After regulation 4 of the Principal Regulations , the following regulation is inserted:4A. Conditions of licence
(1) Pursuant to section 22(1)(j) of the Act, the information specified in Schedule 1 is prescribed as the kind of information to be published by the electricity entity in relation to its energy production capability if it is a NEMMCO-registered electricity entity.(2) Pursuant to section 22(1)(c) of the Act (a) the prescribed information is to be published once a week, no later than 24 hours after the measurement time referred to in Schedule 1 ; and(b) the measurement time is to be the same for each weekly publication, unless the NEMMCO-registered electricity entity and the Regulator agree to another time; and(c) publication of the prescribed information on a website maintained by or on behalf of the NEMMCO-registered electricity entity in a form approved by the Regulator constitutes sufficient publication; and(d) the NEMMCO-registered electricity entity must keep the data from the weekly publications, in chronological order and in a form approved by the Regulator, on that website.(3) Subregulation (2) is not to be taken as preventing the NEMMCO-registered electricity entity from also publishing the prescribed information in other ways.