STRATA SCHEMES MANAGEMENT ACT 2015 - SECT 202
Persons who are to be provided with copies or notice of reports
202 Persons who are to be provided with copies or notice of reports
(1) A building inspector must give a copy of an interim report or a final
report to the following persons not later than 14 days after completing the
report-- (a) the developer,
(b) the owners corporation, if the initial period
has ended,
(c) the Secretary,
(d) the builder responsible for any
defective building work identified in the report.
(2) An owners corporation
must give written notice to the owners of lots in the strata scheme of the
receipt of an interim report or a final report on building work in connection
with the scheme not later than 14 days after receiving the report.
(3) The
notice must contain the particulars, if any, prescribed by the regulations for
the purposes of this section.
: Maximum penalty--5 penalty units.