COASTAL PROTECTION AND MANAGEMENT ACT 1995 - SECT 111
Notice of proposed land surrender requirement
(1) This section applies if the chief executive proposes to require the owner
of the prescribed land to surrender all or part of the prescribed land to the
State for coastal management.
(2) The chief executive must give written
notice (each a
"proposed surrender notice" ) of the proposal to— (a) the applicant; and
(b) if the applicant is not the owner of the land—the owner of the land; and
(c) the planning chief executive; and
(d) if the relevant application is a
development application and the planning chief executive is not the assessment
manager for the application—the assessment manager for the application; and
(e) if the relevant application is a change application and the planning chief
executive is not the responsible entity for the application—the responsible
entity for the application.
(3) Each proposed surrender notice must state—
(a) details of the prescribed land the chief executive proposes be required
for surrender; and
(b) that the owner may, within 15 business days after
receiving the notice, make a written submission to the chief executive about
the proposal.
(4) The notice must be given within— (a) if the relevant
application is a development application and the planning chief executive is
the assessment manager for the application—15 business days after the
application is properly made under the Planning Act ; or
(b) if the relevant
application is a change application and the planning chief executive is the
responsible entity for the application—15 business days after the
application is made; or
(c) otherwise—15 business days after the relevant
application is given to the planning chief executive.