The principal contractor for a construction project must take all reasonable steps to obtain a copy of the safe work method statement relating to high risk construction work before the high risk construction work commences.
: Maximum penalty--(a) in the case of an individual--40 penalty units, or(b) in the case of a body corporate--210 penalty units.
Note : The WHS management plan contains arrangements for co-operation between persons conducting a business or undertaking at the construction project workplace, including in relation to the preparation of safe work method statements (see clause 309(2)(b) and (e)).