Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 8 March 2018
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2017-404-1191 [2018] NZHC 169
UNDER
|
The Companies Act 1993
|
BETWEEN
|
MANCHESTER SECURITIES LTD Applicant
|
AND
|
BODY CORPORATE 172108
Respondent
|
CIV-2017-404-1478
BETWEEN MANCHESTER SECURITIES LTD Applicant
AND BODY CORPORATE 172108
Respondent
Hearing:
|
16 November 2017
|
Appearances:
|
Mr M C Harris for Applicant
Mr T J G Allan for Respondent
|
Judgment:
|
16 February 2018
|
JUDGMENT OF ASSOCIATE JUDGE J P
DOOGUE
This judgment was delivered by me on
16.02.18 at 3.30 pm, pursuant to
Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date...............
MANCHESTER SECURITIES LTD v BODY CORPORATE 172108 [2018] NZHC 169 [16 February 2018]
Background
[1] Manchester Securities Limited, the applicant, asks the court to set
aside two
statutory demands pursuant to s 290(1) of the Companies Act 1993 (“the
Act”).
[2] The following statement of background from this point to the end of
this section of this judgment has been excerpted from
the synopsis of
submissions which Mr Harris filed on behalf of the applicant. I do not
understand that there is any dispute as to
its essential outlines:
1. Manchester asks the court to set aside two statutory demands.
There is a substantial dispute whether the amounts demanded
are due; Manchester
has set-offs in excess of both; and the underlying disputes are subject to
arbitration. The demands are an attempt
to skirt the arbitration
process.
2. The demands have their genesis in a long-running dispute
about the remediation of a “leaky” apartment
complex, the Hobson
Apartments. Manchester owns the 12th floor penthouse unit in the complex, of
which the respondent is the body
corporate.
3. In 2011 the High Court settled a remediation scheme for Hobson
Apartments under the Unit Titles Act 1972. In March 2017
Fogarty J granted an
application by the Body Corporate to vary the scheme terms. A costs judgment was
delivered in June.
4. The 1 June 2017 demand (first demand) claims an interim
payment ordered by Fogarty J and ordinary Body Corporate levies. The 4 July 2017
demand (second demand) seeks payment of Fogarty J’s costs
judgment.
5. Manchester claims two set-offs against the first demand:
b. The second set-off is for disputed remediation costs claimed by the Body Corporate. First, Manchester says the Body Corporate is claiming amounts that it has already recovered from its insurer. Second, Manchester says the Body Corporate’s claim for repair
costs is overstated because it includes additional costs of closing in the
lower level balconies, which constitute betterment. Neither
set- off was
disposed of by Fogarty J in the variation judgment.
7. The second demand seeks payment of Fogarty J’s costs judgment.
Manchester claims a set-off for its legal costs incurred in settling the
original scheme. The set-off is based on an order by Heath
J (confirmed by
Fogarty J) that those costs should be treated as costs of the scheme. It
includes interest at the scheme rate of
10% from the initial judgment date. In
addition, any excess amount from Manchester’s set-off to the first demand
can also be
applied to set-off the second demand.
(Citations omitted)
[3] There has been an important development since the above
statement background was first drafted. That is that the
Court of Appeal has
since delivered judgment1 on the appeal against the determinations
by the High Court2 (“the 2017 judgment”) varying the
remediation scheme. The net effect was that the Court of Appeal upheld the 2017
judgment.
The application to set aside and the opposition
[4] The first point is that there were two statutory demands served,
one on 1 June
2017 and another on 4 July 2017. The first statutory demand was based upon
the 2017 judgment of the High Court dated 3 March 2017,
in which the court
ordered that the applicant pay a contribution to the repair of the common areas
of the building and the sum of
$321,264.79 (plus both GST and interest).3
The first statutory demand also included demand that the applicant pay the
sum of $226,679 representing body corporate “operating”
levies up to
31 May 2017, again with interest.
[5] The grounds upon which the applicant seeks to set aside the first
statutory demand are:
1 Manchester Securities Ltd v Body Corporate 172108 [2017] NZCA 527.
2 Body Corporate 172108 v Manchester Securities Ltd [2017] NZHC 329.
3 Body Corporate 172108 v Manchester Securities Ltd, above n 2, at [157].
b) the applicant is entitled to set-off against amounts owing
to the respondent various costs that in the aggregate
exceed the amounts sought
in the statutory demand;
c) the respondent has disputed the applicants claimed set-off;
d) any dispute as to the amount of the applicant’s
set-off must be determined by arbitration; and
e) it is in the interests of justice for the orders to be made.
[6] The grounds upon which the respondent opposes the making of the orders
setting aside the first statutory demand are:
a) the amounts sought to be paid were the subject of a judgment which
required immediate payment, being the 2017 judgment;
b) the statutory demand also includes body corporate operating levies
of
$226,679 and interest;
c) although the applicant appealed the 2017 judgment, it was not
stayed;
d) so far as the applicant raises set-off claims:
i) they are for unliquidated sums; and
ii) they were disposed of by the 2017 judgment (with the exception of
the cost of repairing the common property on the roof
for which the applicant
has $220,000 of the respondent’s money) either because:
a. the variation to the scheme in CIV-2009-404-6868 renders cl 21.2 of that
scheme nugatory or because:
b. the set-off credits claimed in CIV-2009-404-6868 were rejected by the Court in the course of dealing with the variation application.
e) the applicant received $2,000,000 from the Auckland Council in
satisfaction of all its claims, including costs of consultants;
f) in so far as the unliquidated set-off claims are not excluded by
the 2017 judgment and remain alive, they are limited to
the flashing junctures
at the intersection of L11 and L12;
g) there is no substantial dispute between the parties; and
h) the respondent is solvent, whereas the applicant is insolvent.
[7] The second statutory demand required the respondent to pay the sum
of
$206,919.47 representing the amount of the costs order which was made against
it in
the 2017 proceeding (“the costs
judgment”).4
[8] The originating application which the applicant filed seeking to set
aside the second statutory demand set out the following grounds:
a) the applicant is entitled to set-off against amounts owing
to the respondent various costs that in the aggregate
exceed the amounts sought
in the statutory demand;
b) the respondent has disputed the applicant’s claim to
set-off;
c) any dispute as to the amount of the applicant’s
set-off must be determined by arbitration; and
d) it is in the interests of justice for the orders to be made.
[9] The notice of opposition to the second application sets out the following
grounds:
4 Body Corporate 172108 v Manchester Securities Ltd [2017] NZHC 1252.
a) the amount of $321,264.79 (plus both GST and interest) which the
applicant was adjudged liable to pay was required to be
paid
“immediately” in the 2017 judgment.
b) although the applicant has appealed the costs judgment, it has not
been stayed;
c) there is an issue as to whether the respondent has not already
given credit to the applicant in regard to the costs which
were ordered to be
paid in a 2010 judgment of Heath J (“costs judgment number
4”).5 This followed on from Heath J’s substantive
determination (“the 2010 judgment”).6 The respondent
says that there is no basis for the applicant to argue to the contrary.
Reference is made to the costs judgment number
4 which is now set out:
[17] I direct that the solicitor and own client costs
and disbursements of both [the respondent and the applicant]
shall be regarded
as costs of the scheme, with the consequence that they will be paid out of
levies based on unit entitlements.
d) there has been no unconditional credit and therefore no application
or payment of the costs referred to in the costs judgment
number 4 on various
grounds, including that the costs judgment number 4 has not been sealed, the
respondent gave credit against a
levy which was set aside as part of an
arbitration award between the parties, and the costs order was in any case set
aside by the
costs judgment in the 2017 case.7
Principles relating to applications to set aside statutory
demands
[10] Section 290(4) of the Act provides:
The court may grant an application to set aside a statutory demand if it is
satisfied that—
5 Body Corporate 172108 v Meader (No 4) HC Auckland CIV-2009-404-6868, 10 February
2011.
6 Body Corporate 172108 v Meader (No 2) HC Auckland CIV-2009-404-6868, 19 August
2010.
7 I understand that these various grounds in “d)” operate as an alternative to the contention in
“c)” that credit has in fact been given.
(a) there is a substantial dispute whether or not the debt is owing or is
due; or
(b) the company appears to have a counterclaim, set-off, or
cross-demand and the amount specified in the demand less the amount
of the
counterclaim, set-off, or cross-demand is less than the prescribed amount;
or
(c) the demand ought to be set aside on other grounds.
[11] The principles which are applicable when the Court is applying s
290(4) were stated in the judgment of Abbott AJ in this
Court in North
Harbour Equine Hospital Ltd v DK Little Corporate Trustee Ltd, where the
following statement of principle was made:8
The general principles which the Court applies in approaching its discretion in this matter are conveniently set out in Brookers Company and Securities Law at CA
290.02(1):
“(1) General principles
...
These principles ... are as follows:
a) The applicant must show that there is arguably a genuine and substantial dispute as to the existence of the debt.
b) The mere assertion that a dispute exists is not sufficient. Material, short of proof, is required to support the claim that the debt is disputed.
c) If such material is available, the dispute should normally be resolved other than by means of proceedings in the Companies Court.
d) An applicant must establish that any counterclaim or cross demand is reasonably arguable in all the circumstances.
e) It is not usually possible to resolve disputed questions of fact on
affidavit evidence alone, particularly when issues of credibility
arise.”
[12] The applicant relies predominantly on s 290(4)(b) of the Act. It says there is a substantial dispute whether both demands are due because it has set-offs in excess of
both demands. In other words, it has counterclaims available to it.
That being so, as
8 North Harbour Equine Hospital Ltd v DK Little Corporate Trustee Ltd HC Auckland CIV-
2006-404-7585, 19 February 2007 at [17].
outlined above, it must demonstrate that there are “clear and
persuasive” grounds for
the claims and that there is a “real basis” for the claimed
set-off.9
[13] I will begin by examining the arbitration issue because this will
determine whether I should proceed to explore the grounds
raised under each
statutory demand.
The arbitration issue
[14] As already noted, the application to set aside each statutory demand
asserts that any dispute as to the amount of the applicant’s
set-off or
cross-claim must be dealt with in accordance with the arbitration agreement
which the parties signed. If that contention
is correct, then the court is not
able to come to even a tentative view about the viability of the counterclaim,
cross-demand or
set-off which the applicant has put forward. All those issues
would need to be considered at arbitration.
[15] Clause 13 of the scheme provides for dispute
resolution:
13 Dispute resolution
13.1 The Body Corporate's decision shall be final in all respect all
matters arising under this scheme, except where 5 or more
Owners whose objection
in monetary value cumulatively exceeds $30,000, or where one Unit Owner has an
objection which in monetary
terms exceeds $10,000. Upon receiving notice of such
an objection, the Body Corporate shall refer the matter to
arbitration.
13.2 The objecting Owners must give notice to the Body Corporate of their objection within 15 working days of receiving an assessment as to Costs or other notice from the Body Corporate which is the subject of the objection outlining the grounds on which such objection is made. On receipt of the notice the Body Corporate will refer the matter to an arbitrator (to be appointed by the President of the Quantity Surveyors Association) and the arbitrator shall determine the issue under the provisions of the Arbitration Act
1996. The arbitrator's decision shall be final and the costs of the arbitration shall be borne as between the objecting Owners and the other members of the
Body Corporate generally as the arbitrator shall decide.
13.3 No Owner shall be entitled to withhold payment of a Levy on the basis that
the matter is in the process of dispute resolution
...
9 Provida Foods Ltd v Foodfirst Ltd [2012] NZCA 326 at [32].
[16] The scheme of the arbitration provision assumes that a party who is
liable to pay a levy can bring any disputes concerning
the claim to arbitration.
The entitlement to arbitrate is subject to certain rules about timing of giving
notice that the party requires
the matter to be arbitrated. The arbitration
scheme can mean that a dispute is dealt with by arbitration rather than through
court
processes. However, once a court becomes seized of a matter, perhaps
because no arbitration notice was ever given, or if given,
was not given within
the required time, the arbitration provision ceases to be of any
relevance.
[17] Associate Judge Bell dealt with a similar argument between the same
parties in Manchester Securities Ltd v Body Corporate 172108.10
In that case, Manchester had also applied to set aside a statutory demand
issued by the body corporate. But the statutory demand was
based on remedial
levies.
[18] The Judge first noted that cl 13.3 is effectively a “pay now
argue later”
provision:
[39] I accept the submission as to “pay now argue later”.
There is an obvious practical purpose. It enables the body
corporate to fund
remedial works effectively. Cash flow is assured. Dissident owners who want to
contest levies are still required
to pay, although they may take their
complaints as to the levies to arbitration.
[19] Essentially, the Judge then held that the arbitration provision
governed the situation. If the body corporate brought proceedings
to recover a
remedial levy from a unit owner, the court would apply cl 13.3.11
As the Judge explained:
[41] If the court were to consider the merits of the owner's arguments,
it would be deciding something which, under the scheme,
must be decided by
arbitration. One of the purposes of the Arbitration Act 1996 is to encourage the
use of arbitration as an agreed
method of resolving commercial and other
disputes. Under s 6 of that Act the provisions of schedule 1 apply to an
arbitration in
New Zealand. The first schedule contains rules applying to
arbitration generally. There are rules as to court intervention in arbitrations.
Under article 5, in matters governed by the schedule, no court shall intervene
except where so provided in the schedule. If the court
cannot intervene in any
of the limited ways allowed under the first schedule of the Arbitration Act, the
court cannot determine the
merits of a unit owner's objection to a levy.
Ordinarily then, objections to a levy cannot be a defence to a proceeding
seeking a
payment of a levy by reason of clause 13.3.
10 Manchester Securities Ltd v Body Corporate 172108 [2013] NZHC 177.
11 At [40].
[42] Even if the parties waived the requirement to take the matter to
arbitration, the “pay now argue later” provision
would still apply.
The body corporate would be entitled to obtain summary judgment on a claim for a
remedial levy, leaving arguments
as to the merits of the levy to be decided
later.
(Citations omitted)
[20] I note that there are occasions where the courts may intervene even
though a dispute is to be determined by arbitration.
The first is where it can
be shown that there is not in fact any dispute between the parties.12
The courts have interpreted this as meaning that if it can be shown that a
party does not have any arguable defence to a claim, then
there is no dispute to
be referred to arbitration and the matter should not go to arbitration, but may
instead remain in court.13 The second is to seek interim relief
pending arbitration.14
[21] Manchester had to, therefore, establish that the body corporate
either had no arguable defence, so that there was not in
fact any dispute to be
referred, or that it should have interim relief pending arbitration.15
It could not do either, meaning the application to set aside the statutory
demand was dismissed.
[22] Ultimately, in this proceeding, the respondent submits
that:
(a) The obligation to pay a levy imposed by a body corporate is a
statutory obligation. The body corporate may recover the
levy as a debt due, in
accordance with s 124(2) of the [Unit Titles Act 2010];
(b) Under the scheme because the amount is not determined on the basis
of an “assessment as to Costs or other notice”
issued by the Body
Corporate. Clause 13.2 only engages with respect to such a notice issued by
the Body Corporate ...
12 Arbitration Act 1996, sch 1, art 8(1).
13 Manchester Securities Ltd v Body Corporate 172108, above n 10, at [49]; Cognition
Education v Zurich Insurance Ltd [2012] NZHC 3257.
14 Arbitration Act, sch 1, art 9(1).
15 Manchester Securities Ltd v Body Corporate 172108, above n 10, at [53].
[23] With regard to the last point, the further contention of the
respondent is that it is not an amount assessed by the body
corporate which is
the subject of the statutory demand in this case. Rather:
There is a judgment against which no arbitral regime can be invoked.
[24] I agree with the respondent. The decision of Associate Judge Bell
can be distinguished on the basis that it dealt with
levies and therefore came
within the ambit of the arbitration provision. Here, the obligation to pay
arises from judgments of this
Court.
[25] In my assessment, the position which the respondent takes is therefore correct to the extent that orders which have been made by the courts cannot be challenged by means of invoking the arbitration clause in cl 13 of the scheme under s 48 of the Unit Titles Act 2010. The result is that the court must recognise that, in terms of court judgments and orders, an amount of not less than $576,373.98 is owing by the applicant to the respondent. This amount represents the total of the judgment sum ordered to be paid as part of the 2017 judgment, to which is to be added the sum of
$206,919.40, which were the costs ordered against the applicant at the
trial.
[26] The effect is that the respondent has a present enforceable claim
which the applicant must meet. That is to say, the statutory
demand is
supported by a debt and because of the deferment effect of cl 13.3, there is no
present dispute that the amounts are payable.
[27] Given that conclusion, I will now consider the grounds concerning the first statutory demand. As noted in the applicant’s submissions, the applicant claims a set- off against the amounts sought in the demand of $552,446.
The 2017 judgment for $321,284.79 was ordered to be paid
immediately
[28] There is no argument that in the 2017 judgment the applicant was ordered to pay the sum of $321,264.79 (plus both GST and interest),16 as the respondent sets out
in its notice of opposition to this application.
16 Body Corporate 172108 v Manchester Securities Ltd, above
n 2, at [157].
An obligation to pay immediately?
[29] It is correct that Fogarty J had the expectation that the amount
would be paid forthwith but I am not sure that that adds
anything to, or
influences, the effect that judgments have under pt 11 of the High Court
Rules.
[30] The fact that the judge directed that the amount was to be paid
“immediately” does not in my view provide an
indication that the
court was thereby disallowing any right of set-off. It is difficult to see any
ground upon which the court would
make such an order because it would represent
a conclusion that did not follow from interpretation of the parties’
contract
or some other defensible ground.
[31] Assuming that there is a dispute about whether or not the direction of the judge in the 2017 judgment that the amount which the applicant was required to pay was to be paid “immediately”, then the words which the judge used in pronouncing judgment would not have the effect of excluding the entitlement that the applicant would otherwise have to set-off against the amount of the judgment. I consider that this point is at least arguable for the reasons I have set out in the previous paragraph. The requirement to repay “immediately” does not therefore prevent the applicant in the present proceeding from raising the question of the alleged debt which the respondent owes to it.
The issue of whether “the proviso” survived the variation of
the scheme
[32] In the originating application, which the applicant has filed,
express reliance is placed upon the terms of the remediation
scheme settled by
Heath J in the 2010 judgment.
[33] The submission of the applicant in this regard was as
follows:
5. Manchester claims two set-offs against the first demand:
a. The scheme requires Manchester to carry out repairs to its unit and common property on level 12. The scheme (original and as varied) specifically provides for costs incurred by Manchester on consultants and advisors that benefit the Body Corporate and other unit owners to be shared. Manchester claims a set-off
for these charges (less its unit-entitlement share of them). The scheme, as
varied by Fogarty J, provides for this set-off and for
any dispute about the
amounts due to be referred to arbitration.
[34] The point about the arbitration which is set out above
will need to be considered further on in this judgment.
For the moment,
discussion will be limited to consideration of whether the contention is correct
that the scheme as varied by Fogarty
J actually provided for the set-off. If
there was no express mention of the set-off, was it impliedly abrogated by the
2017 judgment?
[35] The position of the respondent is as follows:
15. MSL now claims (post-judgment) that the proviso to clause
21.2 remains part of the scheme as varied and that the Body Corporate is
required to refer disputes with respect to these costs to
arbitration.
16. Prior to the High Court delivering its Judgment on 3 March
2017 MSL never claimed that it is entitled to set-off these charges of
project management consultants or other construction related
advisors for the
L12 works against operating levies and levies due under the scheme.
17. The Body Corporate does not accept that MSL is entitled to set-off
these costs against the levies sought in the statutory
demand.
18. All of these invoices relate to MSL’s re-development project
situated on its own unit property on level 12. No explanation
by either MSL or
any of the parties who issued these invoices have provided any explanation for
why they provide a benefit to the
Body Corporate under clause [21.2 of] the
scheme. Accordingly the Body Corporate does not receive a benefit for these
costs incurred
by MSL.
19. The Court has already declined to refer this matter to
arbitration and declined to take MSL’s costs of construction
to unit
property on L12 into account when awarding the judgment sum.
20. There is no discretion or compulsion for the body corporate to
attend arbitration:-
(a) The obligation to pay a levy imposed by a body corporate is a statutory obligation. The body corporate may recover the levy as a debt due, in accordance with s 124(2) of the [the Unit Titles Act
2010];
(b) Under the scheme because the amount is not demanded on the basis of an “assessment as to Costs or other notice” issued by the Body Corporate. Clause
13.2 only engages with respect to such a notice issued
by the Body Corporate. There is a judgment against which no arbitral regime
can be invoked.
(Citations omitted)
[36] I have already noted the notice of opposition which the respondent
has filed asserted a wider ground of opposition, being
that the variation of the
scheme brought about by the 2017 judgment rendered cl 21.2 of the 2010 judgment
“nugatory”
and, on the alternative ground, that the set of credits
claimed in the 2010 judgment were rejected by the High Court in the course
of
dealing with the variation application.
[37] There is no clear answer available to the question set out in the
preceding paragraph (paragraph [35]), which is at the heart
of the
dispute.
[38] While I accept that the 2017 judgment proceeded on the basis that
there should be no obligation on the part of the levels
I – XI owners to
underwrite or contribute to the cost of repair of the unit property of the
applicant, the provision in the
2010 judgment was not, as I read the 2017
judgment, expressly abrogated. There are reasons in principle which can be put
forward
for justifying a contribution by the level I – XI owners to costs
which benefited their property, being costs of the kind which
were referred to
in cl 21.2 of the scheme (and cited in the 2010
judgment).17
[39] The roof and walls on level XII are part of the unit property of the
applicant. The case for the applicant is that it is possible
that because of the
physical propinquity of the two parts of the building, money expended on
remediating level XII would generate
benefits to the part of the building
below.
Are the counterclaim costs actually covered by cl 21.1 of the
scheme?
[40] Notwithstanding the foregoing conclusion, it is still necessary for the applicant, before it can establish the dispute that it puts forward as a reason why it should not have to pay the amounts referred to in the 2017 judgment, to show that the
counterclaim costs are such that they actually come within the scope of cl
21.2 of the scheme.
[41] Clause 21.2 provides as follows:
Manchester shall not be liable to pay more than 11.88% of the total Cost of
the Repairs carried out pursuant to this Scheme provided
however that any Costs
of Repairs that do not provide benefit to all other individual proprietors or
the body corporate shall be
borne solely by Manchester. The costs that
Manchester contends provide a benefit to all individual proprietors (other than
Manchester)
or the body corporate shall be made available in writing, together
with supporting documentation to the secretary of the body corporate.
Any
dispute about whether benefit is provided to all individual proprietors (other
than Manchester) or the body corporate shall be
determined under the dispute
resolution provisions of this Scheme.
[42] In this regard, the applicant says:
28. These costs concern the level 12 common property and defects to the
main roof and external walls of the complex (which are
a Body Corporate expense
under the Rules). The practical benefit of the costs is plainly enjoyed by all
owners; the Body Corporate
has not suggested otherwise.
29. The set-off claimed in the application, totalling $552,446
(incl GST), is the amount of the consultant and advisor costs Manchester
claims under the proviso to cl 21.2. This amount alone
exceeds the first
statutory demand, but the figure will increase when additional costs incurred
through 31 October 2017 are added
(to be detailed in a supplemental
affidavit).
(Citations omitted)
[43] In his affidavit sworn 14 June 2017, Mr Cummins, who is a director
of the applicant, summarises the reason why costs were
expended for building
surveys, architectural design and other consultancy costs. It becomes apparent
that remediating the roof was
a very expensive exercise in terms of professional
fees. Consulting engineers had to be retained to advise on the loadings that
would be imposed on the structure as a result of the redesign.
[44] However, it becomes apparent that there is a tension between the position which the applicant is taking and the parameters of the 2017 judgment. The evidence which the applicant puts forward comes close to saying that because the work on level XII is concerned with the roof, it is to be implied therefore that the consultancy costs expended on the repair work must have been for the benefit of the other owners as
well. However, when the 2017 judgment was issued, it cannot have been
overlooked that one effect of the judgment would be that, unless
costs such as
this were explicitly carved out from the costs for which the applicant would be
responsible, the applicant would be
required to pay for the roofing costs
regardless of any element of benefit accruing to the owners of the lower levels
as a result
of the work. It may be inferred, therefore, that these types of
costs were not intended to be recoverable by the applicant and that
therefore
even if there was no explicit direction displacing cl 21.2, it was implicit in
the judgment that the clause would no longer
have any effect or, alternatively,
it would not have the effect of extending to general roofing repairs as the
applicant now contends.
[45] There are other complexities with regard to trying to harmonise both
the 2010 and the 2017 judgment. The 2017 judgment does
not contain any
pronouncement on whether funds which may have been expended in reliance upon the
terms of the 2010 judgment were
not to be recoverable (once the 2017 judgment
amending the earlier scheme took effect).
[46] Another matter bearing on the question is the fact that the amended
order which was eventually issued by the court pursuant
to the 2017 judgment
specifically retained the reference to the applicant being entitled to recover
project management consultants
costs, with the exception of those that “do
not provide benefit to all other individual proprietors or the body
corporate”.18 It is difficult to understand why the provision
should have been retained in the order which was sealed by the court if, as the
respondent
apparently contends, the claims for project management consultants
costs in relation to the level XII work were considered by the
judge when
reviewing the scheme and disallowed.
[47] In summary, to this point, the applicant is able to claim that it has
a counterclaim, set-off or cross-demand pursuant to s
290(4)(b) of the
Act.
The factual question of whether the repairs on level XII benefited the
other owners
[48] The next question concerns the matter of whether, assuming that it
cannot be resolved whether the applicant lost its entitlement
to recover costs
under cl 21.2 as a result of the amendment of the scheme, the professional
services for which partial reimbursement
of costs is now sought actually did
provide any benefit to the proprietors of the lower level units.
[49] The evidence Mr Cummins filed in this proceeding appears to assume that because the applicant carried out repairs to the upper levels of the building, there must, ipso facto, have been benefit to the proprietors of the lower level units. Once again, uncertainties about the effect of the variation orders made in the 2017 judgment arise for consideration. The question is whether claiming on the basis just outlined is at such variance with the orders which were made by the court that it cannot be correct. The basis for stating matters on those terms is that the 2017 judgment was expressed as marking a return to the principles of the Unit Titles Act 2010,19 which would mean that the proprietor of level XII, the applicant, would be obliged at its own cost to meet the repairs of its own property. Much of the level XII structures though, including the roof, were part of the unit property of the applicant and were not common property. To recover costs for repairs to the unit property would cut across the explicit basis of the 2017 judgment. But if the applicant is not able to recover costs on the basis which Mr Cummins implicitly relies upon, what meaning can be attached to the relics of cl
21.2 which were not expressly abrogated in the terms of the order submitted to the court for sealing by the parties? Could the operation of the clause be limited to project management consultant’s costs for professional services that contributed to work both carried out on level XII and the levels below? The evidence before the court does not establish whether there is any factual basis for concluding that there was work which fell into that category. Theoretically, if the project managers had carried out work which facilitated or assisted work to be done to the common property below level XII, it would come within the literal wording of the residual provisions of cl 21.2.
[50] The 2017 judgment was clear in the determination to return the cost
sharing basis for the repairs to the building to that
which was prescribed in
the Unit Titles Act. As part of that, it included a more rigorous insistence
upon categorisation of costs,
which were either to the owners’ units or
the common property. There was to be no blurring between the two. Why cl 21.2
was
retained at all in these circumstances is not clear, as I have already
stated. Why it was restricted to only professional services
of project
management consultants is not clear either.
[51] To return to the central point, though, s 290(4)(b) of the Act
requires the court to “be satisfied” that after
taking account of
the counterclaim, set-off or cross-demand, there is an amount owing that is less
than the prescribed amount.
[52] The question then is whether the interpretation which the applicant
attaches to cl 21.2 as it appears in the amended scheme
is correct. Does the
provision mean that any funds expended on level XII for project management
services relating to the roof and
external walls automatically qualify as being
for the benefit of the owners of the lower-level units in the apartments? My
conclusion
is that such an interpretation is not sustainable, having regard to
the overall approach that the judge took in the 2017 judgment.
[53] If cl 21.2 is not to be treated as a dead letter, it may be possible
that there may be a different type of narrow benefit
that cl 21.2 is aimed at.
The type of benefit envisaged may, in other words, not be a benefit that is
inferred to accrue to the
rest of the building because of enhancements that are
carried out to the top level of the building. It may be possible that project
management information, which was generated at the same time as the level XII
remediation is in progress, solved a problem for the
levels I – XI owners
about how to construct the interface between the two parts of the building, thus
freeing them from the
cost of expending funds in obtaining professional advice
on that question.
[54] Whatever the correct approach is, the way that the case has been put before me does not suggest that it is correct that cl 21.2 envisages the recovery of the costs of
remediation of level XII on the ground that they must be assumed to result in
benefits
being provided to “all individual proprietors (other than
Manchester)”.20
[55] The interpretation of the 2017 judgment is not something
that can be undertaken in the course of deciding the
originating application
proceedings which are before the court. It is incumbent on a party in the
position of the applicant, though,
to at least suggest how a court faced with
the task of interpreting the judgment against the background of the 2010
judgment, in
the change of circumstances since, could reason its way to a
conclusion that matches what the applicant puts forward about the meaning
of cl
21.2 that supports the applicant’s argument in this case.
[56] There is also a factual issue in addition to that of the interpretation question. That arises in regard to the amount of the claim based on cl 21.2. The evidence which has been put forward on behalf of the applicant does not enable the court to come to any view as to whether any part of the funds which were outlaid by the applicant on the costs of project management consultants comes within the provisions of cl 21.2. Inferences are just not an adequate basis to assume that this factual issue has been satisfied. For all the court knows, advice may have been received from consultants about such diverse matters as the aesthetics of the level XII remediation, as well as the thermal efficiency of the roofing structure and wall claddings in regard to the level XII part of the building. The advice may have been received on the relative economies of adopting one form of construction or choice of materials over another which would only advantage the level XII owner by reducing the cost of the repair. While it would not be consistent with the principles upon which applications of this kind are decided to insist upon a rigorous analysis of the benefit to the other parts of the building, having regard to considerations such as those I have just listed, and perhaps others, at least some attempt ought to have been made to confront the point. I am not satisfied that it is seriously arguable that the costs which were expended by the applicant resulted in
benefit to the other owners in the body
corporate.
20 Clause 21.2.
Set-off disposed of by the 2017 judgment?
[57] It was also submitted for the respondent that the claim for a
set-off of the cl
21.2 amounts had been considered and dismissed by the court when giving the
2017 judgment. In my view, Mr Harris for the applicant
correctly stated the
position when he said that self-evidently these matters were not raised for
consideration by the court and that
there is no reference to them in the 2017
judgment.
[58] The alternative approach which the respondent took was that even if
the matters had not been dealt with or raised as part
of the 2017 judgment, they
ought to have been. This alternative approach was not pleaded in the notice of
opposition which the
respondent filed.
[59] The ground is based upon strike out, more specifically abuse of
process:21
Bhanabhai v Commissioner of Inland Revenue.22 As has been
made clear by recent authority,23 the question of whether this type
of argument will prevail is not resolved simply by enquiring whether the claim
for relief could
or could not have been brought in earlier proceedings. An
assessment is required of the background and a “broad, merits-based
judgment” must be undertaken.24 This will take account of
the public and private interests involved and the facts of the case in order to
determine whether a party
is misusing or abusing the processes of the court by
seeking to raise an issue which could have been raised before.
[60] I do not consider that the court has sufficient material before it which enables this type of judgment to be undertaken. As I understand it, the remediation of level XII of the apartment building continues to this day. While it may seem surprising that it has not been possible to dispose of these issues in litigation spanning some seven years, there may be a reason why the issue about the cross-claim has yet to be brought to judgment. While there has been some apparent reluctance on the part of the applicant to meet its due share of the operating expenses of the complex in the form
of ordinary levies, it is not sufficiently clear that it is reluctance
to make payments that
21 High Court Rules, r 15.1(1)(d).
22 Bhanabhai v Commissioner of Inland Revenue [2006] NZCA 368; [2007] 2 NZLR 478 (CA) at [59]- [61].
23 Beattie v Premier Events Group Ltd [2014] NZCA 184 at [44]- [45].
24 Johnson v Gore Wood & Co (a firm) [2002] 2 AC 1 (HL) at 31.
is driving the late introduction of the set-off to the current litigation.
The party should not be prevented from raising an issue
in proceedings on the
ground of abuse of process unless there is some persuasive evidence showing that
the issue has been raised
at a late stage in order to obtain some illegitimate
advantage. A predisposition to resist making payments of body corporate dues
would not in my view seem to provide a solid basis for assuming that it is
abusive for the applicant to raise this issue in these
proceedings.
[61] The just outcome, I consider, in relation to this issue is that this
is not a clear case where an abuse of process argument
should be accepted with
the result that the applicant is barred from raising the set-off. This ground
of opposition is therefore
disregarded.
Amounts already recovered in litigation
[62] A further ground of opposition to the application is that it is not
open to the applicant to rely upon non-payment of the
project management
invoices in relation to cl 21.2 because it, the applicant, has already recovered
full payment of all qualifying
costs through an award of damages that was made
in its favour in the Weathertight Homes Tribunal
(“WHT”).
[63] The evidence which has been submitted by the respondent in supporting this particular ground of opposition comprises an affidavit by Mr Samuel, the chairman of the respondent. He in turn annexes to his affidavit the particulars of claim which were filed by the applicant in the WHT and an affidavit from a quantity surveyor, Mr Maddren. While I agree that the evidence does provide indications that project management type costs were claimed in the tribunal, it is far from certain that the award of compensation which was forthcoming, $2,000,000, actually included and extended to the cl 21.2 costs. I do not therefore consider that the affirmative matters that the respondent relies upon under this ground of opposition are established with sufficient certainty to amount to a separate ground upon which the originating application for order setting aside the statutory demand ought to be declined. In the end though that does not make any difference to the outcome in this case because of the conclusion that I have reached on other grounds that the application fails.
Conclusion concerning first statutory demand
[64] I conclude that the applicant does not have an arguable set-off
arising from cl
21.2 in the sum of $552,446 which it can set off against the amounts claimed
for in the first statutory demand.
[65] According to my calculations, if the set-off claimed in regard to
items arising under cl 21.2 is ignored, the approximate
amended amount of the
statutory demand ought to be $391,043.98. This figure may, however, be affected
by considerations of interest,
costs and possibly GST.
[66] The result of that conclusion is that the remaining set-off and
cross-claims which the applicant puts forward as a ground
for setting aside the
statutory demand are not sufficient order to bring the amount which is claimed
in the statutory demand beneath
the statutory minimum claim prescribed by s
289(2)(a) of $1000.25
The second statutory demand
[67] The second statutory demand is in the sum of $206,919.47, which is
the amount which the applicant was ordered to pay by the
costs judgment as costs
on the variation proceeding which resulted in the 2017 judgment.
[68] The applicant claims to be able to offset its legal costs relating to
the 2010 judgment of the High Court when Heath J settled
the rebuilding scheme.
As part of the orders that Heath J made as part of that judgment, he directed
that the costs of each party
were to be costs in the scheme and were to be met
by levies. This order was not affected by the 2017 judgment. The applicant
claims
that costs for the first stage of the litigation to which it is entitled
amount to $132,605.32.
Background to second statutory demand
[69] The issue that arises in respect to this matter is as follows.
[70] The first issue is that the applicant submits that the costs order
which it obtained as a result of the pooled costs direction
that Heath J gave
has never been paid to it or applied to its credit.
[71] The respondent asserts that it gave credit for the costs amount,
albeit payment of levies on a without prejudice basis, when
it took proceedings
to enforce a claim for levies against the applicant by issuing a statutory
demand in or about April 2011. In
the body of the statutory demand, the
respondent stated the amount that was being sought, noting that the amount was
arrived at after:
without prejudice giving you credit of $132,605.62 on account of money is
claimed by you to be costs of repairs
[72] It is a little difficult to understand why the wording set out above
was actually adopted because the claim is apparently
for legal
costs.
[73] The amount which the applicant claimed for the proceedings leading
up to the
2010 judgment was the sum of $132,605.32.
[74] In 2012, the applicant says the body corporate questioned the
reasonableness of the charges which the applicant was seeking
to recover from
it.
[75] The background thereafter becomes rather confused. Questions arise as to whether or not there ever was a credit given, whether a statement that a credit was being given on a without prejudice basis was effective for purposes about to be discussed, and whether the costs judgment number 4 that Heath J made following the
2010 judgment survived the 2017 judgment (and which has since been considered
on appeal by the Court of Appeal).
[76] The Court of Appeal reviewed the costs judgment, reciting that
Fogarty J had directed that the costs be pooled and treated
as costs of the
scheme, with the consequence that they would be paid out of levies.26
The Court then went on to say:
[74] More controversially in his costs judgment, Fogarty J also set aside
Heath J’s 2011 costs order. Justice Fogarty considered he had
jurisdiction to do that because Heath J had made his costs order not under
the High Court Rules but under s 48 of the Unit Titles Act
...
[77] The Court of Appeal noted27 that there were some
reservations with the order that Fogarty J made, with the costs judgment
recording:28
[24] Justice, however, requires some applications of the direction that
the solicitor and own client costs and disbursements
of both the Body Corporate
and Manchester Securities Ltd shall be regarded as costs of the Scheme. To the
extent that paragraph [17]
of judgment number 4 (dealing with costs) has been
applied between the parties by the Body Corporate prior to March 2013, I do not
think those application should be disturbed.
Costs post-March 2013
[25] However, from 18 March 2013 [the date the Body Corporate filed its
application for a variation], in my view it would be
quite unjust for
Manchester’s legal and client costs in opposition to the application to
vary the Scheme, to be allocated pursuant
to [the 2011 costs order]
...
[78] The outcome of these various matters, as well as subsequent
communications between the parties which the Court of Appeal
referred to at
paragraphs [80] and following, was to the effect that the credit in regard to
the $132,605.62 costs order was preserved
by the 2017 judgment. It is
noteworthy that it was the credit that was preserved when the Body Corporate
apparently concluded that,
on a without prejudice basis, it would “credit
[the] building levy account with the sum of
$132,605.62”.29
[79] The Court of Appeal apparently concluded that there had been an application of the amount of the costs order prior to March 2013 and that therefore even though Fogarty J abrogated part of the costs orders that accompanied the 2010 judgment, the part relating to $132,605.62 remained claimable by the applicant even though the respondent, when acknowledging such an entitlement, did so on a without prejudice basis.30 The eventuality against which it was acknowledged on a “without prejudice” basis was the possibility that the respondent would challenge the amount of costs,
presumably on the basis of quantum.
27 At [74].
28 Body Corporate 172108 v Manchester Securities Ltd, above n 4.
29 Body Corporate 172108 v Manchester Securities Ltd, above n 4, at [80].
30 At [81]-[83].
[80] As I understand it therefore, the costs order which was made is
enforceable. However, it is presumably open to any legal
challenge that the
respondent is able to bring against it. Neither the judgment of the two High
Court judges nor the Court of Appeal
judgment fixed the quantum. The
$132,605.62 is the amount which the applicant claims is owing. The respondent
has yet to unequivocally
admit liability for that sum. If it does not, then it
must be open to the applicant to seek an order either by arbitration or through
the court fixing the amount of the costs.
[81] The issue then becomes where this leaves the court on determining
the present application. There is no doubt that the court
actually made the
costs order in the 2017 proceedings which is the basis of the statutory demand.
However there is also no doubt
that Heath J made the orders which the applicant
intends to use as a set-off. The Heath J order was varied by the judgment of
Fogarty
J. As a result of those variations the question arises whether the
parties had taken any steps to implement the Heath J costs order
prior to March
2013. If they had, it is now too late to undo the effect of Heath J’s
order. So long as there is doubt on
that issue, it seems to me that there is a
reasonable argument available to the applicant that the conditions which Fogarty
J attached
have or have not been satisfied.
[82] In addition, the applicant contends that it should be entitled to interest on the unpaid costs in the sum of $85,055, meaning that the entire amount for which the applicant arguably has a right of set-off would seem to be approximately $220,000.31
If that figure is adopted, then it exceeds the amount of the second statutory
demand of
$206,919.47. On that basis, justice in my view requires that the application
to set aside statutory demand ought to succeed. There
will be an order
accordingly.
Costs
[83] The parties should confer on the issue of costs and, if they are
unable to agree, are to file memoranda not exceeding four
pages on each side
within 20 working days.
31 The sum of the costs order of $132,605.62, plus interest which the applicant claims of
$85,055, totals $217,660.62 as I calculate it, slightly less than the figure
which the applicant has adopted.
J.P. Doogue
Associate Judge
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2018/169.html