You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2024 >>
[2024] NZHC 397
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
IAG New Zealand Limited v Degen [2024] NZHC 397 (6 March 2024)
Last Updated: 13 March 2024
IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE
|
CIV-2023-409-033
[2024] NZHC 397
|
UNDER
|
the Canterbury Earthquakes Insurance Tribunal Act 2019
|
BETWEEN
|
IAG NEW ZEALAND LIMITED
Appellant
|
AND
|
WILLIAM GERARD DEGEN
Respondent
|
Hearing:
|
12 September 2023 (appellant only)
Amicus submissions filed 10 November 2023
Appellant memorandum in reply 20 November 2023
|
Appearances:
|
D J Cooper KC and M K Booth for Appellant W G Degen in person (not
participating)
B Gray KC Amicus Curiae (from 10 November 2023)
|
Judgment:
|
6 March 2024
|
JUDGMENT OF HINTON J
This judgment was delivered by me
on 6 March 2024 at 4.00 pm, pursuant to Rule 11.5 of the High Court
Rules.
Registrar/Deputy Registrar Date:
...............................
Solicitors:
Wotton Kearney, Wellington
IAG NEW ZEALAND LTD v DEGEN [2024] NZHC 397 [6 March 2024]
- [1] Mr
Degen’s house was damaged by the Canterbury Earthquake Sequence. It was
insured under an NZI “Supersurance House”
policy, NZI being a
division of IAG New Zealand Ltd.
- [2] There was a
dispute between Mr Degen and IAG as to whether the house was so badly damaged it
needed to be rebuilt or whether it
could be repaired, and also as to the
required extent of repair.
- [3] The
Canterbury Earthquakes Insurance Tribunal (CEIT), by decision dated 21 December
2022, found against Mr Degen on the principal
issue as to whether the house was
capable of repair. The CEIT found that IAG’s repair strategy would restore
Mr Degen’s
house to the policy standard. The CEIT made further findings as
to the scope of repairs required, these being largely in Mr Degen’s
favour.1
- [4] There were a
number of subsidiary findings, three of which IAG has appealed, being:
(a) That IAG should be required to pay for reinstatement of the house in one
lump sum upon Mr Degen’s entry into a building
contract. IAG says payment
should be made as costs are incurred.
(b) That IAG should be required to pay the costs of certain professional reports
obtained by Mr Degen for the purposes of his claim
against IAG on the basis that
IAG breached a duty to adequately assess the damage and to adequately scope the
repair strategy necessary.
IAG says there is no such duty and it is not liable
for these costs.
(c) That IAG should, alternatively to (b), be required to pay the costs of Mr
Degen’s professional reports under cl C4 of the
policy.
- [5] As to (b)
and (c) above, although the CEIT says its conclusion is reached based on either
policy coverage for professional fees
or failure of IAG to adequately
assess
- Degen
v IAG New Zealand Ltd CEIT-0014-2020, 21 December 2022 [CEIT Decision]. The
CEIT incorrectly said that the decision established the cost of repairs, at
[307].
the damage, the CEIT did not undertake any analysis of policy coverage. Further,
IAG paid the professional fees on a without prejudice
basis following the
decision and given the low quantum involved it does not seek repayment. In the
circumstances, IAG proposed that
I treat the finding as based solely on its
alleged failure to properly undertake assessments, which is the real point of
concern
on the appeal. That then obviates the need to address (c), that is to
analyse whether the professional fees at issue were covered
by the Supersurance
House policy, there being no such analysis on the part of the CEIT. Addressing
that point is best left to a case
where it is squarely at issue.
- [6] IAG required
leave to appeal from the CEIT which Brewer J granted on 27 March
2023.2
- [7] While Mr
Degen attended the hearing, he did not oppose the appeal.
- [8] On its
application for leave, IAG suggested that the Court might wish to appoint amicus
curiae. Brewer J directed that was not
necessary as the issues did not seem to
be precedent-setting. However, at the outset of this hearing, having had the
benefit of reading
IAG’s submissions, I agreed with IAG that the issues
raised were significant for the insurance industry and amicus should be
engaged.
Rather than adjourn, with the concurrence of Mr Cooper KC, I proceeded to hear
from IAG’s counsel on the submissions
filed and subsequently appointed
Bruce Gray KC as amicus to file any additional submissions he considered
appropriate. At my request,
Mr Cooper updated Mr Gray on any authorities and
other material not expressly referred to in his written submissions. Mr
Gray’s
submissions were filed and served on 10 November 2023. His
submissions did not differ materially from those of IAG. Mr Cooper filed
a
memorandum dated 20 November 2023 advising that IAG did not seek to file
submissions in reply.
- [9] Under s
54(1) of the Canterbury Earthquakes Insurance Tribunal Act 2019 a party to a
claim may appeal against a question of law
or fact arising from the CEIT’s
decision. The High Court may “confirm, modify, or overturn the
tribunal’s decision”
or “order a remedy or award costs or
interest that could be ordered or awarded by the
2 IAG New Zealand Ltd v Degen HC Christchurch
CIV-2023-409-33, 27 March 2023.
tribunal”.3 Under r 20.18 of the High Court Rules 2016, appeals
to this Court are by way of rehearing.
Was the CEIT in error as to the required timing of payment of
reinstatement costs?
- [10] Under
the relevant policy provisions,4 where damage is repairable (which
the CEIT found it was) IAG is obliged to pay the reasonable cost of repair. IAG
can choose whether
to undertake those works itself or pay the cost to Mr Degen.
Mr Degen then has the right to choose whether the repair works are to
be carried
out or not. If he elects against repair works, IAG only has to pay the present
value of the house plus reasonable associated
costs (including demolition if
necessary).
- [11] In this
case, IAG did not elect to undertake the works itself and Mr Degen chose to
proceed with repair works. IAG is therefore
obliged to pay Mr Degen the cost of
repairs. The question is when payment has to be made.
- [12] The CEIT
held that Mr Degen’s right to be paid for repair work was absolute once Mr
Degen had entered into a contract for
repair.5 The CEIT reached that
conclusion on the basis of its interpretation of a decision of the Court of
Appeal in Medical Assurance Society of New Zealand Ltd v
East,6 and/or on the basis that such a
finding was in the interests of certainty and finality for the benefit of both
parties.7
- [13] The CEIT
then ordered that the “reasonable cost of repair ... less what has already
been paid to Mr Degen”, should
be paid by IAG to Mr Degen “within 10
working days of Mr Degen providing IAG with a copy of a building contract to
repair his
property”.8
- [14] I agree
with both IAG and Mr Gray that the CEIT erred in ordering full payment upfront.
Rather the CEIT should have ordered that
IAG fulfil its obligations
3 Canterbury Earthquakes Insurance Tribunal Act 2019, s 54(4).
4 Supersurance House Policy, cls C1, C2 and G2.
5 CEIT Decision, above n 1, at [116].
- Medical
Assurance Society of New Zealand Ltd v East [2015] NZCA 250, (2015) 18 ANZ
Insurance Cases 62-074.
7 CEIT Decision, above n 1, at
[118].
8 At [307].
under the policy by paying the relevant contractor(s), or Mr Degen himself, the
reasonable costs of repairs as they were actually
incurred.
- [15] As IAG
submits, the courts have recognised there are “moral hazards”
associated with replacement insurance.9 Where the cost of repair
exceeds the present value of a house, an insured, if entitled to insist upon
payment of repair costs before
the repairs are undertaken, may decide not to
proceed with the repairs but instead demolish and rebuild. This would be
contrary to
the insurance policy which entitles an insured who decides to
demolish and rebuild, only to the present value of the building. As
Mr Gray
identified, these “moral hazards” remain even where an insured
enters into a fixed price agreement, as contracts
can be varied or terminated by
agreement, without performance.
- [16] These
“moral hazards” are one reason why the insurer’s reinstatement
promise is usually qualified expressly
or impliedly by a requirement that the
insured has first incurred the cost of reinstating the dwelling. This means that
the insured
must at least have a legal liability for the cost. That does not
require the insured to actually be out of pocket because in practice,
as Mr
Cooper confirms, the insurer will generally discharge its payment obligation by
payment directly to the builder or other contractor.
- [17] The
Supersurance House policy applicable here makes the point by implication rather
than explicitly. The basic insuring promise
is to “cover” the
insured. In East, the Court of Appeal held that in an insurance context
the words “will cover” are synonymous with will “indemnify
the
insured against”, and that this expressed the insurer’s undertaking
“to pay the rebuilding costs when they are
incurred”.10
- [18] To expand,
the High Court in East had determined that the Medical Assurance Society
was obliged to pay the Easts the estimated cost of repairing the earthquake
damage
to their property irrespective of whether liability to incur those costs
had been, or would ever be, incurred.11 In overturning the decision,
the Court of Appeal said that the underlying basis of a reinstatement benefit is
that an insured is only
entitled
- Xu
v IAG New Zealand Ltd [2019] NZSC 68, [2019] 1 NZLR 600 at [21] and [45];
Tower Insurance Ltd v Skyward Aviation 2008 Ltd [2014] NZSC 185, [2015] 1
NZLR 341 at [26].
10 Medical Assurance Society of New
Zealand Ltd v East, above n 6, at
[20].
11 East v Medical Assurance Society New Zealand Ltd [2014]
NZHC 3399.
to recover their actual, not estimated, costs of reinstatement and “the
cost is not and will not be known until, at the least,
liability to pay for the
work is incurred”.12
- [19] The Court
later said that the insurer’s right to be paid the reinstatement benefit
is “absolute once they incur a contractual obligation for the purpose
of restoring the building”.13 A similar statement is made
at [24]. The CEIT appears to have taken such statements as meaning that an
insured is entitled to payment
immediately upon entering into a building
contract.14 However, read in context, it is clear that
“contractual obligation” is a reference to an obligation to pay.
Such an obligation
will generally not arise under a building contract until an
invoice issues.
- [20] From a
practical perspective, a building contract for repair will seldom, if ever, be
for a fixed sum in an uncertain financial
market. Nor, although the CEIT stated
otherwise, did the decision actually determine the reasonable cost of repair.
The CEIT had
to consider the issue in broad terms to determine whether the house
was repairable, but beyond that the issue was not one for the
CEIT. The
reasonable cost of repair will be determined by entry into a building contract
and by payment of invoices on receipt.
- [21] As the
Court of Appeal further observed in East, and Mr Cooper submitted here,
the approach of an insurer paying build costs on invoices submitted as work
progresses works efficiently
and effectively in practice. The Court considered
this practice did not fetter an insured’s right to replacement value
compensation
because an insurer’s failure to indemnify after being
presented with a valid invoice would carry serious legal and reputational
consequences.15
- [22] As to the
CEIT’s statement that both parties deserve the certainty and finality that
making an order for immediate payment
would achieve,16 I agree with
IAG that such a rationale is not a legitimate basis for the order made. First,
the obligation and timing of payment can
only be dictated by the terms of the
policy and the insurance principles that underpin it. Second, any payment prior
to the quantification
of actual
12 Medical Assurance Society of New Zealand Ltd v East,
above n 6, at [21].
13 At [29].
14 CEIT Decision, above n 1, at [116]-[117].
15 Medical Assurance Society of New Zealand Ltd v East,
above n 6, at [25].
16 CEIT Decision, above n 1, at [118]–[120].
costs would necessarily be based on an estimate, which by its very nature would
create uncertainty in both directions and would run
contrary to the decision in
East.17 Further, as noted above, Mr Degen might choose not to
proceed with reinstatement and use the money for some other purpose which, as
the Court of Appeal observed in East, IAG would be powerless to prevent,
short of taking legal action.18 “Certainty” would be very
one-sided in that context.
- [23] I therefore
set aside the order made at [307] of the CEIT decision. That order is replaced
with a declaration in terms of [5.3(a)]
of the notice of appeal, namely that IAG
is required to pay repair costs to Mr Degen only as and when Mr Degen has
incurred the costs
of such repair, submitted invoices to IAG, and IAG has
assessed the invoices and is satisfied that the costs are reasonable and relate
to the scope of work.
Did the CEIT err in ordering IAG to reimburse certain
professional fees on the basis of a duty to make an adequate assessment of the
insured’s damage?
- [24] The
CEIT held as follows:19
- [280] In this
case the various assessments of the damage by IAG were inadequate, at least
until the matter was filed in the
High Court. Had Mr Degen accepted
IAG’s advised position on the damage and followed its repair strategy he
would not have
been fully indemnified under the policy. Therefore, I proceed on
the basis that if Mr Degen has obtained a report to reasonably address
an aspect
of IAG’s inadequate assessment, the reasonable costs of this report should
fall for cover by IAG. This conclusion
is reached on either policy coverage for
professional fees, or that the cost incurred by Mr Degen has followed from a
failure of
IAG to properly undertake assessments.
- [281] I consider
that IAG breached its duties to Mr Degen by failing its duty to adequately
assess the damage to his property and
therefore failed to adequately scope, and
cost, the repair strategy necessary. If Mr Degen had not commissioned a number
of his own
experts, including engineers and AJ Minkley and Simplexcity to make
their own assessments of the earthquake damage and consequently
repair
strategies and costs beyond what IAG had prepared, his house would not have been
adequately repaired. It is highly likely
this case would have instead been one
about defective scoping and repairs.
- [282] Because of
IAG’s failures I do not consider that reimbursement for expert reports
needs to be limited to those professions
listed in the Policy.
17 See Medical Assurance Society of New Zealand Ltd v East,
above n 6, at [26].
18 At [27].
19 CEIT Decision, above n 1.
- [25] I agree
with IAG and Mr Gray that the CEIT erred in finding at [281] that an insurer has
a duty to adequately assess the damage
sustained by the insured in cases of
insurance policies of this nature. As submitted, again by both IAG and Mr Gray,
there is no
authority for the alleged duty. In fact, it is a fundamental
principle of insurance law that the insured bears the burden of proving
loss,
including its actual quantum. This has been acknowledged in numerous decisions
of this Court following the Canterbury Earthquake
Sequence.20
- [26] In finding
that IAG owed a duty to accurately assess the earthquake damage to Mr
Degen’s house, the CEIT relied on:
(a) the Fair Insurance Code provision requiring IAG to “settle all valid
claims quickly and fairly”;
(b) Young v Tower Insurance Ltd;21 and
(c) the CEIT’s decision in LS v Medical Insurance Society
Ltd.22
- [27] The Fair
Insurance Code is a code of practice that encourages good conduct and
professionalism in the insurance industry generally.23 It is designed
to sit alongside the law relating to insurance and has its own enforcement
regime. It is not part of the terms and
conditions of Mr Degen’s policy,
and I agree with IAG that it is also not extrinsic material that might aid in
its interpretation.
- [28] In any
event, the Code’s reference to settling all valid claims quickly and
fairly is a different matter to, and not inconsistent
with, Mr Degen’s
obligation to prove his loss. I agree with Mr Gray that the Code goes to
promptness of consideration, not
whether there is a duty on an insurer to
undertake their own investigations to discharge a contractual burden of proof
which falls
on the insured. Once an insured submits a valid claim an
insurer must settle it quickly and fairly. Where there is a dispute
about
20 See for example He v Earthquake Commission [2017] NZHC
2136 at [55] following Jarden v Lumley General Insurance (NZ) Ltd [2015]
NZHC 1427, (2015) 18 ANZ Insurance Cases 62-077 at [47]–[54].
21 Young v Tower Insurance Ltd [2016] NZHC 2956, [2018] 2
NZLR 291.
22 LS v Medical Insurance Society Ltd CEIT 0024-2020, 22
March 2021 at [34].
23 Fair Insurance Code 2016 at 2.
the validity of the claim (including as to quantum) the insured bears the burden
of proving the claim. There was clearly a dispute
here about the nature (and
sum) of the claim. I note finally with regard to the actual provision in the
Code, that the CEIT did not
find IAG breached that provision as worded.
- [29] In
Young, Gendall J considered whether there was an implied duty of good
faith in insurance policies and whether this should extend to an
insurer’s
handling of claims.24 The Judge concluded there was such an implied
duty and that, as a minimum, it requires an insurer to disclose all material
information;
act reasonably (including but not limited to the initial formation
of the contract and during and after the lodgement of a claim);
and to process
the claim in a reasonable time.25 In the course of his judgment,
Gendall J considered the Fair Insurance Code obligation to “settle all
valid claims quickly and
fairly”.
- [30] I note the
observations in Young that what is reasonable will depend on all the
relevant circumstances, including whether the insurer shows that reasonable
grounds
exist for disputing the claim.26 An insurer does not breach
the implied term merely by failing to pay while the dispute is continuing. But
the conduct of the insurer
in handling a claim may be a relevant factor in
deciding whether that good faith duty was breached.27
- [31] IAG says it
had reasonable grounds to dispute the claim and that it always accepted it was
liable to pay to remediate. What prevented
the matter from being settled quickly
was Mr Degen’s view that his house needed to be rebuilt, with which the
CEIT ultimately
disagreed.
- [32] IAG says
all that can be taken from Young is that an insurer is under an implied
good faith obligation to process valid claims within a reasonable timeframe and
they will not
be in breach of that obligation if there are reasonable grounds
for disputing the claim. I agree.
24 Young v Tower Insurance Ltd, above n 21.
25 At [163].
26 At [164].
27 At [164].
- [33] I do not
consider that either the Fair Insurance Code or Young go so far as to
say, as the CEIT does, that IAG owed a duty to adequately assess the damage to
Mr Degen’s property and to adequately
scope and cost the repair strategy
necessary. I do not read that obligation in either the Code or in Young.
To find such an obligation would be to elevate the duty of disclosure to a duty
to obtain information. Such a duty would be incompatible
with the duty of an
insured to demonstrate his or her entitlement to be indemnified under a
policy.
- [34] The CEIT
also relied on its own decision in LS v Medical Insurance Society
Ltd.28 The issue in that case was whether an insured had made an
election under the policy to remediate the earthquake damage to their
property.29 The CEIT said in LS that insurers have a duty to
accurately assess claims and communicate details to the insured so the insured
can make the choices the
policy requires of them in an informed manner. No
authority was cited for that view, and both Mr Gray and IAG submit there is no
such authority.
- [35] In LS
the CEIT relied upon Woodhouse J’s decision in van der Noll v
Sovereign Assurance Co Ltd.30 In that case, Woodhouse J held that
an insurer had a contractual (not fiduciary) duty to accurately assess a claim,
by asking the
correct questions of the relevant experts.31 The
discussion in van der Noll concerned an income protection policy and a
claim by an insured that he was suffering from a total disability. The contract
conferred
on the insurer a discretion to determine whether the medical condition
exhibited by the insured qualified him for one or more of
the benefits under the
policy. A duty necessarily fell on the insurer to inform itself when deciding
how to exercise that contractual
discretion.
- [36] The nature
of the contractual powers and corresponding duties in van der Noll were
very different to those at issue here where IAG had no discretion or
decision-making power affecting the availability of cover. While all
insurance claims will require an insurer to decide whether an insured has
discharged their burden of
28 LS v Medical Insurance Society Ltd, above n 22.
29 At [1].
30 van der Noll v Sovereign Assurance Co Ltd [2013] NZHC
3051.
31 At [94].
demonstrating the amount for which they are entitled to be indemnified (if any),
such an evaluation in this case is of a different
character to that in van
der Noll.
- [37] As IAG
says, insurers do engage experts at their cost to assess damage to their
customers’ houses because those customers
might not otherwise have the
time or finances to do this themselves. If it is discovered during the repair
process that this assessment
was inadequate, an insurer will be liable to pay to
repair the further damage. However, that is quite different to the situation
here where an insured has disputed the insurer’s assessment in the first
place. In those circumstances, the burden of proving
damage or the scope of
repair is on the insured. The insurer is not in breach of duty merely because
there is disagreement as to
the required repair scope, and likely consequential
delay.
- [38] I agree
with Mr Gray that the position taken by the CEIT in LS represents a
significant departure from existing insurance law. While there may be an
opportunity for the courts to consider imposing
a duty on an insurer to
accurately assess claims, this is not a suitable case for doing so. The
professional costs incurred by Mr
Degen have been paid and the issue of a novel
duty has not been pleaded nor the subject of evidence which would assist a
Court.
- [39] I conclude
that the CEIT erred in finding IAG owed a duty to adequately assess the
earthquake damage to Mr Degen’s house
in circumstances where the issue of
whether the house was repairable and the cost of repair was in dispute. Such a
duty would override
a fundamental principle of insurance law that the insured
has the onus of proving their loss and the amount of that loss.
Result
(a) IAG is required to pay repair costs to Mr Degen only as and when Mr Degen
has incurred the costs of such repair, submitted invoices
to IAG and IAG has
assessed the invoices and is satisfied that the costs are reasonable and relate
to the scope of work.
(b) IAG was not under a duty to adequately assess, or quantify, the earthquake
damage to Mr Degen’s property.
- [41] There is no
issue as to costs.
- [42] I express
my gratitude to Mr Gray KC for his valuable assistance to the Court as
amicus.
Hinton J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2024/397.html