(1) Subject to subclause (2), the principal contractor for a construction project must ensure that a copy of the WHS management plan for the project is kept until the project to which it relates is completed.: Maximum penalty--(a) in the case of an individual--15 penalty units, or(b) in the case of a body corporate--70 penalty units.
(2) If a notifiable incident occurs in connection with the construction project to which the statement relates, the person must keep the WHS management plan for at least 2 years after the incident occurs.: Maximum penalty--(a) in the case of an individual--15 penalty units, or(b) in the case of a body corporate--70 penalty units.
(3) The person must ensure that, for the period for which the WHS management plan must be kept under this clause, a copy is readily accessible to any person who is to carry out construction work in connection with the construction project.: Maximum penalty--(a) in the case of an individual--40 penalty units, or(b) in the case of a body corporate--210 penalty units.
(4) The person must ensure that for the period for which the WHS management plan must be kept under this clause, a copy is available for inspection under the Act.: Maximum penalty--(a) in the case of an individual--15 penalty units, or(b) in the case of a body corporate--70 penalty units.
(5) In this clause,
"WHS management plan" means the initial plan and all revised versions of the plan.