reinstatement
basis. Their insurance claims remain
unsettled. It is the Group’s position that Southern Response has failed to
discharge
its obligations to them under the insurance policy, and the
intervention of the Court is required to have their claims resolved.
Each claim
has been the subject of a long period of delay, and there remain significant
disputes between Southern Response and the
policyholders.
[4] The Group seeks to bring the proceedings as a representative
action on the basis they share common disputed issues concerning
the
interpretation and application of the policy which require determination by the
Court. It is envisaged that at a later stage
in the proceeding a process will be
put in place for resolving the individual claims based on the resolution
achieved in
relation to those generic issues. Several members of the Group have
filed affidavits in support of the application which detail
the history
of their claims and their involvement with Southern Response.
[5] A prime reason put forward in support of the representative action is that none of the members of the Group individually would be able to afford to bring separate proceedings against Southern Response to resolve their individual claims. The Group, however, has obtained the services of a litigation funder, Litigation Lending Services (New Zealand) (“LLS (NZ)”) to fund a representative action. Each member has signed a litigation funding agreement with LLS (NZ).
[6] Southern Response is an entity established for the singular
purpose of settling claims by policyholders of the insurance
company, AMI, as a
result of damage caused by the Canterbury earthquakes. Following the
second major earthquake on 22 February
2011, AMI considered it did not have
sufficient reserve funds and reinsurance to cover its liability. Following an
approach by AMI,
the Crown agreed to provide a capital injection of $500 million
pursuant to the terms of a Crown support deed. This resulted in a
restructuring
of AMI. Its ongoing day-to-day insurance business was sold and its liability
arising from the Canterbury earthquakes
transferred to a Crown owned company,
Southern Response.
[7] Southern Response became responsible for some 7,626 claims where
the amount exceeded the Earthquake Commission (EQC) cap
of $100,000 (plus GST).
Of these overcap claims, 6,684 claims have been settled, although claims
are still being passed
to Southern Response from EQC, albeit at a reduced rate
in recent times. The 46 claimants with an interest in the present proceeding
are
part of a group numbering some 2,587 whose claims have not been resolved with
Southern Response.
[7] Since February 2016 when Mander J gave the first decision, the plaintiffs’ group has changed slightly. As I understand it, two of the original claimants have settled with Southern Response and the Group’s numbers have now been brought down to 41 (from the original 47). The plaintiffs at the hearing of this matter before me advised they had also nominated a second representative, Mr Kelvin Raymond Yeadon, to join Mr Cameron Preston and Ms Wendy Preston as a representative of the class. Then, as recently as 12 December 2016, counsel for the plaintiffs has filed in this Court a memorandum indicating that Mr and Mrs Preston have now resolved their insurance claim with the defendant. As a result, Mr and Mrs Preston have withdrawn from the present proceeding and are no longer group members. But counsel advise the parties agree this withdrawal does not necessitate the filing of a further amended statement of claim at this point. The present r 4.24 leave application is to continue with Mr Yeadon as the sole representative of the plaintiff group, although I do note also that in a memorandum dated and received by the Court only yesterday, 15 December 2016, counsel for Southern Response advises that settlement and resolution of the claims of several of the other group claimants are likely shortly. It seems also that the plaintiffs again propose a class consisting of Group members and all other policy holders who have not settled with Southern Response and who wish to join the proceeding.
Mander J decision on the plaintiffs’ first r 4.24
application
[8] In the first decision Mander J summarised the plaintiffs’
claim which had been outlined in their original statement
of claim filed 26
August 2015 as follows:
(a) First, that Southern Response had allegedly misrepresented
the options which were available to each of the plaintiffs
under their AMI
policies (given that Southern Response had effectively taken over those
claims from AMI).
(b) Secondly, Southern Response had allegedly applied
additional conditions to the individual claims that were not
consistent with the
insurance policy terms.
(c) Thirdly, Southern Response allegedly applied conditions in relation
to self managed rebuilds that were not consistent with
the insurance policies
and as a result significantly reduced its obligations under those
policies.
(d) Fourthly, Southern Response allegedly systematically understated
the cost of a rebuild or repair, in a number of ways, including
the fact that
demolition, design and administration fees were excluded, by employing
inadequate foundation repair techniques, using
discounted market rates and
undertaking inadequate property inspections.
[9] Mander J noted that the plaintiffs had pleaded two causes of action in their original claim. The first was for breach of “substantive promises” in the policy. The plaintiffs alleged that this was a breach of essential terms of the policy allowing them to reserve their right to cancel. They also sought payment of the amount of each plaintiff member’s insurance claim. This was said to be particularised for each member in the schedule of claims attached to the statement of claim. The schedule, however, simply said that for each member “the true value of the insurance claim cannot be determined” until further work is done.
[10] The second cause of action noted by Mander J claimed against
Southern Response for an intentional breach of “process
rights”
including good faith and the rights set out in the policy requiring prompt,
professional and fair handling of all claims.
The plaintiffs sought general
damages arising from this alleged breach.
[11] In giving his judgment on 24 February 2016 Mander J identified a
number of “deficiencies” in the plaintiffs’
claim and declined
their application for leave to bring a representative action. As I have noted
above, to summarise his findings,
Mander J ruled that the pleadings in the
plaintiffs’ original statement of claim failed to identify any substantial
issue of
significance that was common to the representatives and each proposed
plaintiff class member and that would materially advance the
resolution of each
plaintiff’s claim. Mander J also indicated he was not satisfied that the
proposed representative action
procedure would serve the objects of the High
Court Rules in terms of the just, speedy and efficient determination of
claims.
[12] These rulings however, were specifically in Mander J’s words
“without prejudice to any modified application based
on a reformulation of
the proposed proceeding which meets the concerns expressed in [this]
judgment”. Clearly it was envisaged
that the plaintiffs might seek to
reformulate their claims, as Mander J noted at [90] of his judgment, by
identifying “a number
of groups or sub-groups of members who share the
common substantial issue of significance to each member and would warrant the
making
of not one but a number of representative orders”.
[13] The plaintiffs contend here that this is precisely what they have
done with their first amended statement of claim, but Southern
Response disputes
this.
[14] At this point it is important to note that what is before me is not an appeal. It is an entirely new application under r 4.24. Significantly too, under r 7.52 of the High Court Rules a party who fails on an interlocutory application (as the plaintiffs have done here with Mander J’s first decision) may not apply again for the same or a similar order without first obtaining leave, which may only be granted in “special circumstances”. This rule is consistent with the principles of res judicata and issue estoppel, namely an issue decided by an interlocutory ruling is not to be relitigated in the same proceeding. Here, Mander J gave leave to bring this second r 4.24
application, but only to the extent that it would “meet[s] the concerns
expressed in this judgment”. The plaintiffs were
not otherwise entitled
in effect to have a second go.
[15] Southern Response has filed an opposition to this second
application. Southern Response says the plaintiffs have
not met the deficiencies
and concerns identified in the first decision. They have not identified
subgroups of members with common
interests in particular issues as anticipated
by Mander J’s decision. Instead, they have done little more than change
the
order in which their allegations appear, simply “reformatting”
their claim. The amended claim is substantially the same
as the original
claim.
The test for leave to bring a representative action
[16] Rule 4.24 of the High Court Rules addresses this issue and
provides:
4.24 Persons having same interest
One or more persons may sue or be sued on behalf of, or for the benefit of,
all persons with the same interest in the subject matter
of a proceeding
–
(a) with the consent of the other persons of the other persons who have the
same interest; or
(b) as directed by the Court on an application made by a party or
intending party to the proceeding.
[17] The general approach when applying r 4.24 was outlined recently by
the
Supreme Court in Credit Suisse Private Equity LLC v
Houghton.2
[18] The issue to be decided in Credit Suisse was whether the limitation period ceased to run for all represented parties from when the original statement of claim was filed, or only from when a member joined the representative action. The Court divided on that question, with the majority saying that the limitation period ceased running for all members when the original statement of claim was filed, even for
those who joined later (with Elias CJ and Anderson J
dissenting).
2 Credit Suisse Private Equity LLC v Houghton [2014] NZSC 37; [2014] 1 NZLR 541.
[19] In the course of both the majority and minority judgments
the Court addressed the requirements for obtaining leave
to bring a claim as a
representative action. There was no disagreement between them on that
question. This was referred
to in McGechan on Procedure at HR4.24.01 where
the learned authors stated:
HR4.24.01 A liberal approach
The courts take a liberal approach to representative proceedings. This
approach is consistent with the objective outlined in r 1.2
(securing the just,
speedy and inexpensive determination of the proceeding) and the policy
underlying r 4.1 (which limits the number
of persons named or joined as parties
to those whose presence is necessary or who ought to be bound by the
judgment).
In Credit Suisse Private Equity LLC v Houghton [2014] NZSC 37, [2014]
1 NZLR 541, the Supreme Court considered r 4.24 in the context of limitation of
actions. The following propositions may be
extracted from the majority decision
delivered by Glazebrook J:
(a) The principal purpose of a representative proceeding is the
promotion of efficiency and economy of litigation. The
whole point of
having a representative proceeding is to avoid clogging the courts with a
multiplicity of individual proceedings covering
the same subject matter, which
would undermine the efficiency and economy of litigation: at [147] and
[158].
(b) Flexibility in how r 4.24 is applied accords with the modern
approach to representative proceedings, and the rule should
be applied to ensure
that the overall objective of the High Court Rules as outlined in r 1.2 is
achieved: at [129]–[130].
(c) Where injustice can be avoided, the rules should be applied to
promote the expedition and economy of proceedings: at [151].
(d) The approach of McGechan J in the earlier decision of R J
Flowers Ltd v Burns [1986] NZHC 243; [1987] 1 NZLR 260 (HC) accords with the objectives
of the High Court Rules and the goal of representative proceedings, but it
should
not be treated as the last word on the matter. As long as
defendants are not compromised and the aims underlying representative
proceedings are advanced, there is scope for continual development in this area:
at [152].
So long as the representative proceeding is not allowed to work injustice, it is now well established that r 4.24 should be applied liberally and developed to meet modern requirements: see R J Flowers Ltd v Burns (above) at 271 per McGechan J and Taspac Oysters Ltd v James Hardie & Co Pty Ltd [1988] NZHC 545; [1990] 1 NZLR 442, (1988) 2 PRNZ 621 (HC) at 447, 626 per Barker J.
[20] McGechan on Procedure went on at HR4.24.04 to outline the
principles involved in granting or refusing permission to
bring a representative
action in this way:
HR4.24.04 Principles governing the grant (or refusal) of permission to
bring a representative proceeding
The general principles by which a court determines under r 4.24 whether to permit a representative party to sue or be sued on behalf of others with the same interest may be distilled from the judgment of the Court of Appeal in Saunders v Houghton [2009] NZCA 610, [2010] 3 NZLR 331, (2009)
[2009] NZCA 610; 20 PRNZ 215 at [10]–[14] and [42]:
(a) A representative action may be brought where each member of the
class is alleged to have a separate cause of action, provided
three requirements
are met:
(i) The representation order may not confer a right of action on the
member of the class represented who could not have asserted
that right in
separate proceedings. Nor may the order bar a defence that might have been
available to the defendant in separate
proceedings.
(ii) There must be an interest shared in common by all members of the
group.
(iii) It must be for the benefit of other members of the class that the
plaintiff is permitted to sue in a representative capacity.
(b) The phrase “persons with the same interest” is to be
read more or less widely, and a relatively low threshold
is preferred as
consistent with the objective in r 1.2 of securing the “just, speedy, and
inexpensive determination”
of the proceeding. However, a higher threshold
may be appropriate where the representative proceeding is brought pursuant to a
funding
arrangement.
(c) Having “the same interest” in the subject matter of
the proceeding does not necessarily mean having the same
cause of action or an
entitlement to have or share the same relief.
(d) Careful consideration of the defendant’s position is
required. An application for a representation order may
fail if the
representative proceeding would leave an element of the defence
unaddressed.
(e) A representative proceeding for damages is not foreclosed. If the
conditions for a representative proceeding are otherwise
met, the proceeding may
claim a declaration of liability. Individual claims to establish individual
damage may then follow.
(f) The more likely that the issues to be determined in the proposed representative proceeding would resolve most or much of the dispute for the persons being represented, the more likely a court would be minded to grant a representation order.
[21] Mander J properly noted too in the present proceeding, at para [9]
of the first decision, that the identification by the
Courts of a sufficient
common interest has been seen in a number of cases to require a relatively low
threshold – Strathboss Kiwifruit Ltd v Attorney-General,3
Saunders v Houghton4 citing R J Flowers Ltd v
Burns.5
The present application
[22] Turning to the present application, Mr Cooke QC suggests this
proceeding has been properly “reformulated”,
and noted one
matter first. This was his suggestion that, in the original application
for leave rejected by Mander J, considerable
emphasis was placed on one
particular aspect. This was the idea that this was an unusual representative
action because the plaintiff
applicants were essentially asking the Court to
assist them to seek a resolution of their insurance claims, claims which had
remained
unresolved at that point for over five years. In doing so, Mr Cooke
recognised that, in this Court’s administration of what
has been described
as the “Earthquake List”, the Court has said that it would endeavour
to proactively assist parties
to have their insurance claims resolved. He
referred in this regard also to observations made by His Honour Miller J in 2014
(he
being the High Court Judge in the early period in charge of the Earthquake
List) in a paper he delivered to the New Zealand Insurance
Law Association
Conference 2014 entitled “Reflections on the Earthquake Litigation”
where he remarked:
We [the High Court in the Earthquake List] hope that we would see class
actions”
and:
The Courts recognise that class actions are sometimes needed if a large
group of people sharing the same interest are to secure access
to
justice.
[23] And, in his submissions to me Mr Cooke emphasised that the main focus of the plaintiffs’ initial leave application before Mander J was the fact that their
individual insurance claims had not been resolved and the intervention
of the Court
3 Strathboss Kiwifruit Ltd v Attorney-General [2015] NZHC 1596 at [6].
4 Saunders v Houghton (No 2) [2012] NZCA 545.
5 R J Flowers Ltd v Burns [1986] NZHC 243; [1987] 1 NZLR 260 (HC).
was required in order to achieve some individual resolutions. The plaintiff
contends now that in this first amended statement of
claim they have
reformulated their claim such that this is not simply the case. Mr Cooke
insists the claim now meets the requirements
Mander J set out in his
decision.
[24] In saying this, Mr Cooke explains the plaintiff in this amended
pleading has reformatted a common litigation claim shared
by all members of the
group rather than focusing on their individual insurance claims. He maintains
the reformulated litigation
claim provides the common interest or
“spine” here. It is the claim that Southern Response has engaged
in a strategy
to improperly minimise its overall financial exposure arising out
of the Canterbury earthquake claims. This has been pleaded as
a clear
“strategy”. The plaintiffs contend there are a number of elements
to that “strategy”, the key of
which are said to be:
(a) Southern Response has asserted that it is in control of the
undertaking of all required rebuilding and repair work under
the parties’
insurance policy rather than the homeowner claimants. It does so by having its
partner Arrow International (Arrow)
managing all such work. The plaintiffs say
Southern Response was not entitled to take this stance.
(b) Southern Response has said that there were necessary delays
involved in having such reinstatement or repair work undertaken
and that
plaintiff policyholders would simply need to wait their turn for the work
managed by Arrow to be done. As a consequence,
a number of years have gone by
with all policyholders simply waiting.
(c) The cost of undertaking that work has been disclosed to the
plaintiff claimants in the form of Detailed Repair/Rebuild Analyses
(DRAs)
prepared by Arrow which grossly understate the true cost of undertaking the
required work to the standard set by the policy.
(d) Southern Response has stated it would only cash settle with individual policy claimants at amounts significantly discounted from the DRA figures within the policy, but it has indicated it was prepared to
negotiate “without prejudice” and “out of policy”
responses on a cash
basis, thereby inducing lower financial settlements.
[25] The plaintiff claimants say that, as a result, this strategy
improperly reduces Southern Response’s true policy liability
at the
expense of the individual claimants. In this respect, Mr Cooke suggested that
Southern Response is in a different position
from other insurance companies
dealing with Canterbury earthquake claims. This is because Southern Response is
no longer in business
issuing new insurance policy cover. Its only business
involves settling and paying out on AMI’s Canterbury earthquake claims.
As a result, it is suggested Southern Response had no incentive to maintain a
business relationship with its policyholders or to
attract any new
policyholders and, with no reputation to protect, its only incentive was to
minimise its exposure involved in relation
to Canterbury earthquake claims.
Therefore the claim is made that thereby Southern Response has been incentivised
to adopt the
strategy which the plaintiffs challenge here.
[26] The common interest which Mr Cooke contends is now pleaded
in the amended statement of claim is broadly that
Southern Response engaged
in this deliberate “strategy”, designed to deceive policyholders
and delay claims, with a
view to reducing the proper financial liability that
Southern Response might have had to all its policyholders.
[27] The details of this “strategy”, as I have noted,
involve what Mr Cooke describes as the “litigation
claim”. It is
this which gives the central or common issue which he maintains justifies the
present r 4.24 representative
claim. Linked to, but separate from, this
“litigation claim” is what I have noted Mr Cooke describes as the
individual
“insurance claims” of each of the plaintiff
policyholders. These are the insurance claims which each of the 41
plaintiff claimants have for specific earthquake damage caused to their
individual homes.
[28] The plaintiffs contend the adoption of the “strategy” is in breach of Southern Response’s obligations under the policy and its obligation of good faith as insurer. And, the plaintiffs say their pleaded claim for relief has also been changed to reflect the emphasis they now place on these allegations.
[29] On all these issues, before me Mr Cooke noted one further matter.
This was his suggestion that this whole question of deception
and delay, which
forms the basis of the “litigation claim” here, is now very much out
in the public and media arena.
Therefore, he suggests a strong argument exists
that it is in everyone’s interests, including all the plaintiff claimants,
other Southern Response policyholders and, indeed Southern Response itself, to
have this matter properly ventilated and determined
before the Court. It is
argued this is perhaps a further reason why the representative action sought in
the plaintiffs amended leave
application should be approved and
proceed.
[30] In opposition, Mr O’Brien QC for Southern Response contended
that the present leave application was in effect a simple
re-run of the earlier
application rejected by Mander J in the first decision.
[31] In this area, a comparison between the plaintiffs’ original
statement of claim and their first amended statement of
claim, and an
identification of the differences relating to the plaintiffs’
“strategy” alleged against Southern
Response (said to provide
the particular common interest of these parties), is useful here.
Comparison of significant relevant differences between the first amended
statement of claim and the original statement of claim
[32] The first amended statement of claim at paras 3, 4, 5.1, 5.2 and 6.1
makes a new reference to the four relevant AMI Insurance
policies in existence
for house properties at the time of the Canterbury earthquakes. These were
“Premier House, Market Value
House, Premier Rental and Market Value
Rental”. Specific terms from the “Premier Rental” policy were
added in
cl 5.2, 6.2 and 8.2.
[33] Next, in section “C” at page 4 of the original statement of claim the plaintiff had referred to “Southern Response’s Approach” and, at paras 28, 29, 55.3 and 55.5 of that statement of claim, set out additional matters. These pleadings provided:
9. Each of the claimants suffered damage to their homes covered by
the policy as a consequence of the Canterbury earthquake
sequence between
September 2010 and 23 December 2011.
10. Each of the claimants made claims under the policy. Particulars of
the claims made by the claimants will be provided in
a schedule of claims to be
filed herein.
...
28. The approach of Southern Response as described in paras 11 –
27 above, was to significantly reduce its obligations
under the policy by it
assuming control of the contemplated repairs and rebuilds and including for the
reasons referred to in paras
29 – 46 below.
29. In addition, Southern Response has adopted further policies
in respect of the DRAs which systematically understate
the true assessment of
cost of the rebuild/repair required by the policy, and which accordingly further
misrepresented the claimant’s
entitlement. Particulars of those policies
are provided in paras 30 – 46 below.
...
55.3 There has been a systemic underestimate of the payment to be made,
and a failure to comply with the policy requirements as
referred to in paras 11
– 46 above, leading to delays caused by the existence of disputes.
...
55.5 Southern Response did not have effective procedures to allow it to
assess whether the claimant was over the EQC cap, or for
dealing with EQC in
that context.
[34] In the plaintiffs’ first amended statement of claim the
equivalent section “C” at page 6 is headed “Southern
Response’s Strategy”. It repeats as paras 10 and 11 what is noted
at para [33] above as original paras 9 and 10 generally
as follows:
10. Each of the claimants suffered damage to their homes covered by the
policy as a consequence of the Canterbury earthquake
sequence between September
2010 and 23 December 2011.
11. Each of the claimants made claims under the policy. Particulars
of the claims made by the claimants are provided in the
schedule of claims
previously filed.
[35] The first amended statement of claim however goes on to amplify at
paras
12 – 18.3 inclusive what are said to be new worded pleadings. In particular, the plaintiffs say paras 12, 13 and 14 set out the key new elements of their reformatted claim:
12. At a date or time unknown to the claimants, but prior to Southern
Response responding to any of the claimants’ claims
Southern Response
adopted a strategy which was designed to systematically reduce the cost of
meeting the claims arising out of the
Canterbury earthquakes below its true
liability (the “strategy”).
13. The strategy was applied by Southern Response to all claimants and
involved:
13.1 Misrepresenting the nature of Southern Response’s
obligations and the claimants’ rights as particularised
below.
13.2 Understating the extent of the work required and the cost of
undertaking that work as particularised below.
13.3 Asserting that the claimants’ rights to receive a cash
settlement of their claims were for amounts significantly
below the assessed
cost of undertaking the work in question as particularised below.
13.4 Assuming control of the rebuilding and repair work so that Southern
Response could minimise the cost to it of the required
work as particularised
below.
13.5 Unreasonably delaying in responding to and meeting the claims
of the claimants as particularised below.
13.6 Adopting various other stances designed to reduce its
liabilities as particularised below.
13.7 Inducing “settlements” of the claims made against it for
significantly reduced amounts and through undertaking
substandard repair work
through the implementation of the strategy.
14. Southern Response adopted the approach summarised above in the
knowledge and/or with the intention of reducing its liability
to persons who
could not afford to hire a lawyer, and who without a lawyer would not have the
ability, including through not
having access to all documents required (such
as the unredacted DRAs that are only supplied through requests under the Privacy
Act
1993 that a lawyer knows to make), to promptly realise their full
entitlements under the policy without a need for legal assistance.
15. Each of the claimants’ claims have been addressed by
Southern Response in accordance with the strategy and
Southern Response has
failed to provide the claimants with their entitlements in a fundamental way as
a consequence.
(C1) Overcap policy
16. In accordance with the strategy, Southern Response has taken no steps to assess a claim made on it unless and until the claim has been assessed as “overcap” by EQC.
17. This aspect of the strategy has been applied notwithstanding
that:
17.1 Claims were made by the claimants when there had been earthquake
damage to their homes.
17.2 A claim was payable by EQC when there was earthquake damage to the
home.
17.3 EQC was systematically failing to properly and promptly address the
extent of such claims to the knowledge of Southern Response.
17.4 Southern Response took no steps to assess the claim to be
potentially met by it even when EQC accepted the claimant legitimately
had a
claim for earthquake damage.
17.5 In some cases Southern Response realised that it was likely that the
claim would exceed the amount payable by EQC, but it
still took those
steps.
18. Southern Response’s approach in this respect was in breach of the
policy which required Southern Response:
18.1 To assess whether there was a claim against it, and the extent of
that claim, whenever the house had been damaged by earthquake,
or
alternatively whenever it was assessed by EQC that a claim was
“payable” by EQC.
18.2 To deal with that claim professionally, efficiently, and as quickly
as circumstances allowed; and
18.3 To pay the difference between the amount payable by EQC, and any sum
insured, irrespective of whether it had been assessed
as overcap by EQC.
19. As part of the strategy, once it was accepted that a
claim was overcap, each of the claimants received a letter
in which Southern
Response purported to identify the nature of the cover, and what the
claimant’s rights were. The letters
included a Decision Pack which
required the claimants to elect one of the options described by Southern
Response when Southern Response
assessed that the house was damaged beyond
repair.
[36] In addition, extra paragraphs were added and certain amendments made to
existing paragraphs of the plaintiffs’ pleading
as follows:
24.2 The advice referred to above misrepresented the terms of the Policy
by:
...
24.2 asserting that the assessment of the cost of undertaking the required work was to be undertaken by Southern Response, which it was
doing in the DRAs, without advising of the claimants’ right to have an
assessment undertaken themselves for the purpose of their
claims.
...
24.4 asserting that the cash payment contemplated by cl 1 civ was based
on a depreciated replacement cost calculation on the basis
described (with that
amount based on the DRA figure with a further significant deduction for
depreciation) rather than the
market value of the house, which would mean
that any cash option was always represented as significantly less than the
rebuild
cost assessment.
...
26. In cases of both rebuilds and repairs, Southern Response advised
that there was a queue of claimants awaiting the availability
of the contractors
who would be needed for the repair or rebuild work, so that the claimants would
need to wait their turn.
...
(C6) Control of Builders and Contractors
34. As part of the strategy, Southern Response advised that the builder
for the rebuild or repair was to be determined by Arrow
on Southern
Response’s behalf. The claimant was advised that there could be an
objection to the proposed builder so chosen
by Arrow, but that in call cases the
builder needed to be accepted by Southern Response. Southern Response also
advised that
some engineering reports would not be accepted. Southern
Response had no right under the policy to so control the identity of
the
builder, or other contractors.
...
(C7) Systemic Underestimation of Work
38. Southern Response limited the briefs to persons instructed
to undertake inspections such that the inspections did
not:
...
38.4 in relation to foundations, required the assessment to be
made using DBH/MBIE guidelines that do not necessarily
achieve an “as
new” condition.
...
(C9) Deliberate Redaction of Costs
45. As part of the Strategy and in breach of its obligations, Southern Response have deliberately withheld disclosing the assessment of its calculation of the demolition, design and administration costs in dealing with the claimants, including by redacting the assessment of these costs from the internal DRAs in the version of the DRAs provided to the claimants.
...
(C11) Failure to allow for necessary project management.
50. In accordance with standard industry practice, in order to rebuild
or repair the damage to a home of the type contemplated
by the claimants’
claims involves:
50.1 The instruction of a project manager, usually an architect, who is
responsible for the overall co-ordination of the
project; and
50.2 The project manager then co-ordinating the instruction of the other
experts required to assess and quantify the cost of the
damage, and to plan the
work required to repair or rebuild the house, (including experts such as
geotechnical engineers, structural
engineers, surveyors, builders, and quantity
surveyors.)
51. The procedure described above was required to be followed
by Southern Response in order to satisfy the requirement
that the claim be
acknowledged and dealt with in a professional and efficient manner.
52. The costs of such experts are a necessary cost involved in
repairing or rebuilding the house to the standard contemplated
by the policy,
and are accordingly recoverable under the policy.
53. In breach of the requirements of the policy, and in accordance with
the strategy, Southern Response:
53.1 Will only permit the piecemeal instruction of individual
experts solely to assess the question of the damage caused
by the earthquakes
within that expert’s expertise.
53.2 Fully controls the instruction of such experts;
53.3 Does not permit the instruction of a project manager to co- ordinate
the project; and
53.4 Will not allow the costs of co-ordinated project management and
expert assistance to be included within the claims.
...
D Impact of strategy
...
59. When decisions of the Courts have demonstrated that Southern Response’s approach has been inconsistent with the rights of those who had made claims, Southern Response had adapted its strategy prospectively only and;
59.1 It has not altered what it has paid to those who were induced to
settle as a consequence of its earlier unlawful stance;
and
59.2 It has not offered any compensation for the consequence of its
previous conduct which was in breach of its obligations on
the basis there has
been no loss arising.
60. The strategy has successfully been deployed by Southern Response by
causing and inducing:
60.1 Those who have made claims to enter full and final
settlement agreements well below the true value of the insurance
claim;
and
60.2 Repairs to insured homes to be undertaken at a substandard
level.
61. As a consequence of the strategy, Southern Response has derived
substantial profit at the expense of those who have made
claims upon
it.
[37] Finally, in the prayer for relief in the amended statement of claim,
additional remedies are now sought as follows:
...
(D) General damages of $25,000 for each claimant reflecting the
damages to be paid as a consequence of the existence
of the Strategy.
(E) General damages of $15,000 for each claimant for each year that
satisfaction of the claimant’s claims has been delayed
as a consequence of
the Strategy.
(F) Costs on a solicitor/client basis.
Discussion
[38] In responding to the plaintiffs’ argument that there are
significant differences in the first amended statement of
claim, Mr
O’Brien for Southern Response contends that the so-called
“strategy” outlined in the plaintiffs’
pleading is really
nothing more than what was described in the 26 August 2015 statement of claim as
Southern Response’s “approach”.
He contends, as I note above
that:
(a) The use of this new claimed “strategy” does not identify or
provide
any common interest to justify the representative action sought;
(b) None of this will in any event resolve the insurance claims
with Southern Response affecting these 41 plaintiff
claimants, but it will
simply add a further delay; and
(c) In any event, no worthwhile remedy for these individual
plaintiff complainants can arise if leave to bring this matter
as a
representative action is granted, in light of what is said to be the simple
“parking” of their major individual
insurance loss claims with
Southern Response.
[39] Southern Response goes on to suggest that the present application is
in effect a simple re-run of the earlier application
rejected by Mander J. It
maintains the so- called “strategy” referred to in the amended
statement of claim is simply
a label applied by the plaintiff to a raft of what
are said to be unrelated allegations which can really only be determined on an
individual basis. It is suggested that at most, a resolution of the various
“strategy” allegations will only deal with
part of the various
plaintiffs’ general damages claims against Southern Response. It
will delay resolution of those
individual claims.
[40] Further, it argues the rejection by Mander J of the alleged
“approach” adopted by Southern Response here as a
sufficient common
issue is not in any way altered by changing this label to use the word
“strategy” for what are said
to be essentially the same
claims.
[41] Lastly, Southern Response argues that the plaintiffs’ proposed
common issue here will not serve the objectives of just,
speedy and effective
determination of their customers overall insurance claims.
[42] Although there might be seen to be some merit in certain of these contentions advanced by Southern Response, overall at this point I need to say that, I disagree with the general position put forward on its behalf. As I see it, the emphasis of the plaintiffs’ revised r 4.24 application before me differed to a reasonable degree from that put forward before Mander J in the original application. Furthermore, the amended statement of claim in its reformatted form in my view went somewhat further in material respects from that advanced before Mander J.
[43] The use in the first amended statement of claim of the words
“Southern Response’s Strategy” in place of
the words
“Southern Response’s Approach” in the original statement of
claim is no doubt deliberate, and at one
level it may be seen as not entirely
insignificant. The Chambers Dictionary6 definition of the word
“Strategy” includes:
The art of conducting a campaign (and manoeuvring an army); any long term
plan; artifice or finesse generally.
Further, the definition goes on to define “strategic position” as
“a position that gives
its holder a decisive advantage”.
[44] This needs to be contrasted however, with the dictionary definition of
“Approach”. In the Chambers Dictionary,7
“Approach” is defined relevantly here to include:
...attitude towards, way of dealing with...
[45] Further, the “Strategy” alleged by the plaintiff in the
first amended statement of claim is considerably amplified
at para 13.5 to 18.3
of the first amended statement of claim. Some of these allegations involve
elements which might be seen
as involving newly pleaded complaints from
those outlined in the original statement of claim. The tone, too, that these
matters
might comprise a “campaign” or “long term plan”
which may well involve some degree of “artifice”
additionally might
be seen as new matters which could be of some concern if ultimately they are
proved to be established.
[46] In giving the first decision Mander J recognised too that the plaintiffs could re-cast or reformat their claim in amended pleadings to establish this central common issue. In my view, but perhaps only by a rather fine margin, they have done sufficient here to establish this. This “spine” of the general damages claim, of an improper Strategy adopted by Southern Response to avoid its proper obligations to policy claimants, arguably constitutes a proper litigation claim as described by
Mr Cooke for the plaintiff.
6 Chambers Dictionary (11th ed)
[47] It is not proper at this stage for any view to be expressed over the
range of allegations advanced by the plaintiff in support
of this
“strategy” contention. There is enough, as I see it, in the
strongly contested material which is before the
Court at this early point for
these matters to proceed to trial. In my judgment it is in the interests of
all parties, including
Southern Response, that these issues are properly
addressed.
[48] Matters such as the exclusion at one point from Southern
Response’s provided DRAs of amounts for demolition
costs, design fees,
contingencies or administrative costs, (no doubt to be met with some
explanation involving subsequent
changes in the approach taken) may well
require some consideration. Similarly, issues over self-managed rebuilds,
overall project
management issues, standards of work undertaken, control of
rebuilds and repairs, cash payment options and the alleged
“strategy”
of Southern Response on each of these will be matters for
further consideration. No views at this early point can be expressed
even on a
preliminary basis concerning any of these matters. They do provide,
although perhaps on a reasonably tenuous
basis, what is said to be the common
thread for the claims from the individual plaintiffs comprising this group. It
could transpire
too that these might possibly be addressed here as a preliminary
question. Then, individual claims from each of the 41 group plaintiffs
which
of necessity will relate to the particular circumstances of each home, could be
case managed and addressed as part of the Earthquake
List process in this
Court.
[49] Turning again to Mr O’Brien’s submissions for Southern Response here, in terms of the common interest requirement in r 4.24, he contends the plaintiffs’ claims are significantly different to the types of claims in other recent cases in this country where leave has been given to bring a representative action. In this regard, the
Feltex litigation in Saunders v Houghton8 involved
the determination of an issue
fundamental to all claims, namely whether statements and omissions in a prospectus had been made negligently or in breach of statutory duties.
[50] In the kiwifruit litigation, in Strathboss Kiwifruit Ltd v
Attorney-General9 the representative action centred on whether
duties of care were owed by the Crown to kiwifruit growers in the discharge of
its functions
and responsibilities to maintain New Zealand’s
bio-security.
[51] And in the bank fees litigation in Cooper v
ANZ10 the representative proceeding concerned common types of
fees charged to bank customers under the common terms of their
accounts.
[52] Thus, it is clear from these cases, as Mander J noted at [73] of the
first decision, that in each case “the prime
essential issue of
liability was readily identified as being one that was common to each member
of the group”, determination
of the common issue would
“substantially advance the resolution of the litigation and the individual
claim of each member”
and the “Court’s ruling on the common
issue was an essential prerequisite to any of the members of the group
succeeding
in the litigation”.
[53] In the first decision Mr O’Brien noted that Mander J contrasted the matters noted above with the plaintiffs’ claims before him in the initial statement of claim, which he said were “clearly distinct from the circumstances of other cases where leave has been granted under the rule”. In saying this, Mander J observed that the plaintiffs’ claim “includes a raft of allegations” from which he was unable to “discern prime issues of liability in respect of which the Group’s membership can be
aligned”.11
[54] In my view, however, the situation which is before the Court as outlined in the plaintiffs’ amended statement of claim is somewhat different. Southern Response essentially argues that in substance all the plaintiffs have done in their amended claim is to change the label from “Southern Response’s approach” to
“Southern Response’s strategy” relating to their
various complaints. I disagree.
9 Above n 3.
10 Cooper v ANZ [2013] NZHC 2827.
11 Above n 1, at [75].
[55] As I note at para [43] above, the use of the word
“strategy” may well provide some significant additional
implication when the Southern Response claims processes are being
considered.
[56] Further, clearly in the amended statement of claim at paras 12, 13
and 14 (as noted at para [35] above), the plaintiffs’
complaints
over actions taken by Southern Response under the “strategy” have
been widened and more particularly
identified. As best I can tell, new
allegations as to the application of the “strategy” in this amended
pleading include
the following:
(a) “Unreasonably delaying in responding to and meeting the
claims of the claimants as particularised below.”
(b) “Adopting various other stances designed to reduce its
liabilities as particularised below.”
(c) “Inducing “settlements” of the claims made
against it for significantly reduced amounts and through undertaking
substandard
repair work through the implementation of the strategy.”
(d) “...[unrepresented claimants] not having access to all
documents required [such as the unredacted DRAs that
are only supplied under
requests under the Privacy Act 1993 that a lawyer knows to make] to promptly
realise their full entitlements
under the policy without a need for legal
assistance.”
(e) Various other matters concerning Southern Response’s
over cap policy outlined in paras 16, 17 and 18 of the
amended statement of
claim.
[57] These additional pleadings emphasise the new importance placed by the plaintiffs on their targeting of Southern Response’s “strategy”. The impact of that strategy it is alleged assisted Southern Response but detrimentally affected the plaintiffs, in ways outlined at paras 59-64 of the amended statement of claim. Again
these are new pleadings not before Mander J when he considered the
plaintiffs’
original statement of claim.
[58] In general terms, the plaintiffs claim that Southern
Response’s co-ordinated approach exemplified in its “strategy”
here by way of example, of redacting costs in DRAs provided to claimants,
gaining control of the entire rebuild at costs even below
those estimated by
expert quantity surveying evidence, was all designed to reduce Southern
Response’s proper financial exposure
to its policyholders. The
plaintiffs say this provides the “spine” of an issue common to all
the Group members without
exception. I am satisfied these matters, if
substantiated at trial (perhaps as I note by way of a preliminary separate
question),
might well constitute a breach of Southern Response’s express
obligations under each policy held by the plaintiff claimants.
In this regard,
I note in passing Southern Response’s acknowledgment too at page 7 of the
Premier House Cover Policy in these
terms:
2. Your Rights
(a) You (the claimant) are entitled to:
(i) Have your claim acknowledged and dealt with in a professional and
efficient manner; and
(ii) Receive a fair settlement of your claim as quickly as circumstances
allow; and
(iii) Receive a clear explanation why any claim has not been met.
[59] As I understand it, there is a similar term too on page
8 of Southern Response’s Premier Rental Property
Cover Policy also in
use here. The plaintiffs say, as I understand it, that Southern Response had
an obligation of good faith as
insurer and the adoption of the alleged
“strategy” is a breach of that obligation. The claim for relief in
the amended
statement of claim pleaded by the applicants has been changed, it is
said, to reflect the emphasis the plaintiffs now place on these
allegations. In
particular, as I note at [37] above in the first amended statement of claim the
plaintiffs now seek:
(a) General damages of $25,000 for each claimant as a consequence of the existence of the strategy.
(b) A new requirement for general damages of $15,000 for each claimant
for each year that satisfaction of the claimant’s
claim has been delayed
as a consequence of this strategy.
(c) Costs are also sought in the amended statement of claim on a
solicitor/client basis which, for completeness I simply note,
was not a
specified form of relief in the original statement of claim.
[60] As I understand it, the reduced general damages claim of $25,000 for
each claimant in the original statement of claim was
not the primary thrust of
the claim and was not emphasised before Mander J in the original leave
application before him.
[61] In the amended statement of claim the first cause of action remains
a claim in damages by each of the individual claimants
for the amount of their
substantive insurance policy claim. I accept that is inevitable. This is
because the insurance claim
for each claimant has not been met and it is alleged
generally it has been delayed as a consequence of the existence and operation
of
what is now pleaded as the “strategy”. Moreover, in the first cause
of action each of the plaintiff claimants reserve
their right to cancel their
individual policy for fundamental breach as a consequence of the existence and
operation of the “strategy”.
I accept here too that it is the very
existence of the “strategy” which is the subject of the common
interest claim
shared by each of the individual plaintiff Group members
here.
Conclusion on the leave application
[62] In conclusion, I find but perhaps only by a reasonably fine margin here, that the plaintiffs’ pleadings have been satisfactorily reframed in their first amended statement of claim to meet the concerns expressed by Mander J in the first decision. I say this bearing in mind the comments of the Supreme Court in the Credit Suisse case where Courts were encouraged when considering the growing number of cases which might be the subject of representative actions to take a more liberal, flexible and not too technical approach. Those general comments in the Supreme Court, in particular from the Chief Justice, suggested that once there was some degree of common interest in the subject of a proceeding to satisfy r 4.24 then, all the rest is
essentially “case management”. And, in terms of process, I am
satisfied in the present case that there could be a separate
question or
questions posed for the Court in terms of the representative action to determine
first and then each separate claim from
individual claimants of which there are
presently about 41 could be addressed separately. Again, these subsequent
claims would
be the subject of proper case management under the current
Earthquake List.
[63] I accept that the common interest pleaded by the plaintiffs now that
Southern Response engaged in a deliberate “strategy”
designed to
deceive policyholders and delay claims with a view to reducing the financial
liability that Southern Response might have
to its policyholders is a proper one
for a r 4.24 representative action. I accept too that the substituted
representative plaintiff
Mr Yeadon in all the circumstances here is an
appropriate representative of the plaintiffs’ group. And, on this aspect,
as
I have mentioned above, this whole question of alleged deception and delay it
appears is out in the public arena now. A reasonable
argument exits, as I see
it that it is in everyone’s interests, including the plaintiffs’
group, other parties, and indeed
Southern Response, to have this matter properly
ventilated and determined before the Court. This is perhaps a further reason
why
the present representative action should proceed.
[64] I note too that, in my view, adopting the words of the Chief Justice
in the
Credit Suisse decision:
No injustice arises in the present case if the individual aspects
of [the present] claims are brought on a representative
basis [and] are
addressed distinctly in the course of the same proceeding.
[65] Lastly, it is clear that representative actions under r 4.24 High Court Rules are a continually developing area to meet modern requirements. Given that these actions, like others, must always secure the just, speedy and inexpensive determination of proceedings, I am satisfied that the leave sought by the plaintiffs in their present amended application should be given. An order to this effect is to follow.
Litigation funding arrangement
[66] Southern Response maintains that this Court should not grant leave
for the representative action sought by the plaintiffs
in this case in light of
the funding arrangements they have made.
[67] In the first decision Mander J said that, given his finding, the plaintiffs had not been able to allege a sufficient common issue, he did not need to “come to any detailed or concluded view regarding the Group’s proposed funding arrangements”. Instead Mander J said that “if the Group is to renew its application, the arrangements
can be further reviewed”.12
[68] In turning to consider those funding arrangements I note that the
evidential record at the time of the first hearing has
been supplemented
by an additional affidavit from Mr Preston served shortly before the
hearing of this matter. In
addition, a second affidavit of Mr Rose has
been provided. This contains a complete copy of the publicly accessible parts
of the
Class Action website.
[69] In his first decision at [96] Mander J observed:
...Approval of the funder and the funding arrangement was viewed by the Court
of Appeal [in Saunders v Houghton] as one part of a package of orders
relevant to consideration of the initial [r 4.24] representation
issue...
Indeed the Court of Appeal called this one of the “essential
legs” for making a representative order – Saunders v
Houghton.13 It is also true that in three significant recent
representative action proceedings before this Court, approval was sought of the
funder
and the funding agreement.
[70] Although there is some suggestion here from the plaintiffs that approval of the funding arrangements by the Court in this case is unnecessary, I proceed on the basis this is not the case. These matters are properly before the Court for approval
here.
12 Above n 1 at [106]-[107].
13 Above n 4 at [38].
[71] In undertaking this consideration I note that the present
application has been brought on an “opt-in” basis.
All claimants
who belong to the plaintiff group are persons of full age and capacity and it is
noted they have decided that it is
in their interests to enter into the
litigation funding arrangements which have been arranged for the plaintiff
group. Also, as I
understand the position, no present members of that group, as
directly affected parties, have raised any “problems”
with the
present litigation funding arrangements through the Court or
otherwise.
[72] McGechan on Procedure at para HR4.24.16 addresses this situation of
a representative proceeding facilitated by a litigation
funder and makes the
following comments:
HR4.24.16 Representative proceeding facilitated by a litigation
funder
Where a representative proceeding is being facilitated by a litigation
funder, it is usual for the court to review and approve the
litigation funding
arrangements as a safeguard for the defendants and to ensure that there is no
abuse of process.
In Saunders v Houghton [2009] NZCA 610, [2010] 3 NZLR 331, (2009) 20
PRNZ 215, the Court of Appeal discussed in general terms (at [21]–[34])
when a court may grant
a representation order involving a particular funder.
Where there is a representative proceeding involving a funder, the Court
considered (at [38]) that the judge managing the proceeding should
consider as a “total package” (a) the terms
of the representation
order; (b) whether the funder and the funding arrangement should be approved;
(c) whether security for costs
should be granted; and (d) a provisional
appraisal of the merits (to ensure that those being represented have an arguable
case).
See also French J’s discussion in Houghton v Saunders [2011] NZHC 542; (2011)
20 PRNZ 509 (HC) at [74]–[75].
The Court of Appeal also recognised at [36] that the making of a representation order along with the admission of a litigation funder so substantially alters the balance between plaintiffs and defendants as to justify ordering security for costs under the inherent jurisdiction, even though the represented persons include numerous natural persons (against whom security for costs cannot be ordered under r 5.45 where they are resident in New Zealand). In Strathboss Kiwifruit Ltd v Attorney-General [2015] NZHC
1596, Dobson J recognised at [79] that the “evolving practice”
was for the funder of a funded representative proceeding
to provide security for
costs, which tended to be quantified on a “relatively generous”
basis in favour of defendants.
[73] I now proceed to consider the plaintiffs’ litigation funding
arrangements here
in light of the matters outlined above.
[74] Here Southern Response’s criticisms of, and challenge
to, the plaintiffs’
funding arrangements focus generally on three matters:
(a) First, it alleges that certain communications were made to members
of the plaintiff group in advance of them signing the
Litigation Funding
Agreement (LFA) which were misleading;
(b) Secondly, the remuneration payable to the funder and its
lawyers under the LFA is said be unfair and unreasonable;
and
(c) Finally, no existing claimant received “the required
disclosure” under the Credit Contracts and Consumer Finance
Act 2003 (the
CCCFA), the LFA it is claimed being a contract subject to this Act.
[75] Before turning to consider these matters, it needs to be noted that
Southern Response has not, in any submissions advanced
before me, raised any
concerns about the financial standing and repute of the litigation funding
organisation as a funder in this
proceeding. That funder, Litigation Lending
Services Limited (LLS) was established in Australia in 1999 and since that time
has
provided litigation funding both in Australia and New Zealand. I
understand this has been for 178 claims for commercial and corporate
disputes,
insolvency cases and class actions. LLS (NZ) is a wholly owned subsidiary of LLS
and between them I am told they have provided
funding for five representative
actions (including funding for the current bank fees representative action in
New Zealand) including
the present claims. And, as to that financial standing
issue, indeed LLS has agreed to provide security for costs for the first stage
of this proceeding totalling $155,000. A direction to this effect is to
follow.
[76] Also here, Southern Response has made no suggestion that the funding
arrangements give LLS as the funder an impermissible
amount of control over the
course of this litigation.
[77] With these matters in mind I turn now to consider Southern
Response’s
criticisms of the LFA outlined above.
Misleading communications
[78] Three allegedly misleading statements are identified in the
opposition filed in this matter by Southern Response. Southern
Response says
that the Court should be particularly concerned to ensure that proposed class
members of the plaintiff group are not
misled into joining any representative
action on the basis of misleading or inaccurate claims.
[79] In this area there are three main criticisms advanced by Southern
Response:
(a) The website used to advertise this class action it is said
repeatedly claims that “there is nothing to lose by joining”
this
action, “there is no downside to joining”, that members will be
“no worse off” and that “you pay
nothing if the case is not
successful”. Southern Response maintains these statements are misleading
and convey the impression
that members will not lose any of their existing
entitlement if they enter into the funding arrangements, which it says it not
the
case. Fees and payment to LLS would, of course, be deducted.
(b) The notional material, it is said, repeatedly stated that the
proposed representative action has “very high
prospects of
success”. Southern Response says this is not a balanced assessment
as, in particular, any litigation
carries risk and some is significant. It
says that no realistic assessment of the practicalities and risks of
the present
action have been given to group members.
(c) Southern Response says that plaintiff group members have been mislead so far as the subject matter of the funding arrangements are concerned. They say group members have been led to believe the present action was one only about delay and that they would only be giving up a share of any general damages resulting from the delay claim (rather than giving up a share of their existing insurance entitlements).
[80] Mr Cooke in response for the plaintiffs maintained that these
criticisms were all without substance. He suggested too that
all members of the
plaintiff group made their own individual decisions and, indeed, over 450 people
accessed the Southern Response
Class Action website before those who decided to
join the group made their decision to do so. They, along with all other
claimants,
it is noted, were provided by the LFA with a 14 day “cooling
off” period in which to reflect on and withdraw from the
funding
arrangements if they wished to do so.
[81] What appears clear is that two original members of the
plaintiffs’ group, the Kinghams and Ms Taylor, have now withdrawn
from the
group. Mr Cooke notes that Mr Kingham’s own evidence on that aspect is
that he failed to properly read the material
available to him in relation to the
LFA.
[82] On this issue of allegedly inaccurate communications having been provided to plaintiff group members, I am satisfied, but only by a small margin, that technically, group members may have been, to a limited extent, misled by some of the statements made on the Southern Response Class Action website and elsewhere in material provided. As I have noted, these comments may have contributed to minor misunderstanding on the part of members who have joined the plaintiff group. In my judgment this is able to be remedied by way of a further explanatory letter/memorandum (the terms of which are to be first approved by the Court) provided to existing and any future members of the plaintiffs’ group, giving a further
21 day “cooling off” period to extract themselves from the LFA if
required. In my view this will remedy any possible
complaint as to those
parties being misled by material provided to them to date. A direction relating
to this aspect is to follow.
Unreasonable remuneration
[83] Southern Response’s next complaint about the LFA concerns the remuneration that is provided for in those arrangements. In a second affidavit filed in this proceeding by Mr Stewart Price from LLS, he explains that the remuneration required accords with industry norms and is, if anything, more generous to the claimants as funded parties than the usual terms available on this general litigation funding market.
[84] On this:
(a) As Mr Price explains in his affidavit, LLS here has not charged a
full percentage of entire recovery which is within the
normal range for
litigation funding of 20-30% but, rather, has charged only 10-15%. This is a
less expensive amount because here
Southern Response has admitted that it is
liable to each of the individual plaintiffs to a point in the sense that it has
accepted
there is an insurance claim to be paid out, although it disputes the
amount and settlement terms.
(b) Secondly, LLS and the complainants have had to deal with
the additional difficulty here of identifying when the
litigation can be
regarded as having succeeded in circumstances where Southern Response accepts it
has an obligation to claimants
and owes to them an amount in terms of their
individual policy. This, it seems, has led to the “no worse off”
promise
made by LLS reflecting the fact that its litigation funding success fee
arises only once the claimant recovers more than the DRA
that was in existence
at the time that this funded litigation became known. It is said that seemed a
fair way to deal with the situation
which is inherently problematic when trying
to identify the appropriate success fee obligation. I agree.
[85] As I understand it, Southern Response here has filed no evidence
raising what it says are the “normal” litigation
funding cost
arrangements, nor has it in any real way criticised the evidence before the
Court of Mr Price.
[86] And in a recent New Zealand decision, PricewaterhouseCoopers v
Walker14 a fee said to represent up to 42.5% of net proceeds was
approved by the Court of Appeal. At para [31] of that decision the Court of
Appeal said:
[31] ... we are not prepared to draw the inference that SPF will be paid
too much, relative to its investment in the litigation.
It simply is not
possible to say so without knowing what will be recovered and what will be paid
to recover it...
14 PricewaterhouseCoopers v Walker [2016] NZCA 338.
[87] I conclude that the suggestion from Southern Response
that LLS’s
remuneration is unreasonable is not supported by any material before
me.
CCFA issues – a credit contract?
[88] The final issue that Southern Response identifies is a problem with
the LFA is an allegation that the documentation in this
arrangement is subject
to the CCCFA and that disclosure statutory requirements under this Act have not
been met.
[89] But before me, in his submissions Mr O’Brien for Southern
Response acknowledged that although he says the LFA appears
to be a Consumer
Credit Contract under the CCCFA, the Court at this point does not need to
finally determine whether that Act does
apply to the funding agreement. That is
a matter which, if it arises at all, will be dealt with by negotiations and
proceedings
between LLS and the individual plaintiff group members.
[90] I do note at this point that cl 9.1 of the LFA provides
that each group members grants the funder a first charge
and purchase money
security interest over his or her claim and, in addition, cl 9.2 provides that,
if settlement of the claim involves
a repair or a rebuild rather than a cash
payment, the group member agrees to execute a mortgage in favour of the funder
over the
property. Disclosure issues are raised by Southern Response and Mr
O’Brien contends that the Court here should be entitled
to consider
whether the material provided to potential participants falls short of meeting
LFA’s disclosure obligations set
out in the CCCFA.
[91] Here, issues concerning the CCCFA do not need to be definitively
resolved at this point. If that Act applies in this case
its significance, as I
see it, is that it gives plaintiff group members an additional right so far as
their relationship with the
funder is concerned. I need take that matter no
further at this point.
Conclusion on litigation funding arrangement
[92] For all the reasons outlined above, I reach the following conclusions on the proposed litigation funding arrangement.
(a) The fee charged in all the circumstances here is a fair and
reasonable one.
(b) The funding arrangement can be properly approved on the basis that
the explanatory letter/memorandum outlined at [ ] above
is provided to all
existing and future plaintiff group members in terms approved by this Court, and
giving the 21 day “cooling
off” period noted.
(c) No issues at this point arise regarding the CCFA or disclosure
issues to Group members.
Other orders sought
[93] The plaintiffs here seek other orders as part of their present r
4.24 application. These are:
(a) an “opt-in” direction requiring that there be a period of
three months
for further claimants to opt-in to the representative action;
(b) a discovery direction that Southern Response within 28 days provide
the names and contact details of all unresolved Southern
Response claimants
(which I understand to be something in the region of 11,093
claimants).
I turn now to consider each of these additional matters.
“Opt-in” direction
[94] The plaintiffs seek an opt-in period of three months’ duration
which they say should operate from the time the solicitors
for the plaintiff
group are able to communicate with the unresolved Southern Response
claimants.
[95] In my view an opt-in direction is appropriate here. It is usual in leave applications of this type. There was generally no opposition to such a direction being made. This direction is to follow.
Discovery
[96] A formal application by the plaintiffs for discovery of the names and addresses of Southern Response unresolved claimants was filed around 4 December
2015. It remains undetermined, however, given that Mander J in the first
decision did not make the representation action order sought.
[97] As grounds for the discovery order sought, the plaintiffs
say:
(a) Each claimant should be given a reasonable opportunity to decide
whether they wish to join this representative action,
given the
potential implication the case has for each person.
(b) Direct communication to a potential claimant is preferable here
rather than simply public advertising or comment as to the
existence of the
representative action.
(c) Southern Response has the names and contact details of all
the possible new claimants and is itself able to communicate
with
them.
(d) Discovery orders are the more efficient and effective means by
which such communication can occur.
[98] In bringing this application the plaintiffs rely on rr 8.12 and 1.12
of the High Court and refer to observations of the Supreme
Court in the
Credit Suisse case about the flexibility and need for efficiency with
representative actions. Also in Houghton v Saunders French J declined an
application that a defendant itself notify potential claimants of the
representative action but referred to the
need for that defendant to co-operate
with informing them of it. The plaintiffs say the present order sought has been
structured
in a manner that is appropriate bearing in mind these
comments.
[99] Although little argument was advanced to me on behalf of Southern Response regarding this discovery issue, a concern may well arise over any requirement imposed upon it to disclose a list of names and identifying details of other unresolved Southern Response claimants. That information of Southern
Response or AMI customers may well be seen as confidential
with that confidentiality being able to be waived
only by the individual
policyholders in each case. If the discovery order sought by the plaintiffs
here is granted, to comply with
the order that confidentiality would immediately
be breached. Individual policyholders would also receive an unsolicited
communication
directly from the plaintiffs or their advisors which might well
prove to be unwelcome and intrusive. It is my view that the result
sought to be
achieved by the plaintiffs could be achieved in this case by a simple public
advertising campaign through general media
and website sources. The target
group involved relate solely to Christchurch and Canterbury earthquake affected
property owners
and this campaign could be short-lived and significantly
directed. It would avoid the need for any possible wholesale breach of
confidentiality obligations held by Southern Response here.
[100] For all these reasons, I reject the discovery application advanced
by the plaintiffs. In place of this, a possible advertising
campaign can be
brought by the plaintiffs to identify other possible members to join the
Group.
Result
[101] For the reasons I have given, I grant the plaintiffs’
application for leave to bring these proceedings as a representative
action
pursuant to r 4.24 of the High Court Rules and I approve the terms for the
litigation funder LLS to fund this proceeding as
presented to this
Court.
[102] I direct that within 20 working days of the date of this judgment the
plaintiffs are to provide to the Court for approval
a draft of the terms of the
explanatory letter/memorandum referred to at [82] above, (intended to be
forwarded to existing group
members of the plaintiffs and to any further
intended group members to provide an appropriately qualified explanation of the
representative
action and the funding arrangements for this litigation to meet
the concerns expressed in this judgment).
[103] I direct that the opt-in period (during which any additional claimants are to confirm that they are opting-in to these proceedings) is to end on 16 April 2017.
[104] The plaintiffs’ litigation funder within 30 working days of
this judgment is to provide security for costs on an initial
basis in the sum of
$150,000 in a manner approved by the Registrar of this Court. Additional
security for costs awards are to be
considered and, if appropriate, ordered as
this proceeding progresses.
[105] Counsel for the parties are directed to confer and agree the scope of
common issues to be determined as a first stage of the
representative proceeding
and to file a memorandum when this is confirmed. If agreement cannot be reached
or there are any other
matters arising, counsel may approach the Registrar to
seek an appropriate directions telephone conference.
[106] I direct that Southern Response is to file and serve its statement of
defence to
the plaintiffs’ amended statement of claim within 20 working days of
today.
[107] I direct the Registrar to liaise with counsel and list this matter
for a further case management telephone conference at the
first available and
convenient date after 15 February 2017.
[108] The plaintiffs’ discovery application before me, as noted
above, fails and is
dismissed.
Costs
[109] As to costs, these are reserved at this point. In the event that
counsel are unable to agree on the issue of costs between
themselves then they
may file memoranda (sequentially) which are to be referred to me and in the
absence of either party indicating
they wish to be heard on the matter I will
decide the question of costs based upon the material then before the
Court.
...................................................
Gendall J
Solicitors:
GCA Lawyers, Christchurch
Belly Gully, Auckland
Copy to
Mr Cooke QC, Wellington
Mr O’Brien QC, Wellington
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/3105.html