Updating diving project plan

  (1)   A diving contractor for a diving project must keep the diving project plan for the project up to date during the project.

  (2)   The diving contractor must update the diving project plan if:

  (a)   because of modification of the project, there is a significant increase in the overall level of risk to a diving operation; or

  (b)   the operator for the project proposes to undertake or permit a modification of the project that might influence significantly the level of specific risks to a diving operation or the ranking of risk contributors.

  (3)   If there is no operator for a diving project and the diving project plan has been updated, the diving contractor must resubmit the updated plan to NOPSEMA for consideration.