ENVIRONMENT PROTECTION ACT 1993 - SECT 103Z

103Z—Requirements relating to site contamination audits

        (1)         A site contamination auditor must, within 14 days after the commencement of a site contamination audit for which the auditor is the responsible auditor, notify the Authority in writing of the person who commissioned the audit and the location of the land to which the audit is to relate.

Maximum penalty: $8 000.

        (2)         A site contamination auditor must, within 14 days after the termination before completion of a site contamination audit for which the auditor was the responsible auditor, notify the Authority in writing of the termination and the reasons for the termination.

Maximum penalty: $8 000.

        (3)         A notification under subsection (1) or (2) must be in the form prescribed by regulation.

        (4)         A site contamination auditor must, on the completion of each site contamination audit for which the auditor is the responsible auditor

            (a)         provide a site contamination audit report to the person who commissioned the audit; and

            (b)         at the same time, provide—

                  (i)         a site contamination audit report to the Authority; and

                  (ii)         a site contamination audit statement to the council for the area in which the land to which the audit relates is situated and any prescribed body.

Maximum penalty: $8 000.

        (5)         In this section—

"responsible auditor"—a site contamination auditor is the responsible auditor for a site contamination audit if the work involved in the audit is carried out personally by, or under the direct supervision of, the auditor.