You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2020 >>
[2020] NZHC 1135
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Intellihub Limited v Genesis Energy Limited [2020] NZHC 1135 (27 May 2020)
Last Updated: 7 October 2020
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
CIV-2020-404-471 [2020] NZHC 1135
|
BETWEEN
|
INTELLIHUB LIMITED
Plaintiff
|
AND
|
GENESIS ENERGY LIMITED
First Defendant
ADVANCED METERING SERVICES
LIMITED TRADING AS VECTOR AMS
Second Defendant
|
Hearing:
|
22 May 2020
|
Counsel:
|
J McBride, M Heard and A McDonald for applicant S J P Ladd and B A Keown
for first respondent
S Hunter QC and I Rosic for second respondent
|
Judgment:
|
27 May 2020
|
JUDGMENT OF KATZ J
[Application for leave to
appeal]
This judgment was delivered by me on 27 May
2020 at 1:00pm pursuant to Rule 11.5 High Court Rules
Registrar/Deputy Registrar
Solicitors: LeeSalmonLong, Auckland
Bell Gully, Auckland Gilbert Walker, Auckland
Counsel: J McBride, Richmond Chambers, Auckland
S M Hunter, QC, Shortland Chambers, Auckland
INTELLIHUB LIMITED v GENESIS ENERGY LIMITED & ANOR [2020]
NZHC 1135 [27 May 2020]
Introduction
- [1] On
24 April 2020, I dismissed Intellihub Limited’s application for an interim
injunction preventing Genesis Energy Limited
and Advanced Metering Services
Limited (trading as Vector AMS) from removing approximately 45,000 electricity
meters owned and operated
by Intellihub.1
- [2] Intellihub
now seeks leave to appeal that decision.
Leave criteria
- [3] Section
56 of the Senior Courts Act 2016 introduced a significant change to civil
procedure by introducing a leave requirement
for interlocutory appeals. The
requirement for leave serves as a “filtering mechanism”2
to ensure that valuable court time is not consumed with unmeritorious
appeals. A high threshold therefore exists for granting leave
to appeal,
namely:3
(a) The applicant should raise an arguable error of law or
fact.
(b) The alleged error should be of such general or public
importance that it warrants determination, or otherwise of sufficient importance
to the applicant to outweigh the lack of general or precedential importance.
(c) Leave should only be granted where the circumstances warrant
incurring further delay.
(d) Ultimately, the Court on an application for leave should
stand back and assess, in a pragmatic and realistic way, whether the
interests
of justice are served by granting leave.
- [4] In Ngai
Te Hapu Inc v Bay of Plenty Regional Council, the Court of Appeal confirmed
that leave to appeal should only be granted where the significance or
implications of an arguable
error of fact or law, either for the particular case
or for the
1 Intellihub Ltd v Genesis Energy Ltd & Anor
[2020] NZHC 807.
- Finewood
Upholstery Ltd v Vaughan [2017] NZHC 1679 at [13]; McLaren v McLaren
[2018] NZCA 570 at [3]; Ngai Te Hapu Inc v Bay of Plenty Regional Council
[2018] NZCA 291.
3 Finewood Upholstery Ltd v
Vaughan [2017] NZHC 1679 at [9]- [14].
applicant or as a matter of precedent, warrants the further delay which the
appeal process would involve.4
Overview of Intellihub’s submissions
- [5] In
summary, Intellihub submitted that:
(a) The wrong test for ascertaining whether a “serious
issue to be tried” had been established was applied, namely whether
there
was a “tenable resolution of the issues of facts and law on which the
plaintiff may be able to succeed at trial”.
Mr McBride submitted that the
“serious issue” requirement simply describes a claim that is not
frivolous or vexatious.
(b) The Court erred in finding that there was no serious issue
to be tried in respect of the first cause of action (the tort of causing
loss by
unlawful means).
(c) The Court incorrectly assessed the balance of convenience.
Specifically, if the Court had found that there was a serious question
to be
tried on the first cause of action, as well as the second cause of action, this
may have altered the Court’s assessment
of the balance of convenience.
The serious issue to be tried test and the unlawful means
tort
- [6] The
formulation of the serious issue to be tried test that I adopted in the
injunction judgment has been applied in numerous decisions
of this Court
(including by the current Chief Justice) over a period of at least 35 years. The
test originates from the decision
of Davison CJ at first instance in Harvest
Bakeries Ltd v Klissers Farmhouse Bakeries Ltd.5 I therefore give
little weight to this alleged error of law in assessing whether leave should be
granted. I focus instead on whether
it is arguable that I erred in determining
that there was no serious issue to be tried in respect of the first cause of
action (the
unlawful means tort).
4 Ngai Te Hapu Inc v Bay of Plenty Regional
Council [2018] NZCA 291.
- Klissers
Farmhouse Bakeries Ltd v Harvest Bakeries Ltd (No 2) [1985] 2 NZLR 143,
[1989] RPC 27, (1985) 1 TCLR 294 (HC).
- [7] It is fair
to say that the current state of Intellihub’s pleading of the tort is both
confused and confusing. In its initial
pleading, Intellihub did not allege
unlawful conduct directed against a third party, as required by the tort.
Instead it alleged
that Genesis had failed to enter into an
“arrangement” in relation to Intellihub’s metering
installations with
Intellihub, in breach of the Electricity Industry
Participation Code (this was the relevant unlawful act relied
upon).6
- [8] Genesis and
Vector AMS strenuously disputed any breach of the Code. They also pointed out in
their written submissions that even
if such a breach had occurred, it did not
fall within the scope of the unlawful means tort. That is because the tort
requires that
the relevant unlawful act be directed at a third party.
Intellihub’s original pleading, however, did not allege any unlawful
act
by Genesis against Vector AMS (the relevant third party). Intellihub’s
original pleading of the tort was therefore fatally
flawed.
- [9] Presumably
in response to these criticisms, shortly before the injunction hearing
Intellihub filed an amended pleading. The amended
pleading lacks clarity,
however, in part because it contains many seemingly irrelevant legacy elements
from the original pleading.
The key new allegations have been added as
“particulars” of the original (deficient) pleading. Unfortunately,
Intellihub’s
submissions did little to dispel the confusion. In fairness
to counsel, however, that is not entirely surprising given the time constraints
counsel were no doubt under, and the fact that the unlawful means tort has
perplexed both Judges and academic commentators for several
hundred
years.
- [10] The
judgment outlines the history and modern development of the tort, with
particular reference to the House of Lords decision
of OBG Ltd v
Allan.7 In OBG, the House of Lords sought to resolve
confusion over the scope of the economic torts, including the unlawful means
tort. Some 350
decisions and academic writings were placed before their
Lordships.8
- Clause
11.16 of the Electricity Industry Participation Code provides that, before it
can assume responsibility for a new customer
switching from another retailer, a
retailer must have entered into an “arrangement” with the metering
equipment provider
for the metering installation at that customer’s
ICP.
7 OBG Ltd v Allan [2007] UKHL 21, [2008] 1 AC
1.
8 OBG Ltd v Allan [2007] UKHL 21, [2008] 1 AC 1 at [139]
per Lord Nicholls.
- [11] In New
Zealand, in Diver v Loktronic Industries Ltd the Court of Appeal accepted
that the correct approach to the tort was that of Lord Hoffmann (for the
majority) in OBG.9 (I note, however, that in Loktronic
there was no dispute between the parties as to the correct
approach).
- [12] On
the basis that New Zealand law follows Lord Hoffman’s approach to the
tort, I concluded that the first cause of action
was misconceived and that
Intellihub was attempting “to apply the unlawful means tort to a fact
scenario that is far-removed
from those it was designed to meet.”
Specifically, it was my view that Intellihub’s claim does not raise a
serious issue
to be tried because Intellihub does not plead and/or cannot
establish that:
(a) Genesis wrongfully interfered with the actions of a third
party (Vector AMS) in which Intellihub has an economic interest; and
(b) the ‘wrongful act’ against Vector AMS (being the
alleged misrepresentation by Genesis) restricted Vector AMS’s
freedom or
liberty to deal with Intellihub.
- [13] With the
benefit of more time to consider the issue, Mr McBride was able to more fully
articulate Intellihub’s argument
regarding the unlawful means tort at the
leave hearing and explain why, he says, it is arguable that it applies in this
case. He
submitted that OBG lacks clarity and is open to differing
interpretations. It is arguable, he submitted, whether anti-competitive conduct
is required
at all, let alone the specific elements set out at [12](a) and (b)
above.
- [14] As I noted
in the judgment, in AI Enterprises Ltd v Bram Enterprises Ltd the Supreme
Court of Canada, while generally approving Lord Hoffmann’s narrow approach
to the unlawful means tort, rejected
the requirement that the unlawful means
employed must interfere with the third party’s freedom to deal with the
plaintiff
((a) above).10 Mr McBride submitted that it is possible
that a New Zealand court could take the same approach, if the matter were fully
argued. He
further submitted that a
9 Diver v Loktronic Industries Ltd [2012] NZCA
131.
10 AI Enterprises Ltd v Bram Enterprises Ltd 2014 SCC 12,
[2014] 1 SCR 177 at [87].
New Zealand court may also be persuaded to reject any requirement that the
relevant wrongful act restrict the third party’s
freedom or liberty to
deal with the plaintiff ((b) above). Finally, he submitted that if the
requirements set out at [10](a) and (b)
above do indeed form part of the tort (contrary to Intellihub’s primary
submission) it is arguable that those requirements
are met in this case.
- [15] As Mr Ladd
pointed out, these submissions are a significant departure from
Intellihub’s submissions at the injunction hearing,
which stated
that:
Intentionally causing loss by unlawful means, by which a trader
uses unlawful weapons against a rival and causes him injury, is
a recognised
tort in New Zealand.
- [16] It appears
to me that Mr McBride’s arguments are likely to face some formidable
obstacles. It is possible, however, that
Intellihub may be able to persuade an
appellate court that there is at least a serious issue to be tried, now that its
arguments
are more fully developed. Obviously, this would be particularly so if
the Court of Appeal were to accept Mr McBride’s submission
that the test
of “serious issue to be tried” that I adopted was too high. For
these reasons, I accept that there is an
arguable error of law or fact for the
purposes of assessing Intellihub’s leave
application.
The balance of convenience
- [17] Genesis
and Vector AMS submitted that, even if it is arguable that I erred in concluding
that there was no serious issue to be
tried on the first cause of action, this
cannot have impacted on the subsequent assessment of the balance of convenience,
given that
I found there was a serious issue to be tried in respect of the
second cause of action. The outcome of the application did not therefore
depend
on whether there was a serious issue to be tried, but on the (discretionary)
balance of convenience assessment.
- [18] The
weighing of the balance of convenience is a matter for the Judge and an appeal
is not an opportunity to re-litigate this.11 The Judge’s
assessment is only amenable to appeal if “the judge has erred in law,
taken account of an irrelevant matter,
11 NZ Tax Refunds Ltd v Brooks Homes Ltd
[2013] NZCA 90 (2013) 13 TCLR 531 at [13].
failed to take account of a relevant matter or is plainly wrong.”12
The respondents submitted that Intellihub is simply seeking to challenge
the weight given to various factors in the balance of convenience
assessment,
which is not properly a matter for appeal.
- [19] Although
there is considerable force in these submissions, I accept Mr
McBride’s submission that if there
is a serious issue to be tried on the
first cause of action (contrary to my finding) then this could potentially
impact on the balance
of convenience assessment, for reasons I explain
below.
- [20] In relation
to the second cause of action (breach of contract) Intellihub pleads an implied
term that its meters cannot be displaced
“absent either reasonable notice
or compensation, in accordance with standard industry practice”. As I note
at [65] of
the Judgment, Intellihub’s pleaded case is therefore that its
agreement with Genesis provides for either reasonable notice or
compensation. It follows that on Intellihub’s case the parties
themselves envisaged that monetary compensation would be an adequate
remedy for
insufficient notice. This was not determinative, however, as I accepted that
damages may nevertheless be an insufficient
remedy if Intellihub’s network
was significantly compromised by the displacement of some of its meters. I
concluded, however,
that the risk of damage occurring to Intellihub’s
network was speculative.
- [21] The first
cause of action differs from the second cause of action, however, in that
Intellihub’s case is that Genesis has
no entitlement to remove its
meters, even with reasonable notice. It seeks a permanent injunction restraining
Genesis from displacing
its meters. I accept Mr McBride’s submission that
if the argument is not simply about what is a reasonable period of notice
for
removal of the meters, but whether Genesis is entitled to remove the meters at
all, then this could impact the balance of convenience
assessment, including
whether damages would be an adequate remedy for
Intellihub.
12 NZ Tax Refunds Ltd v Brooks Homes Ltd
[2013] NZCA 90 (2013) 13 TCLR 531 at [13].
Conclusion
- [22] Intellihub
has raised an arguable error of law and/or fact, namely whether I erred in
finding that there was no serious question
to be tried on the first cause of
action. The alleged error is not one of general or public importance.
Nevertheless, I am satisfied
that it is of sufficient importance to Intellihub
(given that it relates to the displacement of 45,000 electricity meters) to
outweigh
the lack of general or precedential importance.
- [23] I accept
Intellihub’s submission that the alleged error is one that could
potentially impact on the assessment of the balance
of
convenience.
- [24] Obviously,
any delay to the displacement project is a matter of considerable concern to
Genesis and Vector. Staff have been hired,
planning has been undertaken, and the
project is apparently “shovel ready”. At this stage, however, no
stay has been
sought and the likelihood of delay (or the extent of it) cannot be
assessed. Any stay application will need to be assessed on its
merits, if such
an application is made.
- [25] In
conclusion, I am satisfied that the overall interests of justice favour granting
leave to appeal.
Result
- [26] The
application for leave to appeal is granted.
- [27] The parties
are encouraged to resolve any costs issues between counsel if possible. If
agreement cannot be reached, then Intellihub
is to file any costs memorandum
within 10 working days of this judgment. Any costs memoranda on behalf of
Genesis or Vector AMS are
to be filed within a further 10 working
days.
Katz J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2020/1135.html