Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 19 September 2023
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
CIV-2022-404-2286
[2023] NZHC 2515 |
UNDER
|
the Contract and Commercial Law Act 2017 section 43(1) and (3)
|
BETWEEN
|
5-9 THE RISE LIMITED
First Plaintiff
GEOFFREY CAWSON
Second Plaintiff
|
AND
|
RENTAL SPACE LIMITED
Defendant
|
Hearing:
|
14 August 2023
|
Appearances:
|
Stephen J Mills KC / P C Crombie for the Plaintiffs
Zane G Kennedy / Mihai D Pascariu for the Defendant
|
Judgment:
|
8 September 2023
|
JUDGMENT OF ASSOCIATE JUDGE C B TAYLOR
[Application for summary judgment]
This judgment was delivered by me on 8 September 2023 at 3:00pm
pursuant to Rule 11.5 of the High Court Rules
............................... Registrar/Deputy Registrar
Solicitors:
CooneyLeesMorgan (Peter Crombie), Tauranga, for the Plaintiffs Hamilton Locke (Mihai Pascariu), Auckland, for the Defendant Copy for:
Stephen J Mills KC, Auckland, for the Plaintiffs
Zane G Kennedy, Barrister, Mills Lane Chambers, Auckland, for the Defendant
5-9 THE RISE LIMITED v RENTAL SPACE LIMITED [2023] NZHC 2515 [8 September 2023]
TABLE OF CONTENTS
Background [2]
The Rise’s application for summary judgment [7]
Affidavit of Geoffrey Cawson dated 2 December 2022 [9]
Supplementary affidavit of Geoffrey Cawson dated 6 December 2022 [20]
Rental Space’s opposition [21]
Affidavit of Peter Graham Hemming dated 14 March 2023 [22]
Reply affidavit of Geoffrey Cawson dated 11 April 2023 [30]
Further supplementary affidavit of Geoffrey Cawson dated 27 July 2023 [36]
Legal principles [39]
Approach taken in this judgment [42]
Was The Rise entitled to waive cl 23? [45]
Was cl 23 for The Rise’s sole benefit? [53]
Was cl 23 severable? [61]
Conclusion in respect of waiver of cl 23 [64]
The rectification defence [65]
Conclusion in respect of rectification [72]
Repudiation [73]
Conclusion in respect of repudiation [78]
Result [82]
Orders [83]
Introduction
Background
23. Finance Condition
This Agreement is conditional for 10 working days after the date of satisfaction or waiver of the condition contained in clause 22 (as may be extended in accordance with clause 24) upon the Purchaser obtaining finance for the Purchaser’s purchase and development of the Property on terms and conditions satisfactory to the Purchaser in all respects and approved by the Vendor acting reasonably. This condition is inserted for the sole benefit of the purchaser.
Operation of Conditions
10.8 If this agreement is expressed to be subject either to the above or to any other condition(s), then in relation to each such condition the following shall apply unless otherwise expressly provided:
...
(6) At any time before this agreement is avoided, the purchaser may waive any finance condition and either party may waive any other condition which is for the sole benefit of that party. Any waiver shall be by notice.
...
(10) working days of receiving agreed version of the same from the Vendor’s solicitor:
- ADLS Term Loan Agreement;
- Deed of Priority and Subordination (if requested by the Purchaser's first ranking lender);
- Deed of Guarantee and Indemnity. together the "Documents”
correct, cl 23 should be rectified as it did not reflect the parties’ common intention that Rental Space approve finance arrangements — it follows that cl 23 was only for The Rise’s sole benefit if Rental Space’s finance under cl 26 was not required. As a further alternative, Rental Space says that as The Rise failed to obtain finance in compliance with the mortgage priorities under cl 26, it had repudiated the Agreement further allowing Rental Space to elect to accept that repudiation and cancel the Agreement.
The Rise’s application for summary judgment
(a) that summary judgment as to liability on the first cause of action, as detailed in the statement of claim dated 30 November 2022, in this proceeding be entered for the first plaintiff against the defendant; and
(b) costs on this application;
(c) any other relief as the Court deems just.
(a) The defendant has no defence to the [first] plaintiff's claim in its first cause of action by virtue of it having repudiated the Agreement for the sale by it to the first plaintiff of two properties at 5-9 The Rise, Auckland ("Agreement") which led to the first plaintiff then cancelling the Agreement in accordance with s 36 of the Contract and Commercial Law Act 2017;
(b) The first plaintiff (as purchaser) was entitled to waive the finance condition (clause 23) in the Agreement and validly did so on 4 July 2022;
(c) The defendant then purported to wrongfully avoid and terminate the Agreement in reliance upon clause 23 not having been satisfied by the first plaintiff by the due date;
(d) The first plaintiff did not accept the defendant's termination of the Agreement and called upon the defendant to settle the transaction on the Settlement Date under the Agreement;
(e) The defendant then sought unilaterally to impose a new date of 11 August 2022 for satisfaction of the finance condition in clause 23 of the Agreement;
2 At [2].
(f) The defendant then gave notice on 16 August 2022 that it had avoided the Agreement and terminated it because the first plaintiff had failed to satisfy the finance condition by 11 August 2022;
(g) The defendant's notice avoiding the Agreement and terminating it on 16 August 2022 was wrongful and was a repudiation of the Agreement;
(h) The first plaintiff elected to accept the defendant's repudiation of 16 August 2022 and cancelled the Agreement on 23 August 2022;
(i) The first plaintiff has suffered loss as a result of the defendant's repudiation and is entitled to compensation under s 43 of the Contract and Commercial Law Act 2017 and/or damages at common law in a sum to be determined at trial;
(j) The entitlement of the first plaintiff to waive the finance condition, the validity of the defendant's notice of termination of the Agreement, and whether its termination on 16 August 2022 was a repudiation are legal issues. There are no contentious factual issues that require findings before the legal issues can be determined;
(k) Upon the further grounds appearing in the affidavit of Geoffrey Cawson filed in support of this application.
Affidavit of Geoffrey Cawson dated 2 December 2022
Deed required The Rise to obtain resource consent, a time consuming and costly process, alongside the management, finance, marketing, valuation, and legal fees that would be associated with pre-sales of units, obtaining finance and the resource consent. He says it was his ability to waive one or more of the conditions in cls 21 to 23 that gave him sufficient comfort to expend this time and these costs. Otherwise, he claims if there was some delay and he could not waive those conditions, Rental Space would be able to avoid the Agreement and maintain the benefit of all of Mr Cawson’s development progress, including any resource consent, to that point. Ultimately, the wording of the inserted clauses, including cl 23, was the subject of specific negotiations.
$2 million to $4 million, inserted a new cash-out clause (cl 28), and inserted a new profit share clause (cl 29).
agreed and that unless The Rise declared the Agreement unconditional that day, the Agreement would be at an end. Rental Space further said that based on proposed finance under the Proposed Variation Deed, which The Rise had already accepted was not proceeding on 28 June, Rental Space did not approve the finance arrangements. Having obtained urgent temporary finance in order to proceed to settlement on 18 July 2022, later on 4 July Mr Cawson advised his solicitors to confirm The Rise waived the cl 23 condition and declared the Agreement unconditional.
$2 million to obtain that consent and pre-sales to proceed with the development, and to perform its obligations under the Agreement.
Supplementary affidavit of Geoffrey Cawson dated 6 December 2022
(1) The Rise was entitled to waive cl 23 of the Agreement;
(2) The Rise waived cl 23 on 4 July 2022 and declared the Agreement unconditional;
(3) Rental Space wrongfully avoided the Agreement by claiming The Rise could not waive cl 23 and therefore did not satisfy cl 23 by 4 July 2022;
(4) The Rise did not accept the avoidance and sought to settle;
(5) Rental Space sought unilaterally to impose a new date to satisfy cl 23;
(6) Rental Space gave notice further avoiding the Agreement because The Rise had not satisfied cl 23 on the date it had unilaterally imposed;
(7) Rental Space’s 16 August 2022 notice terminating the Agreement was wrongful repudiation;
(8) The Rise elected to accept the repudiation and cancel the Agreement on 23 August 2022;
(9) The Rise has suffered loss and damage resulting from Rental Space’s repudiation;
(10) Rental Space is liable for this loss and damage; and
(11) For further reasons set out in his first affidavit and its exhibits.
Rental Space’s opposition
(a) The agreement dated 30 September 2019 for the sale and purchase of the properties at 5-9 The Rise (Property), Auckland (the Agreement) between the defendant as vendor, and the first plaintiff as purchaser, included the following terms:
(i) the purchase price was $8,250,000;
(ii) the defendant would provide a loan of $4 million (Vendor Finance) to be secured as a second ranking mortgage over the Property (clause 26); and
(iii) the first plaintiff’s finance arrangements for the purchase and development of the Property were to be approved by the vendor acting reasonably (Vendor Approval) (clause 23).
(b) The first plaintiff submitted various draft finance arrangements to the defendant for approval on:
(i) 26 May 2022;
(ii) 1 July 2022;
(iii) 19 July 2022; and
(iv) 4 August 2022.
(c) Each proposed finance arrangement:
(i) was a departure from the Agreement;
(ii) significantly increased the credit risk for the defendant; and
(iii) therefore, was not acceptable to the defendant.
(d) At all material times, the first plaintiff was unable to obtain finance on terms that were reasonably acceptable to the defendant.
(e) On or about 4 July 2022, the first plaintiff purported to satisfy the Vendor Approval condition by unilaterally waiving clause 23.
(f) The proper interpretation of clause 23 is that the first plaintiff was not entitled to waive the requirement for the Vendor Approval; and therefore, at all material times:
(i) the Vendor Approval condition remained unsatisfied; and
(ii) the Vendor Finance was not available.
(g) The first plaintiff repudiated the Agreement by purporting to unilaterally waive the Vendor Approval.
(h) If the proper interpretation of clause 23 is that the first plaintiff was entitled to waive the requirement for Vendor Approval (which is denied), then the wording of clause 23 did not reflect the parties' common Vendor Approval intention and should be rectified as pleaded in the statement of defence dated 15 March 2023.
(i) The date for satisfaction of the Vendor Approval condition was 5.00pm Thursday 11 August 2022 (the Due Date), time being of the essence.
(j) The Vendor Approval condition remained unsatisfied on the Due Date, and consequently the defendant validly terminated the Agreement on 23 August 2022 in accordance with clause 10.8(5) of the Agreement.
(k) Alternatively, if the first plaintiff was entitled to satisfy clause 23 by waiving that clause (which is denied):
(i) The Agreement became unconditional with a settlement date on 18 July 2022.
(ii) It was implicit in clause 26 that the first plaintiff had an obligation to procure a finance arrangement that would provide that the defendant's mortgage securing the Vendor Finance of $4 million would be second ranking.
(iii) On 8 July 2022, the first plaintiff proposed that the defendant provided the Vendor Finance under a third ranking mortgage.
(iv) The defendant rejected the proposal on the basis that it was inconsistent with the provisions of clause 26 of the Agreement.
(v) The purchaser failed to procure on or before 18 July 2022 a finance arrangement consistent with clause 26, therefore the Agreement did not settle on the Due Date.
(vi) Further finance proposals were put forward by the first plaintiff on 19 July and 4 August 2022. Both proposals were inconsistent with clause 26 in that:
(aa) the 19 July proposal provided for a bridging loan, which would render the defendant's mortgage third ranking;
(bb) the 4 August proposal provided for the defendant to provide a vendor loan of $5 million, $1 million in excess of the Vendor Finance [agreed] under clause 26.
(vii) The persistent refusal by the first plaintiff to complete the Agreement in accordance with the provisions of clause 26 amounted to repudiation and accordingly, the defendant was entitled to terminate the Agreement
(l) The defendant relies on the further grounds set out in the affidavit of Peter Hemming sworn 14 March 2023.
Affidavit of Peter Graham Hemming dated 14 March 2023
6 Affidavit in answer of Peter Graham Hemming dated 14 March 2023.
Reply affidavit of Geoffrey Cawson dated 11 April 2023
7 Affidavit of Geoffrey Cawson in reply dated 11 April 2023.
for him to obtain finance when he sought it later in the development process. The increase to $4 million was said to be a result of the impact of COVID-19 and to make further financing more attractive.
Further supplementary affidavit of Geoffrey Cawson dated 27 July 2023
Legal principles
12.2 Judgment when there is no defence or when no cause of action can succeed
(1) The court may give judgment against a defendant if the plaintiff satisfies the court that the defendant has no defence to a cause of action in the statement of claim or to a particular part of any such cause of action.
The question on a summary judgment application is whether the defendant has no defence to the claim; that is, that there is no real question to be tried: Pemberton v Chappell. The Court must be left without any real doubt or uncertainty. The onus is on the plaintiff, but where its evidence is sufficient to show there is no defence, the defendant will have to respond if the application is to be defeated: MacLean v Stewart. The Court will not normally resolve material conflicts of evidence or assess the credibility of deponents. But it need not accept uncritically evidence that is inherently lacking in credibility, as for example where the evidence is inconsistent with undisputed contemporary documents or other statements by the same deponent or is inherently improbable: Eng Mee Yong v Letchumanan. In the end the Court’s assessment of the evidence is a matter of judgment. The Court may take a
robust and realistic approach where the facts warrant it: Bilbie Dymock Corp Ltd v Patel.
Having regard to the various authorities, the position appears to be as follows:10
(1) The discretion implied by the use of the word “may” is to be restrictively applied. In a great majority of cases, once the court is satisfied the defendant has no defence, there is no room for the exercise of discretion.
(2) The residual discretion may be invoked to avoid oppression or injustice to the defendant where:
(i) The proceeding involves the actions or possible liability of a third party which is not before the court;
(ii) The proceedings are such that the opportunity should be given to allow discovery or other interlocutory applications to be concluded;
(iii) The circumstances of the case disclose very unusual features, the presence of which leads the court to conclude that the entry of summary judgment would be oppressive or unjust; or
(iv) The combination of complex issues of fact and law justify the dismissal of the application for summary judgment, either as a matter of discretion or because the court cannot be satisfied that the defendant has no defence.
(3) Even where the court is not satisfied that a defence has been made out, in exceptional circumstances the application may be adjourned to allow for other processes to be followed.
Analysis
Approach taken in this judgment
(1) that The Rise was not entitled to waive cl 23 of the Agreement on a proper construction of the clause. Even if it was able to be waived, cl 23 had to be severable from the rest of the Agreement, which it was not, being fundamentally linked to cls 26 and 29. By purporting to waive cl 23 when it was not entitled to do so, The Rise repudiated the Agreement, and Rental Space was entitled to accept that repudiation and cancel the Agreement;
(2) as an alternative to [43](a), Rental Space argues that cl 23 should be rectified at trial to reflect the parties’ common intention — namely, that if cl 23 was waived by The Rise, then that could only be on the basis the vendor financing was no longer required; and
(3) The Rise’s inability to settle the Agreement in a manner consistent with cl 26 amounted to a repudiation by The Rise, which Rental Space was entitled to accept and cancel the Agreement.
Was The Rise entitled to waive cl 23?
11 Bathhurst Resources Ltd v Allan M Cole Holdings Ltd [2021] NZSC 85, [2021] 1 NZLR 696.
in the most obvious and extreme cases”.12 He submits that on application of these interpretative principles to the undisputed facts, The Rise’s interpretation must be upheld, namely that as purchaser it was entitled to unilaterally waive the condition in cl 23.
(1) Clause 1.4(3) of the General Terms of Sale provided “[i]f any inserted term (including any Further Terms of Sale) conflicts with the General Terms of Sale the inserted term shall prevail”.
(2) There is no conflict between the operation of cl 23, the finance condition, and any of the General Terms of Sale;
(3) Clause 10.8(6) of the General Terms of Sale provided:
Operation of Conditions:
10.8 If this Agreement is expressed to be subject either to the above or to other condition(s), then in relation to each such condition the following shall apply, unless otherwise expressly provided:
...
(6) At any time before the Agreement is avoided, the purchaser may waive any finance condition and either party may waive any other condition for the sole benefit of that party. Any waiver shall be by notice.
[Emphasis added by counsel]
(4) Clause 23 is a finance condition and there is nothing in that clause which expressly negates the purchaser’s unilateral right to waive any finance condition as provided in cl 10.8(6) of the Agreement. Clause 23 also expressly states that it was for the sole benefit of the purchaser.
12 Above n 11, at [44] and [45].
(5) Other Further Terms of Sale (cl 21 being the resource consent condition, cl 22 being the pre-sales condition, cl 24 being the right to extend the conditions, and cl 25 being the settlement date) when read as a whole supports the interpretation that The Rise was entitled to waive cl 23. Clauses 21 and 22 mirror the text of cl 23 in saying that they are for the sole benefit of the purchaser. Clauses 24 and 25 expressly state that each of cls 21, 22 and 23 can be satisfied or “waived” by the purchaser.
(6) The question of whether a condition is for a party’s sole benefit is one of construction of the Agreement, turning on whether the condition is in its terms, or by necessary implication, for the exclusive benefit of that party. Mr Mills submits that here there is no need for any “necessary implication” as the text is clear and unambiguous.
(1) in that decision the agreement provided that it was conditional on the purchaser or its nominee obtaining consent to purchase the land under the Overseas Investment Act. The purchaser sought to unilaterally waive the condition and the issue was whether the condition was for the sole benefit
13 Future Sustainable Development Ltd v Liu [2022] NZCA 249.
of the purchaser. The vendor claimed the condition also provided a benefit to it and could not be unilaterally waived by the purchaser;
(2) that in considering the OIA consent condition, and whether it could be unilaterally waived by the purchaser, the Court referred by analogy to the position of the vendor whose purchaser has waived a finance condition. The Court observed that the fulfilment of a finance condition reduced the risks associated with the purchaser subsequently defaulting, because it cannot arrange finance, and the Court recognised that the need for the vendor’s consent offers an advantage to the vendor by reducing the risks associated with any default by the purchaser, but the loss of that advantage was not a “benefit” for the purposes of determining whether the purchaser has the right to waive the condition.
That brings us to the question whether cl 20.3 was for the sole benefit of FSD. The question is one of construction of the agreement, as we have explained. The fact the condition confers an advantage on the other party is not conclusive. The parties may assign risk as they see fit.
(1) The first of these is the risk The Rise had in incurring up-front costs in satisfying conditions in the Agreement, including cls 21 and 22 (obtaining resource consent and pre-sales). Mr Cawson’s evidence is that there would be substantial sunk costs incurred in obtaining the resource consent for the subdivision for construction of the 10-unit apartment building. Further, as the resource consent runs with the land it would be expected to add significant value to it, which created a potential incentive for the vendor to cancel the Agreement and re-sell the property if that increased value could be realised by the vendor by way of sale at a higher price.
14 At [54].
Mr Cawson’s evidence is that it was his ability to waive one or more of the conditions in cls 21 to 23 that gave him the comfort needed to commit the substantial time and costs that would be incurred in seeking to obtain resource consent, the number of pre-sales needed to obtain finance, and then finance.
(2) The second is the risk associated with the cash-out clause that was introduced into the Agreement through the Second Variation Deed, which gave Rental Space the right to give notice to The Rise requiring it to confirm within 30 days whether all the conditions for their benefit had been satisfied or waived, and if it did not declare the Agreement unconditional within that time-frame, Rental Space could immediately cancel the Agreement — and if that occurred, The Rise received only 50 per cent of its sunk costs. Mr Cawson’s evidence is that if The Rise was not entitled to unilaterally waive the finance condition in cl 23, effective control over whether or not the Agreement was terminated under the cash-out would rest with Rental Space. If Rental Space obtained another offer on more favourable terms, and as a result gave notice under the cash-out clause, there would be an incentive for Rental Space to withhold its approval of any financing proposals submitted by The Rise during the 30-working day notice period. Mr Cawson in his evidence says he took comfort from the right to waive the finance conditions as a means of mitigating this risk.
15 Hawker v Vickers [1991] 1 NZLR 399 (CA) at 402.
A party may waive a condition or provision in a contract which is solely for that party’s own benefit and is severable.
[Emphasis added by counsel]
Was cl 23 for The Rise’s sole benefit?
16 Bathhurst Resources Ltd v Allan M Cole Holdings Ltd, above n 11, at [44], [48], [70] and [76].
have, arising out of the vendor’s approval requirement. That protection would be rendered entirely illusory if, at any point prior to the date of satisfaction of cl 23, The Rise could waive the clause irrespective of the terms of its first-ranking secured lending.
(1) it cannot reasonably be suggested that the parties intended that The Rise could dispense with the need to obtain Rental Space’s approval of its development finance arrangements and at the same time force Rental Space to leave a $4 million loan in the development;
(2) the proposition that Rental Space would agree to provide a $4 million loan without any ability to assess the credit risk associated with that loan is not a proposition that could sensibly have been intended by the parties.
mitigating Mr Cawson’s risk in respect of 50 per cent of its sunk costs, the cash-out clause also enabled Rental Space to terminate the Agreement if another party made a more attractive offer.
Was cl 23 severable?
$4 million in the development irrespective of The Rise’s other finance and security arrangements, and their direct impact on its lending risk, makes no commercial sense. Accordingly, he contends the approval of The Rise’s first ranking funding arrangements were inextricably linked to the ability of the parties to complete the documentation required under cl 26.4.
provide vendor finance was conditional on Rental Space’s approval of The Rise’s first ranking lender finance, cl 26 would have said so.
Conclusion in respect of waiver of cl 23
(1) in respect of the first step in the analysis arising from the Bathhurst decision, that the text should be given primacy (as submitted by Mr Mills), the text does not deal with the interpretation of cl 23 definitively because the wording “and approved by the vendor acting reasonably” introduces an uncertainty into the meaning of the text. It is therefore necessary to engage the second part of the analysis referred to in Bathhurst of looking at the prior negotiations and conduct of the parties to ascertain the objective shared meaning. In my view, the course of negotiations discloses that, as a matter of commercial reality, once the vendor finance provision was inserted in the Agreement by the First Variation Deed, the wording requiring Rental Space’s approval of The Rise’s first ranking funding was inextricably linked to the provision of the vendor finance.
(2) As to Mr Mills’ argument that the clause was a finance condition and therefore capable of waiver under cl 10.8(6), I accept Mr Kennedy’s submission that upon insertion of the words “and approved by the vendor acting reasonably”, cl 23 ceased to be a finance condition for the purposes of cl 10.8(6), and therefore the provisions in cl 10.8(6) relating to waiver of a finance condition ceased to apply to it.
(3) I accept Mr Kennedy’s argument that Rental Space, as the provider of
$4 million of vendor finance, had a significant interest in the terms of the first ranking funding arrangements, as clearly they would impactsignificantly on the risk profile of Rental Space’s vendor loan. I agree with Mr Kennedy’s submission that it seems unlikely from a commercial commonsense point of view that the intention of the parties that the protection afforded by the requirement for Rental Space to approve the terms of the first ranking funding could be waived unilaterally by The Rise while still retaining the commitment of Rental Space to advance the $4 million.
(4) I also accept Mr Kennedy’s submission that Rental Space’s right to approve The Rise’s first ranking funding is more than “an advantage” to Rental Space, as discussed in Future Sustainable Development Ltd v Liu.17 It was an important part of Rental Space’s agreement to lend what amounted to approximately half of the purchase price of the property.
(5) Based on the decision of Hawker v Vickers,18 it is arguable that for The Rise to be able to waive cl 23 unilaterally it must be both for the sole benefit of The Rise and severable. I agree with Mr Kennedy’s submission that it is arguable that cl 23 is not severable and it was intrinsically liked to cl 26. In my view, Mr Kennedy is correct that cl 26.4 and completion of the documentation relating to the vendor loan is unworkable without the ability of Rental Space to approve the first ranking lender’s funding terms, from which approval the completion of the documentation contemplated by cl 26.4 would naturally flow. Without the prior approval of the terms of the first ranked lender, cl 26.4 effectively becomes an agreement to agree.
The rectification defence
17 Future Sustainable Development Ltd v Liu, above n 13.
18 Hawker v Vickers, above n 15.
This clause is inserted for the sole benefit of the purchaser if the vendor finance is not required.
(1) That, whether there is an antecedent agreement or not, the parties formed and continued to hold a single corresponding intention on the point in question.
(2) That such intention continued to exist in the mind of both or all parties right up to the moment of execution of the formal instrument of which rectification is sought.
(3) That while there need be no formal communication of the common intention by each party to the other or outward expression of accord, it must be objectively apparently from the words or the actions of each party that each party held and continued to hold an intention on the point in question corresponding with the same intention held by each other party.
(4) That the documents sought to be rectified does not reflect that matching intention but would do so if rectified in the manner requested.
19 Westland Savings Bank v Hancock [1987] 2 NZLR 21 (HC) at 30.
20 Krukziener v Hanover Finance Ltd [2008] NZCA 187, [2010] NZAR 307 at [26].
Conclusion in respect of rectification
21 Watson v Whitehead [2014] NZHC 2992 at [137].
finance was no longer required, The Rise was free to waive the clause and undertake whatever financial arrangements it wished with the first ranked lender.
Repudiation
$4 million vendor loan on the terms recorded in cl 26. He submits that none of the financial proposals circulated by The Rise would have enabled settlement to proceed in accordance with cl 26. He expands this submission as follows:
(1) The finance proposal circulated by The Rise on 26 May 2020 provided for a mezzanine facility of $3.6, million which would render Rental Space’s security third ranking;
(2) the term loan agreement The Rise sent to Rental Space on 8 July 2022 was in the form of the ADLS agreement, but The Rise had included further terms which were unacceptable to Rental Space including provisions that:
(i) The Rise would, in its complete sole and objective discretion, refinance the first ranked lender (being the lender providing the bridging loan and the lender refinancing the bridging loan) at any time during the term (cl 22.1);
22 Kumar v Station Properties Ltd (In Liq and In Rec) [2015] NZSC 34, [2016] 1 NZLR 99 at [65].
(ii) Rental Space would:
(3) the proposed bridging loan significantly increased the risk of Rental Space not being able to recover its loans in full from The Rise, and the bridging loan had not been discussed or agreed previously by the parties. The bridging loan was inconsistent with cl 26 and an unacceptable change in the risk allocation under the Agreement and therefore Rental Space rejected it;
(4) on 19 July 2022, The Rise circulated a further proposal which provided for a two-stage financing arrangement that included the proposed bridging loan from DBR Limited to be secured by a first ranking mortgage. The proposed second stage included a progressive loan facility from MaxCap which would be used in part to refinance the DBR bridging loan. As the proposal retained the bridging loan it was therefore unacceptable to Rental Space;
(5) on 4 August 2022, The Rise circulated a further proposal, under which the DBR bridging loan was replaced by a separate facility provided by the MaxCap (Facility B) together with a development finance facility (Facility A). The effect was the Rental Space’s loan would be repaid only after Facilities A and B were repaid and the deed of priority and subordination required a vendor loan of $5 million, a proposal which Rental Space had previously rejected.
payment of the purchase price by a $4 million vendor loan on standard ADLS terms, secured by a second ranking security. Accordingly, The Rise failed to secure a finance arrangement which would have enabled settlement of the Agreement in accordance with cl 26.
Conclusion in respect of repudiation
Result
Orders
(1) The Rise’s application for summary judgment as to liability on the first cause of action as detailed in the statement of claim dated 30 November 2023 is dismissed.
(2) Counsel are directed to endeavour to agree costs and failing agreement within 20 working days of the date of this judgment, counsel for Rental Space will file a memorandum as to costs (not to exceed 5 pages) within
5 days of the expiry of the 20 working day period, and counsel for The Rise will file a memorandum in reply (not to exceed 5 pages) within 5 working days of receipt of counsel for Rental Space’s memorandum. A decision on costs will then be made on the papers.
................................... Associate Judge Taylor
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2515.html