1 This section applies if a change to a district or regional plan applying in a project area will, if approved, become operative in the project’s transitional period.
2 The relevant local authority must notify Kāinga Ora of that fact, in writing, at least 20 working days before whichever of the following is relevant to the plan change:
a) the date on which the relevant local authority considers whether to approve or adopt the plan change under clause 17 or 18 of Schedule 1 of the Resource Management Act 1991 :
b) the date on which the relevant local authority submits the information required by clause 83(1) of Schedule 1 of the Resource Management Act 1991 to the Minister described in that clause.
History: Section 99 heading: amended, on 23 December 2023, by section 6 of the Resource Management (Natural and Built Environment and Spatial Planning Repeal and Interim Fast-track Consenting) Act 2023 (2023 No 68).   Section 99(1): amended, on 23 December 2023, by section 6 of the Resource Management (Natural and Built Environment and Spatial Planning Repeal and Interim Fast-track Consenting) Act 2023 (2023 No 68).     Section 99(2): replaced, on 23 December 2023, by section 6 of the Resource Management (Natural and Built Environment and Spatial Planning Repeal and Interim Fast-track Consenting) Act 2023 (2023 No 68).  