Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 9 October 2018
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE
CIV-2015-485-933 [2018] NZHC 1705
BETWEEN
|
ACE DEVELOPMENTS LIMITED
Appellant
|
AND
|
ATTORNEY GENERAL Respondent
|
Hearing:
|
5 March 2018
|
Appearances:
|
G D Jones and J Patrick for Appellant
P H Higbee and E J Couper for Respondent
|
Judgment:
|
11 July 2018
|
JUDGMENT OF NICHOLAS DAVIDSON J
A.
|
Introduction
...............................................................
|
[1]
|
|
Nub of the appeal
.........................................................
|
[7]
|
B.
|
Before the Panel
...........................................................
|
[10]
|
|
Mr Hill’s submission to the Panel for Ace
.............................
|
[12]
|
|
The Panel Report
..........................................................
|
[18]
|
C.
|
Litigation Antecedent to appeal
.......................................
|
[29]
|
|
Ace Developments Limited v Attorney-General (High
Court)......
|
[30]
|
|
Ace Developments Limited v Attorney-General (Court of
Appeal)
|
[46]
|
D.
|
The submissions on appeal
.............................................
|
[60]
|
|
The competing positions
..................................................
|
[60]
|
|
For Ace
......................................................................
|
[62]
|
|
For the Crown
.............................................................
|
[74]
|
E.
|
Discussion
..................................................................
|
[87]
|
|
“Business”
..................................................................
|
[87]
|
|
First alleged error – failure to allow disturbance costs
.............
|
[88]
|
|
Second error alleged – valuation, legal costs and other
............
|
[96]
|
F.
|
Disposition
..................................................................
|
[104]
|
ACE DEVELOPMENTS LTD v ATTORNEY GENERAL [2018] NZHC 1705 [11 July
2018]
A. Introduction
[1] This judgment is concerned with the correct measure of compensation
for property compulsorily acquired (“taken”)
by the Crown for the
Metro Sports Facility in Christchurch, part of the rebuild of the city after the
Canterbury Earthquake sequence
which began in September 2010.
[2] Ace Developments Limited
(“Ace”) owned property at
115-117 Moorhouse Avenue, Christchurch, which was developed and leased to car
dealers, Ace Sales Limited and Orix Car Sales. It was
taken by proclamation
under the Canterbury Earthquake Recovery Act 2011 (“the CER
Act”) and vested in the Crown on 14 August 2014.
[3] Part 2, sub-pt 5 of the CER Act established a process to
determine compensation, and while that Act was repealed
by the Greater
Christchurch Regeneration Act 2016 (“the Regeneration
Act”), compensation claims not completed ran on under the CER
Act.
[4] Ace lodged a claim for compensation on 24 April 2014, seeking
$8,135,029 which included the purchase of land in Moorhouse
Avenue in
substitution for that taken. A Compensation Panel (“the
Panel”), heard the claim on 26 June 2015 and the Associate Minister,
as the Minister’s delegate, attended the hearing. The
Panel reported to
the Associate Minister and a decision issued on 29 October 2015 held that Ace
was entitled to compensation of $3,378,899.11
plus interest.
[5] Ace appeals against that decision under s 69(1A) of the CER Act, to which appeals pt 20 of the High Court Rules applies. The appeal proceeds by way of rehearing. It involves analysis of the evidence given before the Panel. Ace sought to improve its evidential position by seeking leave to adduce additional evidence on this appeal, but leave was refused by Gendall J,1 and an appeal against that
judgment was also dismissed.2
1 Ace Developments Ltd v Attorney-General [2016] NZHC 2467.
2 Ace Developments Ltd v Attorney-General [2017] NZCA 409, [2017] 3 NZLR 728.
[6] In response to the judgments which refused leave to adduce further
evidence, Ace has narrowed its claim on appeal, recognising
that parts of its
claim cannot stand. It no longer seeks compensation for the cost of purchasing
substitute land, but says it should
have the costs of developing a substitute
site so that its improvements are equivalent to those taken. That includes
the costs of demolition, erecting new buildings and finding
a tenant. Ace
intended to develop two adjoining parcels of land at 63 and 69 Moorhouse Avenue
as a substitute site, but now intends
only to acquire and develop 63
Moorhouse Avenue from a company with which it is associated through
shareholding.
It seeks compensation to develop the same building which
it intended to put on two sites, as costed by Rawlinsons Quantity
Surveyors
(“Rawlinsons”) on one site of 2,132m2. The land
taken was 2,395m2.
Nub of the appeal
[7] The nub of this appeal, with some ancillary issues, is whether Ace
can claim the cost of developing the site at 63 Moorhouse
Avenue, in order to
lease it for car sales, as a “disturbance” payment under s 66 Public
Works Act 1981 (“PWA”), or whether it has been fully
compensated when paid the value of the property taken, which included
improvements. It says
it has not been paid the “full compensation”
to which it is entitled, whereas the respondent says that Ace
has
received full compensation and that:
The claimed amounts relate to an unreasonable development proposal, allow for
double recovery or betterment, or are unsupported by
the evidence, and are
therefore unrecoverable.
[8] Ace’s disturbance claim was rejected in part because the cost of purchasing replacement property, in this case land, is not a valid disturbance cost. The Court of Appeal held that to be correct, and Ace does not challenge that.3 A claim of $820,000 for loss of “capital value” is no longer pursued. However, Ace still challenges the Panel’s finding that neither it nor any reasonable business person would spend $6,549,000 to gain an asset worth $2,580,000 and submits the Panel and the Minister were wrong in fact and in law as it has not received “full
compensation”.
3 Ace Developments Ltd v Attorney-General, above n 2, at [82].
[9] The claim now made, with 69 Moorhouse Avenue no longer part of
Ace’s
plans, is expressed as follows:
Demolition costs (at 63 Moorhouse Avenue)
|
$35,000
|
Cost of building
|
$2,627,000
|
Leasing fees
|
$47,000
|
Total disturbance claim
|
$2,709,000
|
Less (69 Moorhouse Avenue)
|
- $650,000
|
|
$2,059,000
|
B. Before the Panel
[10] The claim for disturbance costs arising out of relocation was
made as follows:
Cost to buy 63 Moorhouse Avenue
|
$2,275,000
|
Cost to buy 69 Moorhouse Avenue
|
$1,500,000
|
Cost to demolish existing buildings
|
$100,000
|
Cost of new building
|
$2,627,000
|
Leasing fees
|
$47,000
|
Total
|
$6,549,000
|
Less value 115 Moorhouse Avenue
|
- $3,400,000
|
|
$3,149,000
|
[11] The Panel did not accept that Ace or any other reasonable person would spend $6,549,000 to generate an asset (including 63 and 69 Moorhouse Avenue)
which on the evidence would be worth only $2,580,000 It
said:
And
54. We note that the new development at $2,580,000 is
worth substantially less than its cost of $6,549,000
meaning that it is
uneconomic and not a project that any well informed investor would enter. The
claim therefore infringes the claimant’s
duty to mitigate its
loss.
56. We agree that it is reasonable for a car sales business to relocate to Moorhouse Avenue but not reasonable to do it at any cost. According to Mr Alexander, Ace was prepared to spend $6,549,000 to obtain an asset which would be worth, on Mr Reid’s figures,
$2,580,000. We do not consider that a reasonable businessman would do it and despite his assertions to the contrary we do not
believe that Ace (or Mr Alexander) would do it either. As the Privy
Council said, the greater the disparity the more scrutiny is required and this supports our conclusion.
Mr Hill’s submission to the Panel for Ace
[12] Mr Hill presented the claim for compensation by Ace. The total built
area at
115-117 Moorhouse Avenue was 697.2m2 with 1,725m2 of
sealed yard. Most of the property was used by an international vehicle leasing,
financing and retail company, Orix, and a smaller
part at the rear was leased to
Ace Sales Limited. After the Canterbury earthquake sequence, the improvements
were repaired to an
“as new” condition, to Code. This work was
extensive, including replacing most of the concrete tilt slab panels, and
pouring new concrete for most of the building.
[13] Mr Hill submitted compensation should cover relocation of
Ace’s business to another site, and its re-establishment.
He said even
if those costs exceeded the present value of the business, this is not a bar to
compensation on a relocation basis,
citing the Privy Council in Director of
Buildings and Lands v Shun Fung Ironworks Limited (“Shun
Fung”).4 Mr Hill said that Ace could not
obtain an existing property to replicate what was taken, so it found suitable
land to erect
a replacement building, and it relied on s 60 PWA, which states
that the owner of the land taken should have “full compensation”.
He took that expression to mean sufficient compensation to put the land owner in
the same or similar position as if the take had
not occurred.5
The land owner should obtain no more and no less than full compensation,
under the “principle of equivalence”. Ace acquired
no more land than
was needed and it should be neither worse nor better off after the acquisition
has occurred. He called in aid
the Hellenic deities Themis and Dike,6
and the necessary balance between the powers of the Crown and the
rights of citizens. Less prosaically, he referred
to Lord Nicholls’
statement in Shun Fung, which is discussed below.
[14] Mr Hill referred to s 62 PWA which (relevantly)
reads:
4 Director of Buildings and Lands v Shun Fung Ironworks Ltd [1995] 1 All ER 846 (HKPC).
62 Assessment of
compensation
(1) The amount of compensation payable under this Act, whether for
land taken, land injuriously affected, or otherwise, shall
be assessed in
accordance with the following provisions:
(a) subject to the provisions of sections 72 to 76, no allowance shall
be made on account of the taking of any land being compulsory:
(b) the value of land shall, except as otherwise provided, be taken to
be that amount which the land if sold in the open market
by a willing seller to
a willing buyer on the specified date might be expected to realise,
unless—
(i) the assessment of compensation relates to any matter which is not
directly based on the value of land and in respect of
which a right to
compensation is conferred under this or any other Act; or
(ii) only part of the land of an owner is taken or acquired under this
Act and that part is of a size, shape, or nature for
which there is no general
demand or market, in which case the compensation for such land and the
injurious affection caused
by such taking or acquisition may be
assessed by determining the market value of the whole of the owner’s land
and
deducting from it the market value of the balance of the owner’s land
after the taking or acquisition:
(c) where the value of the land taken for any public work has, on or
before the specified date, been increased or reduced by
the work or the prospect
of the work, the amount of that increase or reduction shall not be taken into
account:
(d) the special suitability or adaptability of the land, or of any
natural material acquired or taken under section 27, for
any purpose shall not
be taken into account if that purpose is a purpose to which it could be applied
only pursuant to statutory
powers, or a purpose for which there is no market
apart from the special needs of a particular purchaser or the requirements of
any
government department or of any local authority:
(e) the Tribunal shall take into account by way of deduction from that part of the total amount of compensation that would otherwise be awarded on any claim in respect of a public work that comprises the market value of the land taken and any injurious affection to land arising out of the taking, any increase in the value of any land of the claimant that is injuriously affected, or in the value of any other land in which the claimant has an interest, caused before the specified date or likely to be caused after that date by the work or the prospect of the work:
...
(3) Where any lessor’s or lessee’s estate or interest in
any land is taken or acquired under this Act, such estate
or interest may, if
required by its owner, for the purpose of assessing compensation under this Act,
be valued separately from the
freehold.
[15] Mr Hill said that the Panel and the Crown had wrongly focused on
the “current market value of the land”.
He referred to
Sir Wilfrid Greene MR’s comment in Horn v Sunderland
Corporation, where damage suffered by an owner as the result of
“disturbance”, for example of a business, is not a separate head
of
compensation such as injurious affection, but an element going to build up the
compensation to which the owner is fairly entitled.7
[16] In Shun Fung, Lord Nicholls referred to the value of land as
the value to the claimant, not its value generally, or to the acquiring
authority, so if the land is being used to carry on a business, there is value
in being
able to conduct that business there without disturbance.8
Compensation should cover the “disturbance loss” as well as
the market value of the land. If the business cannot be moved elsewhere,
then prima facie the loss is the value of the business as a going concern. The
“business” may lose value through the
effect of acquisition.
Together, these elements make up a “single whole” being the value of
the land to the owner.
Mr Hill then said compensation should allow for the
replacement of the property “like for like” together
with
costs of relocation, so Ace should have sufficient funds “so that it is
left in a neutral situation”, no worse and
no better off than if the
acquisition had not occurred.
[17] Mr Hill recognised that s 66 PWA sets out specific heads of disturbance that may be claimed, but the list is expressly not exhaustive, and he accepted there must be a causal connection between the loss for which compensation is sought and the acquisition, so losses are not too remote, and the claimant must have acted reasonably. He said a reasonable business owner, in the same “business” as Ace, should be compared with an Oakwood Properties’ (“Oakwood”) development to
house Blackwells, a prominent car sales business in Christchurch. In
short, Mr Hill
7 Horn v Sunderland Corporation [1941] 1 All ER 480 at 484.
8 Shun Fung Ironworks Ltd, above n 4, at 852.
said that if Ace was denied sufficient funds to properly relocate its
business the
Crown would have failed to provide Ace with such
“equivalence”.
The Panel Report
[18] The claim by Ace was described as follows:
4. The amount claimed for the loss of the land is $3,400,000 plus GST (if any)9 which is based on a peer review valuation obtained from Mr Reid Quinlan.
5. Ace also has subsidiary claims which in total exceed the main
compensation claim. They are as follows:
Disturbance-substitute property
|
$3,400,000
|
Disturbance-land value
|
$820,000
|
Sign relocation
|
$47,627
|
Disruption to income
|
$623,263
|
Legal and other costs on substitute site
|
$42,470
|
Legal/valuation fees for claim
|
$48,669
|
Accounting costs
|
$4,000
|
|
$4,986,029
|
[19] The Panel found that the current market value to be compensated is
not the value to the owner, but to hypothetical parties in the market.
“Full compensation” paid under pt 5 PWA means payment of such money
as “will
place the affected owner in as similar a position as possible to
the position existing prior to the acquisition, injurious affection
or
damage”.10
[20] As the Panel observed, a claimant’s position should not be
improved, but be restored. For consequential loss to be
compensated, it must be
directly caused by the take, so as not to be too remote. There is a duty to
mitigate loss caused by the take.
[21] The Panel said that disturbance under s 66 PWA does not include the capital cost of replacement property. It rejected the notion of a claimant being put “in the same position” whatever the cost of that, but rather that the Crown should provide “equivalent value”. In Shun Fung, the Privy Council held that a claim based on
relocation may exceed the amount payable for the land acquired, but the
claimant
9 Unless stated otherwise all amount[s] in the report are plus GST if any.
10 Napier Lane Ltd v Minister of Lands LVP08/07.
had to establish its business could be relocated, that it intended to
relocate, and that a reasonable business owner using his/her
own money would do
so.11 The greater the disparity between compensation on an
extinguishment basis, and on a relocation basis, the more closely it will be
scrutinised, because it is less likely that a reasonable businessman would spend
more money than the value of the land taken. This
reflects, as I understand
it, the “law” of diminishing returns.
[22] The Panel did not accept that Ace was conducting a business
on the land, but instead renting out premises. (I return to this, as I
conclude this appeal does not involve the displacement of a
“business” on the land taken).
[23] Under a Discounted Cash Flow (“DCF”) model
with a slightly lower terminal capitalisation rate, the Panel reached a value
of $3,315,000 and applying the same
valuation methodology as valuers Telfer
Young and Knight Frank, it concluded the current market value was net
$3,300,000.
[24] The claim before the Panel included the purchase of properties at 63
and
69 Moorhouse Avenue, for $3,775,000. As set out above, a new building would
cost
$2,627,000 with $100,000 for demolition and $47,000 leasing fees, a
total of
$6,549,000. The difference between that and the $3,400,000 for the land
taken,
$3,149,000 was said to be the disturbance cost.
[25] The Panel was not aware of any case which held that the cost of building alternative premises, beyond the value of the property taken, is a recoverable disturbance cost. Mr Reid’s evidence was that after development, the replacement site would have a value of $2,580,000, which is $820,000 less than the value of the land taken, but at a “cost” of $6,549,000. (This included land purchase at 63 and
69 Moorhouse Avenue). The Panel said that outcome would be uneconomic and no well-informed investor would entertain that course. The Panel said it was not reasonable to relocate to Moorhouse Avenue at any cost, and reliance on Shun Fung went only so far because Ace was not relocating a business, but purchasing a substitute investment property. If Ace conducted a car sales business, it could have
claimed the costs of setting up facilities for that purpose, but not the
cost of the land
11 Shun Fung Ironworks Ltd, above n 4, at 853.
and buildings. The Panel considered there was no sound legal basis for the
claim and no compensation for development should be allowed.
[26] The claim for disturbance to income based on
“business” interruption was said to apply between the date of the
take and the date a replacement was to be available
on interval from 14
August 2014 to 1 January 2017, when Ace Sales Limited took possession and
moved vehicles onto the
premises and displayed them for sale.
[27] In the end, s 61(b) of the CER Act was engaged, and the Panel found
that compensation excludes claims for economic and consequential
loss and for
business interruption. It held that a claimant must carry on business on the
land acquired, and Ace was just an investor landlord.
[28] The Panel recommended $6,860 be paid for the BBK and Knight Frank accounts, $1,640 for a further invoice, legal fees of $10,000, and $3,000 for one half of Grant Thornton’s fee, and it made a recommendation that Ace be reimbursed
$57,399.11 for the cost of relocating signage.
C. Litigation Antecedent to Appeal
[29] The litigation in the High Court and the Court of Appeal is relevant
to this appeal.
Ace Developments Limited v Attorney-General (High
Court)12
[30] Ace sought to adduce evidence on this appeal being:
(a) Evidence as to the sums being invested and likely return on such
investment by other business people acquiring land in
the vicinity of Moorhouse
Avenue, Christchurch, for development as motor vehicle dealerships.
(b) Expert evidence comparing the economics of the
appellant’s proposal to relocate its business to another
site in Moorhouse
Avenue against the economics of the investments of the other business
people making or proposing similar
projects.
12 Ace Developments Limited v Attorney-General, above n 1.
[31] The Associate Minister disallowed part of Ace’s claim because
no reasonable businessperson using their own money would
undertake the
development project proposed by Ace. Ace complained that it could not get
evidence to support its case because it
had no power of compulsion to put
evidence before the Panel, and further evidence was necessary to establish its
compensation position.
The explanation was said to constitute “special
reasons” for it to be given leave.
[32] Mr Hill, in support of Ace’s application, said that he
“understood” that its legal team approached Oakwood
and Cockram for
information about the Oakwood development but could not obtain it, so Mr Hill
simply gathered what information he
could from publicly available
sources.
[33] The application to adduce further evidence was opposed by the
respondent, on the grounds that it was not relevant because
the CER Act does not
provide for compensation for the purchase and redevelopment of a substitute
property, and the question of “reasonableness”
of Ace’s
development was addressed before the Panel and the Associate Minister, so it was
not new or fresh.
[34] Reservations about the reasonableness of Ace’s proposed course
of action had been put to Ace’s advocate by the
Panel, and mentioned in
the draft report of the Panel of 25 August 2015, to which supplementary
submissions were made but no additional
evidence was provided. Ace said the
reasonableness of its development proposal was irrelevant, and Gendall J held
that it could
not simply recast its case on appeal, but had to live with the
strategy it adopted before the Panel and the Associate Minister; it
had
“nailed its colours to the mast”. There was nothing to support
Ace’s case that it could not obtain evidence
just because there were no
powers to compel it. Hearsay evidence in Mr Hill’s affidavit did not
support that, and the Court
said it could have obtained expert evidence which it
sought to adduce prior to the compensation decision being made. Gendall J found
that Mr Hill’s affidavit lacked certainty as to what enquiries he made, of
whom, and whether there was another source of information
of the kind Ace sought
to put before the Court on appeal.
[35] For the respondent, it was submitted that if the proposed evidence was to be adduced on appeal, the process undertaken before the Panel and Associate Minister
would have been nothing more than a “dummy run”. Gendall J
referred to Ace’s contention that to acquire and develop
an equivalent
property would cost in the region of $8,000,000 rather than the $3,300,000
compensation it received, and for that proposition,
it referred to Shun
Fung.13
[36] Leave to adduce further evidence will be sparingly granted because
appeals essentially proceed on the record of the initial
decision maker. New
evidence must not only be cogent and likely material, but such that it could not
reasonably have been discovered
at an earlier stage.14 Litigants
must in general put their best case forward at first instance and live with the
litigation strategy adopted. There are
of course recognised exceptions where
there is a good explanation and no prejudice or unfair disadvantage to another
party.
[37] Gendall J held there were no special reasons to allow new evidence on this appeal. Mr Hill chose to argue before the Panel and the Associate Minister that the evidence which it sought to adduce on appeal was irrelevant. The Panel asked Mr Hill whether a reasonable company in the business of owning land would expend over $6,500,000 to acquire a property which would in the end have a value below
$2,500,000 and Mr Hill said that it did not matter what the value was at the
end of that exercise, as the question is whether someone
would spend that
money, not what the fiscal outcomes would be. This was truly “nailing
Ace’s colours to the mast”.
[38] The role of the Court (and the role of the Minister) is to consider if, on an objective basis, the course of action is open to a reasonable businessman given the evidence available. If the course of action is not indeed open to that reasonable businessman, then the Court or the Minister should not, indeed must not, interfere. Gendall J also said that adducing further evidence might well exclude the decision maker from being involved in the final decision and that could not be right, because that is a matter which Parliament has entrusted to the Minister. If leave was granted, the Crown could call its own expert evidence, there would be delay, and the evidence would be quite different from that before the Associate Minister. Ace was simply
trying to change its strategy.
13 Shun Fung Ironworks Ltd, above n 4.
14 Dean Selak Carrying Company Ltd v Lonergan [2015] NZHC 2230 at [27].
[39] In its draft report of 6 August 2015 to the Associate Minister of the Panel, it showed that it knew that Oakwood had an ownership interest in Blackwell, whereas Ace would have to find a tenant. The Panel disagreed that the final value of the premises compared with the cost of establishing them was irrelevant. At the
26 June 2015 hearing before the Panel, Mr Hill made three sets of
supplementary submissions which did not address the reasonableness
of
Ace’s proposed course of action, nor mention the difficulty in
getting further information. The Panel expressed
its reservations about
the reasonableness of Ace’s proposed course of action in its draft report
saying that it was reasonable
for a car sales business to relocate to Moorhouse
Avenue, but not reasonable to do so at any cost. Mr Hill challenged the
Panel and said it was not a court’s role or the role of the Minister to
“superimpose upon the
claimant its view as to what a reasonable
businessman may do” and for that reason Ace chose not to provide any
additional evidence
on the issue of reasonableness.
[40] Although Gendall J found there were no special reasons to grant leave to adduce the evidence in question, and that was the end of the leave application, he went on to hold that the proposed evidence was not material to the appeal. Under s 61 of the CER Act “compensation” excludes economic or consequential loss unless provided by that Act. It is not defined as “consequential loss” but Gendall J cited McGregor on Damages:15
The normal loss is that loss which every claimant in a like situation will
suffer. The consequential loss is that loss which is
related to the
circumstances of the particular claimant.
[41] Gendall J addressed the submission that the proposed evidence was not material or relevant to the appeal. Under s 61 of the CER Act, compensation excludes economic or consequential loss except as provided by the CER Act. The statute provides no definition of consequential loss, but it relates to the circumstances of the claimant. He observed that Ace’s business arguably might be that of a landlord leasing commercial properties to high end car dealerships for investment return, and Ace sought to adduce evidence to support its claim for the
costs of acquiring and developing an alternative and equivalent property
to enable it
15 McGregor on Damages (19th ed, Sweet & Maxwell, London, 2014) at [3-0008].
to continue that business. That would fix the compensation to the particular
type of tenant which Ace sought. Gendall J said that
in his view such loss is
not normal or direct, but consequential, and is a loss peculiar to Ace,
so it is not compensatable under the CER Act.
[42] Ace said development costs were compensatable under s 66 PWA as they
fell under “disturbance”. While compensation
is determined as far
as practicable in accordance with the provisions of pt 5 PWA, that does
not oust the statutory definition
of compensation, which is displaced
only where there are strong indications to the contrary, in the statutory
context.
Gendall J thought there is a reasonable argument that s 66 PWA does
not provide for compensation to acquire and develop a substitute
property, whereas disturbance payments such as legal and valuation fees, removal
costs, and improvements not readily
removable from the acquired land, or of a
particular use to a disabled owner, are good examples of disturbance payments
under s 66(1)(a)
and (b) PWA.
[43] Gendall J could not find any authority where s 66 has applied to
award the compensation sought by Ace, but as s 66(1) refers
to “all
reasonable costs”, he accepted Ace’s submission that the word
“including” means the list is
not exhaustive. Ace referred to the
Privy Council in Shun Fung, where a similar statutory provision in Hong
Kong was considered. Gendall J cited this passage:16
The purpose of these provisions ... is to provide fair compensation for a
claimant whose land has been compulsorily taken from him.
This is sometimes
described as the principle of equivalence. No allowance is to be made because
the resumption or acquisition
was compulsory; and land is to be valued at the
price it might be expected to realise if sold by a willing seller, not an
unwilling
seller. But subject to these qualifications, a claimant is entitled
to be compensated fairly and fully for his loss. Conversely,
and built into the
concept of fair compensation, is the corollary that a claimant is not entitled
to receive more than fair compensation.
A person is entitled to compensation
for losses fairly attributable to the taking of his land, but not to any greater
amount. It
is ultimately by this touchstone, with its two facets, that all
claims for compensation succeed or fail.
[44] Ace said that full compensation based on the advice in Shun Fung should include the reasonable costs of acquiring and developing alternative or equivalent
property, but Gendall J found that compensation payable under the CER
Act is
16 Shun Fung Ironworks Ltd, above n 4, at 852.
guided by the principle noscitur a sociis, and took this passage from
Statute Law in
New Zealand:17
Noscitur a sociis (associated words rule) – It is imperative
that a particular word whose meaning is under consideration be read in the
context of the other words of
the section in which it appears. Its exact shade
of meaning may be coloured by those other words. As Stamp J has said (in
Bourne v Norwich Crematorium Ltd [1967] 1 WLR 691 at 696):
English words derive colour from those which surround them. Sentences are not
mere collections of words to be taken out of the sentence,
defined separately
by reference to the dictionary or decided cases, and then put back into the
sentence with the meaning
which you have assigned to them as separate
words.
...
This simple associated words rule of context sometimes goes by a Latin
name, “noscitur a sociis”: “it is known by the company it
keeps”...
[45] Gendall J thought that the costs of acquiring and developing
alternative and equivalent property “does not fit with
the company it
keeps”, because “all reasonable costs” in s 66(1)(a) PWA take
their colour from the list, and those
costs claimed do not fit with the examples
given in the legislation. Further, and of moment, if Ace is correct and s 66
PWA enabled
compensation for purchase and development of an equivalent property,
ss 64 and 74 would have no meaning.
Ace Developments Ltd v Attorney-General (Court of
Appeal)18
[46] The Court of Appeal addressed the intended appeal to the High Court
as predicated on an entitlement to “full compensation”
for
relocation, to be interpreted in light of the “recovery” purposes of
the CER Act, which include businesses having
to engage in extensive rebuilding
and redevelopment, notwithstanding the economic cost of doing so, as they
either would do so or leave Christchurch altogether. This underpinned
Ace’s argument that the economic reasonableness
of the proposal is
irrelevant.
[47] The Court addressed whether relocation costs as a head of
compensation are available under the CER Act and granted leave to appeal against
Crown opposition
17 J F Burrows and RI Carter Statute Law in New Zealand (4th ed, LexisNexis, Wellington, 2009)
at 232.
18 Ace Developments Ltd v Attorney-General, above n 2.
because while interlocutory, the appeal raised an important question of law
that might be dispositive of Ace’s claim. The
Court observed that when
land is compulsorily acquired under the PWA, compensation under s 66 or its
common law equivalent has been
awarded for the costs of relocating a
business, usually described as a “disturbance” payment.
However, Ace says s 66 and other provisions of the PWA apply to land
compulsorily acquired under the CER Act. Gendall J had rejected that
proposition because the CER Act has its own compensation
regime which expressly
excludes economic or consequential loss, and he considered relocation costs are
economic or consequential
loss.
[48] The Court of Appeal addressed the interaction between ss 61 and 64
of the
CER Act with subpt 5 of pt 2 PWA. Compensation is “actual loss”
under s 61
CER Act but expressly excludes economic or consequential loss and some other
forms of loss. Relocation costs are not therefore
compensatable if they are
not an actual loss or are an economic or consequential loss. There is no other
provision in the CER Act
providing for compensation. The Court did not accept
that “actual loss” and “economic or consequential loss”
are “opposites”, nor did it accept that s 61 points to losses that
are not actual losses. The words “actual loss” should have
their ordinary and natural meaning, being real and significant loss
that has
been suffered or will be suffered. That distinguishes a loss which is
non-existent or theoretical. A claim for compensation
for relocation costs is
thus a claim based on actual loss.
[49] The Court then considered whether “economic or consequential
loss” per s 61(L)(vii) includes relocation costs.
“Economic
loss” cannot simply mean all claims for monetary compensation
as all claims would be excluded. In tort, economic loss is
financial loss or harm to an economic interest, as distinct from physical
damage, and falls into one of three categories: (a) consequential economic loss,
being financial loss arising from physical harm;
(b) pure economic loss, being
financial loss which does not arise from physical harm; and (c) relational
financial loss. Ace’s
claim falls within (b).
[50] The Court discussed whether relocation costs incurred by the owner of the land taken are a direct loss, and therefore not consequential. The s 61(b) exclusions
seem to have been generated by the Regulatory Impact Statement of 28 March
2011, issued by the State Services Commission. Consequential
loss must have
been intended to import concepts of causation, directness and remoteness and
relocation costs are in the nature
of a consequence, not direct or
immediate upon the compulsory taking of the land, but downstream, the
product of choices made by the owner of the land taken. They relate to the
circumstances of a particular claimant, and the
loss of every complainant will
differ. Hence, economic or consequential loss does not include relocation
costs within the meaning
of s 61(b) and they are not compensatable, unless
there is a provision in the Act to the contrary.
[51] Under s 64(3) of the CER Act, compensation is to be
determined in accordance with the provisions of pt 5
PWA, recognising
that compulsory acquisition has always been viewed as a serious interference
with individual rights. All the
compensation provisions contained in pt 5 PWA
including s 66 should apply and that left the question whether Ace’s claim
as
mounted was outside the scope of the PWA as Gendall J had found.
[52] The Court of Appeal said that exactly what Ace’s business comprehended was a factual question, beyond the scope of the appeal before it. The High Court should determine the answer, but the Court worked on the assumption that Ace was in the business of owning and leasing specialist car yards, and considered “full compensation” in that context. It accepted that “full” must mean the equivalent of that which has been taken away.19 That means the claimant has the right, so far as money can achieve it, to be put in the same position as if the land had not been taken.20 Ace’s claim is based on its submission that the underlying objective of the compensation regime is to achieve “equivalence”. Common law disturbance payments were compensatable where businesses were required to move as a result of
land being taken, and s 66 made that entitlement
statutory.
19 Drower v Minister of Works and Development [1984] 1 NZLR 26 (CA) at 29; Minister of Works and Developments v David Reid Electronics Ltd HC Dunedin M91/89, 18 December 1989 at 3; and see Russell v the Minister of Lands [1898] NZGazLawRp 6; (1898) 17 NZLR 241 (SC) at 251.
20 Minister of Works and Development v David Reid Electronics Ltd, above n 19, at 2; and Russell, above n 19 at 253.
[53] “All reasonable costs” must be coloured by the
list provided in the legislation, as Gendall J found.
Such costs are
incidental, additional to payment of market value for the land taken. A
disturbance payment of such potential scale
as the capital cost of acquiring
substitute land would have been made express in the legislation, and could well
be the biggest cost
of all, as the Court observed. No case could be found where
a disturbance payment included the cost of buying substitute property,
and s 66
was drafted to confirm and consolidate existing compensation law. This is not
comparable to the effect on a tenant which
leases compulsorily acquired land.
Tenants are paid for the loss of their use of that land
whereas, once compensated based on market value, the land owner can buy
elsewhere.
[54] Part 5 would be meaningless in some respects, particularly as to ss
65, 73 and
74, if the costs of acquiring substitute land were allowed as disturbance
payments. Section 65 applies to land devoted to a purpose
for which no general
demand exists and is a targeted provision. Sections 73 and 74 provide that if
the market value of the owner’s
interest in the taken land is insufficient
for it to acquire another property of an equivalent standard, there may be
financial assistance in the form of a loan. If compensation, rather than a
loan, were available as a disturbance payment, that would make a nonsense of
these two provisions.
[55] Relevant to this appeal, the costs of demolition,
development, and leasing fees were recognised to be in a different category as
they fit more easily
into the concept of disturbance resulting in additional but
incidental costs, consistent with case law. Such costs must be reasonable
and
not too remote and the Court was quite clear that development on a substitute
site may be compensatable if that cost is reasonable and not too remote.
The Court does not seem to have been referred to the evidence of existing
buildings on 63 Moorhouse Avenue which was before the
Panel.
[56] If relocation costs are not disturbance payments under s 66, it was argued that they were recoverable under s 68 as compensation for “business loss” which is not defined in the PWA, but relates to loss of profits. Otherwise, s 74 would be meaningless, as mentioned.
[57] In conclusion, the Court said that compensation is not available for
the difference between the value of the property taken
and the value of
substitute property, nor for the cost of acquiring a substitute property.
Incidental relocation costs including development on a substitute site are in
principle recoverable depending on whether they are
reasonable and to the extent
that they do not result in betterment. These costs may include demolition
and replacement of existing buildings on substitute land, and leasing fees.
This is consistent
with the purpose of the CER Act to ensure that Christchurch
recovers from the earthquakes.
[58] The Court was unclear whether the evidence Ace sought to adduce
was relevant to the reasonableness of relocation costs
but in principle said
such costs may be recoverable. Even if relevant, the Court would
disallow new evidence because Ace was trying to shore up its case on an issue
which was understood at the time the
Associate Minister made her decision. The
Court agreed with Gendall J that Ace had not adequately explained the
difficulties it
had experienced in obtaining evidence which it now sought to
adduce. The Court disapproved of a previous hearing acting as a “dummy
run”.21
[59] Thus, the appeal was dismissed but with the observation that
disturbance costs may include redevelopment and other costs
as part of
relocation.
D. The submissions on appeal
The competing positions
[60] Mr Jones for Ace says it has not been paid “full compensation” which includes the cost of demolition at and development of the substitute site, including construction of a new building equivalent to that which was taken. The question of law is whether that is compensatable as “disturbance” under s 66 PWA. Ace also initially sought full valuation and legal costs of $94,791.49 under s 66(1)(a) of PWA, but reduced that claim to $21,500. I am left uncertain about the figures, and reserve
leave to settle these elements, as discussed
below.
21 Telecom Corporation of New Zealand Ltd v Commerce Commission [1991] 2 NZLR 555.
[61] Ms Higbee for the respondent says that Ace has received full
compensation, and the amounts claimed are for an “unreasonable
development
proposal, allowing for double recovery or betterment”, and are
“unsupported by the evidence, and are therefore
unrecoverable”.
For Ace
[62] Mr Jones refers to s 64(3) which reads:
(3) For compensation for the compulsory acquisition of land,
the Minister must determine compensation having regard
to its current market
value as determined by a valuation carried out by a registered valuer; and so
far as practicable, the Minister
must determine compensation in accordance with
the relevant provisions of Part 5 of the Public Works Act 1981.
[63] The core components of compensation are current market value, and
the provisions of pt 5 PWA. Compensation is defined in
the CER Act.
61 Meaning of compensation
In this subpart, compensation –
(a) means compensation for actual loss; but
(b) except as provided by this Act, does not include compensation for
–
...
(vii) economic or consequential loss:
...
(ix) business interruption:
(x) any other loss that the Minister reasonably considers is
unwarranted and unjustified.
[64] The Court of Appeal held that Ace’s claim for “relocation costs” was “economic or consequential loss” and excluded from compensation unless there was a provision in the Act providing to the contrary, and compensation under pt 5 of the Act is such a contrary provision. All pt 5 provisions of the PWA, including s 66 for
disturbance payments, therefore apply to Ace’s claim.22 Mr
Jones emphasised the
PWA:
60 Basic entitlement to compensation
(1) Where under this Act any land—
(a) is acquired or taken for any public work; or
(b) suffers any injurious affection resulting from the acquisition or
taking of any other land of the owner for any public
work; or
(c) suffers any damage from the exercise (whether proper or improper
and whether normal or excessive) of—
(i) any power under this Act; or
(ii) any power which relates to a public work and is contained in any other
Act—
and no other provision is made under this or any other Act for
compensation for that acquisition, taking, injurious affection,
or damage, the
owner of that land shall be entitled to full compensation from the Crown
(acting through the Minister) or local authority, as the case may be, for such
acquisition, taking, injurious affection,
or damage.
[emphasis added]
[65] Section 62(1)(b) provides that compensation is based on “market
value” but that is further qualified:
62 Assessment of compensation
(1) The amount of compensation payable under this Act, whether for
land taken, land injuriously affected, or otherwise, shall
be assessed in
accordance with the following provisions:
(a) subject to the provisions of sections
72 to 76, no allowance shall be made on account of the taking of any land
being compulsory:
(b) the value of land shall, except as otherwise provided, be taken to
be that amount which the land if sold in the open market
by a willing seller to
a willing buyer on the specified date might be expected to realise,
unless—
(i) the assessment of compensation relates to any matter which is not
directly based on the value of land and
22 Ace Developments v Attorney-General, above n 2 at [49].
in respect of which a right to compensation is conferred under this
or any other Act; or
[66] Mr Jones says this is consistent with the “full
compensation” contemplated by s 60. He refers to separate compensation
provision for “business loss”:
68 Compensation for business loss
(1) The owner of any land taken or acquired under this Act for a
public work who has a business located on that land shall
be entitled to
compensation for—
(a) business loss resulting from the relocation of the business made
necessary by the taking or acquisition which loss, unless
the owner and the
Minister or local authority otherwise agree, shall not be determined until
the business has moved and (if
the circumstances so require) until sufficient
time has elapsed since the relocation of the business to enable the
extent
of the loss to be quantified; or
(b) loss of the goodwill of any such business, if—
(i) the land is valued on the basis of its existing use; and
(ii) the owner gives such assurances and undertakings not to dispose of
the goodwill and not to engage in any similar trade
or business as may be
required by the Minister or local authority.
[67] In combination, Mr Jones submits that the reasonable costs
incurred in moving from the land taken to other land
acquired in substitution,
including development costs, and the “business loss” resulting from
relocation, together comprehend
what Ace seeks on this appeal. He
refers to the Laws of New Zealand:23
66. Full compensation. This term means such sum of money as
will place the dispossessed owner in a position as similar as possible to that
which such
owner was in before the land was taken. The governing
principle of compensation is the award of a monetary equivalent
for what has
been lost. The word “full” has the added purpose of emphasising
that a claimant is entitled to receive
the complete equivalent of that which has
been taken: it implies a direction that the entitlement must not be whittled
down in any
respect.
In compensation cases the Court or Tribunal will resolve doubts in favour of
a more liberal estimate than in cases involving the valuation
of property for
revenue purposes.
23 Laws of New Zealand Compulsory Acquisition and Compensation at [11].
However, the Court or Tribunal must not be over-generous in assessing
compensation, but must award a sum which will fairly and adequately
compensate
for the loss of land of which the owner has been dispossessed in the public
interest.
[68] Ace’s claim for “relocation” costs falls within s
66 and Mr Jones says that while the cost of acquiring
substitute land is not
recoverable, demolition on such site, development costs and leasing fees fall
within the concept of a disturbance
payment, if reasonable and not too removed.
Mr Jones submits that s 66 is not confined to compensation for the owner of a
business on the land, but applies to the owner of any land taken for
a public work whether or not the owner has a business on the land. As such he
says Ace does not need to show it was carrying
on a business to claim relocation
costs, but if it does, he says it was “in business” as many years
ago it developed
the site for car sales and leased it for that use throughout
its time as owner.
[69] While compensation for losses caused to a business is available
under s 68 of the PWA, I say now that I do not think this
argument is tenable as
s 68 refers to a business located on that land not the business of
leasing to a business on that land. It was not Ace’s business to
conduct a business on that land but to provide it for the business purpose of
another.
[70] Mr Jones focuses on the Court of Appeal saying that the cost of
demolition of buildings on a substitute site and its development
and leasing
fees are in principle recoverable as disturbance compensation, contrary
to the Panel’s recommendation to the Minister. The Court did not say what
recoverable costs might amount to in this case, and it was addressing this in
principle only.
[71] Ace called evidence before the Panel from a valuer Mr Quinlan, and costings by Rawlinsons, quantity surveyors. Mr Jones says there is no evidence to suggest those costings are not accurate. Mr Jones accepts that any claim for compensation must be objectively reasonable, so while it is reasonable for a car sales business to relocate to Moorhouse Avenue, this will not come at any cost for the purpose of compensation. The Panel had evidence that major car sales groups had purchased land in Moorhouse Avenue for car yards, and Oakwood had spent a large sum to purchase land to develop and lease to Blackwells. The development of the
Blackwells site was at a much higher cost than Ace’s proposal, on a
pro-rata basis, yet the Panel reported that Ace’s
proposal was uneconomic
and a well-informed investor would not undertake such a proposal, so infringed
Ace’s duty to mitigate
its loss. The Panel said:
59. But we do not reach our conclusion on this basis for the reason
that we do not accept that a reasonable businessman
using his own
money would embark on the project.
[72] Mr Jones says that this conclusion does not stand given the evidence available about the Oakwood development. Comparative figures before the Panel showed that on Ace’s revised plan, the development costs per square metre were
$1,301.13 for Ace, and $2,134 for Oakwood. Mr Jones says Ace seeks only its
reasonable development costs which compare very favourably
with the only other
evidence available, and that such costs are not otherwise too remote, being the
“natural and reasonable
consequence of the dispossession of the
owner”.
[73] While the Court of Appeal said there was no evidence about the
buildings at
63 Moorhouse Avenue, a valuation before the Panel described them as relatively modest - about 110m2 in area, providing showroom space and a workshop, to a value of some $200,000. Those are nothing like the equivalent of the buildings at
115-117 Moorhouse Avenue, developed for car sales in a desirable location,
and Mr Jones says to restore Ace’s position it needed
not just to acquire
another property in the locality but to spend money to develop it to an
equivalent standard, and such is a “direct,
natural, and foreseeable
consequence of the acquisition and is not too remote to be
compensated”.
For the Crown
[74] Ms Higbee referred to the following passages from the Court of
Appeal judgment.
[77] While we consider that the cost of acquiring the substitute land (and the loss of land value) is not recoverable under s 66, we consider that the costs of demolishing the existing buildings on the substitute site and developing it, as well as the leasing fees, are in a different category. They fit more easily into the concept of a disturbance payment being an additional but incidental cost and are consistent with the case law.
[78] However, their recoverability in any given case will depend
on whether the costs are reasonable and not too remote.
There is no evidence
about the existing buildings on the substitute site and Mr Cooke did not know
what they were. He conceded
that if for example it was a 10 storeyed hotel,
then it would not be reasonable to demolish it. He also accepted there would
need
to be an adjustment in the event of betterment. To the extent any
relocation costs have already been taken into account in the assessment
of the
market value of the land taken, there would also have to be an
adjustment.
...
[83] Other incidental relocation costs which have not already been taken
into account when calculating the market value of the
land taken may be
recoverable, depending on whether they are reasonable and to the extent they do
not contain an element of betterment.
The cost of demolishing and replacing
existing buildings on substitute land together with leasing fees may fall within
that category.
Ms Higbee says s 66 of the PWA applies to losses caused by moving from the
land taken to the substitute land, which have not already been taken into
account in the market valuation of the land acquired, not involve any
betterment, and that are otherwise reasonable and not too remote. To avoid
speculation, Ms Higbee agrees that if any further compensation is
payable, then it should be by way of reimbursement of costs incurred as Ace
suggests.
[75] Ms Higbee accepts the aim of s 66 PWA is to put the landowner
“so far as
money can do it, in the same position as if its land had not been taken from
him.”24
In principle s 66 therefore contemplates the owner being put in the position
it held before its land was taken, but it identifies
only one type of
“landowner” – a family – home owner - and that is not
applicable to business relocation,
discussed below.
[76] In Shun Fung, the Privy Council held that full compensation includes the costs of business relocation or payment of goodwill if there is a causal connection between the taking and acquisition, and the loss is not too remote or unreasonable.25
Despite a dearth of authority, Ms Higbee says that a landlord is not entitled to business relocation costs in addition to the market value of the land taken, where the going concern is operated by a third party. The Court of Appeal left it to the High Court to determine, but proceeded on the assumption that Ace was in the business of
owning and leasing specialist car yards. I have said and repeat that I
consider it
24 E Toomey New Zealand Land Law (3rd ed, Thomson Reuters, 2017) at [15.6.07] citing
Horn v Sunderland Corp, above n 7.
untenable that this is a compensatable “business” as
“the business” must be on the land not of the land, by
the statute’s plain words.
[77] Ms Higbee puts it “...what has [Ace] lost?”. If there is a loss, she says it lies in the value of the property taken, compensated through the market value mechanism. She submits there is no evidence of any other loss by Ace, as the owner and lessor of specialist car yards. Parts of the combined 115-117 Moorhouse Avenue site had been leased to other businesses to do with cars, but not necessarily car sales. The essence of this submission is that Ace does not require further compensation under s 66 to put it in the same position as if the land and improvements at
115-117 Moorhouse had not been taken. As a landlord, it simply invested in
a rent-producing asset, and once the value of that asset is compensated,
including improvements, Ms Higbee says: “... there seems to be
little room for further disturbance”. For
reasons which follow, I think
this rather tentative submission does not bar a claim of the kind that
Ace makes here.
[78] Even if relocation costs are to be considered, Ms Higbee submits that development costs claimed are not payable under orthodox considerations, citing Shun Fung and the Court of Appeal’s judgment in this case. When Ace claims
$2,627,000 to erect a new building at 63 Moorhouse Avenue, the Crown says that goes beyond what it is entitled to, as the market value of its improvements have already been factored into the $3,300,000 payable for the property taken. It is not “reasonable” for Ace to spend the claimed sum to erect a new building which is in a different league to that on the land taken. 115-117 Moorhouse Avenue had a late
1990s industrial building on it with a rentable floor area of approximately
680m2.
Earthquake repairs were completed, and the building was well presented, offering a good standard of commercial accommodation. Compensation of $3,300,000 plus GST (if any), included the value of these improvements, and there were seven valuations before the Panel and the Associate Minister, in a range of $2,630,000 to
$3,480,000. The valuation methodologies included
income/capitalisation, depreciated replacement cost, and market
comparison.
[79] The costs of development which Ace claims have therefore already been taken into account when calculating the market value of the land according to
Ms Higbee, so the $2,627,000 first sought (adjusted to $2,050,000) would represent “double recovery” or in valuation language, betterment. Depreciated replacement costs for the buildings on the land taken were estimated somewhere between
$1,100,000 and $1,200,000, and the replacement costs estimated by Rawlinsons
are
$2,267,000.
[80] Ms Higbee accepts that in principle development costs might
fall within the scope of s 66, given the Court of Appeal’s
observations, but if so, it must be subject to such costs not
already
having been taken into account in the market value exercise, and
there being no element of betterment. This proposition is submitted to be
consistent with the scheme of pt 5 of the PWA, as the purpose
of compensation is
to award market value for what has been acquired, with limited
exceptions.
[81] Section 66(1)(b) of the PWA provides an example of disturbance costs
that might be recovered:
an allowance for any improvements not readily removable from the land taken
or acquired which are of particular use to a disabled
owner or any disabled
member of an owner’s family and which are not reflected in the market
value of the land. [emphasis added]
[82] Ms Higbee submits there is no evidence in this case that there is no
general demand or market for the property acquired,
or that some
aspect of the improvements on it are not reflected in its market
value, but to the contrary. Otherwise
“reasonable” compensation
for relocation is described in Shun Fung, by the Privy
Council:26
The law expects those who claim recompense to behave reasonably ... if a
reasonable person in the position of the claimant would not
have incurred, or
would not incur, the expenditure being claimed, fairness does not require that
the authority should be responsible
for such expenditure.
...
It all depends on how a reasonable businessman, using his own money, would
behave in the circumstances. In such a case, however,
the tribunal or court
will need to scrutinise the relocation claim with care, to see whether a
reasonable businessman having adequate
funds of his own might incur the
expenditure. This is particularly so when, as in the case of the claimant
company, compensation assessed on a relocation basis would
greatly
26 Shun Fung Ironworks Ltd, above n 4, at 126-127 (Emphasis added).
exceed the amount of compensation payable on an extinguishment basis.
The greater the disparity, the more closely the claim should be examined,
because the less likely it would be that a reasonable
businessman would behave
in this way. Compensation is not intended to provide a means whereby a
dispossessed owner can
finance a business venture which, were he using his own
money, he would not countenance.
[83] Ms Higbee says the proposal to spend $2,050,000 to erect a new
building at
63 Moorhouse Avenue is not “reasonable”, but that does not mean
it is not “useful”. Rather, she says there
is no evidence of the
value of 63 Moorhouse Avenue so redeveloped, and it is difficult to determine
the impact that putting a building
on one site will have on the
“value proposition” which results. Using Mr Quinlan’s
calculation and methodology, the Crown
says that to spend $2,050,000 to erect a
new building when the total value of the property, including the new building
and underlying
land will be some $1,900,000, is simply not reasonable. Even if
the value on completion of development adjusts to a higher figure,
spending
$4,945,000 to acquire and develop the property is not reasonable, and no one
having adequate funds of his or her own would
incur such
expenditure.
[84] Analogy with Oakwood’s costs of developing a car yard to be
leased to Blackwell Motors is submitted problematic because
there is no evidence
to support the comparative figures advanced by Mr Jones, and Ace’s attempt
to adduce further evidence
was rejected by Gendall J and the Court of
Appeal. Ace referred to publicly available information, but Ms Higbee says
that
was not given to the Panel. There is no evidence of the Oakwood
development’s end value, to assess the overall reasonableness
of the
development to an investor landlord such as Ace. It turns out that Oakwood has
an ownership interest in Blackwell Motors,
and without understanding that
relationship and how the deal was structured, the Court cannot reasonably use
this as a comparator.
[85] The figure of $2,627,000 was first derived from Mr Quinlan’s
evidence given
to the Panel. The land taken is rectangular with frontages on two streets of
about
35.25 metres, at a depth of 68 metres, and level. 63 Moorhouse Avenue extends approximately 105 metres back from Moorhouse Avenue, further than the standard lots in the locality, and the rear of the site has no value as a display yard. It will have a base industrial value for storage, workshop development or similar. The Crown’s
submission is that the Court simply does not know enough on the evidence to conclude that the replacement building can be accommodated at
63 Moorhouse Avenue. I do not make anything of this. The claim proceeds on
the
basis it can be, and I see no reason not to accept Ace’s assertion in
this regard.
[86] Because the Crown considers Ace has received full compensation, it
submits that overall there is no reason for Ace to be
paid the cost of
demolition of existing improvements and the construction of improvements to
achieve full compensation, as it has
that compensation already.
E. Discussion
“Business”
[87] I have said that the proposition that the compensation sought here
is for loss of a “business” is untenable because
on a
straightforward reading of s 68 a “business loss” relates to a
business carried on on the property taken, and it includes reference to
the “goodwill of any such business” which is incompatible
with more of ownership
of land and buildings. The s 68(1) reference to a
“business located on that land” distinguishes the business from
the
land.
First alleged error – failure to allow disturbance
costs
[88] On this important principle, I do not accept that in all circumstances full compensation is achieved simply by reference to the value of the land and buildings or improvements taken. The CER Act is intended to put an owner in the position they were in before the property was taken. The Court of Appeal recognised that one of the purposes of the CER Act is to ensure that Christchurch communities recover from the earthquake. Section 3 refers it to the purpose of “... restor[ing] the social, economic, cultural, and environmental well-being of greater Christchurch communities” and enabling a “focused, timely, and expedited recovery.” Those objectives are clearly not served by displacing a functioning, profitable, job-creating enterprise so that it cannot continue to operate, and “full compensation” in light of these purposes is to allow the enterprise, whatever it is, to continue with as little fuss
and expense as possible. Here, that is the enterprise of owning a property
to lease to high end car sale businesses.
[89] Land and buildings taken may be made up of valuable land, and old
but well-maintained and fit for purpose buildings, achieving
a good rental
return. Faced with the taking of that land and those buildings, the party to be
compensated in full may reasonably
seek to replicate what it had, to
purchase land and construct buildings with the same utility as those taken,
to achieve
the same sort of return. As a matter of principle, full compensation
may reflect this replication, but there is more to it than
that, as the Court of
Appeal has said. If that was all there was to it, to physically replicate what
was taken, that would have
no regard to the economic outcome by way of rent,
return on capital, betterment, or reasonableness.
[90] Full compensation must be fair and reasonable, and not result in
betterment, although I conclude this is not an absolute
proposition. These
concepts inter-relate. There is no intention evident in the legislation nor in
the body of compensation law,
which developed outside of statute, that full
compensation may include an element of betterment. It may be that the party
compensated
must construct a new building to replicate its position as a
lessor, but if it achieves a better outcome, expressed in financial terms by
an increase in property value, whether by a higher rental,
or not, there must be
allowance for that in fixing compensation. The position is more nuanced if
to achieve the same rental and value outcome some extra development expenditure
is required, beyond
the value of what improvements were taken.
[91] I conclude that “fair and reasonable” compensation must bring to account betterment, and a measure of whether the required investment in a substitute property is warranted given the value outcome achieved. It seems wrong that a party be compensated for constructing buildings which, in combination with the underlying land, produces an end value much lower or much higher than the amount expended in purchase and development simply because in a physical sense it wants to replicate what it had. That proposition does not fit with the philosophy of “full compensation”, as to simply reflect the cost involved of replication or replacement is not and has never been the lawful measure.
[92] To be clear, it may be that the cost of redevelopment is
compensatable where it is reasonable, subject to a discount for
betterment where
all the landowner seeks is to be put back in the same or similar position it
occupied before the take, but it must
still be objectively reasonable. It may
be that betterment should financially not be discounted, because the landowner
cannot financially
account for that, but maybe that is to be adjusted by a
security taken over the substitute land to reflect the betterment.
[93] In this case there is an evidential shortfall to assess such
elements following Gendall J’s refusal to grant leave
to adduce further
evidence, upheld by the Court of Appeal. I see no way in which this Court can
or should reverse that course.
[94] In short, I conclude that there will be circumstances where the cost
of new buildings or other development components may
be compensatable as part of
full compensation, however, any calculation must:
(i) reflect no more and no less than the replacement of the physical
space and utility of the land and improvements taken.
(ii) allow for any betterment in value, whether the capital value which
reflects the new buildings by depreciated replacement
cost valuation or
otherwise so that compensation will adjust to avoid a windfall. The assessment
of betterment is an exercise
which evidentially will involve valuation
methodology.
(iii) be fair and reasonable, which means that some commercial reality
must attend development expenditure. This will involve
the reality of the
exercise, just as here whether the commercial outcome justifies the
expenditure.
[95] The lack of evidence before the Court to make such an assessment in this case means the appeal must be dismissed and Ace’s earlier stance, that it is not for the Court to consider the reasonableness of development, is rejected outright.
Second error alleged – valuation, legal costs and
other
[96] Ace says it has not been paid its reasonable valuation and legal costs. Sections 66(1)(a)(ii) and (iii) PWA provide that disturbance costs comprehend all reasonable valuation and legal fees, and costs incurred in respect of the land taken and the land acquired. Ace claimed legal, valuation, survey and accounting costs of
$53,202.49 for the land taken, and $41,589 for the land acquired.
[97] The Panel was in error when it told the Minister that Lane Neave
Lawyers acted for Ace Sales Limited and not Ace Developments
Limited. It was
under the impression that some legal fees were incurred by Ace Sales
Limited, which influenced its advice
as to reimbursement of legal costs. The
Panel seem to have recommended disallowance of some of these costs because it
disallowed
claims for business loss and relocation. If this judgment allowed
the claim for costs of developing a substitute site, then the
appellant sought a
reasonable contribution to its costs of pursuing those claims, but I have found
to the contrary.
[98] In Pryor v Minister of Land Information, the High Court held
that:27
Such reasonable valuation and legal fees recoverable are for those incurred
in an attempt to negotiate a settlement, or until an agreement
is reached. This
is distinct from litigation costs for the hearing in the Land Valuation
Tribunal, and on appeal, which are governed
by s 90.
[99] Costs under s 90 are at the discretion of the Tribunal or Court. There is no GST, but Ace claims compensation for professional fees which relate to the land taken and relocation. The amount compensated was $21,500 (excluding GST),
$18,500 (excluding GST), for reasonable valuation costs, and a contribution
to legal fees prior to the land vesting in the Crown.
The Panel thought some of
the invoices were too late to relate to work regarding the negotiation or
acquisition of the land, as
vesting occurred on 14 August 2014.
[100] Ms Higbee says that the recommendation of the Panel was an appropriate and reasonable award, and it did not compensate for any “loss” which did not justify
compensation. The Associate Minister awarded $3,000 (excluding GST),
for Ace’s
27 Pryor v Minister of Land Information [2015] NZHC 3117 at [18].
professional fees for relocating a billboard, and Ace claims $32,350.65
(excluding GST), for professional fees relating to relocation,
but those costs
relate to the redevelopment proposal which Ms Higbee says is unreasonable and
would result in double recovery and
betterment. The Court does not know how
such costs would reflect the professional work carried out on the proposal to
purchase
the substitute land at 63 and 69 Moorhouse Avenue land, the costs of
which are not recoverable, and the work of professionals on a different
proposal involving one lot only.
[101] Demolition costs are linked to what is said to be an unreasonable
proposal to spend $2,657,000 for erecting the new building,
and $35,000
demolition fees. The demolition fees reduced from $100,000 to $35,000, on
Ace’s instructions to counsel, but there
is no secure evidence in this
regard. There is really insufficient evidence, apart from a description by
Knight Frank of relatively
modest buildings consisting of a showroom and
workshop at 63 Moorhouse Avenue. However, I am sympathetic to those costs as
experience
suggests they may be about right. If the parties cannot agree, I
will hear from them further.
[102] The cost of $47,000 for leasing fees to find a tenant is also
compensatable. While the market value is determined with reference
to the
capitalised market rental for the property, so Ace would receive a lump sum
based on the future income stream, that is a capital
value and leasing fees to
secure a further income stream is part of that exercise if incurred.
Mr Quinlan said that leasing fees are 25 per cent of the estimated market
rent, based on 63 and 69 Moorhouse Avenue being developed,
and it is not known
what the leasing fees would be for one lot at Moorhouse Avenue alone. Again,
this seems in order if the fees
can be substantiated.
[103] In coming to judgment, I have been left uncertain about costs, professional and otherwise, but I will address those further if required. I otherwise conclude these issues in principle, as above. Ace should have its legal fees and all valuation costs for the work which relates to the land taken and it should have all advertising costs for the new site. I reserve leave for memoranda to be filed as to these ancillary issues.
F. Disposition
[104]
|
(1)
|
The appeal on the substantive legal issues for the measure of
compensation is dismissed, and no further compensation is
payable.
|
|
(2)
|
The appeal against the refusal to order further professional fees,
demolition costs and marketing fees is adjourned part
heard but is
|
|
|
answered in principle above. I reserve leave for further argument
if
the parties cannot agree.
|
...........................................
Nicholas Davidson J
Solicitors:
Crown Law, Wellington
Tavendale and Partners, Christchurch
Copy to counsel:
G D Jones, Barrister, Bridgeside Chambers, Christchurch
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2018/1705.html