You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2022 >>
[2022] NZHC 1995
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Erlon Limited v Agrotrust Limited [2022] NZHC 1995 (12 August 2022)
Last Updated: 23 August 2022
IN THE HIGH COURT OF NEW ZEALAND TAURANGA REGISTRY
I TE KŌTI MATUA O AOTEAROA TAURANGA MOANA ROHE
|
|
UNDER
|
Section 143 of the Land Transfer Act 2017
|
BETWEEN
|
ERLON LIMITED
Applicant
|
AND
|
AGROTRUST LIMITED
Respondent
|
Hearing:
|
19 May 2022
|
Appearances:
|
J Delaney for the Applicant
J Hakaria for the Respondent
|
Judgment:
|
12 August 2022
|
JUDGMENT OF ASSOCIATE JUDGE SUSSOCK
This judgment was delivered by me
on 12 August 2022 at 4pm pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Solicitors/Counsel: KM Law, Tauranga
Sharp Tudhope, Tauranga J Delaney, Tauranga
ERLON LTD v AGROTRUST LTD [2022] NZHC 1995 [12 August 2022]
Introduction
- [1] Erlon
Limited has applied for an order that a caveat over two properties in Pakaraka
in the Far North not lapse. The properties
are owned by the respondent,
Agrotrust Limited, and have been converted from farmland into a kiwifruit
orchard.
- [2] Erlon’s
interest in the properties is described on the caveat as:
an equitable interest pursuant to a constructive trust ... by reason of the
Joint Venture Agreement dated 6 November 2021 between
the Caveator and the
registered proprietor of the Properties, and by reason of both direct and
indirect financial contributions to
the Properties.
- [3] In an
application that a caveat not lapse, the overriding issue for determination is
whether it is reasonably arguable that the
interest in the property claimed in
the caveat exists and is an interest in land. Erlon submits that it is
reasonably arguable that
an institutional constructive trust arises and is a
sufficient interest in land to sustain the caveat.
- [4] It is
settled law that an institutional constructive trust is a sufficient interest in
land to sustain a caveat and that the four
elements for such a trust are as set
out in Lankow v Rose, namely that:1
(a) the applicant has made contributions, direct or indirect, to the property in
question;
(b) the applicant had an expectation of an interest in the property;
(c) that expectation was a reasonable one; and
(d) the respondent should reasonably expect to yield the interest to the
applicant.
- [5] Agrotrust
submits there cannot be an institutional constructive trust in Erlon’s
favour because:
- Lankow
v Rose [1995] 1 NZLR 277 (CA) at 294 per Tipping J, as recently confirmed in
Siddiqui v Siddiqui [2022] NZCA 324 at [26].
(a) Erlon could not have had an expectation of an interest in the properties;
(b) Erlon used Agrotrust’s money to fund development of the properties and
did not contribute to the development itself;
(c) Erlon derived a profit from the development of the properties;
(d) even if Erlon did make contributions to the properties:
(i) they did not manifestly exceed the benefit it obtained by way of payment for
its contributions; and
(ii) the works were performed in its capacity as a contractor/service provider,
which do not give rise to an equitable interest that
is capable of supporting a
caveat.
Issues
- [6] The
issues are therefore whether Erlon has established that it is reasonably
arguable that:
(a) Erlon has made contributions, direct or indirect to the properties against
which the caveat is registered;
(b) Erlon had an expectation of an interest in the properties;
(c) Erlon’s expectation was reasonable; and
(d) Agrotrust should reasonably expect to yield an interest in the properties to
Erlon.
Background
- [7] The
relationship between the parties began in late 2019 to early 2020 when Erlon and
Agrotrust first started working together
to develop a kiwifruit orchard in
Pakaraka in Northland. Mr Arizaga, the sole director of Agrotrust, says he
approached Mr Figueiredo,
the sole director and shareholder of Erlon, for advice
about establishing an avocado orchard. Mr Arizaga’s evidence is that
during discussions Mr Figueiredo advised that instead of an avocado orchard, Mr
Arizaga should develop a
kiwifruit orchard in Northland and that he should plant the Zespri red variety
of kiwifruit.
- [8] Mr Arizaga
accepts in his affidavit that he engaged Mr Figueiredo’s company, Erlon,
to find a suitable property to develop
such an orchard.
- [9] In late 2019
Erlon identified the first suitable property at 6846 State Highway 10, Pakaraka,
Far North District (Record of Title
643621, Lot 3 on Deposited Plan 470585)
(Parcel A). At that time the land was used as a dairy farm and work was required
to convert
it into an orchard.
- [10] Erlon
submits that the parties entered into a verbal agreement to establish a joint
venture to develop the orchard. Agrotrust
accepts that the parties entered into
a verbal agreement but only to the extent that Agrotrust and Erlon would enter
into good faith
negotiations on the terms of a proposed joint venture with a
view to entering into a Joint Venture Deed which would record the agreed
terms
between the two parties.
- [11] The parties
agree that the joint venture (either as agreed (Erlon) or as a possibility
(Agrotrust)) was for Erlon and Agrotrust
to share in the capital and operating
costs of the orchard on a 50/50 basis with both sharing in any
profits.
- [12] In April
2020 Agrotrust purchased Parcel A. The purchase price was $3 million. Agrotrust
made arrangements with the vendor to
pay $1,500,000 on the settlement date and
for the remainder to be paid over a two-year mortgage at an interest rate of 4.5
per cent.
- [13] On
approximately 17 June 2020 Erlon provided Agrotrust with a quote from Ground Up
Limited dated 9 April 2020 for the amount
of $3,984,692.04 (including GST). Mr
Figueiredo is the sole shareholder and director of Ground Up. The Ground Up
quote recorded that
it was for materials and labour for the development of the
orchard.
- [14] Between
June and September 2020 Erlon issued the following invoices for progress
payments:
(a) Inv-2238 dated 16 June 2020 in the amount of $664,115 (including GST) (plus
25% deposit for 5 hectares RED licence of $79,062.50);
(b) Inv-2276 dated 7 August 2020 in the amount of $664,115 (including GST);
(c) Inv-2301 dated 7 September 2020 in the amount of $664,115 (including
GST).
- [15] Mr Arizaga
accepts that, except for the deposit for the Zespri Red licence in the first
invoice, the invoices relate to development
of the orchard and total $1,992,345
(including GST). Mr Arizaga’s evidence is that he understood from Mr
Figueiredo that the
$1,992,345 charged in the invoices was for Agrotrust’s
50 per cent share of the development and infrastructure costs of the
orchard,
being half of the Ground Up quote.
- [16] Agrotrust
paid the construction invoices.
- [17] During this
time it was discovered that Parcel A did not have an adequate water source and
that water for that property had previously
come from the smaller neighbouring
property, 6846A State Highway 10, Pakaraka (Record of Title 643620, Lot 2 on
Deposited Plan 470585)
(Parcel B).
- [18] Mr
Arizaga’s evidence is that Agrotrust was therefore forced to purchase
Parcel B for the orchard to become operational.
Agrotrust did so on or about 3
August 2020, paying $1,050,000 for Parcel B. Agrotrust arranged with the vendor
to pay $300,000 as
a deposit and for the remainder of the purchase price to be
paid with a mortgage. A deposit of $300,000 was paid by Agrotrust to
the real
estate agent’s account on 28 July 2020.
- [19] Mr
Figueiredo’s evidence is that Erlon contributed $150,000 towards the
deposit of Parcel B, deducting this amount from
one of its invoices. Mr Arizaga
says there was no agreement between the parties that Erlon would contribute
towards the deposit of
Parcel B but does not otherwise dispute that it was
contributed to in this way.
- [20] Once
Agrotrust had acquired Parcel B, water could be supplied from Parcel B to Parcel
A. With that water source in place, development
of the orchard could continue,
including the planting of approximately 39,200 kiwifruit plants.
- [21] Around 8
October 2020 Erlon provided a quote for the construction of a windbreak. The
quote was for $2,760,000. Mr Figueiredo’s
evidence is that he agreed with
Mr Arizaga that the windbreak invoices would be payable by Agrotrust in three
payments of $460,000.
Again, Mr Figueiredo says the windbreak payments to be
made by Agrotrust totalled 50 per cent of the total windbreak cost. At around
the same time, 8 October 2020, Erlon issued the first windbreak invoice,
INV-2325, for
$460,000. Agrotrust paid the first instalment.
- [22] On or
around 6 November 2020, after several months of negotiation involving the
parties’ lawyers, a Joint Venture Deed
was finally executed between
Agrotrust, Erlon and E-Farms Limited (company incorporated by Mr
Figueiredo).
- [23] The Joint
Venture Deed included clause 3 which set out conditions precedent as
follows:
- Conditions
precedent
- 3.1 This Deed is
in all respects conditional on:
(a) Agrotrust and E-Farms agreeing in writing within 20 days of this Deed being
signed:
(i) a schedule setting out the contributions of each Participant as at the
Commencement Date (which is to include acquisition costs
for the Property, costs
to acquire Zespri Licence, and capital and operational costs paid to Erlon in
connection with the Project);
(ii) the Project Budget; and
(iii) the Project Plan.
(b) The Vendor consenting to E-Farms acquiring a one half undivided share of the
Property as a tenant in common from Agrotrust;
(c) E-Farms assuming responsibility for the Vendor Finance Loan and associated
mortgage in a manner satisfactory to Agrotrust;
(d) Completion of the purchase of a one half undivided share of the Property as
a tenant in common by E-Farms from Agrotrust; and
(e) each holder of Zespri Licence and party to a Licence Lease executing a deed
of trust acknowledging that it holds its allocation
of Zespri Licence and rights
under the relevant Licence Lease on trust for the Joint Venture and will
transfer its Zespri Licence
and surrender its right, title and interest under
the Licence Lease to the Joint Venture as soon as it is able to do so in
accordance
with the terms of the relevant Zespri Licence,
in each case other than clause 3.1(a), within one month of this
Deed.
- 3.2 If the
condition(s) in clause 3.1 are not satisfied within the time period prescribed
in clause 3.1, this Deed will be at an end
and no party will have any rights or
obligations to the other parties except under clause
20.1
(Confidentiality).
- [24] Mr
Arizaga’s evidence is that Agrotrust and Erlon negotiated the project
budget and the project plan to try and satisfy
the conditions precedent in the
Joint Venture Deed within the given timeframe. However, the parties were unable
to complete those
tasks and, on 18 December 2020, agreed by email to extend the
timeframe for satisfaction of the conditions to 15 January 2021.
- [25] By that
date the parties were still unable to agree on the project budget and project
plan. Mr Arizaga’s evidence is that,
pursuant to clause 3.2, the Joint
Venture Deed therefore lapsed on 15 January 2021. He deposes that whilst not
necessary, Agrotrust’s
lawyers communicated this lapse to Erlon’s
lawyers on 15 February 2021 by email. A copy of that email is annexed to his
affidavit
and reads:
As you [the lawyer for Erlon] will be aware the parties have not been able to
progress the conditions precedent and there was no mutual
agreement to extend
the condition date for the purposes of clause 3.2. As a result, and in
accordance with its terms the deed [the
Joint Venture Deed] was at an end from
15 January 2021 and no party has any rights or obligations to the others except
under clause
20.1 (confidentiality).
- [26] On 26 March
2021 Agrotrust gave notice to Erlon that its services were no longer required
and that it was not to access the orchard
to do any more work.
- [27] In May 2021
Agrotrust filed a claim in the High Court against Erlon and Mr Figueiredo. Mr
Arizaga’s evidence is that the
claim is based on his discovery
that:
(a) Erlon had overcharged Agrotrust.
(b) Erlon’s invoices to Agrotrust exceeded 50% of the actual costs of the
orchard development.
(c) Agrotrust had paid to Erlon its share of the purported development costs,
and Erlon used that money to pay for the entire development
of the orchard
without contributing any of its own money.
(d) Erlon used the funds that Agrotrust’s paid for purposes other than for
the orchard development.
(e) Erlon did not complete the orchard development as it said it would.
(f) Erlon had not paid many of its contractors for services undertaken at the
orchard.
- [28] On 16 June
2021 Erlon and Mr Figueiredo filed a statement of defence and counterclaim. The
counterclaim alleges Agrotrust has
been unjustly enriched by the contributions
made by Erlon towards the joint venture.
- [29] Mr
Figueiredo’s evidence is that, in particular:
(a) Erlon had paid a deposit towards the purchase of Parcel B;
(b) Erlon had paid 50 per cent of the cost of planting kiwifruit on Parcel A and
Parcel B, referred to together as “the contributions”.
- [30] Based on
the contributions, Erlon is seeking a declaration that the properties are held
by Agrotrust on constructive or resulting
trust for Erlon.
- [31] On 12
August 2021 a caveat was lodged by Erlon claiming an interest in the properties,
Parcel A and Parcel B, “by reason
of the Joint Venture Agreement dated 6
November 2021 between the Caveator and the registered proprietor of the
Properties, and by
reason of both direct and indirect financial contributions to
the Properties”.
- [32] Mr
Figueiredo’s evidence is that through the contributions and reliance on
the joint venture, Erlon has undercharged on
its normal invoiced rates by
approximately
$4.5 million and has increased the value of the properties from being bare
fields to a fully operational kiwifruit orchard.
- [33] Mr
Figueiredo annexes a spreadsheet to his affidavit providing a breakdown of the
costs incurred by Agrotrust and Erlon for the
joint venture during the orchard
development.
- [34] Mr Arizaga
disputes the figures in the spreadsheet provided by Mr Figueiredo.
Legal principles governing applications to sustain
caveats
- [35] In
Green & McCahill Holdings Ltd v Ara Weiti Development Ltd,2
the Court of Appeal recently confirmed that the core principles covering
applications to sustain caveats under s 143 of the Land Transfer
Act 2017 are
those set out in the Court of Appeal’s decision in Philpott v Noble
Investments Ltd:3
- [26] The
applicable legal principles which governed the application to sustain the
caveats, and which now govern this appeal, are
as follows:
(a) The onus is on the applicants to demonstrate that they hold an interest in
the land that is sufficient to support the caveat,
but they need not establish
that definitively;
(b) It is enough if the applicants put forward a reasonably arguable case to
support the interest they claim;
(c) The summary procedures involved in applications of this nature are not
suited to the determination of disputed questions of fact.
An order for the
removal of a caveat will only be made if it is patently clear that the caveat
cannot be maintained — either
because there is no valid ground for lodging
it in the first place, or because such a ground no longer exists; and
(d) When an applicant has discharged the burden upon it, the Court retains
discretion to remove the caveat which it exercises on
a cautious basis. Before
it does so the Court must be satisfied that the caveator’s legitimate
interest would not be prejudiced
by removal.
(footnotes omitted)
- [36] The Court
of Appeal in Green & McCahill went on to say:
[83] Although summary process does not permit close engagement with contested
facts, the court must still assess the arguability of
the asserted case of a
proprietary right realistically and interrogate the documentary record. As the
Privy Council said in Eng Nee Yong v Letchumanan, a court is not
required:4
... to accept uncritically, as raising a disputed fact which calls for
further investigation, every statement in an affidavit however
equivocal,
lacking in precision, inconsistent with undisputed contemporary documents or
other statements by the same deponent, or
inherently improbable in itself it may
be.
2 Green & McCahill Holdings Ltd v Ara Weiti Development Ltd
[2022] NZCA 218 at [80].
- Philpott
v Noble Investments Ltd [2015] NZCA 342 at [26]; Philpott was
referred to with approval by the Supreme Court in Melco Property Holdings
(NZ) 2012 Ltd v Hall [2022] NZSC 60 at [56].
4 Eng
Nee Yong v Letchumanan [1980] AC 331 (PC) at 341.
- [37] As outlined
above, the parties agree that the applicant needs to establish that it is
reasonably arguable that the four elements
set out in Lankow v Rose are
met in the circumstances of this case. I therefore go through each of these
elements below. Before doing so I note that in Lankow v Rose, Hardie Boys
J held that contributions which are “adequately compensated by the
benefits the relationship itself confers”
will not suffice to support a
constructive trust and that the contributions “must manifestly exceed the
benefits” received.5
- [38] His Honour
further explained that contributions need not be in money and “may be in
services or in any other respect”
but “there must be a causal
relationship between the contributions and the acquisition, preservation or
enhancement”
of the property in issue.6
- [39] In
Almond v Read, the Court of Appeal approved commentary in Equity and
Trusts in New Zealand that a common factor in institutional constructive
trusts is the unconscionability of the respondent denying the applicant an
equitable
interest in the relevant property because of a previous understanding,
whether subjectively agreed upon between the parties or deemed
by the law to be
appropriate in the circumstances.7
Is it reasonably arguable that Erlon made contributions, direct
or indirect to the property in question?
- [40] I
record at the outset that land is defined in the Land Transfer Act as including
“plants, trees, and timber on or under
land”.8
- [41] Erlon
submits that it has made direct and indirect contributions to the properties
by:
(a) identifying the properties as being suitable for conversion from a dairy
farm into a kiwifruit orchard;
5 Lankow v Rose, above n 1, at 282 per Hardie Boys J.
6 At 282 per Hardie Boys J.
7 Almond v Read [2019] NZCA 26 at [65].
8 Land Transfer Act 2017, s 5.
(b) establishing a kiwifruit orchard by constructing structures to support the
kiwifruit vines, installing irrigation and putting
orchard management processes
in place;
(c) growing and planting approximately 39,200 kiwifruit plants across 45
hectares of the property;
(d) only charging 50 per cent of the normal market rate for the orchard
development work;
(e) paying 50 per cent of the deposit on the Parcel B land by deducting
$150,000 from INV-2259 which records “Red Licence $237,187.50 minus
$150,000 for deposit of the new property. Only net payment
of
$87,187.50”.
- [42] Agrotrust
submits in response that Erlon carried out works at the properties as a service
provider and that Erlon’s 50
per cent share of the development costs
“would only be considered a contribution if the joint venture was
established, and only then that would be for the benefit of Mr
Figueiredo”.
- [43] Agrotrust
submits that the Joint Venture Deed makes it clear that Erlon was only a service
provider. Agrotrust relies on the
fact that the Deed was negotiated between
Agrotrust, Erlon and Mr Figueiredo with the assistance of their respective legal
advisers
for five months. The “Background” section of the Joint
Venture Deed records:
E. Erlon has, as a service provider but not (for the avoidance of
doubt) as a participant in the Joint Venture, already provided
certain services
in relation to the orchard development occurring on the Property prior to the
date of this Deed, which are agreed
to be operational costs of the Joint
Venture.
- [44] As set out
above, clause 3.2 of the Joint Venture Deed records that if the conditions
precedent in clause 3.1 are not satisfied
within the time period prescribed, the
Deed will be at an end and no party will have any rights or obligations to the
other party
except under clause 20.1 (Confidentiality).
- [45] Clause 5.3
of the Joint Venture Deed records:
5.3 The parties acknowledge that Erlon, as the date of this Deed, has
provided services to E-Farms in E-Farms’ capacity as participant
in the
Joint Venture. E-Farms and Agrotrust acknowledge that the value of the services
is to be recorded as contribution to the capital
of the Joint Venture by
E-Farms.
- [46] In
addition, Agrotrust relies on clause 23.7 of the Joint Venture Deed which
records:
- 23.7 To the
extent permitted by law, in relation to its subject matter, this Deed:
(a) embodies the entire understanding of the parties, and constitutes the entire
terms agreed by the parties;
(b) sets out the only conduct relied on by the parties; and
(c) supersedes any prior written or other agreement or understanding of the
parties.
- [47] Agrotrust
submits the above clauses show that in executing the Joint Venture Deed, Mr
Figueiredo and Erlon willingly confirmed
that:
(a) Erlon was only a service provider and not a participant in the joint
venture.
(b) Erlon provided services to E-Farms in E-Farms’ capacity as participant
in the joint venture.
(c) Erlon could not have had an expectation of an interest in the property.
(d) Any other and previous understandings of what Erlon was to provide or had an
interest in was superseded by the Joint Venture
Deed.
- [48] Agrotrust
relies on the decision of Associate Judge Bell in Claverdon Developments Ltd
v Housing New Zealand Ltd where his Honour held:9
...
the supply of services and materials on the land of another, gives a builder a
licence to go onto the land to carry out contract
works, but that licence is not
irrevocable and is not coupled with an interest in land. If the employer wrongly
brings the contract
to an end, the builder’s remedy is in damages.
- Claverdon
Developments Ltd v Housing New Zealand Ltd HC Auckland CIV-2009-404-7159, 19
February 2010 at [13].
- [49] Agrotrust
submits therefore that Erlon carried out the services in its capacity as a
contractor/service provider which does not
give rise to any interest that is
capable of supporting a caveat.
- [50] Erlon
submits in response that the fact that Erlon is a party to the Joint Venture
Deed confirms that it has made contributions.
If it had only been a service
provider, there would have been no need for Erlon to be a party. It was
necessary to include Erlon
to ensure that Erlon’s contributions were dealt
with and Erlon could not make a separate claim.
- [51] Furthermore,
Erlon submits it was entirely at Erlon’s discretion whether it
participated in the joint venture itself or,
instead, set up E-Farms to be the
joint venture partner. It is only because Mr Figueiredo and Erlon decided that
E-Farms was to be
the joint venture partner that the Deed referred to Erlon as a
service provider, but then only as a service provider to E-Farms and
not to
Agrotrust. Erlon submits that if the joint venture did not proceed, as Agrotrust
submits, then Erlon is the appropriate claimant
as it is the entity that has
provided the contributions.
- [52] I consider
it is reasonably arguable that Erlon has made contributions to the properties in
question satisfying the first element
from Lankow v Rose. Mr Arizaga
agrees that, inter alia, a term of the original verbal agreement reached was
that:
(c) Erlon would carry out the Services, and would charge Agrotrust 50% of the
actual costs of the Services, plus a reasonable margin
based on market
rates.
- [53] Mr
Arizaga’s evidence is not that Erlon’s invoices necessarily exceeded
the whole of the actual costs of the orchard
development but that they exceeded
50 per cent of the actual costs. The difference between the parties is that Mr
Arizaga’s
evidence is that, in the verbal agreement, the other 50 per cent
cost of the services that Erlon was responsible for would only be
credited as a
contribution if the terms of the proposed joint venture were agreed and
the proposed joint venture established.
- [54] Mr Arizaga
does not say however what would happen if the joint venture was not established
and whether Erlon would then be paid
the remaining 50 per cent for its
services.
- [55] Mr
Figueiredo’s evidence by contrast is that the terms of the verbal
agreement were that Agrotrust and Erlon would form
a joint venture and that
included Erlon providing the orchard management services and charging 50 per
cent of the costs of the services
to Agrotrust. The other 50 per cent was to be
Erlon’s contribution to the joint venture, with arrangements agreed in
relation
to the purchase of the properties and for Agrotrust and Erlon to enter
into a Joint Venture Deed to record the terms of the agreement.
- [56] I accept
that Agrotrust disputes whether it has only paid 50 per cent of the services
provided and has brought proceedings in
that respect. But this is not a matter
that can be determined in the summary context of a caveat application (as
counsel for Agrotrust
accepted at the hearing).
- [57] In
addition, it appears to be reasonably arguable that Erlon contributed half of
the deposit for the Parcel B land ($150,000).
- [58] Agrotrust
submits that Erlon perhaps has an argument for a remedial constructive trust but
that such an argument is not enough
to sustain a caveatable interest given there
would be no present interest in the land. This submission appears to acknowledge
that
there has at least been a contribution by Erlon.
Did Erlon have an expectation of an interest in the
property?
- [59] In
Almond v Read the Court of Appeal held that where a contribution is made
on the basis of a pre-existing common intention that the contribution will
result in a proprietary interest, there will be no difficulty in establishing a
reasonable expectation.10
- [60] In an
earlier decision of the Court of Appeal, Gormack v Scott, Cooke P
expanded on the principles applying to contributions based on a common
intention:11
10 Almond v Read, above n 7, at [69].
11 Gormack v Scott [1995] NZFLR 289 (CA) at 293.
(a) where there has been an express common intention applicable to the
circumstances that have arisen, it is unnecessary to fall
back on reasonable
expectations;
(b) if the common intention was too vaguely expressed, the evidence bearing on
common intention may still be relevant in considering
the reasonable
expectations of the parties;
(c) in considering reasonable expectations, attention is not to be confined to
the inception of the relationship or the time when
any property in question was
purchased, with the enquiry to extend to the whole circumstances and history of
the relationship.
- [61] Erlon
submits that it initially undertook the orchard development work in reliance on
a verbal agreement with Agrotrust that
Mr Figuierdo deposes in this affidavit
had the following terms:
(a) Agrotrust and Erlon would form a Joint Venture;
(b) Agrotrust and Erlon would share in the costs of the purchase, development
and operating costs of the orchard on a 50:50 basis;
(c) Erlon would provide the orchard management services and would charge 50% of
the cost of the services. The other 50% would be
Erlon’s contribution to
the Joint Venture;
(d) Agrotrust would purchase the properties with arrangements in place for
contributions to the purchase price to be made by Erlon.
- [62] Mr Arizaga
for Agrotrust describes the verbal agreement reached as:
(a) Agrotrust and Erlon would enter into good faith negotiations as to the terms
of the Proposed Joint Venture, with a view to entering
into a Joint Venture Deed
which would record the agreed terms between the two parties.
(b) The primary principal of the Proposed Joint Venture was that Agrotrust and
Erlon would share in the capital and operating costs
of the orchard on a 50:50
basis, and both would share in any profits on the same basis.
(c) Erlon would carry out the Services, and would charge Agrotrust 50% of the
actual cost of the Services, plus a reasonable margin
based on market rates.
(d) Erlon would carry out the Services with reasonable skill and care.
(e) Agrotrust would acquire the Zespri Licences.
(f) Agrotrust would purchase the Properties for the Orchard.
(g) If the terms of the Proposed Joint Venture were agreed and the Proposed
Joint Venture established, then:
(i) the other 50% cost of the Services that Erlon was responsible for would be
credited as a contribution of the Proposed Joint Venture
by Mr Figueiredo;
(ii) Mr Figueiredo would acquire a half share of the Properties;
(iii) Agrotrust’s Zespri Licences would be transferred to the Joint
Venture.
(“Agreement”)
- [63] It is not
possible to determine in this caveat application the terms of the verbal
agreement that were agreed and therefore whether
there was a common intention or
not.
- [64] The Joint
Venture Deed was entered into after the development work was completed and Erlon
had made contributions. At the time
of the contributions, in my view, it is
reasonably arguable that Erlon had an expectation of an interest in the
properties.
Was Erlon’s expectation reasonable?
- [65] Agrotrust
submits that Erlon has admitted Agrotrust’s pleading in its statement of
claim in the substantive proceeding
of the terms of the verbal agreement entered
into which includes at paragraph 11(g):
(g) If the terms of the Proposed Joint Venture were agreed and the Proposed
Joint Venture established, then:
(i) the other 50% cost of the Services was to be credited as a contribution of
the Proposed Joint Venture by the second defendant;
(ii) the second defendant would acquire a one-half undivided share of the
Property for the Orchard;
(iii) the Zespri Licences would be transferred to the Joint Venture.
- [66] I do not
consider that the admission of this paragraph by Erlon and Mr Figueiredo in
their statement of defence means their expectation
of an interest in the
property was not reasonable as the verbal agreement, even on Mr Arizaga’s
evidence, did not provide for
the situation where the terms of the joint venture
were not agreed.
- [67] The Joint
Venture Deed included clause 3.2 which said that if the conditions precedent
were not met, “this Deed will be
at an end and no party will have any
rights or obligations to the other parties except under clause 20.1
(Confidentiality)”.
It does not say, the joint venture is at an end, but
instead “this Deed”. The Deed does include an entire agreement
clause
at clause 23.7, providing that the Deed supersedes any prior written or
“other agreement or understanding between the parties”.
- [68] Whether
this clause is effective in superseding the verbal agreement depends on the
operation of s 50 of the Contract and Commercial
Law Act 2017. This is not a
matter I can determine in the context of a caveat proceeding.
- [69] Erlon may
no longer be able to rely on a clear, common intention but Mr Arizaga’s
evidence that the agreement was that
Agrotrust would pay only 50 per cent of the
invoices for the development of the orchard together with the undisputed
evidence that
Erlon paid 50 per cent of the deposit for the Parcel B land
suggests that it was a reasonable expectation that Erlon would have an
interest
in the land it worked to develop.
- [70] As Cooke P
held in Gormack v Scott the enquiry as to whether the expectations were
reasonable needs to extend to the whole circumstances and history of the
relationship:12
For example, developments may occur which
were outside the scope of the original reasonable expectations. Reasonable
persons in the
shoes of the parties might expect these developments to be dealt
with in a different way. So it was here, in the Judge’s view,
with the
payments assessed at $17,000 to give the appellant credit for that sum was a
perfectly proper course.
- [71] Agrotrust
now says that Erlon has charged Agrotrust and Agrotrust has paid Erlon more than
what the orchard has cost to develop.
This claim is the subject of this
substantive proceeding as referred to above. This claim relies on information
obtained by an ex-employee
of Erlon who now works for Agrotrust. Erlon says that
this information was obtained in breach of that employee’s employment
obligations. These are not matters that are able to be determined in the context
of an application to
12 At 293.
sustain a caveat. I proceed on the basis therefore that Erlon invoiced Agrotrust
for 50 per cent of the services and bore the costs
of the remaining 50 per
cent.
- [72] Agrotrust’s
position in relation to the 50 per cent contribution to the deposit for the
Parcel B land does not suffer from
the same complaint from Agrotrust but
Agrotrust says that it did not ask Erlon to contribute. Agrotrust did not
however reject Erlon’s
contribution and only paid the invoice as reduced
by that contribution, in line with what Erlon proposed.
- [73] Here, it is
reasonably arguable that a reasonable person in the shoes of the parties would
expect that Erlon would have an interest
in the property having been paid for
only 50 per cent of the work performed and having contributed 50 per cent to the
deposit for
Parcel B. Erlon submits that it made other contributions including
the selection of the appropriate property and advice on developing
the land as a
Zespri Red orchard. But for the purposes of this caveat, the work for services
performed, 50 per cent of which were
not invoiced, and the contribution to the
deposit for the Parcel B land, are sufficient to establish that it is reasonably
arguable
that Erlon’s expectation of an interest was reasonable. The third
element in Lankow v Rose is therefore sufficiently established for the
purposes of this caveat application.
Should Agrotrust reasonably be expected to yield an interest to
the applicant?
- [74] Agrotrust
proposes Erlon’s application ought to fail on two main grounds:
(a) it denies that Erlon made the contributions, claiming that Erlon overcharged
for the orchard development, and that the payment
from the respondent covered
the entire cost of the development; and
(b) the joint venture was not properly established because the conditions
precedent were not all met and, in those circumstances,
the contributions were
made at Erlon’s risk and do not give rise to an institutional constructive
trust.
- [75] The first
of these arguments, as I have already discussed above, cannot be determined in
the context of this caveat application.
The evidence of overcharging
relies on affidavits from Mr Arizaga and an ex-employee of Erlon that now works
for Agrotrust. Erlon submits this analysis is based
on Erlon’s incomplete
financial records obtained in breach of the ex-employee’s employment
conditions. Furthermore, the
evidence is challenged by an affidavit from
Erlon’s accountant who deposes that the financial accounts produced by
Agrotrust
are incomplete and cannot be relied upon.
- [76] In
addition, Erlon provides evidence of quotes given by it to other clients
consistent with the original quote to Agrotrust as
evidence that it did not
overcharge. These matters are matters in issue in the substantive proceedings
that have already been filed
and are matters that can only be properly
determined after a full hearing including evidence from experts.
- [77] The second
ground on which Agrotrust opposes Erlon’s claim to an interest in the land
is that any interest was conditional
on a joint venture being properly
established and that this did not happen because the conditions precedents were
not all met.
- [78] Erlon
submits that the status of the Deed itself is less determinative than Agrotrust
submits. Erlon says that whether the joint
venture as described in the Deed is
at an end or not, the Deed still evidences that:
(a) the contributions when made by Erlon, were made with the reasonable
expectation of a proprietary interest;
(b) the contributions were accepted by Agrotrust as having been made towards the
capital of the joint venture; capital that has increased
the value of the
properties and gives rise to a constructive trust.
- [79] Erlon
submits that even if the joint venture was “not established”, there
remains the open question of what happens
to the contributions made by the
parties up to that point. For Agrotrust to retain the sole ownership and benefit
of the property,
it would mean Agrotrust would have the benefit of Erlon’s
contributions for which it has not paid, that is 50 per cent of the
invoices
rendered and other costs not invoiced such as the kiwifruit plants.
- [80] Erlon
submits that Agrotrust’s position that this was agreed is not supported by
the evidence, is commercially unsustainable
and would result in Agrotrust having
the benefit of Erlon’s contribution without any obligation to account for
it if the joint
venture was not established.
- [81] I accept
Erlon’s submission that, in such circumstances, it is at least reasonably
arguable that the Court would find it
unconscionable for Agrotrust to deny Erlon
an equitable interest in the properties.
Result
- [82] It
is reasonably arguable that Erlon will be able to establish all four elements
necessary for an institutional constructive
trust. In these circumstances,
Erlon’s application that the caveat not lapse must be granted. Substantive
proceedings have
already been filed with Erlon filing a counterclaim in those
proceedings. There is no need therefore for the order that the caveat
not lapse
to be conditional on proceedings being filed. I therefore order that the caveat
is not to lapse until further order of
the Court, with those orders to be made
following the outcome of the substantive proceedings.
Costs
- [83] I
did not hear from the parties on costs but record my preliminary view that Erlon
is entitled to costs. The opposition by Agrotrust
relies on factual matters
which are in dispute between the parties. Substantive proceedings had already
been filed to determine those
matters, including the filing of a counterclaim
prior to the notice of lapse being filed.
- [84] I ask the
parties to confer and attempt to reach agreement. If that is not possible,
memoranda may be filed of no more than five
pages (excluding costs schedules) on
behalf of the applicant within 20 working days of this judgment and on
behalf of the respondent within a further 10 working days.
Associate Judge Sussock
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2022/1995.html