Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 8 March 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2014-404-1293 [2016] NZHC 352
BETWEEN
|
ALARM NEW ZEALAND LIMITED
Applicant
|
AND
|
15 HOPETOUN LIMITED Respondent
|
Hearing:
|
3 March 2016 (by telephone)
|
Appearances:
|
B M Stainton for Applicant
R Butler for Respondent
|
Judgment:
|
4 March 2016
|
JUDGMENT OF WHATA J
This judgment was delivered by Justice Whata on
4 March 2016 at 11.00 a.m., pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Date:
Solicitors:
Stainton Chellew,
Auckland
ALARM NEW ZEALAND LIMITED v 15 HOPETOUN LIMITED [2016] NZHC 352 [4 March 2016]
[1] This matter came before me as Duty Judge under urgency. The
plaintiff, Alarm New Zealand Ltd, seeks an urgent interim
injunction
restraining the defendant, 15 Hopetoun Ltd, from selling, transferring, or
providing exclusive possession to persons
other than the plaintiff, accessory
units numbered AU73-76 inclusive, as included in Computer Unit Title Register
Identifier 721740
pending further order of the Court.
[2] The application was initially made without notice, but under
direction from me a copy of the application was served on the
defendant. Having
conferred with counsel it was agreed that, for clarity’s sake, an interim
injunction should be imposed pending
a hearing of the application proper.
Timetabling was also agreed and is noted at paragraph [20].
[3] I also indicated to counsel that I considered it would be
appropriate for me to briefly state the reasons in support of
the interim
injunction and that is the purpose of this judgment.
Overview of issues
[4] Alarm leases premises from 15 Hopetoun Ltd. On 12
February 2016
Associate Judge Christiansen made the following order:
To restrain the defendant from disposing of or diminishing the value of its
right, title and interest (legal or beneficial) in level
3, pending further
order of the Court.
[5] An application to review that decision was filed challenging the
jurisdiction
of the Judge to make such an order and the Judge’s substantive
decision.
[6] The defendant claims, among other things, that the freezing order was in the nature of an injunction with the jurisdiction conferred by s 26J of the Judicature Act
1908.
[7] Complicating matters, the defendant intends now to transfer two accessory units (AU73 and 74), being two car parks. The plaintiff and the defendant disagree as to whether the Judge’s order affects these units.
[8] These issues came before Muir J and undertakings to protect the
plaintiff’s interests together with the prospect
of an application
for interim injunction in relation to AU73 and 74 were mooted. In any
event, Muir J made a number of orders
timetabling the defendant’s review
application to a hearing.
[9] As noted, the application for interim injunction in respect of the
units (and additional units 75 and 76) has now been filed
and has been placed
before me as Duty Judge.
Background
[10] I preface this judgment by observing that this application
is not an opportunity to revisit (and/or regularise)
the judgment of Associate
Judge Christiansen by side route. That judgment has effect unless and until set
aside by way of the review
process. I, therefore, adopt the background as
provided by Associate Judge Christiansen:
Background
[1] The plaintiff applies for particular discovery and a freezing
order. The plaintiff is the tenanted occupant of Level 3,
15 Hopetoun Street,
Freemans Bay, Auckland (Level 3). It entered into a lease of Level 3 by deed
dated 1 October 2013. Its lease
is for 10 years. It has a five year right of
renewal.
[2] The defendant acquired ownership of the building at 15 Hopetoun
Street in December 2013.
[3] The building comprised 11 levels. On 2 December 2013
the defendant obtained resource consent for a change of
use of the building from
commercial offices to 91 residential apartments. On 19 December 2013 the
defendant applied to Auckland
Council (the Council) for building consent to add
a further three levels to the building and to convert each tower level to six
self
contained residential apartments. The building consent application showed
the plaintiff’s leased premises on Level 3 were
divided into six
residential apartments.
[4] The building consent application plans included seismic structural
strengthening design construction features.
[5] The evidence is that the plaintiff did not know nor was consulted
regarding the plans for Level 3.
[6] There was discussion between the parties in February 2014 concerning disruption of the plaintiff’s quiet enjoyment of the lease during building renovation works. On 23 February the plaintiffs sent an email to
Mr Mahoney the defendant’s director and sole shareholder
setting out possible terms and conditions for relocating including
the
requirement for assistance with expenses, costs and compensation. There was no
reply.
[7] On 24 February the defendant’s consultant engineers
expressly acting as the defendant’s agents wrote
to the Council’s
building consent division advising they had carried out a review of the building
and identified what they
considered were critical structural weaknesses,
requiring [sic] to be addressed in the building consent. The plaintiff says
this and other communications on behalf of the defendant amounted to a request
by the defendant for the Council to issue an earthquake
prone notice when the
defendant and its agents knew or ought to have known that the building did not
meet the criteria required for
the issue of such.
[8] On 27 February 2014 the Council issued an earthquake prone notice
(Council Notice) in respect of the building.
On 11 March 2014 the
defendant forwarded the Council Notice with the defendant’s own notice as
lessor citing clause 21.1
of the lease and requiring the plaintiff to give full
and uninterrupted access to the leased premises to carry out the structural
strengthening work as described in the Council Notice.
[9] On 21 March 2014 the defendant’s solicitor wrote to the
plaintiff stating that due to the Council Notice and advice
from engineers
stating the building could not be occupied while Council Notice work was carried
out, that the plaintiff would be
required to vacate the premises until that work
was completed and to enable entry into the premises to carry out the repair
work.
[10] The defendant indicated work would be completed by 30 September
2014.
[11] The defendant refused to offer any compensation.
[12] On 15 August 2014 the Chief Executive, Ministry of Business
Innovation and Employment (MBIE) determined pursuant to s 188
of the Building
Act 2004 that the Council incorrectly exercised its power of decision
in issuing the Council Notice and reversed that decision.
[11] The Associate Judge also provides details as to the nature of the
plaintiff’s claim and the defendant’s claim at
paragraph [14]-[18]
of his judgment:
The plaintiff's claim
[14] The plaintiff's initial statement of claim was filed on 29 May 2014. It sought special damages of $255,000 for temporary relocation costs and
$120,000 for loss of business profit. At the same time the plaintiff filed an application for orders restraining the defendant from pre-selling any
proposed apartments on Level 3 or from undertaking any work on Level 3 not related to earthquake structural strengthening, and preventing the
defendant from removing the plaintiff's fitout or from erecting any walls,
partitions or otherwise reconfiguring the layout of Level 3. Those issues resulted in the defendant's undertaking agreeing that Level 3 would not be
converted to residential apartments while the plaintiff's lease of the
premises was on foot.
[15] An amended statement of claim was filed on 23 January 2015. That
claimed damages of $530,277 for temporary relocation
costs, loss of
business profit and legal expenses. Causes of action included, inter
alia:
(a) Breach of quiet enjoyment of the lease for failing to take all steps to arrange for the renovation work to be carried out in ways and by means that minimised disruption of access and due to having deliberately sought an incorrect and invalid notice from the Council in order to force the plaintiff to relocate.
(b) Misrepresenting the reasons why the plaintiff should relocate
temporarily by promising the work required to be done would
be limited when the
Council Notice did not require the property to be vacated at all.
(c) That the defendant breached undertakings including permitting
reoccupation on 30 September 2014 and failed
to honour
undertakings to consult in a timely way with the plaintiff as to additional work
being done on Level 3 which had not
been heralded.
(d) Misleading and deceptive conduct by the manner and means used to
require the plaintiff to relocate by 31 May 2014 when
no such proper reason
existed.
(e) Trespass — for all those various reasons already
identified.
[16] Mr Stainton for the plaintiff summarises the position as
the defendant removing the plaintiff it having obtained
and relied upon
an invalid earthquake-prone notice issued by the Council and misrepresented the
plaintiff would be in breach of
its lease unless it vacated to enable building
strengthening work required by the notice. Further that it was in fact the
defendant
that carried out all the renovation work using Level 3 and having
failed to reinstate Level 3 premises to the same standard as it
undertook to
this Court and to the plaintiff. Further, the plaintiff says the defendant has
lost the fitout the plaintiff had when
it vacated Level 3.
The defence
[17] The defendant filed a statement of defence on 13 February 2015. The
defendant does not dispute the plaintiff's lease “continues”
in the
sense that it runs with the title to Level 3.
[18] Regarding the plaintiff's claim that the defendant obtained and
relied on the Notice in order to obtain possession over
Level 3 and to undertake
renovations for the remainder of the building, this is denied. The defendant
does admit:
(a) It wrote to the Council with respect to the presence of
non-ductile, and therefore earthquake prone, columns within the
building;
(b) The Council for its part issued the Notice;
(c) The plaintiff was served with the Notice, and a related notice
under clause 22.1 of the lease, which, in effect, required
the plaintiff to
vacate the premises;
(d) The parties entered into negotiations with respect to the
plaintiff's relocation and the plaintiff relocated as a result;
(e) The Notice was subsequently found by MBIE to have been invalidly
issued; and
(f) The defendant gave undertakings, dated 19 June 2014, to the effect
that the renovations were without prejudice to the plaintiff's
rights under the
lease.
[12] In short, the plaintiff ’s leasehold interest is not
disputed, but the defendant
denies that it relied on a Building Act notice in order to obtain possession
of level 3.
The basis for the application
[13] The plaintiff claims that its leasehold interest in level 3 and the
10 identified car park spaces at 15 Hopetoun Street have
been compromised by the
defendant changing the nature of the ownership of the building from freehold
title to separate titles for
principal units and accessory units (car parks),
two of which it has sold to third parties. It claims further that the defendant
has retained for itself level 3 and 11 car parks, but now seeks to transfer AU73
and 74. These spaces, the plaintiff says, must
be retained in order for the
defendant to perform its lease obligations.
[14] The plaintiff is concerned that, while the freezing order provides a
temporary hold on the transfer of level 3, it is unclear
as to whether it
applies to AU73 and AU74.
[15] The plaintiff has also provided an undertaking as to damages in
support of its application in the usual way.
The defendant’s position
[16] Mr Butler has helpfully provided a detailed memorandum setting out the position of the defendant in relation to the application. While he agrees that a temporary injunction pending a proper hearing of the application is in order, he does not resile from his core position, namely that:
(a) The plaintiff has no exclusive interest in AU73 and AU74;
(b) The defendant has complied with its obligations under the lease in
terms of assigning ten covered car parks to the plaintiff;
(c) Transferring the two car parks would not impinge upon the freezing
order and that the only connection between the AUs in
level 3 is that level 3
happens to also be the Principal Unit for the purposes of the Unit Titles Act
2010;
(d) Overall the plaintiff has no seriously arguable case for
exclusive interest, the balance of convenience lies in
protecting the right of
the defendant to sell, as well as the equitable interests of the third parties.
It follows that the overall
interests of justice support the declining of an
interim injunction.
Assessment
[17] Given that this is only a temporary injunction pending the
substantive hearing
I record in summary form only the basis for the order namely:
(a) A temporary injunction is necessary as Units AU73 and 74 are
subject to a sale and purchase agreement;
(b) I am satisfied (in a preliminary way) that the plaintiff has a
seriously arguable case that it enjoys proprietary interests
in AU73 and 74 (as
secured car parks);
(c) The transfer of the car parks to the third parties (bona fide
purchasers) would defeat the plaintiff’s application
for injunction as the
car parks could not then be returned to the plaintiffs.
[18] I further observe, as Mr Butler correctly noted, that given the potential effect of the freezing order it would not be prudent, in any event, for the defendant to transfer AU73 and 74 as that may in fact breach the freezing order. The legality of
the freezing order and its scope, of course, is a matter that is set down to
be resolved in April. Mr Butler also indicated that
the defendant is prepared
to abide by that freezing order and will not transfer the units pending the
outcome of that review.
[19] For completeness, I note that the plaintiff had sought an order in
relation to two other units. There is nothing before
me to suggest that there
is any risk of the transfer of those units. Therefore my order at this
stage is simply limited
to restraining 15 Hopetoun Ltd from transferring its
interests in the AU73 and 74 units to the third parties, pending the resolution
of the interim injunction.
Orders
[20] Given the foregoing I make the following orders:
(a) The defendant, 15 Hopetoun Ltd, is restrained from selling
or transferring, or providing exclusive possession to
other than the plaintiff,
accessory units numbered AU73–74 inclusive, as included in Computer Unit
Title Register Identifier
721740, pending the hearing of this application
for interim injunction;
(b) The plaintiff must serve a copy of the application and any
supporting affidavits together with a copy of this judgment on
the third parties
by way of their solicitors, Burton & Co by 5.00 pm Friday 4 March 2016. I
reserve leave to those solicitors
to come back to this Court in the event that
service on them has not proven to be effective for the purposes of notifying the
third
parties of this proceeding.
(c) Any notice of opposition and affidavit in support of such notice is to be filed by the defendant and the third parties by 5.00 pm Friday 11
March 2016;
(d) Any reply affidavits are to be filed by 5.00 pm Wednesday 16
March
2016;
(e) There shall be a half-day hearing as soon as possible thereafter.
(f) Submissions in support of the application are to be filed four days
out from the hearing and submissions in opposition are
to be filed two days out
from the hearing.
[21] I also grant leave for any party to come back to the Court on 48 hours notice if, for whatever reason, it is necessary for the Court to address the interim injunction or other orders made.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/352.html