BUILDING INDUSTRY FAIRNESS (SECURITY OF PAYMENT) ACT 2017 - SECT 15F
Contracts with less than 90 days until practical completion
15F Contracts with less than 90 days until practical completion
(1) A project trust is not required for a contract if there is less than 90
days between— (a) the first day a project trust would, apart from this
section, be required for the contract (the
"trigger date" ); and Note— If the effect of an amendment of a contract is
that the contract becomes eligible for a project trust for the first time, the
trigger date is the day the amendment takes effect. See section 14A .
(b)
the day practical completion for the contracted work is expected to occur.
(2) If a project trust is not required for a contract because of subsection
(1) , the contracted party must review the application of this section to the
contract each time an amendment of the contract is made that is likely to
affect the day practical completion for the contracted work is expected to
occur.
(3) In this section—
"practical completion" , for contracted work for a contract, means— (a)
practical completion as provided for under the contract; or
(b) if the
contract does not provide for practical completion—when the contracted work
would reasonably be estimated to be completed— (i) in compliance with the
contract, including all plans and specifications for the work and all
statutory requirements applying to the work; and
(ii) without any defects or
omissions, other than minor defects or minor omissions that will not
unreasonably affect the intended use of the work.