ELECTRICITY ACT 1996 - SECT 60A

60A—Responsibility to ensure correct polarity and phase relationship

An electricity entity that operates a transmission or distribution network must ensure that any work carried out on behalf of the entity that could affect the safety of connected electrical installations is appropriately tested to ensure the correct polarity and phase relationship.

Maximum penalty: $50 000.