BUILDING ACT 2004 (NO. 11 OF 2004) - SECT 36

Period for which approvals operate

    (1)     A building approval operates until the end of the earliest of the following:

        (a)     3 years beginning on the day of its issue;

        (b)     the development period applying to the building work;

Note     A building approval ends if a further approval is issued for the same building work (see s 34).

    (2)     If the development period applying to the building work is extended, the certifier may extend the period of operation of the building approval to a day that is no later than the day the extended development period ends.

    (3)     However, subsection (2) does not authorise the extension of the period of validity of a building approval to a day that is more than 3 years after the day the approval was issued.

    (4)     In this section:

"development period" means a period within which, under another law in force in the ACT or a condition of the relevant lease, the building work must be completed.