You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2021 >>
[2021] NZHC 717
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
HJS AG Limited v Tumatatoro Limited [2021] NZHC 717 (31 March 2021)
Last Updated: 4 October 2021
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
CIV-2021-404-67
|
BETWEEN
|
HJS AG LIMITED
Applicant
|
AND
|
TUMATATORO LIMITED
First Respondent
MATILDA ORA THOMPSON, MOANA VICKI THOMPSON, SAM THOMPSON
and RIPEKA PATENE-STOUT as trustees of THE KAHUPEKA TE WAERO WHANAU
TRUST
Second Respondent
|
Hearing:
|
31 March 2021
|
Appearances:
|
H Thompson for Applicant
K Naidu and S Loa for First Respondent
|
Judgment:
|
31 March 2021
|
JUDGMENT OF LANG J
[on costs]
This judgment was delivered by me on 31 March 2021 at 3.30
pm, pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date...............
Solicitors:
McMahon Butterworth Thompson, Auckland
HJS AG LTD v TUMATATORO LTD [2021] NZHC 717 [31 March 2021]
- [1] HJS AG
Limited (HJS AG) and Tumatatoro Limited (Tumatatoro ) are parties to the lease
of rural land situated on East Coast Road
near Kaiaua. Tumatatoro is the owner
of the land and the lessor whilst HJS A is the lessee.
- [2] The
relationship between the parties has not always been harmonious, and this has
led to previous litigation between them. HJS
AG refused to pay rental between
September 2020 and January 2021 because Tumatatoro had failed to pay costs
awarded against it in
an arbitration. This led to Tumatatoro purporting to
cancel the lease and re-take possession of the land on 25 January
2021.
- [3] In this
proceeding HJS AG sought an order under s 253 of the Property Law Act 2007
granting it relief against cancellation of
the lease. Tumatatoro subsequently
returned possession of the land to HJS AG and withdrew the notices it had issued
purporting to
terminate the lease. It is therefore no longer necessary for HJS
AG to pursue the proceeding but it seeks costs against Tumatatoro
to reflect the
fact that it was required to issue it.
- [4] Tumatatoro
opposes any award of costs being made. It contends the parties entered into a
settlement other than in relation to
the issue of costs, and that the Court has
no means of assessing which party would have succeeded if the proceeding had
gone to trial.
It therefore says the Court should make no award of
costs.
Background
- [5] One
of the disputes that led to an arbitration during 2020 resulted in the
arbitrator, Mr Ben Vanderkolk, finding in favour of
HJS AG. In a written award
delivered subsequently on 16 October 2020, the arbitrator awarded costs in
favour of HJS AG. HJS AG then
registered the award of costs in this Court as a
judgment.1 It therefore has a judgment debt in its favour in the sum
of $219,019.80.
1 Under Article 35(1)(b) in Schedule 1 to the
Arbitration Act 1996.
- [6] Tumatatoro
did not respond to requests for payment of the judgment sum. HJS AG then stopped
paying the monthly instalments of
rent under the lease. It did not pay rent
between September 2020 and January 2021.
- [7] This
prompted Tumatatoro to give notice of its intention to cancel the lease for
non-payment of rent. HJS AG refused to comply
with those notices because it
considered them to be defective. Tumatatoro then purported to cancel the lease
for non-payment of rent.
It entered and took possession of the property on 25
January 2020. This led HJS AG to issue the present proceeding on 26 January
2021.
- [8] On 29
January 2021 Tumatatoro withdrew the notices it had issued. It also restored
possession of the property to HJS AG. This
meant it was no longer necessary for
HJS AG to seek relief against forfeiture of the lease.
Did the parties reach a settlement other than in relation to
costs?
- [9] Because
it is fundamental to Tumatatoro’s argument on costs I deal with this issue
first.
- [10] On
Tumatatoro’s behalf Mr Naidu sought to rely on email correspondence
between the parties’ legal advisers that occurred
between 26 and 29
January 2021. He says this demonstrates they settled the outstanding dispute
other than the issue of costs. If
that is so costs should be determined in
accordance with a line of authority discussed by Mackenzie J in Ng v
Pauatahanui GS Ltd.2 These cases show that, where a case has been
settled but for costs, the courts will often be unable to make any award of
costs because
it is not obvious which party would have been successful if the
matter had proceeded to trial.
- [11] The two
principal email communications in this context occurred on 29 January 2021
between Mr Howard Thompson, HJS AG’s
solicitor, and Mr Richard Smith,
Tumatatoro’s solicitor. At 8.40 am Mr Thompson sent the following email to
Mr Smith:
2 Ng v Pauatahanui GS Ltd [2014] NZHC 3397 at
[7]- [11], citing Brawley v Marcynski (No 1) [2002] EWCA Civ 756, [2003] 1
WLR 813, BCT Software Solutions Ltd v C Brewer & Sons Ltd [2003] EWCA
Civ 939 and Venture Finance Plc v Mead [2005] EWCA Civ 325.
Dear Richard
Further to my earlier correspondence, I now attach, by
way of service on Tumatatoro Limited, an interim charging order issued by the
High Court. The effect of this order is to charge
the rent due by my client to
yours and to charge future rent as it becomes due, with the obligation to pay
the judgment debt obtained
by my client against yours.
Your client is in unlawful occupation of the farm and my client
will hold Tumatatoro Limited and Sam Thompson, personally, responsible
for all
losses it will suffer as a result of this. A very valuable milk supply contract
is in jeopardy, apart from anything else.
If your client hands possession of the farm back to mine, today,
my client would still be willing to negotiate with yours with a view
to
restructuring the debt your client owes to mine in a way that will allow your
client (or the Kahupeka Te Waero Whanau Trust [KTWWT],
as the case may be) to
service its bank debt on an interest only basis until the judgment debt is
satisfied. However, if my client
must resort to a court order to obtain
possession of the farm, its attitude is likely to harden.
Of course any restructure of the debt assumes that the lease
will be renewed. To that end, please treat this email as a notice by
HJS AG
Limited to Tumatatoro Limited [of its] intention to renew the lease pursuant to
cl 41.2 of the lease, for the Renewal Period,
as defined in the lease.
- [12] Mr Smith
responded to this at 2.40 pm the same day as follows:
Dear Howard
Further to our telephone conversation of 1:10pm today, we can
confirm that there have been discussions with Tumatatoro Ltd and its
advisors in
relation to your correspondence of 8:40 am today. We are advised that both the
Director of Tumatatoro and the Trustees
of the Kahupeka Te Waero Whanau Trust
are prepared to enter into negotiations with your Client HJS AG Ltd. To that
extent we have
been given an undertaking that the farm property located at
Kaiuaua will be vacated today. In doing so, both Tumatatoro Ltd and the
Kahupeka
Te Waero Whanau Trust meet the terms as described in your correspondence insofar
as entering into a negotiation in respect
of the costs award are concerned.
Further, we are advised that the Notices of Breach are now set
aside. In doing so, the necessity for your Client’s Application
to the
Court for Injunctive Relief to be heard in the High Court, Auckland on Wednesday
3 February 2021 is not necessary. We are
advised that our Client will take no
further action in respect of the subject Notices as they wish to achieve a
positive outcome
in negotiations. We expect to be in a position to commence
those negotiations once the Director and all Trustees have been consulted.
We
expect that process to be completed within four weeks; consequently it would be
reasonable to expect negotiations to commence
in the first week of March
2021.
- [13] The
arrangements recorded in these emails led to Mr Thompson and Mr Smith signing a
joint memorandum on 2 February 2021 in which
they advised the Court that HJS AG
no longer needed to pursue its application for interim
relief:
1. This memorandum is filed in respect of the first call of the
applicant’s application for interlocutory relief, to take place
at 10 am
tomorrow, 3 February 2021.
2. The first respondent has now withdrawn its default notices
against the applicant and has restored the applicant to possession of
the leased
premises.
3. Thus, the parties acknowledge that the applicant no longer
requires interim relief. However, the parties have not yet reached agreement
on
costs.
...
- [14] I do not
consider these communications demonstrate that the parties had reached any
settlement of outstanding issues by 2 February
2021, or thereafter. By that date
Tumatatoro had withdrawn the notices it had earlier issued and had restored
possession of the land
to HJS AG. The parties had also agreed to commence
dialogue about how Tumatatoro would pay the judgment debt. Matters went no
further
than that.
- [15] It is
therefore necessary to determine costs in accordance with conventional
principles on costs.
Relevant principles
- [16] Rule
14.2(1)(a) of the High Court Rules 2016 provides that the party who fails with
respect to a proceeding should pay costs
to the party who succeeds. Matters are
different where the plaintiff discontinues a proceeding before it has been
finally determined.
In that event r 15.23 provides that the plaintiff must pay
the defendant’s costs of the proceeding to that point. The rationale
for
this rule is that discontinuance “is ordinarily tantamount to judgment for
the defendant”.3
- [17] In the
present case HJS AG had not discontinued the proceeding when the hearing before
me took place so r 15.23 is arguably not
directly engaged.
Nevertheless
3 Powell v Hally Labels Ltd [2014] NZCA 572 at
[19].
it is plain that HJS AG has no need to continue the proceeding because it has
regained possession of the land and Tumatatoro has
withdrawn the notices it
issued. Furthermore, Mr Thompson confirmed during the hearing that it would now
be appropriate for me to
grant leave to discontinue the proceeding given that it
no longer serves any purpose. I therefore consider it appropriate to grant
HJS
AG leave to discontinue the proceeding and to determine costs according to the
principles that generally apply following discontinuance.
- [18] In this
context I derive assistance from the principles enunciated by the Court of
Appeal in Powell v Hallys Labels Ltd, the case relied upon by HJS AG. In
that case the Court observed:
- [20] The Court
guards its discretion over costs, but as a matter of practice it does not
lightly allow a plaintiff to displace the
presumption that costs follow
discontinuance. We make three points.
- [21] First, the
Court does permit a plaintiff to show that its discontinuance should not be
interpreted as failure; the proceeding
having ended unilaterally rather than by
judgment, the Court is prepared, in a clear case, to recognise that the
plaintiff may have
achieved its end by other means or otherwise discontinued for
reasons not connected to the merits.
That is consistent with the principle that costs follow the
result.
- [22] Second, the
Court may consider, in a clear case, why the parties brought and defended the
proceeding, and whether steps taken
in it were reasonable. For example, a
governmental or third party decision may have intervened, rendering the
proceeding redundant.
But this is merely to recognise that the interests of justice occasionally may
require that such matters be taken into account.
It is not to invite a general inquiry into the reasonableness of the parties
conduct.
- [23] Third, and
consistent with what we have just said, a plaintiff may not displace the
presumption merely by showing that it had
some merit on its side. Indeed, the
Court need not consider the merits and ordinarily refuses to do so unless they
are immediately
apparent.
- [24] The Courts
reluctance to embark on inquiries into merits or conduct reflects the objectives
of the rules, which allow a plaintiff
by discontinuance to end its proceeding
unilaterally and fix its liability for costs at that point, and further
contemplate that
the liability should be predictable and the quantum readily
calculable. To conduct a post-discontinuance inquiry into the merits
or the
reasonableness of the parties conduct is ordinarily contrary to these
objectives; the inquiry causes the litigation to linger
on its deathbed and puts
the parties to further expense in pursuit of an uncertain award,
all of which discourages discontinuance in other cases. Faced with the
prospect of such an inquiry, Lord Denning MR said:
“It is
plain that neither side wishes to go on with the action so as to get his own
costs. But neither side wishes to pay the
other sides costs. Each will fight
rather than pay the other sides costs. So what is to be done? Is this case to go
on simply about
costs? I think not.”
(footnotes omitted)
Decision
- [19] I
do not consider HJS AG’s decision to discontinue the proceeding should be
interpreted as failure on its part. Rather,
I am satisfied that the proceeding
achieved its desired purpose because it was one of the factors that prompted
Tumatatoro to restore
HJS AG to possession of the land and to withdraw the
notices it had issued. To all intents and purposes HJS AG is therefore the
successful
party.
- [20] Furthermore,
I consider this is one of those rare cases in which the Court can confidently
state that HJS AG would have succeeded
if the proceeding had gone to trial. This
requires consideration of the merits of its claim, an exercise that is often
difficult
when a plaintiff has discontinued a claim. Fortunately this is not
such a case.
- [21] I accept
that HJS AG was not initially entitled to withhold payments of rental to reflect
the fact that Tumatatoro had failed
to pay the costs awarded in the arbitration.
In withholding the rental payments HJS AG purported to apply a form of set-off
against
the amount owed to it under the judgment debt. However, the lease
required HJS AG to pay rental “on the due date without deduction
or
set-off whether legal or equitable in the manner directed by the
Lessor”.4 This meant HJS AG had no ability under the lease to
set rental off against the amount owing under the judgment
debt.
- [22] Matters
changed on 27 January 2021 when HJS AG obtained a charging order over the rental
payable under the lease. Thereafter
it became entitled to set off rental
payments against the amount due under the judgment debt. Mr Thompson attached a
copy of the
charging order to his email to Mr Smith on the morning of 29 January
2021. This may well have been the final factor that prompted
Tumatatoro to alter
its stance.
4 Clause 3 in Schedule 2 to the Deed of Lease.
- [23] I am
therefore satisfied that HJS AG would inevitably have succeeded in obtaining
relief against forfeiture once it obtained
the charging order on 27 January
2021. It could therefore rebut the presumption against costs contained in r
15.23.
Result
- [24] Tumatatoro
is to pay costs to HJS AG in relation to both the interlocutory application and
the substantive proceeding. Costs
are to be calculated on a Category 2B basis
together with disbursements as fixed by the Registrar. Costs in relation to the
hearing
before me are to be calculated on the basis that the hearing related to
an interlocutory issue.
- [25] Counsel
have leave to file concise memoranda if they cannot reach agreement regarding
the quantum of costs.
Lang J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2021/717.html