Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 20 April 2016
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-3130 [2016] NZHC 476
BETWEEN
|
ANN-LOUISE EVELYN CHANTAL
WEAVER AND GRAHAM WILLIAM ANDERSON
Plaintiff
|
AND
|
HML NOMINEES LIMITED First Defendant
HELEN MARTHA MOORE Second Defendant
Continued ...
|
Hearing:
|
8 December 2015
|
Counsel:
|
M C Frogley for plaintiffs
D J Barr for third defendant
|
Judgment:
|
18 March 2016
|
JUDGMENT OF KATZ J
This judgment was delivered by me on 18 March 2016 at 4:45pm pursuant to Rule 11.5 High Court Rules
Registrar/Deputy Registrar
Solicitors: Rainey Law, Auckland LeeSalmonLong, Auckland Simpson Grierson, Auckland Wilson Harle, Auckland
Rice & Co, Auckland
Counsel: D R Bigio, Shortland Chambers, Auckland
N J Scampion, Shortland Chambers, Auckland
WEAVER & ANDERSON v HML NOMINEES LIMITED & ORS [2016] NZHC 476 [18 March 2016]
AUCKLAND COUNCIL
Third Defendant
STONESCAPES LIMITED (IN LIQUIDATION)
First Third Party
FLEXCO (NZ) LIMITED
Second Third Party
ASHTON MITCHELL ARCHITECTS LIMITED (DISCONTINUED)
Third Third Party
BUILDING CODE CONSULTANTS LIMITED (DISCONTINUED)
Fourth Third Party
KELVIN LEONARD WALLS (DISCONTINUED)
Fifth Third Party
COOPER ROOFING COMPANY (DISCONTINUED)
Sixth Third Party
FLEXCO (NZ) LIMITED
Seventh Third Party
MOHAN ROOFING SERVICES LIMITED
Eighth Third Party
POINT CONSTRUCTION LIMITED (DISCONTINUED)
Ninth Third Party
STONESCAPES LIMITED (IN LIQUIDATION)
Tenth Third Party
JACKSON CLAPPERTON AND PARTNERS LIMITED (DISCONTINUED)
Eleventh Third Party
Introduction
[1] The plaintiffs, Ann-Louise Weaver and Graham Anderson, suffered
loss due to the defective installation of stone cladding
on their house in
St Mary’s Bay, Auckland.
[2] In my judgment of 28 August 2015 (“Judgment”) I found
the previous owner of the property, HML Nominees Limited
(“HML”)
liable for the costs of remediating the stone cladding, because it had breached
vendor warranties in the agreement
for sale and purchase of the property. I
also found the Council liable for the costs of remediating the stone cladding,
because
it was negligent in relation to its inspections of the property and the
issue of a code compliance certificate.1
[3] The plaintiffs were therefore entitled to seek to recover
the costs of remediating the stone cladding (“the
stone cladding
award”) from either HML or the Council, or both of them, subject
only to the requirement that the
total sum recovered could not exceed the
stone cladding award. Because HML is liable in contract, and the Council in
tort, they
have no rights of contribution against each other as joint
tortfeasors.
[4] The plaintiffs reached a settlement with HML, post judgment, which
did not involve any monetary contribution towards the
stone cladding award. The
plaintiffs then sought to enforce the entirety of the stone cladding award
against the Council. The Council
submits that the effect of the
settlement agreement between the plaintiffs and HML is to satisfy the stone
cladding award.
As a result, any enforcement of the award against the Council
would result in excessive recovery.
[5] The issue I must determine is whether the liability of both HML and the
Council, as concurrent wrongdoers in respect of the same loss, has been
discharged by the settlement agreement between HML and the
plaintiffs.
1 Weaver v HML Nominees Ltd [2015] NZHC 2080.
Factual background
[6] HML undertook remedial work on the property in 2005 and 2006. HML
is the corporate trustee of Helen Moore’s
family trust. The
plaintiffs issued proceedings against HML and Mrs Moore in relation to
alleged defects in the
remedial work. Auckland Council was joined as a third
defendant.
[7] I awarded the plaintiffs damages of $118,525.20 consisting
of:
(a) The costs of remediating defective stone cladding in the
sum of
$96,406.22, plus interest. HML and the Council are each liable for the
stone cladding award, in contract and tort respectively.
(b) General damages of $20,000. HML and the Council are separately liable
for $10,000 each.
(c) Costs for remediating the chimney and flu vent in the sum
of
$2,118.98. Only the Council is liable for this amount.
[8] At [184] of the Judgment I recorded that:
HML Nominees is liable in contract in respect of the stone cladding defects
only. The Council is liable, in negligence, in
respect of both the
stone cladding and the chimney cap flashing and new flu vent. If the parties
were joint tortfeasors I would
likely have apportioned liability on a 50/50
basis. They are not, however, and there is no apparent legal
basis
for apportionment of liability between the Council and HML Nominees.
Obviously, however, the plaintiffs cannot recover more than
their total
loss...
[9] Following delivery of the Judgement, the Council wrote to HML
offering to split the stone cladding award equally. HML did
not accept that
offer, but instead entered into separate negotiations with the
plaintiffs.
[10] Meanwhile, the plaintiffs filed a notice of appeal seeking
an additional
$55,352.46 in damages, plus interest and costs. The appeal related to two claims that had been unsuccessful at trial, relating to the garage cladding and front entrance. The appeal was resolved as part of the settlement between the plaintiffs and HML. The key terms of the settlement agreement are that:
G. The parties wish to settle all issues between them arising out of the
proceeding...
...
(1) HML and Mrs Moore will pay the plaintiffs the following
amounts:
(a) $10,000 being the amount that was awarded to the plaintiffs as general
damages against HML in the judgment sum.
(b) $20,000 as a contribution to the cost of reinstating the garage
cladding and the front entrance which were issues on which the
plaintiffs were
unsuccessful at trial and had intended to appeal to the Court of Appeal.2
In the appeal the plaintiff would have been seeking the further sum of
$55,352.46 plus interest and costs.
(2) In consideration for the above payments the plaintiffs:
(a) Agree not to appeal against any finding in or a party to the judgment;
and
(b) Agree not to enforce the judgment against HML.
(3) In addition, the parties agree that they will not to [sic] seek
any award of costs against each other in respect of the
proceeding.
(4) This agreement shall not affect the plaintiffs right [sic] to
enforce the judgment it has obtained against the Council
or to seek costs from
the Council in the proceeding.
The Council’s application
[11] As I have noted above, the plaintiffs sought to recover the full
amount of the stone cladding award from the Council. The
Council says that it
has no obligation to make any payment at all towards the stone cladding award,
and that if it were to do so,
it would result in the plaintiffs making an
excessive recovery. The Council relies on rule 17.4 of the High Court Rules,
which provides:
No excessive recovery
(1) An entitled party is not entitled to recover a greater sum than the
amount owing under the judgment or order, the costs and
expenses of and
incidental to issuing and effecting an enforcement process, and any interest due
under the judgment or order.
2 The reference to an “intention” to appeal appears to reflect that the notice of appeal was originally forwarded to the Court of Appeal with a request that it be “held” until the final day for filing an appeal. It was treated, however, in the normal way and registered for filing.
“Entitled party” is defined as including the judgment
creditor.3
[12] The Council submits that, pursuant to the settlement agreement, the
plaintiffs have received satisfaction (whether in cash
or by some other benefit
such as HML foregoing the right to seek costs) for the stone cladding award.
It is not for the Court to
inquire into the adequacy of that consideration. An
agreement to not enforce the Judgment in consideration for payment of any amount
is, the Council submits, a settlement of all the rights that the plaintiffs had
against HML in respect of the stone cladding award.
In essence, the
Council’s position is that, upon payment of $30,000 by HML to the
plaintiffs, the stone cladding award was
satisfied. As a result, the plaintiffs
cannot now seek to recover any further sum in respect of the award from the
Council.
[13] The Council acknowledges that clause 4 of the settlement
agreement expressly retains the plaintiffs’ right
to enforce the Judgment
against the Council. The Council submits that the provision is irrelevant,
however, as the plaintiffs are
only entitled to enforce the Judgment to the
extent allowed by law. As the stone cladding award has been fully satisfied,
it cannot
be further enforced. There is no “loss” left for the
plaintiffs to recover.
Does the settlement agreement between HML and the plaintiffs prevent the
plaintiffs from enforcing the stone cladding award against
the
Council?
Relevant legal principles
[14] At common law, if the plaintiff released one joint tortfeasor, all the others were released as well (“the release rule”). The learned authors of Civil Remedies in New Zealand argue that this rule should now be regarded as abolished by statute,4
although they acknowledge that some doubt continues to linger on.5
Further, issues
have arisen as to the application of the release rule (if it still exists) to concurrent tortfeasors. Concurrent tortfeasors are tortfeasors who commit separate torts that
contribute to a single instance of damage to a
victim.
3 High Court Rules, r 17.1.
4 Peter Blanchard (ed) Civil Remedies in New Zealand (2nd ed, Brookers, Wellington, 2011) at
[15.4.1]; see Judicature Act 1908, s 94 Law Reform Act 1936, s 17.
5 See the differing views in Robinson v Tait [2001] NZCA 217; [2002] 2 NZLR 30 (CA).
[15] In this case the Council and HML are neither joint nor concurrent
tortfeasors. Rather, the Council’s negligence (tort)
and HML’s
breach of the vendor warranties (contract) have both separately contributed to
the stone cladding defects. As a
result they are both liable for the same loss
(the cost of remediating the stone cladding), albeit based on entirely different
causes
of action. They are therefore concurrent “wrongdoers”
rather than concurrent tortfeasors. In distilling the legal
principles that
should apply to the present application counsel for both parties have referred
to the case law relating to concurrent
tortfeasors, by analogy. I will do the
same.
[16] The Council relied primarily on the decision of the House of Lords in Jameson v Central Electricity Generating Board.6 Mr Jameson issued proceedings in relation to a personal injury (asbestosis) he allegedly suffered in his work place. He settled with his employers, but his estate subsequently brought further proceedings against the owner of his work premises. The House of Lords held that the release rule applied to concurrent as well as joint tortfeasors and that the
settlement reached with Mr Jameson’s employers prevented him from
making a further claim against the owner of the premises where
he had allegedly
come into contact with asbestos. As a result, Mr Jameson, having settled with
one tortfeasor, was not entitled
to re-open the question as to whether the
amount which he had agreed to accept in full and final settlement represented
full value
for his claim, in subsequent proceedings against another
tortfeasor.
[17] In Allison v KPMG Peat Marwick the New Zealand Court of Appeal
distinguished Jameson on its facts and also strongly rejected the
majority’s reasoning in that case. Thomas J stated that:
7
[the decision of the majority] departs from long-established, settled
and sound principle that a release of one concurrent
tortfeasor does not release
another concurrent tortfeasor; it will in circumstances other than an
exceptional factual situation
of the kind which existed in that case
be contrary to common notions of justice; it is inconsistent with the step which
Parliament has taken in exempting joint tortfeasors from being bound by a
settlement to which they are not a party in statutory developments
which
Parliament has seen fit to enact; it is not required to meet any development or
need which has emerged in trade or commerce;
it cannot be said to be necessary
to meet the reasonable expectations of the community; it will, as
6 Jameson v Central Electricity Generating Board [2000] 1 AC 455 (HL).
7 Allison v KPMG Peat Marwick [2000] 1 NZLR 560 (CA) at [160].
with any precedent arising out of hard facts, undoubtedly lead to further
uncertainty and litigation as plaintiffs with separate causes
of action against
concurrent tortfeasors seek to carve out exceptions to a rule perceived to work
an injustice; and, finally, it
is unlikely to be followed in other common law
jurisdictions such as Australia, Canada and the United States. Furthermore, as I
have
endeavoured to demonstrate in this judgment, the analysis and reasoning of
the majority is not convincing.
[18] His Honour further observed that:
[142] At this point it is helpful to recollect that a release is not
necessarily to be equated with the concept of satisfaction.
If the basic rule
is that a plaintiff cannot recover more by way of damages than the amount of the
loss, the rule does not conceptually
preclude the possibility of multiple
proceedings to make up that loss. Indeed, it assumes such proceedings are
possible. The term
satisfaction as in accord and satisfaction is used in a
particular sense and serves a different purpose. Accord and satisfaction
as
between the plaintiff and one tortfeasor does not automatically equate with the
satisfaction of the entire loss. Where the settlement
is for less than the full
loss it cannot be suggested that a release of the settling tortfeasor represents
satisfaction of the plaintiff’s
claim against a different tortfeasor
liable on a different cause of action arising out of a different
obligation.
[19] Tipping J also made a number of observations that are potentially
relevant to the current application, including that:8
Only if the plaintiff in the settlement reached with concurrent tortfeasor A
has expressed the intention to release concurrent tortfeasor
B, should B be able
to rely on the settlement as a bar to proceedings against B.
[20] Jameson was revisited by the House of Lords in Heaton v
AXA Equity & Law Life Assurance Society Plc.9 Lord
Bingham of Cornhill noted that he had “gained much assistance
from the clear and illuminating judgments
of the New Zealand
Court of Appeal in Allison v KPMG Peat Marwick....”10
Their Lordships confirmed that the release of one concurrent tortfeasor or
contract breaker does not in law release any co-defendants
and suggested that
the decision in Jameson may have been misunderstood:11
The majority decision of the House in Jameson v Central Electricity
Generating Board [2000] 1 AC 455 appears to have been understood by some as
laying down a rule of law that A, having accepted and received a sum from
B in
full and final settlement of his claims against B in tort, is
8 At [190].
9 Heaton v AXA Equity & Law Life Assurance Society Plc [2002] EWHC 967; [2002] 2 AC 329 (HL).
10 At [9].
11 At [6] and [9].
thereafter precluded from pursuing against C any claim which formed part of
his claim against B. I do not think that my noble and
learned friend Lord Hope
of Craighead, in giving the opinion of the majority of the House, is to be so
understood.
[21] Lord Bingham further observed that:12
While it is just that A should be precluded from recovering
substantial damages against C in a case where he has accepted a
sum representing
the full measure of his estimated loss, it is unjust that A should be so
precluded where he has not.
[22] The decision in Jameson was therefore explained on the basis
that, on the particular facts of that case, the settlement was accepted
by the parties
as representing the full measure of the plaintiff’s
loss. There was accordingly full satisfaction and nothing more for which
the
plaintiff could sue.13
[23] Determining whether there has been full satisfaction in any given
case is ultimately a matter of interpreting the relevant
settlement agreement,
as Lord Hope stated in Jameson:14
The intention of the parties is to be found in the words of the settlement.
The question is one as to the objective meaning of the
words used by them in the
context of what has been claimed.
[24] As for the relevance of an express reservation in a settlement
agreement of a right to sue another tortfeasor, Lord Bingham
observed
that:15
While an express reservation by A of his right to sue C will fortify the
inference that A is not treating the sum recovered from B
as representing the
full measure of his loss, the absence of such a reservation is of lesser and
perhaps of no significance, since
there is no need for A to reserve a right to
do that which A is in the ordinary way fully entitled to do without any such
reservation.
[25] In summary, a settlement with one tortfeasor will not release a concurrent tortfeasor unless it is clear that the settlement was intended by the parties to represent the full amount of the plaintiff’s loss. An express reservation of rights
against a concurrent tortfeasor in a settlement agreement with another
tortfeasor will
12 At [5].
13 At [8]-[9] and [79].
14 Jameson v Central Electricity Generating Board, above n 6, at 476.
15 Heaton v AXA Equity & Law Life Assurance Society Plc, above n 11, at [9].
tend to support an inference that the parties did not intend the settlement
to be in
satisfaction of the full amount of the plaintiff’s loss.
Have the plaintiffs accepted a sum from HML/Ms Moore that was intended to
represent the full measure of their loss in respect of the
stone
cladding?
[26] In order to determine the Council’s claim that there
has already been satisfaction of the stone cladding
award, it is necessary to
answer the question posed by Lord Bingham in Heaton, namely, has the
claimant accepted a sum which was intended to represent “the full measure
of [the claimant’s] estimated
loss”?16
[27] It is necessary to answer this question by interpreting the words
used in the settlement agreement, in the light of the
circumstances in
which HML and the plaintiffs used them. In particular, two inter-related
questions must be considered:
(a) Did the parties intend that the consideration provided by HML under
the agreement would fully satisfy the stone cladding
award?
(b) What did the parties intend should be the effect of the settlement
agreement (if any) on the right of the plaintiffs to
pursue enforcement of the
award against the Council?
[28] In my view there is nothing in the terms of the settlement agreement, or in the surrounding circumstances, to suggest that the parties to the settlement agreement intended it to be in full and final satisfaction of the stone cladding award not only against HML, but against the Council as well. Indeed the contrary intention is evident in clause 4, which expressly provides that the agreement shall not affect the plaintiffs’ right to enforce the Judgment against the Council, or to seek costs from the Council in the proceeding. As noted by Lord Bingham in Heaton, an express reservation by a plaintiff of his right to sue a concurrent tortfeasor (or in this case a concurrent wrongdoer) will fortify the inference that the plaintiff is not treating the
sum recovered from the first tortfeasor as representing the full measure
of his loss.17
16 At [5].
17 At [9].
[29] The agreement records that the parties wish to settle all issues
between them arising out of the proceeding. HML and Mrs Moore agreed to
pay the $10,000 in general damages owing under the Judgment, plus $20,000
as a
contribution to the cost of reinstating the garage cladding and the front
entrance which were issues on which the plaintiffs
were unsuccessful at trial
and had intended to appeal to the Court of Appeal. In consideration of those two
payments the plaintiffs
agreed not to pursue their appeal and not to enforce the
judgment against HML.
[30] The settlement agreement does not constitute
“satisfaction” of the Judgment as a whole. It is simply a promise
not to enforce the judgment against HML. Words such as “full and final
settlement” or “satisfaction” are
not used. Rather, the
agreement is framed, in effect, as a covenant not to sue HML or Mrs
Moore, by enforcing the
judgment against them.
[31] The express reservation of rights against the Council is consistent with the agreement being interpreted as a covenant not to sue HML/Mrs Moore, rather than being in full satisfaction of the Judgment. As the learned authors of Chitty on Contract observe:18
The courts generally construe a release as a covenant not to sue if it
contains an indication of intention that the other debtors
are not to be
discharged. Moreover, even an accord and satisfaction with one joint or joint
and several debtor will not discharge
the others if the agreement, expressly or
impliedly, provides that the creditor’s rights against them shall be
preserved.
[32] The interpretation of the settlement agreement advanced by the Council is contrary to commercial sense and would require the Court to disregard the broader factual context. The plaintiffs have obtained judgment from both HML and the Council in respect of the stone cladding award (approximately $100,000) after protracted, expensive and hard fought litigation. They are entitled to enforce it against either or both of the judgment debtors. At least one of those debtors (the Council) is clearly solvent and judgment worthy. Yet, if the Council’s
interpretation of the settlement agreement is correct, the plaintiffs
have agreed to
accept, in effect, no specific
monetary payment at all (from either HML or the
Council) in respect of the stone cladding award as the “full measure of
their loss”.
[33] The settlement agreement cannot reasonably be interpreted in that way. Rather, the agreement is clearly structured in such a way as to maximise the plaintiffs’ overall recovery in the litigation. They have elected to enforce the stone cladding award against the Council only, as they are entitled to do. They have agreed not to pursue HML in respect of the stone cladding award, provided that HML pays the general damages awarded against it and also contributes towards the costs of other remedial work, which was the subject of a (now abandoned) appeal. For the avoidance of doubt, I note that I am satisfied that the appeal against the Judgment was brought reasonably and in good faith. It raised tenable issues for
consideration by the Court of Appeal.19 The plaintiffs’
agreement to abandon the
appeal was therefore good consideration for the $20,000 payment made by HML
and
Mrs Moore.
[34] It seems clear that at least one of the concerns driving the present
application is the Council’s belief that the plaintiffs’
conduct in
seeking the entirety of the stone cladding award from it is inherently unfair.
From the Council’s perspective,
the appropriate course would have been for
the liable defendants (HML and the Council) to have shared responsibility for
payment
of the award equally, as it proposed to HML. Indeed, I noted in the
Judgment that had HML and the Council been joint tortfeasors,
I would have
allocated liability 50/50. Because the Council and HML are not joint
tortfeasors, however, the Council now faces paying
the entirety of the stone
cladding award, with no ability to seek a contribution from HML.
[35] The Council is not alone in its view that situations such as the present one are unfair. The Law Commission, in its 1992 Discussion Paper on Apportionment of Civil Liability, described the inability of defendants to seek a contribution from a co-defendant in these types of circumstances as “plainly unfair”.20 The Law Reform
Commission of Hong Kong earlier reached a similar view (in 1984) stating
that:21
19 The plaintiffs set out their grounds of appeal in some detail in their submissions.
20 Law Comission Apportionment of Civil Liability (NZLC PP19, 1992) at [70].
21 Law Reform Commission of Hong Kong Report on the Law Relating to Contribution Between
Wrongdoer (Topic 5, 1984) at [5.3].
We are in complete agreement with this extension of the right to
contribution. The present restriction of the
right to contribution
to tortfeasors cannot be justified on any policy grounds, and is merely
an accident of legal
history. Furthermore, we see this reform as the
most important of our recommendations.
[36] In England the Civil Liability (Contribution) Act 1978
addressed the anomaly by extending rights of contribution
to all wrongdoers in
respect of the same damage, whatever the legal basis of their liability
(“whether tort, breach of contract,
breach of trust, or
otherwise”).22 This is also the position in Hong Kong,
under section 2(3) of the Civil Liability (Contribution) Ordinance 1997. Other
countries have
enacted similar provisions, but New Zealand has not.
[37] As a result, both the Council and HML are liable for the entirety of the stone cladding award, but neither defendant has a right of contribution from the other. The plaintiffs were entitled to enforce the stone cladding award against either or both of HML and the Council, as they chose. In Malborough District Council v Altimarloch Joint Venture Ltd the majority of the Supreme Court held that there was no duty on the purchaser of a property to first recover from the vendor in contract before seeking to recover against the Council for a separate tort causing the same quantum
of loss.23 The only caveat is that the plaintiffs
cannot recover more than the
judgment sum.
[38] The plaintiffs elected to enforce the stone cladding award solely
against the Council. They entered into a settlement agreement
with HML in which
they agreed not to enforce the Judgment against it in exchange for HML agreeing
to pay the general damages owing
and $20,000 in exchange for the plaintiffs
abandoning their appeal rights. The agreement did not provide for HML to make
any contribution
to the stone cladding award.
[39] Regardless of any broader “fairness” issues, the present case turns simply on whether the plaintiffs accepted a sum from HML/Mrs Moore pursuant to the settlement agreement that was intended to represent the full measure of their loss.
For the reasons outlined above, I am satisfied that they did
not. There will
22 Civil Liability (Contribution) Act 1978 (UK), s 6(1).
23 Marlborough District Council v Altimarloch Joint Venture Ltd [2012] NZSC 11, [2012] 2 NZLR
726 at [201].
accordingly be no excessive recovery in terms of rule 17.4 if the plaintiffs
enforce the stone cladding award against the Council.
Any such enforcement will
not result in the plaintiffs recovering a greater sum than the amount owing
under the Judgment.
Result
[40] The Council’s application is dismissed. The interim
order I made on
14 October 2015, restraining the plaintiffs from enforcing the Judgment
against the
Council to the extent of $20,000 (only) is discharged.
[41] The plaintiffs, as the successful party, are entitled to
the costs of this application on a 2B scale
basis.
Katz J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2016/476.html