Commonwealth Numbered Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

PIPELINE CONSTRUCTION (YOUNG TO WAGGA WAGGA) ACT 1980 No. 8, 1980 - SECT 3

Authority to construct pipeline
3. (1) The Pipeline Authority shall construct a pipeline from Young to
Cootamundra and Wagga Wagga in the State of New South Wales con- sisting of a
324 millimetre diameter pipeline on the route described in Schedule 1 and an
89 millimetre diameter pipeline on the route described in Schedule 2.

(2) The Pipeline Authority may make such deviations, not exceeding 1,000
metres on either side of the routes described in the Schedules, as are, in its
opinion, necessary or reasonable for the better construction and working of
the pipeline.
(3) In this section, "pipeline" has the same meaning as in the Pipeline
Authority Act 1973. 